Documente Academic
Documente Profesional
Documente Cultură
Project J Hostel
Owner P4P Nacpan Holding Corporation
Location El nido Palawan
5. Structural Works
a. Chb Laying
1st Floor Walls 28 sq.m
2nd Floor Walls 78 sq.m
3rd Floor Walls 26 sq.m
Roof Deck 48 sq.m
b. Plastering Works
1st Floor Walls 100 sq.m
2nd Floor Walls 166 sq.m
3rd Floor Walls 74 sq.m
Roof Deck 110 sq.m
Perimeter Walls 240 sq.m
c. Roof Deck
Concrete Chairs 1 lot
Garden Wall 1 lot
Bar Counter 1 lot
6. Steel Works
a. Resto Bar ' 20 sq.m
b. Pergola 1 lot
7. Water Proofing
a. Cr
2nd Floor 28 sq.m
3rd Floor 28 sq.m
b. Roof Deck ( Hot Membrane ) 150 sq.m
8. Architectural Works
8.1 Tiling Works
a. 1st Floor
Hallway 43 sq.m
Rooms 58 sq.m
Cr
Wall 93 sq.m
Floor 16 sq.m
b. 2nd Floor
Hallway 22 sq.m
Rooms 68 sq.m
Cr
Wall 215 sq.m
Floor 26 sq.m
c. 3rd Floor
Hallway 16 sq.m
Rooms 78 sq.m
Cr
Wall 215 sq.m
Floor 26 sq.m
8.3 Doors
a. D1 .85m x 2.1m Panel Type Door 3 sets
b. D2 .75m x 2.1m Panel Type Door 1 sets
c. D3 .9m x 2.1m Panel Type Door 17 sets
d. D4 .7m x 2.1m Panel Type Door 15 sets
e. D5 1.6m x 2.3m Glass Swing Door 1 sets
8.4 Windows
a. W1 3m x 2.3m 1 set
b. W2 6m x 2.3m 2 sets
c. W3 1.16m x .36m 8 sets
d. W4 2.216m x 1.5m 1 set
e. W5 3.6m x 2.3m 1 set
9. Electrical Works
a. Panel Boards 4 pcs
b. Wires
b.1 2mm 15 box
b.2 3mm 15 box
b.3 5.5mm 10 box
c. Breakers
c.1 150 AT 4 pcs
c.2 30 AT 15 pcs
c.3 20 AT 9 pcs
c.4 15 AT 16 pcs
d. Pipes
d.1 1 inch 50 pcs
d.2 3/4 inch 25 pcs
d.3 1/2 inch 15 pcs
e. Junction Box 100 pcs
f. Utitility Box 130 pcs
g. Flexible Hose 150 meters
h. Lighting Fixtures
h.1 Drop Light 18 pcs
h.2 Halogen recessed Light 200 pcs
h.3 Flourescent Lamp 100 lm
h.4 Air Vent 15 pcs
h.5 Led Lights 100 lm
i. Convinience Outlet
i.1 Indoor 120 pcs
i.2 Outdoor 10 pcs
Prepared By:
13,440.00 0.25%
39,000.00 0.72% 35 45% 0.32%
13,520.00 0.25% 15 58% 0.14%
24,960.00 0.46%
40,000.00 0.73%
66,400.00 1.22% 20 12% 0.15%
31,820.00 0.58% 10 14% 0.08%
47,300.00 0.87%
103,200.00 1.89%
-
-
13,000.00 0.24%
6,500.00 0.12%
13,000.00 0.24%
-
-
36,830.00 0.68%
40,020.00 0.73%
36,830.00 0.68%
48,590.00 0.89%
61,600.00 1.13%
60,000.00 1.10%
-
23,400.00 0.43%
-
60,000.00 1.10%
-
-
80,000.00 1.47%
-
40,000.00 0.73%
5,460.00 0.10%
5,460.00 0.10%
87,750.00 1.61%
32,250.00 0.59%
43,500.00 0.80%
-
51,150.00 0.94%
8,800.00 0.16%
-
-
16,500.00 0.30%
51,000.00 0.94%
-
118,250.00 2.17%
14,300.00 0.26%
-
-
12,000.00 0.22%
58,500.00 1.07%
-
118,250.00 2.17%
14,300.00 0.26%
-
6,600.00 0.12%
