Sunteți pe pagina 1din 87

QUANTITATIVE RISK ANALYSIS

TRADITIONAL AND
NEW RISK DRIVERS APPROACH TO
SCHEDULE AND COST RISK ANALYSIS

AUGUST 7, 2008

DAVID T. HULETT, PH.D.


HULETT & ASSOCIATES, LLC
LOS ANGELES, CA USA

1
© 2008 Hulett & Associates, LLC
Introduction

• Large and complex projects need quantitative


risk analysis of cost and schedule
• Traditionally and in the PMBOK® Guide the
method has been to put “3-point estimates” on
schedule duration and cost line items. This
focuses on the impacts of risk.
• Recently we have developed an approach, the
“Risk Driver” approach, that focuses on the risks
themselves, not on the impact of risks on
durations or costs
2
© 2008 Hulett & Associates, LLC
Agenda

• This presentation introduces quantitative risk


analysis:
– Traditional 3-point estimate
– New Risk Driver approach
• The benefits of the new approach are discussed
and contrasted with the traditional approach

3
© 2008 Hulett & Associates, LLC
Introduction

USAF Approach to Schedule Risk


“A Most Probable Schedule (MPS) will be
prepared by assessing the durations presented
in the offeror’s MIPS (this means estimating the
longest, the shortest, and the most likely duration
for each task, activity, event, and milestone) and
preparing a network-based Monte Carlo
simulation in order to determine a schedule that
has a 90% probable completion date.”
Integrated Risk Management Guide,
Aeronautical Systems Center (ASC), draft, 9 April 1994

4
© 2008 Hulett & Associates, LLC
Overrun Risk is Not a New Issue (1)

“Initial cost and schedule estimates for major


projects have invariably been over-optimistic.
The risk that cost and schedule constraints will
not be met cannot be determined if cost and
schedule estimates are given in terms of single
points rather than distributions”

5
© 2008 Hulett & Associates, LLC
Overrun Risk is Not a New Issue (2)

“A formal risk analysis is putting on the table


those problems and fears which heretofore were
recognized but intentionally hidden.”

Source: “Final Report,”


US Air Force Academy
Risk Analysis Study Team 1973

6
© 2008 Hulett & Associates, LLC
Schedule Risk Is Common,
It’s Not just in Aerospace Projects
“The opening of Denver International Airport, originally
scheduled for last October (1993), has been delayed
yet again, this time until May 15 (1994) because of
problems in troubleshooting its complex baggage
system… The delay will cost the city, and United and
Continental airlines a total of $30 million.”

Aviation and Space Technology, March 7, 1994, p. 32

7
© 2008 Hulett & Associates, LLC
Some Reasons for Schedule Risk
• Fundamental uncertainty in the work
• Unrealistic baseline schedule
• Natural, geological causes
• Project complexity
• Scheduling abuses
• Relying on participants outside the organization
• Subcontractor late

8
© 2008 Hulett & Associates, LLC
Some Reasons for Schedule Risk
(continued)
• Design changes
• Staffing Manufacturing problems
• Contracting problems
• Customer (government) not supportive
• Cannot get subcontractor under contract
William Cashman, “Why Schedules Slip…”
Air Force Institute of Technology (AFIT) Master’s Thesis, 1995

9
© 2008 Hulett & Associates, LLC
Risk Analysis vs. CPM Scheduling

• Can address questions CPM cannot: The


three promises
1. What is the likelihood of meeting schedule?
2. How much schedule contingency do we need to
provide?
3. Where is there risk to the project schedule?
• Purpose is to help the project manager act
– Early warning of problems
– Location of problems for risk mitigation

10
© 2008 Hulett & Associates, LLC
Pitfalls in Relying on CPM

• CPM network scheduling is deterministic


• Single-point activity durations
• OK only if everything goes according to plan
But there are no “facts” about the future

• CPM durations are really probabilistic


assessments

11
© 2008 Hulett & Associates, LLC
Risk of an Individual Activity

• Simple activity duration estimates are risky

30d

Design Unit 1

12
© 2008 Hulett & Associates, LLC
Common Probability Distributions

Date: 1/13/2003 5:21:27 PM Date: 1/13/2003 5:18:35 PM


Samples: 3000 Samples: 3000
Unique ID: 3 Unique ID: 3
Name: Design Unit Name: Design Unit
0.09 1.0 0.16 1.0
0.08 0.9 0.9
0.14

Cumulative Probability

Cumulative Probability
0.07 0.8 0.8
0.12
0.7 0.7
0.06
Frequency

Frequency
0.6 0.10 0.6
0.05
0.5 0.08 0.5
0.04
0.4 0.06 0.4
0.03 0.3 0.3
0.02 0.04
0.2 0.2
0.01 0.1 0.02 0.1

6/21 7/3 7/15 6/21 7/2 7/15


Completion Date Completion Date
Uniform Distribution Triangular Distribution

Uniform Triangular

13
© 2008 Hulett & Associates, LLC
Common Probability Distributions
(continued)
Date: 7/10/2002 3:19:37 PM Date: 7/10/2002 3:20:30 PM
Samples: 3000 Samples: 3000
Unique ID: 3 Unique ID: 3
Name: Design Unit Name: Design Unit

