Sunteți pe pagina 1din 39

Sunnica Energy Farm

Consultation Booklet
22 September - 2 December 2020
275000
Sunnica Energy Farm Proposed Layout

Sunnica East Site A

Sunnica East Site B


270000

About us
File Name:C:\Users\Anna.Dilieto\AECOM Directory\Sunnica Energy Farm - GIS - General\Layout\Communications_Team\200902_SunnicaEnergyFarm_Comms_SchemeBoundary.mxd

Sunnica Energy Farm is


being brought forward by
Sunnica Limited – a joint Sunnica West Site B

venture between two


established solar developers,
Tribus Energy and PS
Renewables. Together, the
Sunnica West Site A
Scheme partners have
assembled an experienced Burwell National
Grid Substation
team with a strong track
record of delivering high
quality solar and energy
storage developments.
265000

0 1,000 2,000 3,000 4,000 5,000m


560000 565000 570000
Introduction

Welcome to this consultation booklet on


our proposals for Sunnica Energy Farm

We originally planned to hold a statutory consultation Since then, we have considered the feedback we
in early 2020 and had hoped to hold a series of public received from the non-statutory consultation and have
events to showcase our proposals, which have been continued with our environmental impact assessments.
updated following the non-statutory consultation we We have updated our proposals taking into account
held in 2019. However, due to the ongoing COVID-19 the consultation feedback and the outputs of the
pandemic, it has taken us longer to reach this point than assessments. As a result, we are now seeking your views
we had anticipated, and we are now asking for your views on our design proposals and the preliminary outcomes
using alternative methods to the previous consultation. of our environmental impact assessments.

We have thought carefully about how to ensure that This is a statutory consultation process that we are
everyone across the community can respond to our required to carry out by the Planning Act 2008 because
consultation on the proposed Sunnica Energy Farm. the project is classified as a Nationally Significant
We have developed a revised approach to consultation Infrastructure Project (NSIP). We are holding this
during the COVID-19 pandemic, working closely with the statutory consultation between 22 September 2020 and
relevant local authorities. You can find out more about 2 December 2020.
how you can respond to the consultation at the end of
this booklet. Following the consultation, we will have regard to the
feedback received through this process as we develop
We first introduced our initial proposals during a the final Scheme. We will then prepare and submit an
non-statutory consultation held between June and July application for a Development Consent Order (DCO). The
2019. These are for a new solar energy farm and battery planning process for the application will be managed
storage facility connecting to the Burwell National Grid by the Planning Inspectorate (PINS) on behalf of the
Substation in Cambridgeshire that would allow for the Secretary of State for Business, Energy & Industrial
generation, storage, import, and export of electricity. Strategy (BEIS).

1
The planning
process
The proposed Sunnica Energy Farm is classified as a Nationally Significant 47 of the Planning Act 2008; and to publicise the Scheme locally and nationally
Infrastructure Project (NSIP) because its proposed generating capacity is higher under section 48 of the Planning Act 2008. It also provides a fixed role for local
than 50MW. authorities and means we will be following a well-established and clear process to
develop the proposals for the Scheme.
NSIPs are major developments which require planning permission to be granted by
the relevant Secretary of State through a Development Consent Order (DCO). This Voluntarily, we carried out a non-statutory consultation on the Scheme proposals
is a process established by the Planning Act 2008. during June and July 2019. We are now carrying out this further, statutory,
consultation to fulfil the requirements of the Planning Act 2008. Our next step, at
Unlike local planning permissions, which are considered by local authorities, DCO the end of the consultation, will be to have regard to all the feedback we receive
applications are made to the Planning Inspectorate (PINS). This independent and, where appropriate, revise the Scheme accordingly. A consultation report will
body administers the application process on behalf of the relevant Secretary of then be submitted as part of our DCO application which will explain how we had
State, including a maximum six month examination into the proposals with which regard to this feedback.
interested parties can get involved. In this case, the appropriate government
department is the Department for Business, Energy & Industrial Strategy (BEIS). We have set out details of how we intend to consult with the local community
under section 47 of the Planning Act 2008 in a document called a Statement of
DCOs are governed by a fixed, statutory process which requires us to consult Community Consultation (SoCC). Details of how to view the SoCC are provided
with persons with an interest in the land and certain bodies as prescribed later in this booklet.
under section 42 of the Planning Act 2008; the local community under section

