Formularul Nr.
38,16
Cofrarea elementelor monolite m²
17,90
-panou de cofraj m² 0,11000 50,00 5,50
-scîndură răşinoase m³ 0,00100 3001,13 3,00
-lemn rotund răşinoase m³ 0,00150 2100,00 3,15
-dulapi răşinoase m³ 0,00100 3404,95 3,40
-cuie cu cap conic kg 0,03000 15,60 0,47
9 CB03A -decofrol kg 0,12000 6,50 0,78
-scoabe de oţel kg 0,03000 35,00 1,05
-şuruburi uzuale pătrate buc 0,30000 0,30 0,09
-piuliţe buc 0,30000 0,30 0,09
-şaibe buc 0,00500 0,30 0,00
-dulgher c-4 h-om 1,00000 15,36 15,36
-muncitor deservire h-om 0,30000 8,48 2,54
-macara h-ut 0,02000 136,07 2,72
9,64
Armarea elementelor monolite kg
0,88
-oţel beton kg 1,02000 8,45 8,62
10 CC01D -sîrmă de oţel kg 0,01000 11,52 0,12
-distanţieri buc 0,15000 0,15 0,02
-fierar beton c-4 h-om 0,05500 15,36 0,84
-muncitor deservire h-om 0,00400 8,48 0,03
1110,22
Betonarea elementelor monolite m³
80,84
-beton m³ 1,02500 930,00 953,25
-betonist c-4 h-om 4,95000 15,36 76,03
11 CA03E
-muncitor deservire c-2 h-om 0,45000 10,69 4,81
-centrală de beton h-ut 0,05700 90,00 5,13
-buldozer h-ut 0,01800 163,84 2,95
-macara h-ut 0,28000 136,07 38,10
-vibrator de adîncime h-ut 0,60000 49,92 29,95
Montarea blocurilor talpă şi perete 331,50
buc
de fundare 42,18
-bloc talpă şi perete buc 1,01000 196,23 198,20
-mortar de ciment m³ 0,00600 720,00 4,32
-dulapi răşinoase m³ 0,00050 3404,95 1,70
-apă m³ 0,00300 22.96 0,08
12 CP10B
-ciment kg 2,30000 1,44 3,31
-nisip m³ 0,00800 125,00 1,00
-ipsos kg 0,30000 1,43 0,43
-montator c-5 h-om 2,25000 17,56 39,51
-muncitor de servire c-2 h-om 0,25000 10,69 2,67
-macara h-ut 0,59000 136,07 80,28
Executarea hidroizolatiei 47,83
m2
orizontale 4,06
-mortar de ciment m3 0,03100 990,00 30,69
13 IzF50A -sticla solubila kg 0,50000 25,00 12,50
-apa m3 0,00300 22.96 0,08
-muncitor deservire c-2 h-om 0,38000 10,69 4,06
-autocamion h-ut 0,00400 125,00 0,50
369,93
Executarea hidroizolatiei verticale m²
0,81
-bitum kg 1,60000 6,98 11,18
-carton bitumat m² 1,10000 11,00 12,10
14 IzF04F -filer de calcar kg 0,32000 0,50 0,16
-lemn de foc de răşinoase kg 1,15000 300,00 345,00
-cuie cu cap conic kg 0,02000 15,60 0,31
-izolator hidrofug c-3 h-om 0,06000 13,48 0,81
-topitor de bitum h-ut 0,01300 28,53 0,37
3161,24
Montarea planşeelor CC buc
41,30
-element prefabricat buc 1,01000 1322,56 1335,78
-mortar de ciment m³ 0,00600 990,00 5,94
-dulapi răşinoase m³ 0,00050 3404,95 1,70
-apă m³ 0,00300 22.96 0,08
15 CP10A
-ciment kg 2,30000 720,00 1656,00
-nisip m³ 0,00800 125,00 1,00
-ipsos kg 0,30000 1,43 0,43
-montator c-5 h-om 2,20000 17,56 38,63
-muncitor deservire c-2 h-om 0,25000 10,69 2,67
-macara turn h-ut 0,85000 140,00 119,00
Formularul Nr.
Nr Denumirea Unitate Preţ de Cheltuieli Cheltuieli de Valoare de
materialelor de achiziţii de achiziţii de deviz
masura fara transport depozitare
TVA
1 2 3 5 6 4
Formularul Nr.
Formularul Nr.
