Sunteți pe pagina 1din 14

PAPERS Linking Policies to Projects: The Key to

Identifying the Right Public Investment


Projects
Asmamaw Tadege Shiferaw, Norwegian University of Science and Technology, Department
of Civil and Transport Engineering, Trondheim, Norway
Ole Jonny Klakegg, Norwegian University of Science and Technology, Department of Civil
and Transport Engineering, Trondheim, Norway

ABSTRACT ■ INTRODUCTION ■
olicies determine the environment and the framework within which
This article reviews the merits of project gover-
nance in linking policies to projects and focuses
on public investment projects in African coun-
tries. In this region, every year, huge sums of
money are spent on public investment projects.
It is relevant to ask whether the objectives of
P development takes place (Cusworth & Franks, 1993). Projects are pol-
icy implementation tools, and one means by which policies are put in
practice. Projects are designed in order to provide economic, institu-
tional, or social development by using limited available resources. At the
strategic level, policies should be aligned with public needs and priorities.
Objectives of public projects should be aligned with policies. In other words,
these projects are set and fulfilled according to
the objectives of projects should be aligned with the important priorities in
the needs and priorities of the target group, or
the society and the needs of the users (Samset, 2003). Public investment
whether they are consistent with the develop-
projects should be subjected to questioning along this line, and decision
ment policies of governments in the target
makers should examine the relationship between projects, public needs, and
countries. After examining different conceptual
policies before making decisions.
and contextual literatures, the authors provide
Often, public investment projects are criticized and judged unsuccess-
a project governance model to link policies to
ful when seen from the society perspective. Many public investment proj-
projects, a checklist for good project gover-
ects are implemented without examining the public needs and priorities.
nance, and an outline of factors that could
Some projects are implemented with several billions of dollars but do not
affect the project governance implementation.
give a sustainable benefit to the society. Some projects are implemented
even though they have negative impacts on the environment, society, or
KEYWORDS: linking; policy; project gover-
economy. Generally, trying to implement too many projects by too few peo-
nance system; right projects
ple is a common problem (Englund & Graham, 1999). A study conducted by
the UK Office of Government Commerce (OGC) indicated that lack of clear
links between the project and the organization’s key strategic priorities is
one of the top causes of unsuccessful projects (OGC, 2005). We believe the
same is true in African countries. Implementing several public investment
projects by only a very few decision makers, with no apparent link to the
policies and strategies of countries, is a common problem in many African
countries.
This article aims to discuss the project governance system as a linkage
between policies and projects to improve success in the public investment
projects in developing countries. The article looks at public investment proj-
ects in developing countries, particularly in Africa; the project governance
system; the importance of the project governance system in selecting the
right projects; and factors that could affect the implementation of the proj-
ect governance system.
Project Management Journal, Vol. 43, No. 4, 14–26
© 2012 by the Project Management Institute The Research
Published online in Wiley Online Library The research is qualitative and is based on conceptual and contextual lit-
(wileyonlinelibrary.com). DOI: 10.1002/pmj.21279 eratures to present the idea of a project governance system considering

14 August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj


stakeholders, limitations, and mecha- Williams and Samset (2010, p. 40) majority of the poorest African and
nisms of identifying the right project. It explained such projects as “the wrong some Asian countries.
focuses on the missing link between solution to the problem at hand, or only At different times, different reasons
policies and projects and discusses the a partial solution, sometimes creating have been given for the low success rates
importance of change in the project gov- more new problems than it solves.” of public investment projects in these
ernance system of developing countries. Most often, public investment proj- countries. For instance, different World
The proposition of the research is ects in the developing countries have Bank reports explained weak implemen-
to link development polices with proj- been initiated by different agencies, tation and poor governance capacity as
ects through a mandatory project gov- including national governments, local obstacles to achieve the desired results
ernance system, which will bring governments, international organiza- (Samset, 1998). Weak implementation
changes in the process of selecting the tions, politicians, nongovernmental means the inability to implement proj-
right public investment projects and organizations (NGOs), and others ects efficiently—projects are not com-
improve the success of those projects. (Baum & Tolbert, 1985). These sources of pleted on time, cost exceeds project
public investment projects are criticized budget, and the quality of the output is
Projects in Developing Countries for lacking methodological arrangement below the standard. On the other hand,
Public investment projects include or method of organization. Usually, their failure due to poor project governance
projects from small-scale, thousand- approach is unsystematic and follows would be seen when projects are not
dollar projects to high-scale, multibil- poor project selection methodology. able to give the intended benefits to the
lion-dollar budget works. The main That means projects are not often devel- target groups. With poor project gover-
theoretical objectives of the majority of oped from development policies or nance, projects do not achieve their
these development projects are poverty strategies (national plan or other medi- formal goals; projects will not have sig-
reduction and development. Today, um- or long-term strategic documents) nificant positive impact on beneficiar-
several public investment projects are of countries. Some countries do not ies; projects will not be relevant in rela-
under way throughout the African even have an organized development tion to public needs and priorities, and
countries, with the objectives of either policy that could serve as a source of projects will not have long-term positive
eradicating poverty or answering a cer- projects. The existence of credible strate- effects no matter how well the imple-
tain need of the society or for develop- gic guidance to public investment, mentation process was performed. The
ment. However, the number of projects which can be meaningfully interpreted following strategically unsuccessful
that cannot satisfy the needs and prior- at the sector or subsector levels, should projects are presented as an illustration
ities of the public are also increasing. It be a basic requirement. of the poor project governance systems
is a contradiction: the demand for proj- When public investment projects of some African countries.
ects increases, but the number of projects are being planned, the task of designing The Chad-Cameroon oil pipeline
that cannot satisfy the public needs and defining project goals based on the was the biggest development project in
also increases (Morris & Hough, 1991; development strategy of the country Africa when it was completed in 2003.
Samset, 2009). Project failure has come has not been given sufficient attention. The project cost was US$4.2 billion. In
as a common phenomenon in the pub- Objectives have been set based on the 2001, the World Bank signed an agree-
lic view. Therefore, people feel that interests of project initiators, usually ment with the Chad government to
there are “too many unneeded proj- decision makers (Shiferaw & Klakegg, finance the project with a specific
ects” (Englund & Graham, 1999, p. 52) 2011). Several projects have no definite agreement that substantial oil rev-
and criticize these projects as white ele- objectives. This has affected the rele- enues would be directed to poverty
phants, “something whose cost and vance of projects. A project is relevant if reduction. However, the government of
subsequent upkeep is much greater to the objectives of the project correspond Chad refused to allocate adequate
the owner than its value” (Williams & to the needs and priorities of the own- resources critical for poverty reduction
Samset, 2010, p. 38). Billions of dollars ers, the intended users, and the affected in education, health, infrastructure,
have been spent each year on these parties (Organisation for Economic rural development, and governance, as
projects, but very little is known about Co-operation and Development [OECD], per the agreement (World Bank, 2008).
the impacts of these projects on the 2006). In this regard, a study conducted Surprisingly, in 2005, the Chad govern-
public (Baker, 2000; Samset, 1998). by Samset (1998) indicated that projects ment announced that oil money would
Baker and Samset are not talking about in developing countries are evaluated go toward the general budget and
failure of projects due to lack of effi- as low on relevance and not sustain- rearming the military, tasks that go
ciency. They are talking about the fail- able, compared to projects of indus- completely against the original project
ure of projects due to lack of usefulness trialized countries. Most of these objective. This World Bank loan agree-
and sustainability—strategic failure. unsuccessful projects are found in the ment with the government of Chad was

