Documente Academic
Documente Profesional
Documente Cultură
: Page 1 of 6
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-SLT-008
IMPORTANT:
CONTENTS
0 SCOPE
1 MATERIALS
2 EQUIPMENT & RESOURCES
3 METHOD
4 QUALITY CONTROL PROCEDURE
5 HEALTH, SAFETY AND ENVIRONMENT
6 TRACK POSSESSION
7 SUMMARY OF FORMS
METHOD STATEMENT Page No. : Page 3 of 6
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-SLT-008
1.0 SCOPE
This procedure applies to all bored piles that require sonic logging test.
0 MATERIALS
Not required.
i) Sonic pipes
4.0 METHOD
0 Installation
1 A Site Welder shall prepare four sets of sonic pipes for 900mm dia.
bored pile and six sets for 1500mm dia. bored pile that need to be
tested. The bore pile depth will determine the length of each sonic pipe.
2 Sonic pipes shall be assembled using 6m long steel pipes with outside
diameter of 50mm. Each pipe shall be joined using a welded outer
sleeve to form 12m sections. The outer sleeve should be 100-150mm
long.
3 The pipes to be installed at the toe of the pile shall have one end sealed
by welding.
METHOD STATEMENT Page No. : Page 4 of 6
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-SLT-008
4 As the steel cage is being installed to the bore pile, four 12m sections
shall be welded to the cage at the toe.
6 The top of the final sections of sonic pipe should be 1m above the
platform level.
7 The installed sonic pipes shall be filled with water and then sealed by
black tape.
0 The Site Superintendent shall check the condition of the sonic pipes to
be tested and refer to the Site Manager if any of the closed ends have
been damaged. If the sonic pipes are undamaged the closed ends shall
be removed.
1 Each sonic pipe shall be checked by lowering a dummy probe into the
pipes. If any of the pipes are blocked, they shall be flushed with running
water until all obstructions are removed.
3 The person performing the test shall ensure that all connections are
okay and that the transmitter and receiver are operating correctly.
4 If any of the pipes cannot be cleaned to the toe of the pile, the Site
Manager shall inform the Client to request a concession or other
corrective action requirement.
METHOD STATEMENT Page No. : Page 5 of 6
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-SLT-008
4.3 Testing
1 The test probes shall be lowered into the sonic pipe in accordance to the
specified logging profile. Care must be taken to prevent the probes from
sticking in the pipes.
2 When the probes reach the pipe toe, they shall be raised to about 1m
above the pile toe to avoid any end effects at the base of the pile.
3 The probe levels shall be adjusted until a stable signal is achieved. This
is when there are minimal changes in intensity and delay.
4 When the stable signal is achieved, the probes shall be lowered to the
toe of the pile and then the cables placed across the meter wheel.
5 The test machine is then activated to begin logging. The probes should
be raised at a rate of around 1.0m/sec.
6 When the first profile is completed, logging is terminated and the data is
stored internally on the test machine. The top part of the log that
records the removal of the probes shall be ignores/disposed.
7 The operator shall proceed to the second profile by extracting any one
of the probes and lowering it into an adjacent sonic pipe in accordance
to the specified logging profiles.
8 Steps 4.3.1 to 4.3.8 shall be repeated until all logging profiles are
completed. After conducting the tests, all tubes shall be filled with non-
shrink grout of similar strength of pile concrete.
METHOD STATEMENT Page No. : Page 6 of 6
Revision : 0
Issued : Dec 2001
UE Construction Sdn Bhd UEC-MS-BR466-SLT-008
4.4 Reporting
1 The test operator shall print out the results and a qualified engineer will
determine the integrity of the bore pile. A detailed report shall be given
to the S.E. upon completion of the test.
Not required.
Not required.
Not required.