Indicative Timeline

AUTUMN 2020 WINTER 2020 SPRING 2021 SUMMER 2021 SUMMER 2022 AUTUMN 2022 AUTUMN/WINTER 2022
Statutory Finalise our Submit our PINS begins Decision Post-decision If approved,
consultation Scheme DCO application examination expected period construction
proposals starts on site

2
The Environmental Impact
1. Scope
Consult with statutory bodies on the type

Assessment process and method of assessments we need to


carry out.

For the proposed Sunnica Energy Farm, we are required 2. Conduct assessments
to carry out an Environmental Impact Assessment (EIA)
Including air quality, landscape and
of our proposals as part of the planning process. visual amenity, transport, noise, vibration,
socioeconomics, cultural heritage,
water and flood risk, ecology and nature
The output from this assessment has informed the site conservation, and any cumulative effects.
design and content of this consultation.

As part of the EIA design process, we formally areas such as ecology, landscape, and visual
‘scoped’ our approach with PINS and, on the impacts that were raised during the last
3. Consult
11 April 2019, we received its formal Scoping consultation. The results are presented
Publish the preliminary results of our
Opinion. This confirmed the scope of work in a document called the Preliminary
findings during the statutory consultation.
that should be included in our EIA and should Environmental Information Report (PEI
be reported in the Environmental Statement Report). You can view the PEI Report on our
that will accompany our DCO application website (www.sunnica.co.uk/downloads).
when submitted to the Secretary of State.
In addition to this, we have considered the Following this statutory consultation, we
will have regard to all feedback received and
4. Consider
feedback we received through the non-
statutory consultation and have continued will finalise the Environmental Statement. Consider all feedback received and
to engage with local authorities and other This will be submitted in support of our finalising our Environmental Statement.
regulatory bodies, such as Historic England DCO application and will set out the final
and the Environment Agency, on our approach outcomes of our assessments, as well as
to the EIA. details of any proposed mitigation. During
the statutory consultation process, we will
We are now sharing the preliminary results of continue to engage with other regulatory 5. Submit
our assessments as part of this consultation. bodies.
This booklet summarises our findings in We must submit an Environmental
Statement as part of our DCO application.

3
Our previous
consultation

We held a non-statutory We asked for views on our outline proposals for the The issues raised during the non-statutory
Scheme and our proposed approach to assessing its consultation have informed the content we are
consultation on the proposed environmental impacts. We received 265 responses presenting as part of this consultation and are
Sunnica Energy Farm in June overall. The issues most commonly raised through addressed in this booklet and the PEI Report. We
the consultation were: present more information on how specific pieces
and July 2019. As part of the of feedback have influenced our proposals later in
consultation, we wrote to 1. The scale of the proposed Sunnica Energy Farm – this booklet.
many people who responded felt it was too large
more than 10,000 addresses
2. The proximity of parts of the proposed Scheme
in the local area, held 8 boundary to nearby homes
public exhibitions, and made 3. The visual impact of the Scheme
information available online. 4. The loss of valued agricultural land

5. The need for the Scheme to include extensive


screening/mitigation

4
5
Our proposals

We are proposing to build a new energy farm with solar


photovoltaic (PV) and energy storage infrastructure
connecting to the Burwell National Grid Substation in
Cambridgeshire.

As you will see, the Scheme is now located across four sites as set out in We have considerably reduced the degree to which our Scheme impacts
the plans on page 7. These are: on nearby communities as part of this process. Around 26% of the land
within the Scheme boundary is no longer proposed for energy production
• Sunnica East Site A, near Isleham
or battery storage. It will instead be used for landscaping, ecological or
• Sunnica East Site B, near Freckenham and Worlington archaeological mitigation purposes. The areas proposed for development
• Sunnica West Site A, near Chippenham and Kennett are now set further back from nearby villages. One of the sites that
we presented at the non-statutory consultation – Sunnica East – now
• Sunnica West Site B, near Snailwell comprises two smaller sites: Sunnica East Site A and Sunnica East Site B.