August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj 15


PAPERS
Linking Policies to Projects

hailed as “groundbreaking” because it turn could affect the sustainability and What Links Policies to the Right
channeled revenue to the poor, but long-term effects of the projects. Projects?
it ended up as one of the most disas- In these and many other similar Doing the right projects requires an
trous and ambiguous projects of the unsuccessful projects, we can see many effective front-end project governance
bank in Africa (Bank Information problems with project development: process in order to select and deliver
Center [BIC], 2008) because the poor the need for projects is not well justi- the selected projects in a way that
could not benefit as per the original fied; the project’s objectives are not meets the expectation of key stakehold-
project objective. clearly specified; alternative solutions ers (Weaver, 2007). Therefore, it is very
In Ivory Coast, Félix Houphouët- are not identified and compared; rele- important to create a project gover-
Boigny built the largest church in the vant stakeholders are not asked to par- nance model that would help decision
world with a cost of US$360 million at ticipate at the beginning. Indeed, in makers to anticipate, understand,
Yamoussoukro (Basilica of Our Lady of many cases the project’s goals and and take action around the intended and
Peace of Yamoussoukro) (Ayittey, 1992). objectives seem to have been selected unintended consequences of their
The Guinness Book of World Records lists as part of a random process. choices and decisions (Shaw, 2003).
the project as the largest church in the The responsibility for the failure of This can be handled by establishing
world. However, it stands empty today. projects to achieve the intended effects some form of link between projects and
The government of Uganda, with the lies more often with planners and development policies of countries. The
help of the World Bank and the African designers (Cusworth & Franks, 1993). link would help to check and control
Development Bank, constructed a 200- But the decision-making processes at the most common challenges of proj-
megawatt dam near Bujagali Falls on the the top governance level could be the ects, such as unclear goals and objec-
Nile. The dam had a devastating effect most important reason for the failure of tives, lack of alignment across stake-
on communities in the area. The back- projects. In this regard, recent studies holders to project goals, commitment
flow submerged a huge area of cultivable have indicated most of the reasons for from key stakeholders, availability of
and settled land, forcing migration and failures of projects are facets of ineffec- alternatives, prioritization, and others.
resettlement of large numbers of people tive project governance. For example, This link could be a project governance
(International Rivers, 2012). According the UK Government’s Office of system, because with a formal gover-
to International Rivers, the project will Government Commerce (OGC), the nance system it is possible to choose
do nothing to help the 95% of Uganda’s developers of PRINCE2, and the OGC the right projects; allocate scarce
population who are not connected to Gateway review process, have compiled resources to the high-priority public
the national grid. a list of common causes of project fail- needs; and elicit the desired behavior
Housing development projects in ures. Decision-making failure, lack of from public enterprises (Baum &
Ethiopia are implemented in different clear senior management (ownership Tolbert, 1985).
regions of the country with huge and leadership), and lack of effective Garland (2009) defined project
amounts of money. The evaluation of engagement with stakeholders are high governance as “the decision-making
the projects by Shiferaw and Klakegg on the list (Garland, 2009). According to framework that guides the develop-
(in press) indicated a shortfall, espe- Garland, inefficient project governance ment of a project and within which the
cially in small towns. In the small leads projects to failures. critical project decisions are made.”
towns, the housing projects were not There is no doubt that relevant and Project governance develops a basis
considered by the public to be a priority. sustainable public investment projects and implements decisions (Klakegg,
The decision to implement similar improve the living standards of millions Williams, Magnussen, & Glasspool,
projects in every town without under- of poor people in nations across the 2008). Project governance is also a
taking a solid proper problem analysis developing world. On the other hand, means for organizations to ensure that
affected the success of projects. as we said earlier, nonrelevant and their projects/programs are aligned to
According to the evaluation, some unsustainable projects will waste pub- their development objectives; the res-
towns had completed apartments that lic resources and cannot provide the ponsibility of parties and stakeholders
did not attract end users, and the proj- intended benefits to the public. is established; objectives of projects are
ect implementation process was Therefore, decision makers in these checked; uncertainties are analyzed;
stopped before the project objectives countries should be sure that they are alternatives are searched; and cost esti-
were fulfilled. The financial recovery of doing relevant and sustainable projects mates are evaluated. Effective project
the projects was not as successful as before making decisions on public governance has mandatory screening
expected, and the contribution of the investment projects. However, the sieves. The screening helps to check
projects toward the strategic goal of question is, how do they ensure that the quality of the decision basis.
the program was not significant. This in they are doing the right projects? According to Weaver (2007), effective