0.20 1.0 0.22 1.0


0.18 0.9 0.20 0.9

Cumulative Probability

Cumulative Probability
0.16 0.8 0.17 0.8
0.14 0.7 0.7
Frequency

Frequency
0.15
0.12 0.6 0.6
0.13
0.10 0.5 0.5
0.10
0.08 0.4 0.4
0.3 0.08 0.3
0.06
0.04 0.2 0.05 0.2
0.02 0.1 0.03 0.1

6/21 7/3 7/15 6/21 7/1 7/13


Completion Date Completion Date
Normal Distribution Beta Distribution

Normal BETA

14
© 2008 Hulett & Associates, LLC
Comparison of Four Distributions
• The three distributions have different characteristics
• The uniform expresses most risk (mean, Standard deviation)
• Triangular is fairly conservative
• The Beta is the least risky

Comparison of Probability Distributions


(20d, 30d, 45d)
Mean Standard Deviation
Uniform 33d 7.2d
Triangular 32d 5.1d
Normal 33d 4.1d
Beta 31d 3.4d

15
© 2008 Hulett & Associates, LLC
Risk Along a Contiguous Schedule Path

• Path risk is the combination of the risks of its


activities
Design Build Test
Test
Start Finish
Unit Unit Unit
Unit

16
© 2008 Hulett & Associates, LLC
Really Simple Schedule

• This schedule finishes on September 3


– 7-day weeks, like a model changeover, refinery turnaround

ID Task Name Duratio Start Finish May June July August SeptemOctober
1 Project 95 d 6/1 9/3
2 Start 0d 6/1 6/1 6/1
3 Design Unit 30 d 6/1 6/30 6/1 6/30
4 Build Unit 40 d 7/1 8/9 7/1 8/9
5 Test Unit 25 d 8/10 9/3 8/10 9/3
6 Finish 0d 9/3 9/3 9/3

• If we can get into trouble with this simple schedule, we


can get into trouble with real project schedules

17
© 2008 Hulett & Associates, LLC
Add Duration Risk to the Schedule using
Triangular Distributions

ID Task Name Rept ID Min Rdur ML Rdur Max Rdur Curve


1 Project 2 0d 0d 0d 0
2 Start 0 0d 0d 0d 0
3 Design Unit 0 20 d 30 d 45 d 2
4 Build Unit 0 35 d 40 d 50 d 2
5 Test Unit 0 20 d 25 d 50 d 2
6 Finish 0 0d 0d 0d 0

Here we are showing the Data Entry Table from Risk+, a


simulation package that is a MS Project add-in

18
© 2008 Hulett & Associates, LLC
What is a Simulation?

• How do you find total project results? With the


durations specified as probability distributions:
– Cannot add distributions
– Must combine distributions
• Combining distributions using simulation
– Almost all possible combinations of durations
– “Perform” the project many times

19
© 2008 Hulett & Associates, LLC
Monte Carlo Simulation

• Monte Carlo Simulation of the schedule - 50-year old


method
– A simulation is made up of many (thousands) iterations
– Each iteration uses a new set of activity durations chosen at
random from the probability distributions
– Iteration is just a CPM analysis using those durations
– Iterate many times to reflect uncertainty in duration estimates
– Collect the data, make probability distribution of results
• CPM is not even the most likely completion date and may
not be very likely, given risks

20
© 2008 Hulett & Associates, LLC
Monte Carlo Simulation Results for a
Really Simple Schedule
CPM date is not even the most likely – That’s about 9/9

Date: 8/1/2006 9:37:21 AM Completion Std Deviation: 8.94 d


Samples: 5000 95% Confidence Interval: 0.25 d
Unique ID: 2 Each bar represents 3 d
Name: Project

0.14 1.0 Completion Probability Table


0.9
Risk+

Cumulative Probability
0.12
0.8
Prob Date Prob Date software
0.05 8/31 0.55 9/14
0.10 0.7 0.10 9/2 0.60 9/15
Frequency

0.6 0.15 9/4 0.65 9/17


0.08
0.5 0.20 9/6 0.70 9/18
0.06 0.4 0.25 9/7 0.75 9/20
0.3 0.30 9/8 0.80 9/21
0.04
0.35 9/9 0.85 9/23
0.2
0.02 0.40 9/11 0.90 9/26
0.1 0.45 9/12 0.95 9/29
8/19 9/14 10/15
0.50 9/13 1.00 10/15
Completion Date
One-Path Schedule
80% Target is
CPM date is <15% Likely to be met 9/21
21
© 2008 Hulett & Associates, LLC
Risk at Merge Points:
The “Merge Bias”
• Many parallel paths merge in a real schedule
• Finish driven by the latest converging path
• Merge Bias has been understood for 40
years

