Sunteți pe pagina 1din 2

SET-A

Subject Code: (16ME8T29)

IV B.Tech II Semester II Mid Examinations, September-2020


Production Planning and Control

Time: 20 mins. (Mechanical Engineering)

Max Marks: 10
Date: 15-09-2020 Marks secured

Answer all questions

Q.No. CO Question Answer


Routing prescribes______________
1 CO4 a) Operations b) some of the material processing c) sequence of operations to be [ C ]
followed d) none of the mentioned
Which of the following Statement is correct?
2 CO4 a) Various tests belong to same job b) tasks are performed in various facilities [ ]
c) acts is a constraint for scheduling d) a & c
CO4 Production planning consists of_________
3 [ ]
a) Planning b) preplanning and routing c) Routing d) scheduling
PFA stands for___________
4 CO4 a) Production free analysis b) planning free analysis c) production flow analysis [ C ]
d) none of the above
CO4 The function which authorizes production as well as control is____________
5 [ ]
a) scheduling b) flow analysis c) preplanning d) processing
CO4 _________is a method of identifying part facilities that uses the data flow
6 [ ]
a) PFS b) PFA c) planning d) expediting
Routing function in production system design is concerned with _________
7 CO4 a) geometric shape of the work piece b) Machine assembling c) function of the machine [ D ]
d) machine utilizations
Master scheduling considers?
8 CO5 a) Demand Forecasts b) pending orders c) minimize the men [ ]
d) Demand Forecasts & pending orders
CO5 The preplanning of productions, workforce and inventory at the broadest level is
9 [ ]
a) Aggregate planning b) planning c) Assembling d) none of the above
CO5 Gantt chart is mostly used for
10 [ B ]
a) Routing b) Scheduling c) Follow up d) Inspection and quality control

PRAGATI ENGINEERING COLLEGE:: SURAMPALEM


(Autonomous)

Q.No
CO Question Answer
.
Which one of the following is NOT a decision taken during the aggregate production planning
CO stage?
11 5 [ A ]
a) Scheduling of machines b) Amount of labour to be committed c) Rate at which
production should happen d) Inventory to be carried forward
CO A _________ strategy means producing the amounts demanded at any given time
12 5 [ B ]
a) production leveling b) chase c) subcontracting d) TQM

CO The monitoring and follow up function intended for completion of job within the due date is
13 5 called__________ [ ]
a) Routing b) scheduling c) processing d) Expediting
CO ____________ assigning the tasks to the work stations in such a way that workstations have
14 5 approximately equal time requirements. [ ]
a) Line Balancing b) Planning c) Job shop d) Units
CO Centralized and decentralized are the types of
15 6 [ B ]
a) Routing b) Dispatching c) Scheduling d) Follow up
Dispatching authorizes the start of production operations by
(i) Release of material and components from stores to first process
CO (ii) Release of material from process to process
16 6 [ D ]
(iii) Issue of drawings instruction sheets
Which of the following is true?
a) Only i b) Only ii c) i & ii d) i , ii & iii
CO The correct sequence of operations in production planning and control is
17 6 a) Routing-Scheduling-Dispatching-Follow up b) Scheduling-Routing- Dispatching-Follow up [A ]
c) Dispatching-Routing-Scheduling- Follow up d) Routing-Scheduling-Follow up-Dispatching
CO Dispatching stations located along the __________
18 6 [ ]
a) Production station b) sequence of stages c) production line d) units
CO Which type of computer is used in production planning and control
19 6 [ ]
a) analog computers b) digital computers c) super computers d) none of above

CO Magnetic drum is used for____________


20 6 a) Recording operators b) Specifications of products c) Internal storage of information [ ]
d) counting digits at very high speed

PRAGATI ENGINEERING COLLEGE:: SURAMPALEM


(Autonomous)

S-ar putea să vă placă și