16 August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj


project governance is a key feature of decision making. This will later lead Similarly, the UK Gateway review
successful investments. Therefore, by to the selection and go-ahead of the process examines project or program
establishing effective project gover- preferred alternative (Samset, 2009). concepts at the critical decision points
nance, it is possible to create a link As shown in Figure 1, the Norwegian at the front end and during the imple-
between development strategy and the project governance system has two mentation period. According to the
objectives of projects, and to control key decision points. These are QA1 OGC (n.d.a), the Gateway review
whether objectives of projects are pre- (Quality Assurance 1) and QA2 (Quality process is a quality assurance system to
pared based on the needs and priori- Assurance 2). The aim of QA1 is to check the successful progress of pro-
ties of the public. make sure that the choice of project grams or projects at the specified key
Studies by Klakegg, Williams, and concept is rational. QA1 focuses on checking points before they progress to
Magnussen (2009) indicated that some need assessment, alternative analysis, the next step. The system uses different
industrialized countries in the world strategy document, guidance for the techniques in order to effectively deliver
have executed project governance sys- pre-project phase, and overall require- the intended benefits to the beneficiar-
tems. The objectives of the implemen- ments. On the other hand, the focus of ies. In the Gateway review process, pro-
tation of governance systems are to QA2 is checking cost estimates, con- grams or projects are examined by
build effective and accountable institu- tract strategy, and an overall project independent professionals using their
tions in the public sector and to deploy management document (Concept experience and expertise. Interviews,
the best available skills and experience to Research Program, n.d.; Samset, Berg, & document reviews, and the team’s expe-
facilitate investments in the public sec- Klakegg, 2006). rience are the major techniques used by
tor. It includes devising necessary qual- The quality assurance points are the independent practitioners in order
ity assurance systems and governance fixed at the critical points, and decision to provide valuable additional perspec-
frameworks. The governments of makers will be provided advice and tive on the process.
Norway and the United Kingdom have guidance from professionals at these The OGC Gateway process is
established governance systems to critical points before making decisions. designed to provide independent guid-
ensure best practices in planning at the In this system, the decision-making ance to important stakeholders around
front end. There are indications of suc- process is political, and decision mak- the program or projects on how best to
cess in this regard. To illustrate, the ers will decide whatever they find ensure that their programs and projects
Norwegian project governance system appropriate. However, good decisions are successful. During the life cycle of
and the UK Gateway review processes depend on the quality of available the project, there are five Gateway
are discussed. information. In the Norwegian project review processes, as shown in Figure 2.
The Norwegian project gover- governance regime, decision makers These are: Gateway 0: strategic assess-
nance system was established in 2000. are expected to make democratic deci- ment; Gateway 1: business justification;
It was designed to improve the quality sions based on the information from Gateway 2: delivery strategy; Gateway
of the decision basis of major public the analytic process of the assigned 3: investment decision; Gateway 4:
investment projects in Norway independent consultants, the prefer- readiness for service; and Gateway 5:
(Klakegg, 2010). The model for decision- ences, and political priorities. The operations review and benefits realiza-
making follows logical and chronolog- regime is a good initiative for informed tion. The first three are review processes
ical sequences between analysis and decision making. at the front end, whereas the last two

Cabinet Parliamentary
decision approval

Needs Pre-study Pre-project Project Effects

QA1 QA2

Figure 1: The Norwegian quality-at-entry regime for major public investment projects (Concept Research Program, n.d.).

August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj 17


PAPERS
Linking Policies to Projects

Policy design Policy


Policy operation Policy review
& evaluation implementation

PROGRAMME PROJECT(S)

START
PROGRAMME Develop
business
case
Develop OGC Gateway
programme Key decision point
Review 1:
Business
mandate justification
OGC Gateway
Review 0: Develop
Key decision point
Strategic delivery
assessment strategy
Develop
programme OGC Gateway
brief Key decision point Review 2:
OGC Gateway Delivery
strategy
Review 0: Key decision point
Strategic
assessment Undertake
competitive
Early DELIVER procurement
Gateway 0
PROGRAMME OGC Gateway
Review 3:
Key decision point Investment
decision
Manage
delivery Design,
OGC Gateway build, test
Review 0:
Key decision point
Strategic OGC Gateway
assessment Key decision point Review 4:
Readiness
Manage for service
delivery
OPERATIONAL
OGC Gateway SERVICE
Review 0:
Strategic Key decision point OGC Gateway
Establish Review 5:
assessment
service Operational review
Key decision point and benefits
Manage realisation
delivery
Initial
OGC Gateway Close project, Gateway 5
Review 0: Key decision point manage OGC Gateway
Strategic
delivered Review 5:
assessment
Operational review
solution and benefits
Mid and realisation
Mid
Gateway 0 performance
CLOSE Gateway 5

PROGRAMME OGC Gateway


OGC Gateway Key decision point Review 5:
Review 0: Key decision point Operational review
Strategic and benefits
assessment Decommission
realisation
solution/exit Final
Close
Final contract Gateway 5
Gateway 0

Feeds into subsequent programmes

Figure 2: The overall OGC framework (OGC, n.d.b; Klakegg et al., 2009).