Design Unit 1 Build Unit 1 Test Unit 1

Start
Finish
Design Unit 2 Build Unit 2 Test Unit 2

22
© 2008 Hulett & Associates, LLC
This Schedule has
Three Parallel Paths

ID Task Name Rept ID Min Rdur ML Rdur Max Rdur Curve May June July August Septemb
1 Project 2 0d 0d 0d 0
2 Start 0 0d 0d 0d 0 6/1
3 Unit 1 1 0d 0d 0d 0
4 Design Unit 0 20 d 30 d 45 d 2 6/1 6/30
5 Build Unit 1 0 35 d 40 d 50 d 2 7/1 8/9
6 Test Unit 1 0 20 d 25 d 50 d 2 8/10 9/3
7 Unit 2 1 0d 0d 0d 0
11 Unit 3 1 0d 0d 0d 0
15 Finish 0 0d 0d 0d 0 9/3

Two paths are collapsed


Each path has exactly the same structure

23
© 2008 Hulett & Associates, LLC
Evidence of the Merge Bias
Date: 8/1/2006 9:37:21 AM
Samples: 5000
Unique ID: 2
Name: Project

0.14 1.0
0.9

Cumulative Probability
0.12
0.8
0.10 0.7

Frequency
0.6
0.08
0.5
0.06 0.4
0.04 0.3
0.2
0.02
0.1

8/19 9/14 10/15


Completion Date

Three Path Schedule One Path Schedule

24
© 2008 Hulett & Associates, LLC
Evidence of Merge Bias (continued)

Three Path Schedule One Path Schedule

25
© 2008 Hulett & Associates, LLC
Graphical Evidence of the Merge Bias
Merge Bias

100%
90%
80%
70%
Cum. Prob.

60%
One Path
50%
Three Path
40%
30% Merge Bias
20%
10%
0%
8/11 8/21 8/31 9/10 9/20 9/30 10/10 10/20
Date

26
© 2008 Hulett & Associates, LLC
What are the Highest Risk Activities?

• Monte Carlo simulation


– Activities on critical path in most iterations
• Path delaying the project may not be the critical
path identified by CPM
• This is “Schedule Critical” not Technically Critical
– Combination of risk and low float (slack)

27
© 2008 Hulett & Associates, LLC
What are the Highest-Risk
Activities?
Units 1 & 3 are Shorter and Not Risk Mitigated
ID Task Name Duration Start Finish May June July August September October
1 Project 95 d 6/1 9/3
2 Start 0d 6/1 6/1 6/1
3 Unit 1 93 d 6/1 9/1
4 Design Unit 1 28 d 6/1 6/28 6/28
5 Build Unit 1 40 d 6/29 8/7 8/7
6 Test Unit 1 25 d 8/8 9/1 9/1
7 Unit 2 95 d 6/1 9/3
8 Design Unit 2 30 d 6/1 6/30 6/30
9 Build Unit 2 40 d 7/1 8/9 8/9
10 Test Unit 2 25 d 8/10 9/3 9/3
11 Unit 3 92 d 6/1 8/31
12 Design Unit 3 30 d 6/1 6/30 6/30
13 Build Unit 3 37 d 7/1 8/6 8/6
14 Test Unit 3 25 d 8/7 8/31 8/31
15 Finish 0d 9/3 9/3 9/3

“Critical” Unit 2 is Identified for Risk Mitigation


28
© 2008 Hulett & Associates, LLC
Risk Critical GANTT Chart
ID Task Name Total Slack Critical % Critical Risk Critica May June July August Septembe October
1 Project 0d Yes 100 Yes 100
2 Start 0d Yes 100 No 6/1
3 Unit 1 2d No 45 Yes 45
4 Design Unit 1 2d No 45 Yes 45
5 Build Unit 1 2d No 45 Yes 45
6 Test Unit 1 2d No 45 Yes 45
7 Unit 2 0d Yes 17 Yes 17
8 Design Unit 2 0d Yes 17 No 17 6/30
9 Build Unit 2 0d Yes 17 No 17 8/9
10 Test Unit 2 0d Yes 17 No 17 9/3
11 Unit 3 3d No 39 Yes 39
12 Design Unit 3 3d No 39 Yes 39
13 Build Unit 3 3d No 39 Yes 39
14 Test Unit 3 3d No 39 Yes 39
15 Finish 0d Yes 100 No 9/3

The “Critical Path” has been managed and is only 17% likely to delay the
project. Now we should mitigate risk in Units 1 & 3
The Risk GANTT chart in Risk+

29
© 2008 Hulett & Associates, LLC
Using the Risk Register in
Project Schedule Risk Analysis
with Monte Carlo Simulation

David T. Hulett and Waylon T. Whitehead


Hulett & Associates, LLC (USA)

2nd Annual Oil & Gas


Project Risk Management Conference
Kuala Lumpur, Malaysia
29th & 30th October, 2007

30
© 2008 Hulett & Associates, LLC
Agenda

• Risk Register identifies high-priority risks


• Explain “Risk Factors” approach and module in
Pertmaster
• Compute Monte Carlo simulation results
• Estimate sensitivity and net effect of key risks
• Apply Risk Factors to simple refinery schedule
• Collecting risk data for the model
• How results are used to manage project risk