The following pages will detail the specific features of each site. We have also further developed our proposals for connecting Sunnica
Energy Farm to the National Grid. This has included confirming the route
Since the last consultation, we have looked carefully at where we would
that the underground cable will take from the above sites to the connection
locate the different elements that comprise the Scheme and how we would
point at Burwell. Whilst the cable corridor route has been confirmed, the
manage their impact on the local environment. We are now able to show
width of the corridor remains wider than will actually be required as we are
the locations of the different elements of the Scheme in our proposals,
still undertaking environmental assessment and design work.
such as solar panels, battery storage, landscaping, and screening. These are
shown in the plans in this section of the booklet.

6
The Scheme Boundary

560000 565000 570000


THIS DRAWING IS TO BE USED ONLY FOR THE PURPOSE OF
ISSUE THAT IT WAS ISSUED FOR AND IS SUBJECT TO AMENDMENT

LEGEND
Scheme Boundary
275000

Sunnica East Site A

Sunnica East Site B

NOTE:
Public highways run through the Sunnica East Site,
which are not part of the site boundary. These have
been digitised based on the 1:1250 scale OS
270000

Mastermap.
File Name:C:\Users\Anna.Dilieto\AECOM Directory\Sunnica Energy Farm - GIS - General\Layout\Communications_Team\200902_SunnicaEnergyFarm_Comms_SchemeBoundary.mxd

Copyright:
Contains OS data © Crown copyright and database right 2020

Sunnica West Site B

Purpose of Issue

COMMUNICATIONS
Client

SUNNICA LTD
Sunnica West Site A
Project Title

Burwell National
Grid Substation

Drawing Title

SCHEME BOUNDARY
265000

Drawn Checked Approved Date


AD DW NC 02/09/2020
AECOM Internal Project No. Scale @ A3
60589004 1:50,000
THIS DOCUMENT HAS BEEN PREPARED PURSUANT TO AND SUBJECT TO THE
TERMS OF AECOM'S APPOINTMENT BY ITS CLIENT. AECOM ACCEPTS NO LIABILITY
FOR ANY USE OF THIS DOCUMENT OTHER THAN BY ITS ORIGINAL CLIENT OR
FOLLOWING AECOM'S EXPRESS AGREEMENT TO SUCH USE, AND ONLY FOR THE
PURPOSES FOR WHICH IT WAS PREPARED AND PROVIDED.

AECOM
Unit 1 Wellbrook Court,
Girton,

±
Cambridge, CB3 0NA
United Kingdom
Telephone (01223) 488000
www.aecom.com

Drawing Number Rev

0 1,000 2,000 3,000 4,000 5,000m 60589004_COMMS_001 0


560000 565000 570000

7
Sunnica East Site A and Sunnica East Site B

We received a large number of comments In particular, each site will include the following elements:
about Sunnica East during the last round of
consultation. Sunnica East was the largest of the Sunnica East Site A
initial proposed sites and was located between • Solar PV panels
Freckenham and Worlington. The most consistent
• Solar stations
comments were that it was too large, that it
was too close to homes and surrounding nearby • A battery energy storage system (BESS) and electrical compound made up of a substation and control
villages, that its visual impact was significant, and building within the area marked E33 on the plan
that views of Sunnica East from homes as well as • Office space including mobile welfare units, canteens, and storage space. This will be in use for the duration
roads and footpaths going through the site would of the Scheme’s operating life. We propose that this is located within the area marked E33 on the plan
need to be screened. There were also concerns
• A number of internal access tracks
about the impact of development on wildlife.
• Visual and ecological mitigation including offsets, grassland planting, new woodland, and infilling of
In response, we have developed a landscaping existing vegetation at a number of areas marked on the plan
scheme to mitigate the visual impact of the
• An archaeological mitigation area with native grassland planting to be located between the areas marked
proposals. This includes setting back solar
E05 and E07 on the plan
panels from the parts of the Scheme boundary
near homes and introducing planting and
Sunnica East Site B
screening, particularly in areas where the fields
containing development would be visible from • Solar PV panels
homes and roads through the site. We have
• Solar stations
also set aside parts of the site for ecological
mitigation – there is more information about • A battery energy storage system (BESS) and electrical compound made up of a substation and control
this in the following pages. building within the area marked E18 on the plan

