Documente Academic
Documente Profesional
Documente Cultură
: Page 1 of 18
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-MLT-006
IMPORTANT:
CONTENTS
1.0 SCOPE
2.0 MATERIALS
3.0 EQUIPMENT & RESOURCES
4.0 METHOD / TEST PROCEDURES
5.0 QUALITY CONTROL PROCEDURE
6.0 HEALTH, SAFETY AND ENVIRONMENT
7.0 TRACK POSSESSION
8.0 SUMMARY OF FORMS
1.0 SCOPE
2.0 MATERIALS
4.1 Installation
Having established the test pile location, the centers of the reaction
piles will also be accurately located to facilitate their construction (see
Attachment 1 for layout).
The anchorage tendons will be in the form of steel P.C. strands, which
will be prefabricated into bundles of the required number, length and
diameter (see Attachment 2). These tendons shall then be fixed to the
reinforcement cage of the reaction piles.
Once the bores are completed to the required penetration length the
prefabricated cages and tendons are lowered into the bore until the
base is reached. The minimum projection of the tendons above the
working platform level is determined by the arrangement of the reaction
beams (see Attachment 1).
The pile head (for testing purposes) will be constructed together with
the actual test pile wherever possible. Where not possible, the
unprepared head will be trimmed down and levelled to ensure that only
clean and sound material is exposed for testing. If required, the pile will
be built up to the necessary level using materials of at least the grade
and quality of the original.
4.3.1 Assembly
A suitable platform will be prepared over the working area of the test.
This will aid the stability and accurate assembly of the test rig.
Kentledge blocks or cribbage are then placed directly onto the bearing
surface to provide temporary support for main reaction beam(s). These
supports will be positioned in such a way as not to interfere with the
anchors. The main reaction beam(s) are then carefully aligned and
levelled to ensure that the beam-pile head loading points are in the
same vertical axis.
The secondary reaction beams are then carefully placed on top of the
main beam(s) and the apertures aligned with the anchors. These beams
are then tack-welded into place for stability.
The tendon strands are then carefully threaded through the main and
secondary beam apertures before each strand is located through the
anchor head locking plate.
Finally, wedges are inserted into the anchor head at each strand
location across both sets of beams. Each strand is then carefully pre-
stressed in such a sequence as to maintain even distribution across the
test rig. This procedure minimises the elongation of the strands during
the test. Disassembly is the reverse of the above after cutting of the
anchor strands.
The loading will be applied to the test element using hydraulic jack(s)
reacting against the lower main beam and thus the secondary beams
and reaction piles.
In cases where the test loads exceeds a single jack capacity, a multiple
jacking system with corresponding numbers of load cells will be used.
The jack(s) will be carefully aligned on the steel bearing plate to ensure
the transference of load axially through the pile. The actual value of load
being applied will be read and recorded from calibrated, electronic,
compressive load cell(s) located between the jack(s) and the lower main
beam. Additionally, an in-line, calibrated pressure gauge, may be
installed into the hydraulic system to monitor any gross errors. Steel
packers and/or platens will be inserted before pressuring the system
slightly until contact is made with the main beam.
4.4.3 Instrumentation
Loading shall not commence until the material strengths exceed twice
the average direct stress in any element section under the maximum
required test load.
4.5.2 Loading
The loading is then increased to the next value and held for the required
time interval. The test will continue in accordance with test pile loading
sequence (Attachment 4). All results are recorded upon the field record
sheet (Appendix B).
After completion of the test and disassembly of the test set-up, the
redundant ground anchors will be cut back to working platform level for
subsequent further cutting back by the Main Contractor as his
excavation work progresses.
4.7 Results
The work to be carried out in accordance with the Project Safety Plan.
Particular activities requiring attention are highlighted in the Appendix
D. The toolbox meeting will be carried out on construction area at
regular intervals to ensure compliance with the Safety Plan and
familiarity with accident and emergency procedures.
Track possession would depend on the actual location of each works and
would be addressed separately if required.
APPENDIX A
QUALITY INSPECTION PLAN
METHOD STATEMENT Page No. : Page 11 of 18
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-MLT-006
APPENDIX B
INSPECTION AND TEST PLAN
METHOD STATEMENT Page No. : Page 12 of 18
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-MLT-006
APPENDIX C
QUALITY FORMS
METHOD STATEMENT Page No. : Page 13 of 18
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-MLT-006
APPENDIX D
SAFETY, HEALTH AND ENVIRONMENT
METHOD STATEMENT Page No. : Page 14 of 18
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-MLT-006
ATTACHMENT 1
TEST SET-UP DETAILS
METHOD STATEMENT Page No. : Page 15 of 18
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-MLT-006
ATTACHMENT 2
ANCHORAGE DESIGN DETAILS
METHOD STATEMENT Page No. : Page 16 of 18
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-MLT-006
ATTACHMENT 3
TEST BEAM DETAILS
METHOD STATEMENT Page No. : Page 17 of 18
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-MLT-006
ATTACHMENT 4
TEST LOADING SEQUENCE
METHOD STATEMENT Page No. : Page 18 of 18
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-MLT-006