31
© 2008 Hulett & Associates, LLC
Driving Risk Quantitative Schedule
Risk by Register Risks
• Typical schedule risk analysis starts with the
activity that is impacted by risks
– Estimates the 3-point estimate for optimistic, most
likely and pessimistic duration
– Creates a probability distribution for activity duration
– Performs Monte Carlo simulation
• Which activities have the most overall schedule
risk? These questions are typically answered by:
– Sensitivity
– Criticality
– Cruciality (combination of both)
32
© 2008 Hulett & Associates, LLC
Some Problems with Traditional
Approach
• Can tell which activities are crucial, but not
which risks are driving
• Makes poor use of the Risk Register that is
usually available
• Cannot decompose the overall schedule risk into
its components by risk driver
– Ability to assign the risk to its specific risk drivers
helps with risk mitigation

33
© 2008 Hulett & Associates, LLC
We Propose a Risk Driver Approach:
Focus on Risks, not Activity Durations
• Drive the schedule risk by the risks already analyzed
in the Risk Register
• For each risk, specify:
– Probability it will occur
– Impact on time if it does
– Activities it will affect
• Starting with the risks themselves gives us benefits
– Links qualitative analysis to the quantitative analysis
– Estimates the impact of specific risks for prioritized
mitigation purposes

34
© 2008 Hulett & Associates, LLC
Simple Example of Risk Register Risks

• Use the Risk Factors module in Pertmaster Risk


Expert v. 8
• Collect probability and impact data on risks
• Load the risks
• Assign risks to schedule activities

35
© 2008 Hulett & Associates, LLC
Risk Factors Mechanics

• The risk factor drives the uncertainty in the


duration of activities it is assigned to
– E.g., new technology may mean that design activities’
duration is optimistically the base, most likely is +10%
and pessimistic is + 30% of the base estimate
– E.G., productivity uncertainty means duration of
construction may be -10% or +15% from our base
• The risk factor is assigned a probability of
occurring
– E.g., technology labor productivity leads to a result
different from the Plan only 50% of the time

36
© 2008 Hulett & Associates, LLC
Risk Factor
Applied to a 100 day Task (1)

0 0 1 0 - C o n s tr u c tio n : D u r a tio n
1 0 0% 11 5
2 50
9 5 % 1 11

9 0 % 1 09

8 5 % 1 08

Here the 2 00
8 0 % 1 06

7 5 % 1 05

Ranges are 7 0 % 1 04

6 5 % 1 04

based on

Cumulative Frequency
6 0 % 1 03
1 50

deviations + 5 5 % 1 02
Hits

5 0 % 1 01

and – from 4 5 % 1 01

4 0 % 1 00
1 00

the Plan. 35% 99

30% 99

Probability 25% 98

is 100% 50 20% 97

15% 96

10% 95

5 % 94

0 0 % 90
90 95 10 0 1 05 1 10 11 5
D istrib u tio n (sta rt o f in te rva l)

Base Duration 37
© 2008 Hulett & Associates, LLC
Risk Factor
Applied to a 100-day Task (2)

0 0 4 0 - T e c h n o lo g y D e s ig n : D u r a tio n
100% 130

95% 125
200
90% 122

85% 121
180

Here the 80% 119

75% 118
160

Plan is the 70% 117

140 65% 116


Optimistic

Cumulative Frequency
60% 115

Value. 120 55% 114


Hits

50% 113

Probability 100
45% 112

is 100% 80
40% 111

35% 110

30% 109
60
25% 109

20% 108
40
15% 107

20 10% 105

5% 104

0 0% 100
100 110 120 130
D istrib u tio n (sta rt o f in te rv a l)

Base Duration 38
© 2008 Hulett & Associates, LLC
Assigning a Probability Less than 100%

• The essence of “risk” is the uncertainty


– Uncertainty of its occurrence, specified by a
probability
– Uncertainty of its impact, specified by a range of
durations
• If the risk may or may not occur, we specify the
probability that it will occur
– The risk “fires” and affects the activities it is assigned
to on X% of the iterations, chosen at random
– On (1 – X)% of the iterations, the plan value is used

39
© 2008 Hulett & Associates, LLC
Assigning a Probability less than 100%

0010 - Construction : Duration 0040 - Technology Design : Duration


100% 115 100% 130

Spike 95% 107 95% 123

contains
90% 103 1200 90% 120 Spike
85% 101 85% 118

70% of
2000
80% 100 80% 116 contains
the
75% 100

70% 100
1000 75% 114

70% 113
40% of
probability
65% 100 65% 111
the

Cumulative Frequency
Cumulative Frequency
1500
60% 100 800 60% 110

55% 100 55% 109 probability

Hits
Hits

50% 100 50% 107

45% 100 600 45% 105

1000 40% 100


40% 100

35% 100 35% 100

30% 100 400 30% 100

25% 100 25% 100

500 20% 100 20% 100

15% 100 200 15% 100

10% 99 10% 100

5% 97 5% 100

0 0% 100
0 0% 91
100 110 120 130
95 100 105 110 115
Distribution (start of interval) Distribution (start of interval)

