Sunteți pe pagina 1din 7

NIPUN CONSULTANTS

Proposal for Knowledge Management


System at Don Bosco School

Manohar Gadre : 9030241015


Kranti Deori: 9030241013

1/26/2011

The document provides a proposal for developing knowledge management system at Don Bosco
School, Hinjewadi Pune as suggested by Nipun Consultants, Pune.

1
Table of Contents

1 Preface ................................................................................................................................ 3
2 Scope of Work .................................................................................................................... 3
3 Client Dependencies & Commitment ................................................................................. 4
4 Project Effort & Duration ................................................................................................... 5
5 Price, Terms & Conditions ................................................................................................. 5
5.1 Price............................................................................................................................. 5
5.2 Pricing Model .............................................................................................................. 6
5.3 Set-Offs & Discounts .................................................................................................. 6
5.4 Taxes & Duties ............................................................................................................ 6
5.5 Validity of proposal ..................................................................................................... 6
6 Payment terms .................................................................................................................... 7
7 Commencement of Work.................................................................................................... 7

2
1 Preface
Don Bosco School (Here in after called DBS) is public school located in Hinjewadi,
Pune affiliated to Central Board of Secondary Education, New Delhi. It is school of great
repute with over 15 years in existence. The school provides education up to 10th Standard
with English as a medium of instruction.

Nipun Consultants (Here in after called as NC) is leading consultant in developing


information technology solutions in the e-learning domain and has an in-depth
experience in developing knowledge management systems.

DBS has requested NC to propose a solution for developing a Knowledge Management


System for modernization of teaching & learning activities for students of classes’ 8th, 9th
& 10th standards. DBS has requested NC to provide a solution covering following areas:

1. A software tool that would aid the delivery of contents by the teachers by using
computers, projectors and audio systems in class rooms for 8th,9th & 10th standards.
2. A library of contents in self running mode accessed by students through kiosks
placed in library.
3. A tool for providing self based evaluation on each topic or subject accessed through
kiosks placed in library.

Based on the above stated requirements NC proposes following options for solution:

Option A: An On Premise model based on web server architecture with server in school
premises.

Option B: A detailed System Requirement Study document and building a prototype


model for proposed system.

2 Scope of Work
Option A: (System Requirement study along with implementation)

 Conducting a System Requirement Study for understanding the user requirements in


detail.
 Developing architecture for proposed system.
 Building a prototype model for the system.
 Procuring necessary hardware & software licences for development and end users.
 Developing tools for accomplishing specified objectives of content delivery in class
room mode & self delivery mode along with self based evaluation.
 Setting up necessary infrastructure in the school for meeting the objectives.
 Deploying the system & accomplishing user acceptance testing.
 Providing necessary training.

Option B: (Only System Requirement Study & development of architecture)

3
 Conducting a System Requirement Study for understanding the user requirements in
detail.
 Developing architecture for proposed system.
 Building a prototype model for the system.

3 Client Dependencies & Commitment


All the system access, human resources interaction, remote connectivity, access to
physical infrastructure required to facilitate the timely completion of implementation/
customization of Knowledge Management System (KMS) will be provided to NC by
DBS. In addition following dependencies have been identified by NC.

Sl. No. Activities Sub-activities/ Deliverables Dependency

1. Knowledge Transfer by DBS on KMS Training Sessions, Interviews, DBS


environment, Existing process Close Group Discussions with
changes, Network Configurations. both the teams, AS IS process
documentation, Preliminary
Project Plan, Preliminary
Project Scope document,
Project Charter

2. Deployment & Configuration of the Installing projectors, Desktops, NC


software and hardware Kiosks, LAN connections and
required operating systems/
applications

3. Provide necessary access to relevant Access Permissions, Temp ID DBS


systems for Implementation and cards
Provide access to relevant
documentation for understanding
existing system.

4. Detail Requirements Gathering, Requirement Specification DBS


Document Review / Signoff Document, Project Scope, Project
Plan, Schedule Plan, Accepted
Deliverables, Change Requests

5. Overall Coordination for the PM Plan, Communications DBS


engagement Management Plan, Project Scope,

4
Schedule Plan

4 Project Effort & Duration


Option A

The estimated time for each of the activities specified is given below:

Sr Activity Duration
No.
1 System Requirement Study 4 Weeks
2 Developing architecture for proposed system 2 Weeks
3 Building a prototype model 3 Weeks
4 Procuring Hardware (Desktops/ Kiosks/ Servers/ 2 Weeks
Routers)
5 Developing tools for accomplishing specified 6 Weeks
objectives:
 Content delivery
 Self delivery mode
 Self based evaluation
6 Setting up infrastructure 2 Weeks
7 Deploying the system & achieving user acceptance 2 Weeks
8 Providing necessary training 2 Weeks
Total 23 Weeks

Option B

The estimated time for each of the activities is specified is given below:

Sr Activity Duration
No.
1 System Requirement Study 4 Weeks
2 Developing architecture for proposed system 2 Weeks
3 Building a prototype model 3 Weeks
Total 9 Weeks

5 Price, Terms & Conditions


5.1 Price
NC believes in activity based costing for each of the activities being carried out under
various options offered to DBS. The pricing can be described below:

Option A

5
Sr Activity Pricing
No.
1 System Requirement Study Rs. 2,00,000
2 Developing architecture for proposed system Rs. 1,25,000
3 Building a prototype model Rs. 1,25,000
4 Procurement of H/W (Based on Market Prices of the Rs 12,00,000 (Approx)
components required)
5 Developing tools for accomplishing specified Rs. 4,00,000
objectives:
 Content delivery
 Self delivery mode
 Self based evaluation

6 Setting up infrastructure Rs. 1,00,000


7 Deployment of Software/Hardware Rs. 1,00,000
8 Providing Training to end users Rs 1,25,000
Total Rs. 23,75,000

Option B:

Sr Activity Pricing
No.
1 System Requirement Study Rs. 2,00,000
2 Developing architecture for proposed system Rs. 1,25,000
3 Building a prototype model Rs. 1,25,000
Total Rs. 4,50,000

5.2 Pricing Model


The pricing model is based on efforts required to complete each activity as specified by
the time duration with best efforts from the consultants at NC. The rates charged are as
per industry standards & applied in relation to the assignment at hand.

5.3 Set-Offs & Discounts


In case DBS decides initially to choose Option B, however, if it wishes to continue with
NC for carrying out the development & implementations as specified in Option A.
There would be waiver for fees charged for the activities already carried out. The
pricing for other activities would remain the same.

5.4 Taxes & Duties


The above prices shall be exclusive of taxes, including transaction taxes, sales tax,
service tax, import duties etc. All such taxes shall be borne by DBS. The above is also
exclusive of expenses like travel & accommodation outside Pune city limits which
would be billed at actuals by NC.

5.5 Validity of proposal


The proposal and mentioned pricing remains valid for a period of Six months from the
date of submission of the proposal. If there is no work order/ purchase order issued

6
against this proposal by DBS within Six months of submission of this proposal, then all
the conditions & pricing of the proposal stands void.

6 Payment terms
The payment schedule for both Option ‘A & B’ will be as per following norms:

1. 80% of stated amount before the start of each activity of the project.
2. 20% of amount within 15 days of accomplishment of the specific activity.

7 Commencement of Work
The work would be commenced by NC within 2 weeks of release of purchase order &
accomplishment of down payment, amounting to 80% amount of first activity for either
of options.