18 August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj


are checked during the service imple- same development strategy have weak the system and the process are to give
mentation. coordination; and different projects decision makers access to all the infor-
The OGC Gateway process provides under the same sector are not processed mation they need and to improve the
assurance and support for the relevant in coordination and integration (Ministry quality of the decision basis.
decision makers with the following of Finance and Economic Development Of course, it is very important to
points (OGC, 2007): [MoFED], 2006). Decisions, actions, or have some form of system that works on
• The best available expertise and expe- operations have no formal procedure behalf of the government and the public
rience are set up on the program or or the procedure is not followed strictly. to ensure that public investment proj-
project. Efficient procedures save time, money, ects are efficient, effective, relevant, and
• All the stakeholders are aware of the and human resources. Disorganized sustainable. In this regard, high-quality
project/program status and the issues procedures and the absence of an effec- processes and procedures for planning
involved. tive governance framework are the main investment projects have played a vital
• There is assurance that the pro- causes of project failure and wastage role in high-performing countries in
gram/project can progress to the next of resources—even in the developed East Asia. On the other hand, invest-
stage of development or implementa- countries. ment in general in sub-Saharan Africa,
tion. Moreover, there is no clear system where governance is comparatively
• More realistic time and cost targets for to check the relevance of the sectors’ weak, has had little impact on growth
programs and projects are achieved. project proposals with the government (Devarajan, Easterly, & Pack, 2003;
• Improvement of knowledge and skills development strategy; there is no sys- Kenny, 2007). The development experi-
among government staff occurs tem that checks how public needs and ences of these countries confirmed that
through participation in review priorities are included in the project governance has a crucial role in pro-
teams. objectives and development processes. moting and sustaining development.
• Advice and guidance are provided to Various project implementation sectors From the above discussion, we can
program and project teams by fellow do not have guidelines for preparation understand that establishing some
practitioners. of public investment projects. These form of effective governance system as
issues have created various shortcom- a link between projects and policies is
Improving Governance of Public ings: a failure to map public needs and very important to increasing the suc-
Investment Projects in priorities; a failure to analyze the rela- cess of public investment projects. We
Developing Countries tionship between policies and projects; have seen two of the most recent proj-
Developing countries have a scarcity of and a failure to analyze various levels of ect governance systems (the UK OGC
resources. These scarce resources are planning processes. Gateway and the Norwegian quality
mostly committed to projects, since Therefore, good and effective man- assurance system) and their principles,
most countries’ governing agencies agement and control of programs and and we have described the impacts of
believe that projects are the means for projects is essential to the success of good governance on fast-growing
organizing resources to invest in devel- government objectives (OGC, n.d.a). countries in East Asia. We believe that
opment. Of course, different profes- Developing knowledge and expertise at African countries need to implement
sionals agree that programs and proj- the front end of projects, from the initial some form of effective project gover-
ects provide an important vehicle for visualization until the decision to nance system. The question is, which
the efficient and timely delivery of implement, is very important (Concept type of project governance system will
governments’ aims. However, this argu- Research Program, n.d.). A framework is best improve the success of public
ment is often weakened by the low suc- very important to stakeholders who investment projects in this region?
cess rate of public investment projects want to ensure successful investments We suggest establishing a separate
in a number of dimensions, including (Samset et al., 2006). It is therefore desir- project governance system based on
poor project concept selection, unfair able to have a well-functioning public the contexts and norms of each coun-
procurement practices, cost and time investment system to identify the specific try. The governance structures, models,
overrun, incomplete projects, and fail- weaknesses that would contribute to principles, and governance elements
ure to operate and maintain assets poor outcomes and to suggest appropri- are not the same in different contexts.
effectively (Rajaram, Le, Biletska, & ate institutional and technical remedies Copying the UK Gateway review or the
Brumby, 2010). that could correct such failures Norwegian quality assurance system or
Most often, developing countries (Rajaram et al., 2010). This indicates the any other form of governance system
have no formal project governance sys- importance of a system to link projects from developed countries may not
tems, or such systems are implemented with investment guidance or govern- have a significant effect, because in
weakly; different sectors working for the ment policies. The main objectives of designing the governance and strategic

August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj 19


PAPERS
Linking Policies to Projects

ideologies of projects, the development


ideologies of industrialized countries
are taken as the main inspirational tool Public priorities Policy direction Actions
(needs) (strategy) (projects)
for the last decades. Experts from differ-
ent fields have continuously looked for
ways to transfer the experiences of
developed nations to the developing Government Implementing
countries, believing that development executives sector
follows a common path that all coun-
tries have passed through. But in prac-
tice it does not work well. Quality assurance
system
Therefore, establishing a separate
project governance system within the
context of each country is very impor-
Figure 3: Project governance model for public investment projects.
tant. This helps to create a link between
development strategy and projects. It
provides a common base for preparing
projects financed by the public sector.
But wherever it is implemented, project
governance must be clear in its objec- other hand, the sectors should disag- other relevant stakeholders. According
tive; it must enable effective and effi- gregate the strategic plan and could to OGC (n.d.a), this type of quality
cient decision making; it must provide develop concepts of projects. To ensure assurance system is important for
clarity of accountability; and it must the alignment of objectives of projects delivery of projects and provides deci-
ensure that the interests of all stake- with the policy direction and then to sion makers with a wide view of the
holders are considered within the deci- the public needs, some form of quality project portfolio and an agreed view of
sion-making process (Garland, 2009). assurance system is important between risk. The system would have an inde-
In order to ensure its effectiveness, any the government executives (decision pendent examination for each proposed
governance system should be based makers) and implementing sectors. The alternative using top independent exter-
around core principles (Klakegg, 2010). quality assurance system needs to have nal professionals or consultants.
These principles must be used as the some form of criteria and checklist to Alternatives should be examined for
basis of the design of governance evaluate project proposals. Through the any probable risk and all the available
model. Governance principles include quality assurance system, project con- relevant (qualitative and quantitative)
transparency, accountability, rule of cepts will be screened step by step, and data should be collected and analyzed.
law, efficiency and effectiveness, then decisions will be made by govern- Collecting and analyzing factual infor-
responsiveness, and forward vision ment executives. The decision makers mation is the most important step in
(Klakegg, 2010). These are important can decide whatever they like, but in the process because the absence of fac-
principles that a project governance this scenario, they are informed about tual information is often a pretext for
system in these developing countries the costs, consequences, and potential not seeking information at the front
needs to embed in its policies. for success of projects. end (Samset, 2009).
Figure 3 illustrates a project gover- The quality assurance system in the Quality assurance should be con-
nance model for public investment project governance model, as shown in tinuous, and all major public invest-
projects. The model shows how public Figure 3, is designed to deliver the right ment projects should pass through the
investment projects could develop and information to the decision makers. system. In the same way, other small
who would be responsible for the activ- The information from the system could projects should pass through a similar
ities in the project development be used as the decision basis. The process- internal quality assurance system since
process. According to this model, proj- es and procedures inside the quality the ultimate goal is to implement the
ects are initiated from the policy direc- assurance system must be designed right projects no matter their size.
tion of the government through a based on the contexts of the imple- In the previous two sections, effec-
strategic plan or similar document. The menting country, as seen in the cases tive project governance is explained as
policy direction should address the from Norway and the United Kingdom. a system that can be used to select the
public needs and government execu- However, any type of quality assurance right public investment projects. It is
tives are responsible for designing system must be able to give delivery also explained as an important link
the policy direction of the state. On the confidence to decision makers and any between policies and the right projects.