40
© 2008 Hulett & Associates, LLC
Assigning
More than One Risk to an Activity
• If more than one risk is acting on an activity, the
resulting ranges are the multiplication of the
percentages
– Risk 1 has 90%, 100% and 115%
– Risk 2 has 100%, 110% and 130%
– The resulting risk has ranges of, approximately:
• Optimistic: 90% (.9 x 1.0)
• Most Likely:110% (1.0 x 1.1)
• Pessimistic:150% (1.15 x 1.3)

41
© 2008 Hulett & Associates, LLC
Two Risks affect One Activity
using Factors

0040 - T echnology Design : Duration


100% 144

95% 130

90% 127
140
85% 124

80% 123

120 75% 121

70% 119

Range 100
65% 118

Cumulative Frequency
60% 117
from 90 to 55% 116
Hits

150 days, 80 50% 115

45% 114

Peak about 60
40% 113

35% 111
113 days 30% 110

40 25% 109

20% 108

15% 106
20
10% 104

5% 102

0 0% 93
100 110 120 130 140
Distribution (sta rt of inte rva l)

42
© 2008 Hulett & Associates, LLC
Two Risks with Less than 100%
Probability Affecting one Activity

0040 - T echnology Design : Duration


1100 100% 144

95% 123

The spike at 1000 90% 119

85% 116

100 days 900


80% 113

represents (1) 800


75% 111

70% 110

the likelihood 700


65% 108

Cumulative Frequency
60% 106

that neither risk 600 55% 104


Hits

50% 102
occurs and (2) 500 45% 101

the chance that 400


40% 100

35% 100

100 days is 300


30% 100

25% 100
picked when 200
20% 100

one or both 15% 100

10% 99
100

occur 5% 97

0 0% 91
100 110 120 130 140
Distribution (sta rt of inte rva l)

43
© 2008 Hulett & Associates, LLC
Sensitivity to the Risk Factors, NOT to the
Activity Durations that are Affected

Risk #1 has
larger
percentage
extremes but
Risk #2 has
a higher
probability.

44
© 2008 Hulett & Associates, LLC
Simple Refinery Schedule

Software used: Pertmaster v. 8.0

45
© 2008 Hulett & Associates, LLC
Two Types of Risk

• Estimating Error based on the maturity of the


information, called “ambiguity”
– Used Quick Risk of -5% and +10%
• Discrete risk events derived from Risk Register
– Summarized from detailed Risk Register
– These have a probability of occurring and an impact
on specific activities if they do
– Parallel to their Risk Register information, which is
used in data collection

46
© 2008 Hulett & Associates, LLC
Schedule Estimating Error Only

Estimating Error: Optimistic -5% and Pessimistic +10%

47
© 2008 Hulett & Associates, LLC
Results with Estimating Error Only
Refinery C onstruction
E ntire P lan : Finish D ate
100% 18/A ug/14

500 95% 20/Jun/14

90% 09/Jun/14
450 85% 02/Jun/14

80% 27/May /14


Deterministic:
400
75% 21/May /14 14MAR14 is 5%
70% 15/May /14
350
65% 12/May /14
P-80: 27MAY14

Cumulative Frequency
60% 08/May /14
300
55% 05/May /14
Hits

50% 30/A pr/14


250
45% 25/A pr/14

40% 22/A pr/14


200
35% 18/A pr/14

30% 15/A pr/14


150
25% 10/A pr/14

100 20% 07/A pr/14

15% 31/Mar/14

50 10% 24/Mar/14

5% 14/Mar/14

0 0% 24/Jan/14
27/Feb/14 18/A pr/14 07/Jun/14 27/Jul/14
Distribution (sta rt of inte rva l)

48
© 2008 Hulett & Associates, LLC
Risk Analysis on Refinery Project
Risk Register Risks using “Risk Factors”

• Seven risk factors have been identified and


quantified.
• Each Risk has 0.0 < Probability < 1.0
• Some have optimistic ranges possible, others
are pure threats
49
© 2008 Hulett & Associates, LLC
Results Adding
Risk Factors to the Estimating Error
Refin e ry C o n stru c tio n
E n tire P lan : F in ish D ate
100% 02/Dec /15

700 95% 09/A pr/15

90% 03/Mar/15

85% 09/Feb/15
600
80% 19/Jan/15

75% 30/Dec /14 P-80 is


500
70% 17/Dec /14

65% 02/Dec /14


19Jan15,

Cumulative Frequency
60% 18/Nov /14 compared to
400 55% 05/Nov /14
the schedule
Hits

50% 23/Oc t/14

300
45% 10/Oc t/14
of 14MAR14
40% 30/Sep/14

35% 16/Sep/14

30% 02/Sep/14
200
25% 20/A ug/14

20% 04/A ug/14

15% 15/Jul/14
100
10% 20/Jun/14

5% 16/May /14

0 0% 11/Feb/14
18/A pr/14 04/Nov /14 23/May /15 09/Dec /15
Distribution (sta rt of inte rva l)