66,690.00 1.22%
66,120.00 1.21%
68,400.00 1.25%
62,500.00 1.15%
31,590.00 0.58%
-
87,750.00 1.61%
31,320.00 0.57%
-
75,000.00 1.38%
32,400.00 0.59%
15,000.00 0.28%
96,000.00 1.76%
12,000.00 0.22%
22,000.00 0.40%
22,000.00 0.40%
22,000.00 0.40%
-
-
19,500.00 0.36%
6,500.00 0.12%
110,500.00 2.03%
72,000.00 1.32%
25,000.00 0.46%
26,000.00 0.48%
104,000.00 1.91%
10,400.00 0.19%
12,500.00 0.23%
31,500.00 0.58%
178,500.00 3.27%
64,600.00 1.19%
27,000.00 0.50%
42,000.00 0.77%
16,500.00 0.30%
22,100.00 0.41%
120,000.00 2.20%
8,750.00 0.16%
-
-
31,200.00 0.57%
-
54,600.00 1.00%
74,100.00 1.36%
71,500.00 1.31%
-
4,160.00 0.08%
8,775.00 0.16%
5,265.00 0.10%
7,280.00 0.13%
-
11,050.00 0.20%
2,925.00 0.05%
1,365.00 0.03%
5,200.00 0.10%
5,915.00 0.11%
3,900.00 0.07%
-
54,000.00 0.99%
78,000.00 1.43%
13,000.00 0.24%
29,250.00 0.54%
19,500.00 0.36%
-
23,400.00 0.43%
2,600.00 0.05%
-
-
20,800.00 0.38%
13,000.00 0.24%
4,420.00 0.08%
1,300.00 0.02%
1,300.00 0.02%
585.00 0.01%
585.00 0.01%
292.50 0.01%
-
-
31,200.00 0.57%
11,375.00 0.21%
2,600.00 0.05%
2,600.00 0.05%
2,600.00 0.05%
975.00 0.02%
4,550.00 0.08%
3,900.00 0.07%
-
-
87,500.00 1.61%
38,500.00 0.71%
-
-
390,000.00 7.16%
90,000.00 1.65%
42,000.00 0.77%
119,000.00 2.18%
-
-
-
-
140,000.00 2.57%
30,000.00 0.55%
30,000.00 0.55%
200,000.00 3.67%
60,000.00 1.10%
200,000.00 3.67%
-
-
-
115,000.00 2.11%
5,450,667.50 Total Percent Accomplished 2%
272,533.38 Percent Amount 132,600.00
5,723,200.88 Running Cost as of July 18 2020 201,744.00
Project: J Hostel
Location: El nido
1st Month
Scope of Work 1st week 2nd week 3rd week 4th week
1. Demolition Works
Walls
2. Dismantling Works
Windows
Doors
3. Chipping Works
Tiles
Hallway, Rooms and Cr
4. Water Proofing
Roof Deck
Cr
5. Chb Laying
1st floor
2nd floor
3rd floor
Roof Deck
6. Plastering Works
1st floor
2nd floor
3rd floor
Roof Deck
7. Steel Works
Resto Bar
Pergola
Roofing 3rd Floor
Art Design Main Entrance
Mesh Wire Cladding in Front
8. Ceiling Works
Framing Works
Installation of Boards
9. Tiling Works
Hallways
Rooms
Cr
16. Doors
17. Windows
Prepared By
Sand 21,500.00
Week 2
Construction Materials
and Tools 810.00 53,000.00
140.00
260.00
1,950.00
1,200.00
240.00
7,720.00
7,550.00
235.00
Sand 10,000.00
CHB 9,600.00
7,800.00
5,200.00
7,800.00
Chipping hammer by Sir Jerzon 11,000.00
1,500.00 400.00
320.00
1,820.00 400.00
72,659.00
2,000.00 330.00
100.00
2,000.00
150.00
4,250.00 330.00
129,085.00
Total Construction Cost as of July 18 2020 201,744.00