Sunteți pe pagina 1din 11

Part Number Part Name A Leadtime 1 Lot size L4L

Period 0 1 2 3 4 5 6
Gross Requirements 20 20 60
Scheduled receipts
Proj. On Hand Inv. 20 20 0 0 0 0 0
Net Requirements 0 20 0 0 0 60
Planned Order receipts 0 20 60
Planned order Release 20 60

Part Number Part Name B Leadtime 1 Lot size


Period 0 1 2 3 4 5 6
Gross Requirements x 120
Scheduled receipts 30
Proj. On Hand Inv. 50 50 40 40 40 40 0
Net Requirements 0 80
Planned Order receipts 80
Planned order Release 80 100

Part Number Part Name C Leadtime 2 Lot size L4L


Period 0 1 2 3 4 5 6
Gross Requirements 60 180
Scheduled receipts
Proj. On Hand Inv. 60 60 0 0 0 0 0
Net Requirements 0 180
Planned Order receipts 180
Planned order Release 180 150

Part Number Part Name F Leadtime 2 Lot size 100


Period 0 1 2 3 4 5 6
Gross Requirements 360 80 300 100
Scheduled receipts
Proj. On Hand Inv. 0 0 0 0 40 60 60
Net Requirements 360 40 240 40
Planned Order receipts 360 100 100 100
Planned order Release 400 100 300 100

Part Number Part Name D Leadtime 1 Lot size 50


Period 0 1 2 3 4 5 6
Gross Requirements 180 150
Scheduled receipts
On Hand 25 25 25 25 45 45
Net Requirements 155 105
Planned Order receipts 155 105
Planned order Release 200 150

Part Number Part Name E Leadtime 2 Lot size 100


Period 0 1 2 3 4 5 6
Gross Requirements 180 150
Scheduled receipts
Proj. On Hand Inv. 0 20 20
Net Requirements 180 130
Planned Order receipts 180 130
Planned order Release 200 200
7 8
50

0 0
0 50
50
50

7 8
100

0
100

7 8
100

0
100
150

7 8

7 8

7 8
Each Unit of A is composed of  2  units of B and 3 units of C..
Each B is composed of One unit of F,
C is made of one unit of D , one unit of E  and two units of F
Items A, B, c, and D have 20, 50, 60, and 25 units of on hand inventory. Items A, B & C use lot-for-lot .
while D, E &F require multiples of 50, 100 and 100 respectively, to be purchased
B has scheduled receipt of 30 in period 1
Leadtimes are one period for item A, B and D, and two periods for items C, E &F.
Gross Requirements for A are 20 units in period 1, 20 units in period 2, 60 units in period 6, and 50 unit
Item - Ladder back chair ass
week 0 1 2 3 4 5 6 7 8
Gross Requirements 50 133 67 83 133
Scheduled Receipts
Projected On-hand Inv.
Net Requirements 60 133 67 83 133
Planned receipts 60 133 67 83 133
Planned order Release 50 133 67 83 133 34

Item : Ladder back Subass


week 0 1 2 3 4 5 6 7 8
Gross Requirements 50 133 67 83 133 34
Scheduled receipts
Projected On-hand Inv.
Net Requirements 50 133 67 83 133 34
Planned receipts 150 150 150 150
Planned order Release 300 150 150
9 10 11 12
34 117

34 117
34 117
117

9 10 11 12
117

117
150
150
Part Number Part Name A Leadtime 1 Lot size L4L
Period 0 1 2 3 4 5 6
Gross Requirements 20 20 0 0 0 60
Scheduled receipts 0 0 0 0 0 0
Proj. On Hand Inv. 20 0 0 0 0 0 0
Net Requirements 0 20 0 0 0 60
Planned Order receipts 0 20 0 0 0 60
Planned order Release 20 0 0 60 0

Part Number Part Name B Leadtime 1 Lot size


Period 0 1 2 3 4 5 6
Gross Requirements 40 0 0 0 0 120
Scheduled receipts 0 0 0 0 0 0
Proj. On Hand Inv. 50 10 10 10 10 10 0
Net Requirements 0 0 0 0 0 110
Planned Order receipts 0 0 0 0 0 110
Planned order Release 0 0 0 0 110 0

Part Number Part Name C Leadtime 2 Lot size L4L


Period 0 1 2 3 4 5 6
Gross Requirements 60 0 0 0 180 0
Scheduled receipts 0 0 0 0 0 0
Proj. On Hand Inv. 60 0 0 0 0 0 0
Net Requirements 0 180
Planned Order receipts 0 180
Planned order Release 0 180 150

Part Number Part Name F Leadtime 2 Lot size 100


Period 0 1 2 3 4 5 6
Gross Requirements 360 0 410 0
Scheduled receipts
Proj. On Hand Inv. 0 40 0 30
Net Requirements 360 370
Planned Order receipts 400 400
Planned order Release 400 400 100

Part Number Part Name D Leadtime 1 Lot size 50


Period 0 1 2 3 4 5 6
Gross Requirements 0 0 180 0 150 0
Scheduled receipts
On Hand 25 25 25 45 45
Net Requirements 155 105
Planned Order receipts 200 150
Planned order Release 200 150
Part Number Part Name E Leadtime 2 Lot size 100
Period 0 1 2 3 4 5 6
Gross Requirements 0 0 180 0 150 0
Scheduled receipts
Proj. On Hand Inv. 20 70
Net Requirements 180 130
Planned Order receipts 200 200
Planned order Release 200 200
Total
7 8
0 50
0 0
0 0
0 50
0 50
50

7 8
0 100
0 0
0 0
0 100
0 100
100 0

7 8
150 0
0 0
0 0
150
150

7 8
100 0

0 30
70
100

7 8
0 0

45 45
7 8
0 0

70 70
Each Unit of A is composed of  2  units of B and 3 units of C..
Each B is composed of One unit of F,
C is made of one unit of D , one unit of E  and two units of F
Items A, B, c, and D have 20, 50, 60, and 25 units of on hand inventory. Items A, B & C use lot-for-lot . .
while D, E &F require multiples of 50, 100 and 100 respectively, to be purchased
B has scheduled receipt of 30 in period 1
Leadtimes are one period for item A, B and D, and two periods for items C, E &F.
Gross Requirements for A are 20 units in period 1, 20 units in period 2, 60 units in period 6, and 50 units in