20 August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj


No. Checkpoints Remark
1 Is there a real problem that requires initiating a project?
2 Why is an activity initiative selected? Is it the priority of the public?
3 Are the objectives of the project consistent with the policy direction of the country?
4 What is the final objective of the project? Is it possible to achieve?
5 Are all relevant stakeholders informed and allowed to be involved?
6 Can resources be used efficiently? Is the funding available?
7 What are the negative and positive impacts of the proposed project?
8 Is the net value of the project encouraging?
9 Are the project estimates accurate?
10 Is the result of the cost benefit analysis encouraging? Does the cost benefit analysis
consider all the relevant costs and benefits?
11 Can the program or project be better designed to achieve the intended outcomes?
12 Is all the relevant information collected and analyzed?
13 What are the associated contextual and operational uncertainties? Are they analyzed?
What is the result?
14 What are the alternatives? How are they compared? How are the results interpreted?

Table 1: Information quality checklist for decision makers.

The implementation of a project gover- ment from senior management, and critical. There are indications that
nance system is advised for the long-term support from other relevant stakehold- could support this argument. For
success of public investment projects. ers. The implementation process has example, planning for public invest-
Quality assurance system is designed in challenges of cultural issues, policy ment projects has been widely accept-
a project governance system in order to issues, structural issues, and resourcing ed (at least theoretically) in the devel-
analyze all the relevant formation and to and skill issues (Garland, 2009). Taking oping world for a long time. It also has
give delivery confidence for decision into consideration the contexts of been a requirement from financing
makers. It is expected that decision mak- developing countries, the following fac- parties like the World Bank. In this
ers will use the information from the tors are selected and discussed as regard, developing countries have
system as a base for the decision. Table factors that could affect the implemen- implemented project preparation
1 illustrates a sample checklist pre- tation process of a project governance guidelines for public sector projects.
pared for decision makers and quality system. However, the actual formulation of the
assurers that would allow them to guidelines has been slow, and the diver-
check the quality of information before Commitment From the Government gence between the guidelines and their
making decisions. Executives implementation has frequently been
Englund and Graham (1999) and noticed (Islam, 2003). This indicates
Factors That Could Affect the Graham and Englund (1997), in their that unless there is a commitment from
Implementation of a Project study of project strategy, explained the the government executives, the imple-
Governance System in commitment of executives as critical to mentation of project governance sys-
Developing Countries creating a conducive environment for proj- tems could be difficult.
The project governance system imple- ect success. Similarly, even though there Executives in developing countries
mentation process requires proper care are many contextual factors that could may lack commitment to a mandatory
toward its acceptance and anchoring affect the successful implementation of project governance system for many
(Klakegg, 2010). It also requires true a project governance system, the need different reasons. Some governments
interest from decision makers, commit- and commitment of top management is are not democratic and it is obvious

August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj 21


PAPERS
Linking Policies to Projects

that they do not want to have a demo- Renaissance Dam (project cost US$4.8 any other stakeholder trained within an
cratic decision-making process. That billion) is one example. In this case, the undemocratic system. Any attempt at
means they might not be committed to project governance framework of leading change in the linkage of proj-
the consistent and coherent execution Ethiopia is static; it has not been ects with strategy is bound to meet
of project governance rules and brought to life because the system of resistance from top management
responsibilities. On the other hand, governance that includes the activities (Englund & Graham, 1999).
some countries may have project gov- of executives in the governance model Therefore, the idea of linking proj-
ernance systems that are not function- is not dynamic through the system. ects with policies needs proper care
ing properly or practically. Others may On the other hand, the low commit- and implementation procedures.
not have a project governance system ment of executives toward the new Taking a copy of the Western project
and allow decisions on projects to project governance model can affect governance system and implementing
appear almost randomly. As illustrated the attitudes of other subordinates it in a developing country may not fit
previously, politicians in undemocratic in the governance system. When people the political or social system therein.
developing countries like to build big feel that the executives do not commit Therefore, it is very important to design
projects. Building big projects in these to the governance system, they are hes- a link (a project governance system)
countries is part of a “big-man syn- itant to follow with enthusiasm between governance structure and
drome,” in which public needs and pri- (Englund & Graham, 1999). project structures, taking into consider-
orities and the net effects of the proj- ation the government’s nature and cul-
ects might not be criteria for decisions. Cultural Issues tural norms.
They could make decisions on multi- Any government or organization has its
million-dollar projects overnight own culture (values, beliefs, and Policy Issues
because they do not have a framework norms). The implementation of a proj- Linking policies with the right projects
for a decision-making process. They are ect governance system may require is possible only if there is a clear devel-
often committed to fulfill their political, changes in the government’s culture of opment policy and strategy. Without a
individual, or group interests. project handling. Quality assurance clear development policy and strategy,
Therefore, support from top gov- steps, gateway review processes, proj- projects will be free to fill the vacuum.
ernment executives is very important ect appraisals, and other processes that Often policy or some form of strategic
for the successful implementation of a are associated with project governance plan is a source of projects, but without a
project governance system. The project systems are important new arrange- clear policy, different parties could
governance system could function ments in the governance of public design different strategies and could have
according to the guideline of the investment projects. The new arrange- different projects with different ulti-
authority if and only if there is genuine ment prioritizes the usefulness and sus- mate goals and purposes. On the other
support from the top government exec- tainability of projects, public participa- hand, it is obvious that different gov-
utives. If government executives are not tion, transparency, discussion, and ernments have different political sys-
committed for a specific project gover- constructive criticism. As Graham tems, and these political systems have
nance system, change will not come, and Englund (1997) said, during change different policies and strategies. Some
because the project governance system the existing culture may causes prob- political systems have good develop-
cannot function according to the lems to the new arrangements. ment policies, and it is possible to
guideline. During our recent survey on Politicians and decision makers of implement and exercise project gover-
the project governance system of some undemocratic countries want to nance systems within those policies.
Ethiopia, we saw several multimillion- be known for implementing big proj- There are also, however, political sys-
dollar projects decided directly by the ects. In these countries, big projects are tems that do not have good develop-
top executives. According to the project political weapons and are implemented ment policies; in those countries, it will
governance system of Ethiopia, a proj- as a means to achieving glory, great- be difficult to implement an effective
ect concept should develop by sectors. ness, and, more important, the accu- project governance system and suc-
Then the Ministry of Finance and mulation of wealth for themselves and cessful public projects.
Economic Development (MoFED) their partners. The implementation of a
checks the proposal, and then the project governance system in these Interests of Donors and Financial
Council of Ministries will debate countries may be perceived by politi- Institutions
the proposal before the Parliament cians as a loss of power. Therefore, the Donors and financial institutions, such
makes a final decision. However, there process of implementation or the exer- as the World Bank, the International
are projects that are approved out of cise of the project governance system Monetary Fund (IMF), the African
this procedure; the Grand Ethiopian could face resistance from politicians or Development Bank (AfDB), and others