50
© 2008 Hulett & Associates, LLC
Results from the Simulation
Summary Results from the Factors Risk Analysis
Base Schedule
Percentile Date P-5 P-95 Months
Deterministic 14-Mar-14 N/A
Background Risks Only
P-80 27-May-14 14-Mar-14 20-Jun-14 3.2
Contingency Months 2.4
All Background and Risk Register Risks
P-80 19-Jan-15 16-May-14 9-Apr-15 10.8
Contingency Months 10.2

The all-in risk results show a wide range of 10.8 months and a contingency of
10.2 months or 15% in terms of calendar days on a 69-month project

51
© 2008 Hulett & Associates, LLC
Risk Factor Tornado Chart
from All-In Simulation

52
© 2008 Hulett & Associates, LLC
Contribution of Each Risk to the
Contingency in Order of Mitigation Priority
Priority Risks to Mitigate, Contribution to Savings
P-80 Savings from Total Mitigation
All Risks In Date 19-Jan-15 Days Saved Percent of Total
Specific Risks, Taken Out in Best Order (differs from the Tornado Chart)
LLE Supplier Risk 11-Nov-14 69 22%
Construction Supervision Risk 26-Sep-14 46 15%
Suppliers Busy Risk 22-Jul-14 66 21%
Construction Logistics Risk 1-Jul-14 21 7%
Financing Risk 17-Jun-14 14 5%
Vendor Rep Risk 5-Jun-14 12 4%
Design Productivity Risk 27-May-14 9 3%
Background Risk 14-Mar-14 74 24%
Total Contingency Days 14-MAR-14 to 19-JAN-15 311 100%

53
© 2008 Hulett & Associates, LLC
Project Cost Risk Analysis:
The Risk Driver Approach
Prioritizing Project Risks
and Evaluating Risk Responses
David T. Hulett, Ph.D.
Keith Hornbacher, MBA
Waylon T. Whitehead
Hulett & Associates, LLC
Los Angeles, CA USA
www.projectrisk.com

54
© 2008 Hulett & Associates, LLC
Outline
• Some limitations of the traditional 3-point
estimate quantitative risk analysis
• Introducing the Risk Driver Method to cost risk
analysis
– Method illustrated
– Data collection considerations
– Some benefits of the Risk Driver approach
– Simple refinery construction example

55
© 2008 Hulett & Associates, LLC
Risk Prioritization – New approach

• More complete and powerful than the standard


qualitative risk analysis using the Probability and
Impact approach
• Compute the effect of individual risks on the
cost, then sort risks by priority
• Risks are prioritized as they affect the cost
through simulating the model of the project
• Assists risk mitigation decisions

56
© 2008 Hulett & Associates, LLC
Benefits of the
Risk Driver Approach (1)
• Focus on the risks, not their impact on line item
costs
• Provide management with prioritized list of risks,
not activities, that need mitigation
• Interviews are conducted at the level of risk
where people think of risk, not line items. They
are more intuitive for all parties and simpler to
verify and validate
• Interviews are generally shorter than when using
traditional 3-point estimating

57
© 2008 Hulett & Associates, LLC
Benefits of the
Risk Driver Approach (2)
• Correlations occur often in cost risk
– If steel prices increase, the prices for structural steel,
pipe and vessels will increase together
– If labor productivity declines, direct and indirect labor
will cost more, together
• Traditionally we have to estimate correlation
coefficients – not easy because data are not
available and the concept is not familiar to most
people
• Risk Driver method models how correlations
come about due to risks affecting more than one
line item. No more guessing at correlation
coefficients.
58
© 2008 Hulett & Associates, LLC
Introducing the
Risk Driver Method
• Start with the Risk Register risks – the linkage to
the qualitative risk analysis exercise is obvious
and direct
• Characterize the risks by their probability as well
as impact, not just impact range as traditional
analysis
• Probability and impact are the TWO dimensions
of a risk

59
© 2008 Hulett & Associates, LLC
Risk Driver Methodology

• Identify risks to be included from Risk Register


• Quantify risks’ probability and impact range
– The impact is a multiplicative factor
– The line item costs will be multiplied by the factors
• Assign risks to cost line items
– Risks can affect several line items
– A cost line item can be affected by several risks
• Run Monte Carlo simulation for overall cost risk
• Prioritize risks for further mitigation
60
© 2008 Hulett & Associates, LLC
Identify Risk Drivers
Use the Risk Register Directly
Risk Register - Model Input Data
ID Risk Name
R.1 Contracting Strategy (LSTK) may cause bidders to bid high
R.2 Design Changes may be greater than anticipated
R.3 Equipment Suppliers may be busy
R.4 Quality Key Staff JV / PMT may not be available
R.5 Number of Bidders may be limited due to availability of other work
R.6 Integration Management of detailed engineering may be inadequate
R.7 Labor Rate may differ from expectations
R.8 Construction Labor Productivity may differ from expectations
R.9 Bulk Material Cost may differ from expectations
R.10 Construction Management Staff may be lacking in experience