• A compound area for offices and storage space that will be used for the duration of the Scheme’s
The design of the Scheme for the original Sunnica operating life. The proposed location for this is within the area marked E18 on the plan
East site has therefore evolved with the creation
• A primary access point for Sunnica Energy Farm from the road network via the A11 and B1085
of two smaller sites, which we are calling Sunnica
East Site A and Sunnica East Site B. Both sites • A number of internal access tracks
are detailed in the plan on page 9.
• Visual and ecological mitigation including offsets, grassland planting, retention of existing woodland, new
woodland, and infilling of existing vegetation at a number of areas marked on the plan

8
Sunnica East Site A and Site B Parameter Plan

566000 567000 568000 569000 570000 571000


THIS DRAWING IS TO BE USED ONLY FOR THE PURPOSE OF
ISSUE THAT IT WAS ISSUED FOR AND IS SUBJECT TO AMENDMENT
4m
3m
7m
4m 6m LEGEND
275000

4m
6m 7m
Scheme Boundary
Public Highway within Scheme
8m

Proposed Scheme Plan


11m
6m
4m 4m
C
" 3m 4m
E01 " E02
C Developable Area
11m

C
" Boundary Fence
BESS and Substation
4m 7m

C
"
C
" 6m
Compound Area (Permanent)
C
"
Solar PV Array
7m
C
"
E04
E03 C
" Illustrative Locations of Solar
C
" C
" C
"
Station
8m 8m
9m

C
" C
" C
" C
" C
"
Proposed Road
274000

7m 9m

E33 6m Green Infrastructure


E05 Office/Warehouse
8m
Native Grassland Planting within
9m
C
" C
" C
" Archaeological Mitigation Areas
E08 10m

Native Grassland Planting


7m
C
"
C
"
Proposed Woodland (new
E09
8m

C
" E10 planting or infilling of existing
C
" 9m
12m C
" C
" 9m
9m
6m
vegetation)
Retained Woodland
8m
13m

Sunnica
8m

Proposed Hedgerow (new


File Name:C:\Users\Anna.Dilieto\AECOM Directory\Sunnica Energy Farm - GIS - General\Layout\PEIR\Chapter_3_Scheme_Description\200907_SunnicaEnergyFarm_PEIR_Figure 3-1_SunnicaEastA_B_Parameter_Plan.mxd

planting or infilling of existing


8m
East Site A vegetation)
17m
Potential Provision of Permissive
Route
273000

9m

C
"
E11
14m Copyright:
C
" C
" E27
C
"
11m
E23 11m
E26 Contains OS data © Crown copyright and database right 2019
Contains public sector information licensed under the Open Government
E07 C C
" C
"
C
" Licence v3.0
C
" E24 C " C" 12m
C
" C
" " C
" Sheet Layout
C
" C
"
E30 E32
C
"
C
" E28 E29 E31
10m
13m C
" C
" C
" C
" C
" C
" C
"
E12
E25 C
14m
" 13m

C
" C
" C
"

8m 14m
E13
7m
14m
C
" C
"
Sunnica
14m
Purpose of Issue

PEIR
39m

East Site B
272000

Client
9m

SUNNICA LTD
12m E14 37m

8m
9m C
"
Project Title
12m

E15
C
"
C
" E17
C
" C
" 26m

17m
E16 C
"

Drawing Title
14m
E18 FIGURE 3-1
SUNNICA EAST SITE A AND B
C
PARAMETER PLAN
12m
17m " 19m
17m

E19 C
"
E20
271000

18m Drawn Checked Approved Date


14m
12m AD DW NC 07/09/2020
C
" C
" 17m
18m
AECOM Internal Project No. Scale @ A3

