If non availability of correct and up-to-date data in the existing
HR system may impact the interface activities and post go live
stabilisation Negative 3
6
You might accept the risk, this means you understand it could
occur and you have a plan for what to do if it does occur. But
you're not taking action to prevent the risk.
Example: Perhaps there's a risk that a key team member might
leave. But you're not allowed to hire a replacement until that
Accept person gives notice.
And there are responses you take in advance to try and prevent
the risk from occurring. If you opt to avoid the risk, it means
you're changing your plan so that you eliminate the risk.
Example: If you participate in outdoor construction work, you
might simply not schedule projects during the rainy season. You
Risk Likelihood
opt to avoid the risk of the rain, well, at least during the known
Avoid rainy season that is
If you transfer the risk, it mean you are making another party
responsible. You are giving the ownership of the potential risk
and the work associated with the risk. It doesn't mean the risk
goes away, it means that you have transferred it to a party who
Transfer should be more qualified to deal with it.
Risk Ex
HR Connect - Identify Project Risks
Risk Impact Overall Priority Response Strategy Mitigation
Thorough evaluation of the current
processes and create to be global
process taking into consideration
the leading practices.
5 Medium Avoid
1. Project plan has been prepared
after discussion and acceptance
from the GPO.
2. Project plan has been prepared
keeping in mind other HR important
activities to avoid the conflict
3. Joint weekly project reviews are
planned with GPO where project
planned activities are discussed in
advance
5 Low Avoid
1. Project plan has been prepared
keeping in mind other HR important
activities to avoid the conflict
2. Fortnight project news letter will
be sent to the HR community
highlighting the project progress
and key planned activities.
4 High Avoid
Data validations are done 1 week
prior to commencement of this
project and found that the data is
update and accurate.
5 Medium Avoid
1. Read and understand update
release notes
2. Partner with product
development team to address any
critical product gaps in timely
manner
Very low - 1 1 2 3
Low - 2 2 4 6
Medium - 3 3 6 9
High - 4 4 8 12
Very High - 5 5 10 15
Risk Exposure Description Very Low -1-5, Low -6-10, Medium - 11-15, High - 16-20, Very High -20-25
Contingency
AED 2000 is kept for external
consultant for their review and
advise on the to be process
pact
4 5
8 10
12 15
16 20
20 25
High - 16-20, Very High -20-25