22 August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj


are the major stakeholders in the devel- In a properly implemented front- concepts should be searched, evaluat-
opment of major public investment end project governance system, the real ed, and screened through predefined
projects in Africa. Development assis- problem and the subsequent selection criteria to come up with a short list.
tance and loans from these sources have of a particular initiative will be ana-
Estimate Benefits of Alternatives
been used to implement public invest- lyzed; the project’s relation to the whole
The benefits, opportunity costs, and
ment projects for several years. The sup- development policy will be identified;
impacts of each alternative must be
port may be bilateral (support from one and alternative solutions will be identi-
identified and qualified. At this point, it
country directly to another) or it could fied, evaluated, and compared. The
is very important to take care to avoid
be multilateral, given by the donor front-end project governance system
exaggerated benefits, because it might
country to an international organization ends by making a preferential decision
affect the process of choosing the right
such as the World Bank or the United on the most promising alternative.
project.
Nations Agencies (UNDP, UNICEF, Then, the preferred alternative will be
UNAIDS, etc.) However, these bodies subject to a detailed project study. In Estimate Costs of Alternatives
have their own agendas and often proj- order to do this, there are some impor- After screening possible alternatives, it
ect solutions onto other societies and tant steps that any form of governance is desirable to select a few critical possi-
cultures. They have their own modalities system should follow. The following bilities. The next step is to prepare
to support projects. Designing a project section will discuss these steps. preliminary cost estimates for these
governance system in one of the aid alternatives. At this stage, it is impor-
Important Steps of a Project
recipient countries may consider the tant to check and avoid tactical under-
Governance System to Select a Right
interests of these parties. Therefore, estimation and overestimation because
Project
the interests of these parties could affect it might affect the selection of the right
the implementation of the project gov- Conduct Needs Assessment project.
ernance system in one way or another. A needs assessment is the process used
Evaluate Cost Benefit for Each
On the other hand, the structure of for determining how to close the gap
Alternative
the government; lack of expertise and between the present and the desired
The next step is calculating the cost
experience; shortage of reliable factual (Gupta, 2007). This process includes
benefit for all alternatives. Cost-benefit
information, concepts, and methods of comparing the present condition with
analysis of each alternative must con-
measurement in collecting data; and the desired condition; defining the
sider social, environmental, and eco-
great pressure from decision makers to problem; identifying what can be con-
nomic perspectives of the project.
make immediate decisions can also tributed to the current condition; iden-
affect project governance implementa- tifying if and how the current condition Prioritize Projects
tion and its effectiveness. could be improved; and developing Before making the final decision, a
solution strategies. It could be a discus- credible governance system helps to set
How Are the Right Projects sion between the central government, policy priorities and establishes a basis
Identified Through a Project local authorities, municipalities, and for decision. It also checks whether a
Governance System? the public. proposed project is within the scope of
From the previous sections, it is clear identified priorities. It is not possible to
Set Goals and Objectives
that decisions on public investment address all identified needs in one proj-
After a needs assessment is completed,
projects should consider the long-term ect. Therefore, priorities have to be set.
the next step is to set achievable objec-
realization of public needs and sus- This has to be done by including the
tives or goals based on the identified
tainable development. We also under- opinions of the relevant stakeholders
needs and the overall strategy of the
stand that in order to make the right and political interests of the decision
country. It is an improved situation in
decisions, development policies makers.
which a project or a program is expect-
should be linked to projects by some
ed to contribute, and it is expressed in Decision
form of governance system. A mandato-
terms of benefits to be achieved by the The last step is the decision. This can be
ry project governance system checks
target group. According to Englund and a decision on the preferred solution, a
the link between projects and policies to
Graham (1999), it is a vivid description decision to reject unconvincing proj-
enable the right decisions to be made
of the future state. ects, or a decision to return for improve-
at the top level. It also helps to estab-
ment.
lish a framework at the sector level, Find Alternatives
where sector investment strategies, After identifying needs and setting Process Tools
priorities, and supporting policies are goals, the next step is to find the alter- The steps previously outlined in a proj-
elaborated. native solutions. Alternative project ect governance system need process

