Documente Academic
Documente Profesional
Documente Cultură
Approval
Amendment Record
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN
AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
Table of Contents
1. Purpose .............................................................................................................................. 3
2. Background........................................................................................................................ 3
3. Abbreviations..................................................................................................................... 3
4. Definitions.......................................................................................................................... 4
6. Responsibilities ................................................................................................................. 5
7. Considerations .................................................................................................................. 5
8. Process .............................................................................................................................. 6
8.1 Start Up Meeting & Risk Assessment ............................................................................... 6
8.2 Approval to undertake Overlapping Design Process ......................................................... 7
8.3 Modification Process ........................................................................................................ 7
8.4 Cancellation or Rescheduling of Projects.......................................................................... 8
9. Liabilities............................................................................................................................ 8
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 2 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN
AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
1. Purpose
The purpose of this document is to highlight the process and responsibilities for an
overlapping design agreement where two or more contractors are required to produce
designs under concurrent or compressed timescales. This agreement is applicable for all
designs relating to MTM.
2. Background
Within Rail projects there are often multiple contractors involved that may require the same
engineering drawings. The Public Transport Victoria’s Drawing Management System
(DMS) is limited to the update from only one contractor at a time via a book in / book out
process. The limitation of this process is that, if a second contractor wanted to work on the
same design, the first contractor who is in control of the drawings would be required to
book the drawings back into DMS (relinquishing their control of the drawings) to allow for
the second contractor to modify the drawings. This can be both time consuming and costly.
This procedure allows for two or more contractors to “mark up” drawings in a controlled
manner and reduce the consequences of allowing only one contractor to update drawings.
Also, when more than one contractor is involved in modifying the engineering designs in
the same area of the network in parallel, there is no clear line of responsibility to ensure the
design updates are all incorporated in a coordinated manner. Hence, this procedure will
formalise and document the process that has been informally applied by a number of
projects, which has often resulted in the loss of revision control, thus allowing the drawings
to be updated in a controlled manner.
3. Abbreviations
AIS As In Service
DMS Drawing Management System
DOT Department of Transport
IFC Issued For Construction
MTM Metro Trains Melbourne
PTV Public Transport Victoria
RDE Responsible Design Engineer
RODE Responsible Overlapping Design Engineer
VRIOGS Victorian Rail Industry Operators’ Group Standards
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 3 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN
AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
4. Definitions
Drawing Controller MTM staff responsible for the control of drawings
booked out from DMS and allocation to the Project
Manager / Design Contractors
CAD File Computer Aided Design File that is required to modify
drawings. This can take on numerous file types
depending on the design
MTM Engineering MTM Engineering responsible for ensuring
compliance of all designs to be booked back into DMS
Primary Contractor Contractor who the drawings are booked out to. Often,
this is the contractor whose works must proceed
before the second contractor
Project Engineer MTM staff who assists the Project Manager in the
design / testing and commissioning aspects of the
Project. A Project Engineer may be required as a
conduit to communicate with the Contractor
Project Manager The lead responsible for the deliverables for a Project.
Depending on the project, there may be two Project
managers – one for each Design Contractor. It must
be the Project Manager(s) who initiate the
Overlapping Design Agreement
Responsible Design Engineer Representative of the Contractor as a direct contact
(RDE) relating to the designs. In order to avoid confusion and
ambiguity -there shall only be a single Responsible
Design Engineer for each Contractor concerned
Responsible Overlapping Person appointed by MTM for the purpose of
Design Engineer (RODE) coordination and facilitation of the Overlapping Design
Agreement.
Secondary Contractor Contractor that requires modifications to the designs
but is booked out to the Primary Contractor
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 4 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN
AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
6. Responsibilities
Shown below is a breakdown of the responsibilities
Drawing
Drawing Controller Management
(MTM) System
(DMS)
Project Manager(s)
(MTM)
MTM & DMS
RODE Engineering
(MTM) (MTM)
Project Engineer / Responsible Design Engineer Project Engineer / Responsible Design Engineer
(MTM / Primary Contractor) (MTM / Secondary Contractor)
Contractor
Secondary
Primary Contractor
Contractor
7. Considerations
An overlapping Design allows for more than one contractor to modify engineering designs.
The potential consequences for this are: integrity of data can be reduced, incorrect versions
of the drawings being used, confusion of responsibilities and disputes / conflict of interest
from the different contractors.
