Tomorrow Schedule for Inspection Date 18-05-2020

S.No Description Date Time No of Layer Activity Contractor Position Omran Position Remarsk

Plot No# 08
1 104-105 19-May-20 7:00 AM N/A Inspection of Rebars of R/F Fayaz Khan QA/QC Abdul Zahoor RE

Plot No# 08
Installation of Plumbing Sewerage Pipes of
2 104-105 19-May-20 7:15 AM N/A Fayaz Khan QA/QC Abdul Zahoor RE
R/F
Plot No# 08
Water Leakage Test of Sewerage Plumbing
3 104-105 19-May-20 7:30 AM N/A Fayaz Khan QA/QC Abdul Zahoor RE
Pipes of R/F
Plot No# 08
4 104-105 19-May-20 7:45 AM N/A Installation of Water Supply Pipes of R/F Fayaz Khan QA/QC Abdul Zahoor RE

Plot No# 08
5 104-105 19-May-20 8:00 AM N/A Installation of Electrical Conduits of R/F Fayaz Khan QA/QC Abdul Zahoor RE

Plot No# 08
6 104-105 19-May-20 8:15 AM N/A Formwork of R/F Fayaz Khan QA/QC Abdul Zahoor RE

Plot No# 08
7 104-105 19-May-20 7:00 PM N/A Pouring Structural Concrete of R/F Fayaz Khan QA/QC Abdul Zahoor RE

Plot No# 08
8 106-107 19-May-20 8:45 AM N/A Inspection of Rebars of R/F Fayaz Khan QA/QC Abdul Zahoor RE

Plot No# 08
Installation of Plumbing Sewerage Pipes of
9 106-107 19-May-20 9:00 AM N/A Fayaz Khan QA/QC Abdul Zahoor RE
R/F
Plot No# 08
Water Leakage Test of Sewerage Plumbing
10 106-107 19-May-20 9:15 AM N/A Fayaz Khan QA/QC Abdul Zahoor RE
Pipes of R/F
Plot No# 08
11 106-107 19-May-20 9:30 AM N/A Installation of Water Supply Pipes of R/F Fayaz Khan QA/QC Abdul Zahoor RE

Plot No# 08
12 106-107 19-May-20 9:45 AM N/A Installation of Electrical Conduits of R/F Fayaz Khan QA/QC Abdul Zahoor RE

Plot No# 08
13 106-107 19-May-20 10:00 AM N/A Formwork of R/F Fayaz Khan QA/QC Abdul Zahoor RE

Plot No# 08
14 106-107 19-May-20 8:00 PM N/A Pouring Structural Concrete of R/F Fayaz Khan QA/QC Abdul Zahoor RE

Plot No# 02
15 19-May-20 10:15 AM N/A Installation of Rebar's of Walls Fayaz Khan QA/QC Abdul Zahoor RE
143

Plot No# 02
16 19-May-20 10:30 AM N/A Installation of Rebar's of Walls Fayaz Khan QA/QC Abdul Zahoor RE
144-145

Plot No# 02
17 19-May-20 10:45 AM N/A Installation of Rebar's of Walls Fayaz Khan QA/QC Abdul Zahoor RE
146-147

Plot No# 02
18 19-May-20 11:00 AM N/A Installation of Rebar's of Walls Fayaz Khan QA/QC Abdul Zahoor RE
148-149

Plot No# 02
19 19-May-20 11:30 AM N/A Installation of Rebar's of Walls Fayaz Khan QA/QC Abdul Zahoor RE
150-151