August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj 23


PAPERS
Linking Policies to Projects

Iteration to consider the constraints, objectives, or criteria

Forecasting
future
contexts

Boundaries
and Building and
Identifying,
using models Comparing
Initiation Formulating constraints designing, Alternatives
for Consequences Communicating
and
the and (impacts) results
Objectives predicting the ranking
problem screening the
Values and consequences alternatives
alternatives
criteria

Iteration to improve alternatives


Iteration to reformulate the problem

Figure 4: Systems analysis procedures with iteration loop (Priemus, 2008).

tools. System analysis, Logical Frame- sion makers, and other stakeholders. long-term impacts of each alternative
work Approach (LFA), the Organisation In parallel, contextual and operational project on the economy, the society,
for Economic Co-operation and uncertainties are assessed and ana- and the environment could be
Development (OECD) investment eval- lyzed. Alternative solutions, including assessed.
uation criteria, Sustainability Impact zero alternatives, are identified and Finally, alternatives are compared and
Assessment (SIA), and other project then evaluated. ranked according to their merit,
assessment methodologies have been LFA could be used for defining and and the most promising project alter-
used for a long time to support the establishing a sound basis for goals native is communicated to the decision
decision-making process. Figure 4 illus- and objectives of alternatives and as an makers for their choice.
trates a system analysis procedure that evaluation tool to organize the planned
is developed to help the selection of the action (Klakegg & Haavaldsen, 2009). Conclusion
right project. On the other hand, OECD (2006) invest- A project governance system is used to
In this system, formulating the ment evaluation criteria (efficiency, check the consistency of public needs
problem; identifying, designing, and effectiveness, impact, relevance, and with the objectives of a proposed proj-
screening alternatives; predicting conse- sustainability), along with the six cross- ect and then the potential effects of the
quences, and comparing and ranking cutting issues (economic and financial project with development policies and
alternatives are basic steps. It is an itera- issues, institutional issues, socioeco- strategies. In this regard, the imple-
tion loop that reforms problems and nomic issues, technological aspects, mentation of an effective project gover-
alternatives to select the right project. environmental aspects, and policy nance system at the top governance
In this process, the first step is for- issues), could be used as assessment level helps to select the right public
mulating specific problems. Problems criteria for selecting the right project. investment projects and to ensure their
are identified from public need assess- SIA, a tool for informed decision mak- successful development. Effective proj-
ments and policy reviews. The next step ing used to predict the consequences of ect governance systems are designed
is to set objectives and devise solutions decisions at the front-end (OECD, with mandatory screening sieves, where
that could satisfy the objectives, values, 2008), is an important criterion to be problems are identified, stakeholders’
and requirements of the public, the deci- considered. Using SIA, the short- and opinions are collected and analyzed,

24 August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj


alternative solutions are evaluated, Baum, W. C., & Tolbert, S. M. (1985). Projects and Project Profiles, IX(2),
consequences of each alternative are Investing in development: Lessons of the 40–51.
predicted, and the most promising World Bank experience. New York, NY: Klakegg, O. J., Williams, T., &
solution is selected and communicated Oxford University Press. Magnussen, O. M. (2009). Governance
for decision. Concept Research Program. (n.d.). QA frameworks: For public project develop-
In this article, the implementation scheme. Retrieved from http://www ment and estimation. Newtown
of a mandatory project governance sys- .concept.ntnu.no/qa-scheme Square, PA: Project Management
tem in African countries is advised to Institute.
Cusworth, J. W., & Franks, T. R. (1993).
improve the success rate of public
Managing projects in developing coun- Klakegg, O. J., Williams, T., Magnussen,
investment projects. Within a mandato-
tries. Harlow, UK: Longman Group. O. M., & Glasspool, H. (2008).
ry project governance system, execu-
Devarajan, S., Easterly, W., & Pack, H. Governance frameworks for public
tives in African countries are expected
(2003). Low investment is not con- project development and estimation.
to decide according to the rules and
straint on African development. Project Management Journal, 39(S1),
procedures of the project governance
Economic Development and Cultural 27–42.
system, based on the information pro-
Change, 51(3), 547–571. Ministry of Finance and Economic
vided through the project governance
system, and according to the policy Englund, R. L., & Graham, R. J. (1999). Development (MoFED). (2006).
direction of the government. Linking projects to strategy. Journal of Guidelines for the preparation of public
For the successful implementation Product Innovation Management, sector projects. Addis Ababa, Ethiopia:
of an effective project governance sys- 16(1), 52–64. Author.
tem, governments in Africa should create Garland, R. (2009). Project governance: Morris, P. W. G., & Hough, G. H. (1991).
an enabling environment. The quality A practical guide to effective project The anatomy of major projects. A study
assurance system in a project gover- decision-making. London, UK: Kogan of reality of project management.
nance system should operate effectively Page. Chichester, UK: Wiley.
to create an effective link between proj- Graham, R. J., & Englund, R. L. (1997).
Office of Government Commerce
ects and policies. Creating an environment for successful
(OGC). (n.d.a). OGC gateway review for
However, the implantation of a projects. San Francisco, CA: Jossey-
programmes and projects. Retrieved
mandatory project governance system Bass.
from http://webarchive.nation-
in Africa could have different chal- Gupta, K. (2007). A practical guide to alarchives.gov.uk/20100503135839
lenges. The commitment of decision needs assessment. Indianapolis, IN: /http://www.ogc.gov.uk/what_is_ogc
makers, development policies, the Pfeiffer. _gateway_review.asp
political culture, and other issues are
International Rivers. (2012). Bujagali
identified as important challenges. Office of Government Commerce
Dam, Uganda. Retrieved from
Relevant other challenges have to be (OGC). (n.d.b). A manager’s checklist.
http://www.internationalrivers.org/ca
identified, and important precautionary Retrieved from http://webarchive
mpaigns/bujagali-dam-uganda
measures must be taken for the success- .nationalarchives.gov.uk/201005031358
ful implementation of a project gover- Islam, N. (2003). Exploration in devel- 39/http://www.ogc.gov.uk/ppm
nance system and for the selection of opment issues. Wiltshire, UK: Antony _documents_ogc_gateway.asp
the right public investment projects. ■ Rowe Ltd.
Office of Government Commerce
Kenny, C. (2007). Infrastructure gover-
(OGC). (2005). Common causes of proj-
References nance and corruption: Where next?
ect failure. Retrieved from
Ayittey, G. B. N. (1992). Africa betrayed. (World Bank Policy Research Working
http://webarchive.nationalarchives.go
New York, NY: St Martin’s Press. Paper, 4331). Washington, DC: World
v.uk/20110822131357/http://www.ogc
Baker, J. L. (2000). Evaluating the Bank.
.gov.uk/documents/cp0015.pdf
impact of development projects on Klakegg, O. J. (2010). Governance of
project: A handbook for practitioners. major public investment projects: In Office of Government Commerce
Washington, DC: World Bank. pursuit of relevance and sustainability. (OGC). (2007). OGC GatewayTM
PhD thesis, The Norwegian University process. Review 0: Strategic assessment.
Bank Information Center (BIC).
of Science and Technology. Trondheim, London, UK: Author.
(2008). World Bank announces with-
drawal from Chad-Cameroon pipeline Norway: Tapir Academic Press. Organisation for Economic Co-operation
after early repayment. Retrieved from Klakegg, O. J., & Haavaldsen, T. (2009). and Development (OECD). (2006).
http://www.bicusa.org/en/Article.3892 Complex projects: Evaluation criteria Development Assistant Committee
.aspx[JS2] for front-end governance. Journal of (DAC). Draft standard on development