Thus, the use of overlapping designs should be limited to cases where delivery of the
projects is within a concurrent / compressed timeframe and / or there are large financial and
safety repercussions.
When considering an overlapping design agreement the following preferences should
follow (with 1 being most preferred.)
1. Reschedule works to remove the requirement for an overlapping design.
2. Utilize the same contractor to perform the designs where overlapping is expected.
3. Undertake an overlapping design arrangement as per this procedure, subject to
approval by MTM Engineering.
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 5 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN
AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
8. Process
The following outlines the typical process when undertaking an Overlapping Design
Agreement.
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 6 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN
AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
1
Refer to Appendix A for a flowchart of the Overlapping Design process.
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 7 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN
AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
5. The Secondary Contractor works on the CAD file copy and keeps a log of any
issues. All changes made by the Secondary Contractor should be identified by a
separate color or any other agreed methodology. The Secondary Contractor shall
ensure that their portion of the works is checked and independently reviewed (if
required) prior to sending the designs back to the Primary Contractor.
6. Once the necessary works are complete – the Secondary Contractor issues the
CAD file copy to RODE, with the temporary revision box filled in.
Examples of the temporary revision box can be seen in Appendix D – Sample
Temporary Title Block Locations.
7. The RODE logs the movement as per step 3.
8. The Primary Contractor receives the CAD file and performs any other mark ups
required (with the applicable checking and independent review requirements
satisfied).
9. In the event that the Commissioning works are within the same time frame – only 1
Master Test Copy shall be produced (typically done by the Primary Contractor
unless otherwise agreed). There should also only be a single Tester in Charge for
the scope of works of the Primary and the Secondary Contractor. This must be
agreed to prior to accepting the Overlapping Design Agreement.
10. In the event that the Commissioning dates are separate, each Contractor will be
required to perform their own commissioning works independently (e.g. Production
of Test copies, Construction Copies and Interim Maintenance copies). In this
instance, the Tester in Charge may be different for each Contractor’s
commissioning activity. Refer to Appendix B – Interim Maintenance Copies
Distribution Process and Appendix C – As-Built Submission Process.
11. It is the Primary Contractor’s responsibility (unless otherwise agreed) to bring the
drawings up to DMS Compliance or seek dispensation.
9. Liabilities
Each contractor is liable for their own design. Any updates made by the Contactors on
behalf of another Contractor under the Overlapping Design Agreement, does not import
any liability from the Contractor requesting the change.
The Overlapping Design Agreement will still require all Design Procedures to be followed
for each Contractors portion of works. This includes – certification, checking and
independent review.
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 8 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN
AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
11. Appendices
Appendix A - Flowchart of Overlapping Design Process
Appendix B - Interim Maintenance Distribution Process
Appendix C - As-Built Submission Process
Appendix D - Sample Temporary Title Block Locations
Appendix E - Overlapping Design Agreement Application
Appendix F - Overlapping Design Agreement Design Transfer Log
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 9 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN
AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 10 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN
AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 11 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN
AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 12 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN
AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
OR
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 13 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
Drawing Controller:
Organisation:
The Responsible Overlapping Design Engineer (RODE)
shall be:
Name Email Phone Number Signature
Responsible Overlapping Design
Engineer
Organisation:
The RODE will be required to coordinate and track all movements related to the affected Engineering Designs between differing contractors.
It is the RODE's responsibility to ensure that integrity of the designs are preserved.
The Primary Contractor that will provide have the Engineering Designs booked to shall be:
Name Email Phone Number Signature
Organisation
The Primary Contractor must provide the final designs incorporating all related Contractors design modifications and comments. It is the Primary Contractors
responsibility to return the plans to DMS compliance
Organisation (1)
The Following Engineering Designs will be undertaken via an Overlapping Design methodology
PTV DMS
Dispensation Number (if any) :
Attached to this application shall be the Start Up meeting minutes and Risk Register
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 14 of 15
CHIEF ENGINEER PROCEDURE
MANAGEMENT OF OVERLAPPING DESIGN AGREEMENT
L1-CHE-PRO-007 Version: 1 Effective from: 30th May 2014
# Overlapping Design Agreement Design Transfer Log to be maintained by RODE for record and keeping track of the status of drawings
Approving Manager: Chief Engineer Approval Date: 30/05/2014 Next Review Date: 30/05/2017
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 15 of 15