Nr Simbol IND Denumirea U./M. Cantitatea Valuarea de deviz
lucrărilor Lei
Unitate Total
1 2 3 4 5 6 7
TsE04A1 -buldozer h-ut 183,68 186,08 34179,1744
TsC18A1 -buldozer h-ut 1542,93 186,08 287108,973
TsC03 E1 -excavator h-ut 1726,74 247,05 426592,229
TsD02C1 -buldozer h-ut 196,568 163,84 32205,7175
TsD06A1 -mai mecanic h-ut 2049,33 29,27 59983,8013
-macara h-ut 6,6425 136,07 903,844975
-vibrator de
CA02C suprafata h-ut 10,628 25 265,7
CB03A -macara h-ut 26,6504 136,07 3626,31993
-centrală de beton h-ut 95,8546 90 8626,9158
-buldozer h-ut 30,2699 163,84 4959,41714
-macara h-ut 470,865 136,07 64070,5733
-vibrator de
CA03E adîncime h-ut 1009 49,92 50369,0803
CP10B -macara h-ut 373,47 136,07 50818,0629
IzF50A -autocamion h-ut 0,52 125 65
IzF04F -topitor de bitum h-ut 4,54688 28,53 129,722486
CP10A -macara turn h-ut 538,05 140 75327
TOTAL 1099231,53
MANOPERA
TsA02B1 -mucitor necalificat h-om 31,6183 30,92 977,637836
-muncitor deservire
TsD06A1 c-2 h-om 1840,21 30,92 56899,355
-betonist c-4 h-om 21,256 30,92 657,23552
TsC54B -mucitor deservire h-om 5,0483 30,92 156,093436
-betonist 3 h-om 102,295 30,92 3162,94594
CA02C -muncitor deservire h-om 17,2705 30,92 534,00386
-dulgher c-4 h-om 1332,52 30,92 41201,5184
CB03A -muncitor deservire h-om 399,756 30,92 12360,4555
-fierar beton c-4 h-om 866,496 30,92 26792,0687
CC01D -muncitor deservire h-om 63,0179 30,92 1948,51409
-betonist c-4 h-om 8324,22 30,92 257384,79
-muncitor deservire
CA03E c-2 h-om 756,747 30,92 23398,6172
-montator c-5 h-om 1424,25 30,92 44037,81
-muncitor de servire
CP10B c-2 h-om 158,25 30,92 4893,09
-muncitor deservire
IzF50A c-2 h-om 50,2208 30,92 1552,82714
-izolator hidrofug c-
IzF04F 3 h-om 20,9856 30,92 648,874752
CP10A -montator c-5 h-om 1392,6 30,92 43059,192
-muncitor deservire
c-2 h-om 158,25 30,92 4893,09
TOTA
L 524558,1191
MATERIALE
TsC54B -pietriş m³ 29,227 176,59 5161,19593
-beton m³ 27,2343 930 25327,8525
-apa m³ 2,657 22,96 61,00472
CA02C -material marunt % 26,57 1 26,57
-panou de cofraj m² 146,577 50 7328,86
-scîndură răşinoase m³ 1,33252 3001,13 3999,06575
-lemn rotund
răşinoase m³ 1,99878 2100 4197,438
-dulapi răşinoase m³ 1,33252 3404,95 4537,16397
-cuie cu cap conic kg 39,9756 15,6 623,61936
-decofrol kg 159,902 6,5 1039,3656
-scoabe de oţel kg 39,9756 35 1399,146
-şuruburi uzuale
pătrate buc 399,756 0,3 119,9268
-piuliţe buc 399,756 0,3 119,9268
-şaibe buc 6,6626 0,3 1,99878
CB03A -oţel beton kg 1359,17 8,45 11484,9899
-sîrmă de oţel kg 157,545 11,52 1814,9161
CC01D -distanţieri buc 2363,17 0,15 354,4758
CA03E -beton m³ 1723,7 930 1603042,4
-bloc talpă şi perete buc 639,33 196,23 125455,726
CP10B -mortar de ciment m³ 3,798 720 2734,56
-dulapi răşinoase m³ 0,3165 3404,95 1077,66668
-apă m³ 1,899 22,96 43,60104
-ciment kg 1455,9 1,44 2096,496
-nisip m³ 5,064 125 633
-ipsos kg 189,9 1,43 271,557
-mortar de ciment m3 4,09696 990 4055,9904
-sticla solubila kg 66,08 25 1652
IzF50A -apa m3 0,39648 22,96 9,1031808
-bitum kg 559,616 6,98 3906,11968
-carton bitumat m² 384,736 11 4232,096
-filer de calcar kg 111,923 0,5 55,9616
-lemn de foc de
răşinoase kg 402,224 300 120667,2
IzF04F -cuie cu cap conic kg 6,9952 15,6 109,12512
-element prefabricat buc 639,33 1322,56 845552,285
-mortar de ciment m³ 3,798 990 3760,02
-dulapi răşinoase m³ 0,3165 3404,95 1077,66668
-apă m³ 1,899 22,96 43,60104
-ciment kg 1455,9 720 1048248
-nisip m³ 5,064 125 633
CP10A
-ipsos kg 0,43 1,43 905,19
TOTAL 3837859,88
1.Man+Ut+Mat 5461649,52
2.cas(27%*Man) 141630,69
3.total,1+2 5603280,21
4.14,3*tab3 80126907
5.total 3+4 85730187,2
6.ben,dev0.06*rez5 5143811,23
7.total (6+5) 90873998,4
8.TVA(0,2*rez7 18174799,7
9.total 7+8 109048798
10.Man+Cas 666188,809