August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj 25


PAPERS
Linking Policies to Projects

evaluation. Retrieved from http://www (pp. 18–35). Basingstoke, UK: Palgrave No: 2009/073/AFR. Retrieved from
.oecd.org Macmillan. http://web.worldbank.org/WBSITE
Organisation for Economic Co-operation Samset, K., Berg, P., & Klakegg, O. J. /EXTERNAL/COUNTRIES/AFRICAEXT
and Development (OECD). (2008). (2006). Front end governance of major /CHADEXTN/0,,contentMDK:2189453
OECD sustainable development studies: public projects. Paper presented at the 0⬃menuPK:349894⬃pagePK:2865066
Conducting sustainability assessments. EURAM Conference, Oslo, Norway. ⬃piPK:2865079⬃theSitePK:349862,00
Paris, France: Author. .html
Shaw, J. C. (2003). Corporate gover-
Priemus, H. (2008). How to improve nance and risk: A system approach.
the early stages of decision-making on Hoboken, NJ: Wiley. Asmamaw Tadege Shiferaw, MSc, has 14 years
mega-projects. In H. Priemus, Shiferaw, A. T., & Klakegg, O. J. (in of practical and research experience. He has
B. Flyvbjerg, & B. V. Wee (Eds.), press). Project evaluation: worked as a researcher, contract administrator,
Decision making on mega projects: Cost Accomplishments, shortfalls and les- construction engineer, and an assistant lecturer.
benefit analysis, planning and innova- sons learned in the case of housing Currently, he is working as a PhD research fel-
tion (pp. 105–119). Cheltenham, UK: development projects in Ethiopia. low in the Department of Civil and Transport
Edward Elgar. Journal of Management in Engineering. Engineering at the Norwegian University of
Rajaram, A., Le, T. M., Biletska, N., & Shiferaw, A. T., & Klakegg, O. J. (2011). Science and Technology (NTNU). He was educat-
Brumby, J. (2010). A diagnostic frame- Governance of public investment proj- ed at Addis Ababa University, where he received
work for assessing public investment ects in Ethiopia. In Peer-reviewed pro- his MSc in construction management. His PhD
management. Policy Research Working ceedings of the 12th annual internation- study focuses on the front-end governance of
Paper 5397. Washington, DC: World al conference: Challenges in the era of major public investment projects. In addition, he
Bank. globalization (pp. 742–751). Edmonton. has interests in uncertainty management, con-
Samset, K. (1998). Project management International Academy of African tract administration, and project evaluation.
in a high uncertainty situation: Business and Development (IAABD).
Uncertainty, risk and project manage- Weaver, P. (2007). Effective project gov- Ole Jonny Klakegg, MSc, PhD, has 23 years of
ment in international development ernance: Linking PMI’s standards to experience in research, teaching, and consulting
projects. PhD thesis, The Norwegian project governance. PMI Global within project management. He is currently a
University of Science and Technology, Congress-Asia Pacific proceedings professor of project management at NTNU in the
Trondheim, Norway: Tapir Academic CD. Newtown Square, PA: Project Department of Civil and Transport Engineering.
Press. Management Institute. Retrieved from He also holds a part-time position as R&D direc-
Samset, K. (2003). Project evaluation: http://marketplace.pmi.org/Pages/Pro tor at Faveo Project Management—the largest
Making investments succeed. ductDetail.aspx?GMProduct⫽00101185 project management consultancy in Scandinavia.
Trondheim, Norway: Tapir Academic 801 He has experience from a large number of major
Press. Williams, T., & Samset, K. (2010). projects in Norway in the private and public sec-
Samset, K. (2009). Projects, their quality Issues in front-end decision making on tors, including building, transportation, health,
at entry and challenges in the front-end projects. Project Management Journal, and defense projects. His special interests
phase. In T. Williams, K. Samset, 41(2), 38–42. include project governance and risk/uncertainty
& K. Sunnevåg (Eds.), Making essential World Bank. (2008). Statement on management. He has authored books, reports,
choices with scant information Chad-Cameroon pipeline. Press release papers, and articles on project management.

26 August 2012 ■ Project Management Journal ■ DOI: 10.1002/pmj


Copyright of Project Management Journal is the property of John Wiley & Sons, Inc. and its content may not be
copied or emailed to multiple sites or posted to a listserv without the copyright holder's express written
permission. However, users may print, download, or email articles for individual use.

S-ar putea să vă placă și