61
© 2008 Hulett & Associates, LLC
Discovery of Risk Factors

• From exploratory interviews w/ all project


stakeholders to arrive at their general ideas
about what the risks are
• From the project risk register
• From general knowledge about conditions that
might affect the project
• Risks should be independent of each other.
Related risks may be consolidated

62
© 2008 Hulett & Associates, LLC
Detailed Interviews for
Information about Risk Factors
• Using the arrived at Risks, conduct interviews to
assess their likelihood and impact
• Be alert to the discussion of new risks during the
interviews
• The use of pre-read information can assist with
the amount of information that can be covered in
a time limited interview

63
© 2008 Hulett & Associates, LLC
Applying Risk Factors

• Cover what type of cost line items the risk factor


will apply to
• Be alert to the need for applying the same risk
factor with more than one range for different
types of costs
• Be alert to the need to divide cost lines in order
to discretely apply Risk Factors

64
© 2008 Hulett & Associates, LLC
Use Trigen Function to Correct for Narrow
Ranges from Interviews

Design Changes
3-point estimate is
.95, 1.05, 1.15
Trigen makes it
.87, 1.05, 1.23

Using @RISK from


Palisade Corporation

65
© 2008 Hulett & Associates, LLC
A 100% Risk Factor Applied to a
Cost Line Item of $1 million

A Cost of 1.00 million impacted


by a 100% Risk Factor
TriGen (.95, 1.05, 1.15, 10, 90)

66
© 2008 Hulett & Associates, LLC
A 40% Risk Factor Applied to
Cost Line Item of $1 million
A Cost of 1.00 million impacted
by a 40% Risk Factor Trigen
(.95, 1.05, 1.15, 10, 90)
The spike has 60% of the
probability, indicating that the
risk occurs only in 40% of the
iterations

67
© 2008 Hulett & Associates, LLC
A Cost of $1.0 million
Affected by Two 100% Risk Drivers
Affected by Two 100%
Trigen (10,90) Risks
(1) .95, 1.05. 1.15
(2) .90, 1.00, 1.05

68
© 2008 Hulett & Associates, LLC
A Cost of $1.0 million
Affected by Two 50% Risk Drivers
Affected by Two 50%
Trigen (10,90) Risks
(1) .95, 1.05. 1.15
(2) .90, 1.00, 1.05

69
© 2008 Hulett & Associates, LLC
Risk Factors Model How Correlation Occurs
Coefficients are Calculated (1)
Risk #1
P = 50%, Factors
.95, 1.05, 1.15

Cost Item A Cost Item B

Cost Items A and B


Correlation is
Calculated to be 100%

70
© 2008 Hulett & Associates, LLC
Risk Factors Model How Correlation Occurs
Coefficients are Calculated (2)
Risk #2 Risk #1 Risk #3
P = 25%, Factors P = 50%, Factors P = 45%, Factors
.8, .95, 1.05 .95, 1.05, 1.15 1.0, 1.1, 1.2

Cost Item A Cost Item B

Cost Items A and B


Correlation is
Calculated to be 48%
Correlation is modeled as it is caused in the project
Correlation coefficients are generated, not guessed
71
© 2008 Hulett & Associates, LLC
Simplified Cost Model
of a Refinery Project (1)
Refinery Construction Project Baseline Estimate (1)
Cost Category Labor Equipment Total
Direct Field Costs ($ millions)
Long Lead Equipment (LLE) 15 330 345
Equipment 30 1,200 1,230
Materials 288 1,935 2,223
Total Direct Field Costs 333 3,465 3,798
Indirect Field Costs
Supervision 360 0 360
Time-Related Overhead 315 0 315
Total Indirect Field Costs 675 0 675
Total Direct & Indirect Costs 1,008 3,465 4,473

72
© 2008 Hulett & Associates, LLC
Simplified Cost Model
of a Refinery Project (2)
Refinery Construction Project Baseline Estimate (2)

Labor Equipment Total

Cost Category ($ millions)


Construction Management 630 630
Material Related 180 540 720
Home Office Engineering Staff 540 540
Overhead & Fees 560
Total Contractor Related 2,358 4,005 6,923
Owner-Related
Project Management Team 450 0 450
Materials 0 400 400
Total Owner-Related 450 400 850
TOTAL BASE ESTIMATE 7,773

73
© 2008 Hulett & Associates, LLC
Risk Factors
Probability and Impact Ranges
Risk Drivers and their Properties

3-Point Estimate of RiskFactor


ID Name Prob.
Minimum ML Maximum
R.1 Contracting Strategy 40% 0.90 1.10 1.25
R.2 Design Changes 60% 0.95 1.05 1.20
R.3 Equipment Suppliers Busy 45% 1.00 1.05 1.30
R.4 Availability of Key Staff JV / PMT 40% 0.95 1.00 1.20
R.5 Number of Bidders 40% 0.95 1.00 1.50
R.6 Integration Management 40% 1.00 1.05 1.15
R.7 Labor Rate 50% 0.90 1.00 1.20
R.8 Construction Labor Productivity 45% 1.00 1.10 1.30
R.9 Bulk Material Cost 40% 0.90 1.05 1.20
R.10 Construction Management Staff 70% 1.00 1.05 1.15