E21 19m
60589004 1:18,000
C
" THIS DOCUMENT HAS BEEN PREPARED PURSUANT TO AND SUBJECT TO THE
TERMS OF AECOM'S APPOINTMENT BY ITS CLIENT. AECOM ACCEPTS NO LIABILITY
FOR ANY USE OF THIS DOCUMENT OTHER THAN BY ITS ORIGINAL CLIENT OR
16m C
" FOLLOWING AECOM'S EXPRESS AGREEMENT TO SUCH USE, AND ONLY FOR THE

E22 19m 18m


PURPOSES FOR WHICH IT WAS PREPARED AND PROVIDED.

16m AECOM

±
Unit 1 Wellbrook Court,
18m Girton,
Cambridge, CB3 0NA
United Kingdom
19m 12m 19m Telephone (01223) 488000
www.aecom.com
16m
Drawing Number Rev
18m

60589004_PEIR_SD_001 0
18m
0 500 1,000m
566000 567000 568000 569000 570000 571000

9
Sunnica West Site A and Sunnica West Site B

While we received fewer comments overall In particular, each site will include the following elements:
about Sunnica West Site A and Sunnica West
Site B than Sunnica East during the last round of Sunnica West Site A
consultation in 2019, they were along similar lines • Solar PV panels
to those of Sunnica East.
• Solar stations
A number of responses said the site was too • A battery energy storage system (BESS) and electrical compound made up of a substation and control
large, while others said it was too close to building within the area marked W17 on the plan
housing, that they were concerned about loss of
• A compound area for offices and storage space that will be used for the duration of the Scheme’s
farmland, and that they were concerned about
operating life. The proposed location for this is within the area marked W17 on the plan
impacts on wildlife.
• A primary access point for Sunnica Energy Farm from the road network via the Chippenham junction of the A11
We have developed a landscaping scheme for
• A number of internal access tracks
the Sunnica West sites taking these comments
into account. As with Sunnica East, this includes • Visual and ecological mitigation including offsets, grassland planting, retention of existing woodland, new
setting back solar panels within fields as well woodland, and infilling of existing vegetation at a number of areas marked on the plan
as planting and mitigating views into and out
• An archaeological mitigation area with native grassland planting to be located between the areas marked
of the sites. It also includes areas set aside for
W07 and W09 on the plan and between the areas marked W03 and W04
ecological and archaeological mitigation.

Our revised proposals for Sunnica West Site A Sunnica West Site B
and Sunnica West Site B are set out in the plan • Solar PV panels
on page 11.
• Solar stations

• A number of internal access tracks

• Visual and ecological mitigation including offsets, retained native grasslands and wetlands, and retained
woodland marked on the plan

• An archaeological mitigation area with native grassland planting to be located within the area marked W01
on the plan

10
Sunnica West Site A and Site B Parameter Plan

564000 565000 566000 567000 568000 569000


270000

THIS DRAWING IS TO BE USED ONLY FOR THE PURPOSE OF


13m ISSUE THAT IT WAS ISSUED FOR AND IS SUBJECT TO AMENDMENT

LEGEND
Scheme Boundary
Woodstore - 20m Buffer
18m
18m
Proposed Scheme Plan
Developable Area
Boundary Fence
BESS and Substation
Compound Area (Permanent)
Solar PV Array
Illustrative Locations of Solar
C
"
Station
Proposed Road
Green Infrastructure
269000

21m

18m
Native Grassland Planting within
Archaelogical Mitigation Areas
16m

Native Grassland/Wetland
22m
Native Grassland Planting
Heritage Offset with additional
W01 C
" C
" C
"
C
" W02 18m planting along The Avenue
W13 Proposed Woodland (new
C
" C
" C
" planting or infilling of existing
C
"
Sunnica vegetation)
C
" C Retained Woodland
West Site B
"
21m
W14
C
" C
" Proposed Hedgerow (new
planting or infilling of existing
24m
File Name:C:\Users\Anna.Dilieto\AECOM Directory\Sunnica Energy Farm - GIS - General\Layout\PEIR\Chapter_3_Scheme_Description\200907_SunnicaEnergyFarm_PEIR_Figure 3-2_SunnicaWestA_B_Parameter_Plan.mxd

