Sunteți pe pagina 1din 4

EXPEDITING VISIT REPORT AT STRUFFER MECHANICAL ENGINEERS

Date : 02/09/2020

CLIENT – ORIENTAL AROMATIC LTD

PROJECT - SCD-10KL-VADODARA

PO NO – PO/1920/04457 Dated 06-03-2020

Tag No – TF-4601, TF-4602,TF-4603,TF-4604 & TF-4605

Vendor - Strufer Mechanical Engineers

CDD dated – 30/03/2020

Manpower – Fitter -02, Grinder -02,Welder -03, Driller -01 No,Helper -01

Expediting Visit carried out at Strufer Mechanical Engineers Pvt Limited and following Progress as
follows

Tag TF-4601 (3000mmID x 6mm Thick x 4500mm lg)

27/08/2020

1. Shell material cut as per size and circumference. Shell material outsourced to Vendor Jai Ambe
for Shell rolling. No Shell Rolling work Started till date. Total Shell Segment required are 3 nos
with length 1540mm,1540mm and 1420mm
2. Bottom Plate Longseam welding completed along with Radiography.
3. Cone Fabrication completed. Longseam welding of Cone balance.
4. fabrication of Curb Angle completed.

30/08/2020 - Nozzle Prefabrication work is in progress.

31/08/2020- Rolling of Handrailing pipe completed.

01/09/2020 & 02/09/2020

Nozzle to Pipe fit up completed for Tag N1A/N1B ( Qty - 02 Nos -25NB Sch 40)

Nozzle to Pipe fit up for N8 (Size – 40NB Sch 40)

Nozzle to Pipe fit up for N10 (Size – 50NB Sch 40)

Tag TF-4602 (3000mmID x 6mm Thick x 4500mm lg)

27/08/2020

1. Shell material cut as per size and circumference. Shell material outsourced to Vendor Jai Ambe
for Shell rolling. No Shell Rolling work Started till date. Total Shell Segment required are 3 nos
with length 1540mm,1540mm and 1420mm
2. Bottom Plate Longseam welding completed along with Radiography.
3. Cone prefabrication completed and Longseam welding of Cone balance.
4. fabrication of Curb Angle completed.
EXPEDITING VISIT REPORT AT STRUFFER MECHANICAL ENGINEERS

30/08/2020 – Nozzle Prefabrication work is in progress.

31/08/2020 – Rolling of Handrailing pipe completed.

01/09/2020 & 02/09/2020

Nozzle to Pipe fit up completed for Tag N1A/N1B ( Qty - 02 Nos -25NB Sch 40)

Nozzle to Pipe fit up completed for N8 (Size – 40NB Sch 40)

Nozzle to Pipe fit up completed for N10 (Size – 50NB Sch 40)

Tag TF-4603 (3000mm ID x 6mm thick x 4500mm Lg)

27/08/2020

1. Top and Bottom Shell Long seam welding completed. Middle Shell rolling and set up balance
2. Curb angle to Top shell welding is in progress. Bottom Shell to Bottom plate welding completed.
Bottom plate Radiography completed.
3. Cone Fabrication completed. RT of Cone balance.

30/08/2020 –

1. Roof Cone to Curb angle fit up and welding completed. Roof cone Nozzle opening marking also
completed for the same.
2. Intermediate shell rolling and set up completed. Longseam welding completed from one side and
backchip is in progress.
3. Nozzles Prefabrication completed. Handrail rolling is in progress.

31/08/2020 –

1. Nozzle and Rafter set up on Roof Cone completed. Welding is in Progress.


2. Lifting Lug on Shell fit up completed and welding is in progress.
3. Intermediate shell welding completed and gauging completed. V preparation completed on both
the shell.
4. Handrail pipe rolling completed.

01/09/2020 & 02/09/2020

1. Nozzle to roof cone outside welding completed. Inside Backchip completed along with welding.
2. Internal Nozzle flush grinding completed. Handrail cleats to Curb angle fit up and welding
completed. Stiffners to Nozzle fit up and welding completed. V Preparation of Top Shell
completed.
3. Top shell to Intermediate shell fit up completed.

Tag TF-4604 (3000mm x 6mm Thick x 4500mm lg)

27/08/2020

1. Top and Bottom Shell Long seam welding completed. Middle Shell rolling and set up balance.
2. Curb angle to Top shell welding is in progress. Bottom Shell to Bottom plate welding completed.
Bottom plate Radiography completed.
EXPEDITING VISIT REPORT AT STRUFFER MECHANICAL ENGINEERS

3. Cone Fabrication completed. RT of Cone balance.

30/08/2020

1. Roof Cone to Curb angle fit up and welding completed. Nozzle along with RF pad set up on roof
cone completed. Rafter Fit up on cone is in progress.
2. Intermediate shell rolling and set up completed. Longseam welding completed from one side and
backchip is in progress.
3. Nozzles Prefabrication completed. Handrail rolling is in progress.

31/08/2020

1. Nozzle Welding on Roof cone completed. Rafter fit up and welding on cone completed.
2. Lifting lug fit up and welding on shell completed.
3. Intermediate shell welding completed and gauging completed. V Preparation of Shell
completed.
4. Nozzle Backchip on Roof cone is in Progress.

01/09/2020 & 02/09/2020

1. Top Shell to Intermediate shell to Bottom Shell fit up completed.


2. Top shell to Intermediate shell to bottom shell cirseam welding from Inside Completed. Inside
seal welding from curb angle to shell is in progress.
3. Nozzle and Manhole opening done on shell .

Tag TF-4605 (3000mm x 6mm Thick x 4500mm lg)

27/08/2020

1. Top and Bottom Shell Long seam welding completed. Middle Shell rolling and set up balance.
2. Curb angle to Top shell welding is in progress. Bottom Shell to Bottom plate welding completed.
Bottom plate Radiography completed.
3. Cone Fabrication completed. RT of Cone balance.

30/08/2020 –

1. Roof Cone to Curb angle fit up and welding completed. Roof cone Nozzle opening marking also
completed for the same.
2. Intermediate shell rolling and set up completed. Longseam welding completed from one side and
backchip is in progress.
3. Nozzles Prefabrication completed. Handrail rolling is in progress.

31/08/2020

1. Nozzle and Rafter set up on Roof Cone completed. Welding is in Progress.


2. Lifting Lug on Shell fit up completed and welding is in progress.
3. Intermediate shell welding completed and gauging completed.
4. Handrail pipe rolling completed.
EXPEDITING VISIT REPORT AT STRUFFER MECHANICAL ENGINEERS

01/09/2020 & 02/09/2020

1. Lifting lug to curb angle welding completed


2. Nozzle to Roof cone outside welding completed . Backchip grinding is in progress.
3. Rafter to cone welding completed.