74
© 2008 Hulett & Associates, LLC
Assign Risk Drivers
to Cost Elements
Cost Category Risks

Contract Design Equip. JV/PMT # of Integ. Labor Labor Bulks


Direct Field Costs Strategy Changes Supplier Staff Bidders Mgt. Rate Prod. Cost
CM Staff

Long Lead Equipment


X X X
(LLE)
Equipment X X X X
Materials X X X X
Total Direct Field Costs
Direct & Indirect Labor
X X X
Costs
Construction
X
Management
Material Related X X
Home Office
X X X
Engineering Staff
Overhead & Fees X x
Owner-Related
Project Management
X
Team
Materials X
75
© 2008 Hulett & Associates, LLC
Cost Risk Analysis Results (1)

Most Likely cost is


about $8 billion

76
© 2008 Hulett & Associates, LLC
Cost Risk Analysis Results (2)
Base Cost is 9.3%
likely

80th percentile is
$9.53 million for a
$1.76 million (23%)
Contingency
Reserve

77
© 2008 Hulett & Associates, LLC
Cost Risk Analysis Results (3)

Percentile $ mill.  %

10% 7,793  0%

20% 7,999  3%

30% 8,183  5%

40% 8,383  8%

50% 8,611  11%

60% 8,866  14%

70% 9,168  18%

80% 9,529  23%

90% 10,118  30%

78
© 2008 Hulett & Associates, LLC
Risk Sensitivity –
Beginning of Risk Prioritization

These are Risks, not


cost line items

79
© 2008 Hulett & Associates, LLC
Risk Drivers Listed in Priority Order
All Risks Included 9.53
Improvement if Mitigated
Risks $ Bill. % Savings
Number of Bidders 0.42 4%
Equipment Suppliers Busy 0.41 4%
Contracting Strategy 0.30 3%
Design Changes 0.14 1%
Bulk Material Cost 0.12 1%
Construction Labor Productivity 0.10 1%
Availability of Key Staff JV / PMT 0.07 1%
Labor Rate 0.04 0%
Construction Management Staff 0.02 0%
Integration Management 0.01 0%

These risks are prioritized as if they could be completely mitigated. That is


not possible, but it indicates the priority for risk mitigation actions.
80
© 2008 Hulett & Associates, LLC
Partial Risk Mitigation (1)
• The number of bidders in today’s heated oil and
gas building environment is problematic and
deemed as an important cost risk driver
• With few bidders we expect contractors to feel
freer to include high levels of risk premium and
profit into their bids
• A similar observation can be made about
procurement prices for equipment suppliers that
are busy

81
© 2008 Hulett & Associates, LLC
Partial Risk Mitigation (2)

•Suppose that we were willing to allow bidders to


form Joint Ventures or funding their bidding
expenses?. What could happen?

3-Point Estimate of RiskFactor


Prob.
Example of Risk Mitigation Minimum ML Maximum
Before Risk Mitigation
Number of Bidders 40% 0.95 1.00 1.50
After Risk Mitigation
Number of Bidders 20% 0.90 1.00 1.25

82
© 2008 Hulett & Associates, LLC
Risk after Mitigating
Number of Bidders Risk

83
© 2008 Hulett & Associates, LLC
Number of Bidders is Now
Lower on the Priority List

84
© 2008 Hulett & Associates, LLC
Impact of Partially Mitigating the Number of
Bidders Risk
No Mitigation Partial Mitigation
Percentile
$ mill. 
10% 7,793  7,746 
20% 7,999  7,920 
30% 8,183  8,083 
40% 8,383  8,248 
50% 8,611  8,424 
60% 8,866  8,633 
70% 9,168  8,869 
80% 9,529  9,185 
90% 10,118  9,637 

Partially mitigating Number of Bidders Risk


improves the risk at the P-80 level
85
© 2008 Hulett & Associates, LLC
Summary – Quantitative Risk Analysis Results
and Risk Prioritization using Risk Drivers
• Project risks are characterized by their:
– Probability of occurring
– Impact range as a multiplicative factor
– Cost line items they impact if they occur
• Monte Carlo simulation develops:
– Probability of achieving the cost target (without
contingency)
– Contingency reserve of cost needed to satisfy the
organization’s appetite for risk
• Risks can be taken out of the simulation one at a
time and their marginal impact (through the cost
model) calibrated:
– Risk prioritization is based on this analysis
– Partial risk mitigation can be studied for benefit/cost
analysis

86
© 2008 Hulett & Associates, LLC
QUANTITATIVE RISK ANALYSIS
TRADITIONAL AND
NEW RISK DRIVERS APPROACH TO
SCHEDULE AND COST RISK ANALYSIS

AUGUST 7, 2008

DAVID T. HULETT, PH.D.


HULETT & ASSOCIATES, LLC
LOS ANGELES, CA USA

87
© 2008 Hulett & Associates, LLC

S-ar putea să vă placă și