CORAL ALLIANCE SD BHD

SITE SURVEY FORM (INSULATION)


Client FPSO VENTURE SDN BHD
Location PUTERI DULANG
This site survey form is to be used to record the client requirement, quantity of works, current condition and plant on which the job will be perform.

No. Line No Pipe Thk (mm) Length Elbow (ea) Tee (ea) Flange Valve (ea) Remarks
Size (m) (ea)

1 LNG TANK NO 2 (S) 50 1 3


2 Z-24-101 A 100 2
3 Z-24-101 B 100 2
4 Z-24-101 C 100 2
5 Z-24-101 D 100 2
6 S-15-101 B 100 3 2
7 S-75-105 A 50 1 1
8 S-75-105 B 50 1 1
9 V-22-101 150 1
10 S-75-106 A 50 1 1
11 S-75-106 B 50 1 1
12 24''-PG-27-013-13451X-IC 24'' 150 7 1
Prepared By Approved By

Name : Name :

Signature : Signature :

Date : Date :
INSULATION SURVEY REPORT 2019
Site Survey Inspection Findings

LOCATION FPSO PUTERI DULANG DATE

23PT-1412 23PT-1416

22QT-010 Z-24-101 A
Z-24-101 B Z-24-101 C

Prepared By MUHAMAD FIKRI Inspetion date 10/12/2018

PENINSULAR MALAYSIA ASSET INSULATION SURVEY 2018


Inspection Findings

LOCATION PFLNG 1 DATE

Z-24-101 D S-15-101 B
S-15-101 B S-15-101 B

S-15-101 B S-15-101 B

Prepared By MUHAMAD FIKRI Inspetion date 10/12/2018

PENINSULAR MALAYSIA ASSET INSULATION SURVEY 2018


Inspection Findings

LOCATION PFLNG 1 DATE


S-75-105 A&B

V-22-101

S-75-106 A & B 6"-LNG-27-002-13451E-IC

24''-PG-27-013-13451X-IC 6"-LNG-27-002-13451E-IC

Prepared By MUHAMAD FIKRI Inspetion date 10/12/2018


PENINSULAR MALAYSIA ASSET INSULATION
SURVEY 2018
Inspection Findings by Inspector

LOCATION PFLNG 1 DATE

3''-LNG-27-005-13451X-IC K-30-101

K-30-101 21-UZV-012
21-HV-932 42''-RN-21-051-31011X

Prepared By MUHAMAD FIKRI Inspetion date 10/12/2018

PENINSULAR MALAYSIA ASSET INSULATION SURVEY 2018


Inspection Findings

LOCATION PFLNG 1 DATE

12''-LNG-23-224-13451E-IC 10''-LNG-23-240-13451E-IC
10''-LNG-23-240-13451E C-16-101

C-16-101 C-16-101

Prepared By MUHAMAD FIKRI Inspetion date 10/12/2018


PENINSULAR MALAYSIA ASSET INSULATION SURVEY 2018
Inspection Findings

LOCATION PFLNG 1 DATE

C-16-101 C-16-101
C-16-101 C-16-101

V-60-101 V-60-101

Prepared By MUHAMAD FIKRI Inspetion date 10/12/2018


PENINSULAR MALAYSIA ASSET INSULATION SURVEY 2018
Inspection Findings

LOCATION PFLNG 1 DATE


10''-PG-18-007-61492X-IH 10''-PG-18-007-61492X-IH

10''-AM-16-009-310335X-IH 10''-PG-30-005-11602X-IH

10''-PG-30-005-11602X-IH 6''-PL-30-031-11432X-IH

Prepared By MUHAMAD FIKRI Inspetion date 10/12/2018


PENINSULAR MALAYSIA ASSET INSULATION SURVEY 2018
Inspection Findings

LOCATION PFLNG 1 DATE


6''-PL-30-031-11432X-IH
12''-AM-16-001-61007-IH

12''-AM-16-001-61007-IH

Prepared By MUHAMAD FIKRI Inspetion date 10/12/2018


10/12/2018
2/2018

10/12/2018
2/2018

10/12/2018
2/2018
10/12/2018
2/2018

10/12/2018
2/2018

10/12/2018
2/2018

10/12/2018
2/2018

10/12/2018
2/2018