vegetation)
22m
C
"
C
"
Potential Provision of Permissive
Route
268000

22m
" W10
C C
"
C
"
27m
C
" Copyright:
C
" Contains OS data © Crown copyright and database right 2019
C
" W16 Contains public sector information licensed under the Open Government
16m 29m
C
" W11 C
"
Licence v3.0
C
"
C
" Sheet Layout
W08 C
" C
"
19m
C
" C
" W15
34m
C
" C
"
C
" C
"
W17 C
" W12 C
" C
" C
" C
"
W03
28m
31m 22m

C
" C
" C
"
17m C
" C
" C
" C
"
C
" C
"
W06 C
"
W09
C
"
C
"
C
" Purpose of Issue

PEIR
267000

23m C
"
22m
C
" C
"
Client

C
" W07 SUNNICA LTD
C
"
20m
C
" C
"
C
" C
"
Project Title
W04
Office/Warehouse
19m
18m C
"

22m
C
" C
" C
" Sunnica
C
"
W05 West Site A
C
" 28m
C
"
Drawing Title

C
" FIGURE 3-2
SUNNICA WEST A AND B
42m
PARAMETER PLAN
266000

21m Drawn Checked Approved Date


38m
AD DW NC 07/09/2020
AECOM Internal Project No. Scale @ A3
46m
22m 60589004 1:17,500
THIS DOCUMENT HAS BEEN PREPARED PURSUANT TO AND SUBJECT TO THE
TERMS OF AECOM'S APPOINTMENT BY ITS CLIENT. AECOM ACCEPTS NO LIABILITY
FOR ANY USE OF THIS DOCUMENT OTHER THAN BY ITS ORIGINAL CLIENT OR
FOLLOWING AECOM'S EXPRESS AGREEMENT TO SUCH USE, AND ONLY FOR THE
PURPOSES FOR WHICH IT WAS PREPARED AND PROVIDED.

AECOM

±
Unit 1 Wellbrook Court,
Girton,
Cambridge, CB3 0NA
United Kingdom
Telephone (01223) 488000
www.aecom.com
56m
23m Drawing Number Rev
28m

0 500 1,000m
46m
60589004_PEIR_SD_002 0
564000 565000 566000 567000 568000 569000

11
Solar PV Modules

Solar PV technology

We will be using the technology detailed


below across the four sites. The proposed
locations of each element are shown on
the Parameter Plans.

The areas marked as ‘developable’ will include solar photovoltaic (PV) modules The inverters will convert the direct current (DC) electricity collected by the PV
that will convert sunlight into electrical current. We are proposing that each solar modules into alternating current (AC). This needs to happen to ensure that the
module will be approximately up to 2.5m long and 1.3m wide. The modules will electricity generated can be exported to the National Grid.
each consist of a series of PV cells beneath a layer of glass. Each module will
make up a single solar panel. Transformers are required to control the voltage of the electricity generated
by each of the four sites before it reaches a substation. From a substation, the
Each solar PV module will be oriented to the south at a slope of between 15 and electricity is then exported to the National Grid.
35 degrees from the horizontal. The modules will be mounted on a rack that is
driven into the ground. This approach is common across existing UK solar farms. Switchgear is a combination of electrical disconnect switches, fuses or circuit
Each module will be between 0.6m and 2.5m above ground level. This range has breakers. They are used to control, protect, and isolate electrical equipment.
been chosen to assist with visual mitigation.
Each solar station would be situated either outdoors or inside a container.
Solar stations will be constructed at regular intervals across each site, illustrative Indicative images of each of these options are shown on the next page.
locations for these stations are marked on the plans on the previous pages. Each
solar station is made up of an inverter, transformer, and switchgear. Each of these
elements is outlined here:

12
Outdoor Solar Station

Example of White Indoor Solar Station Exterior Indoor Solar Station Interior
LV Cabinet and
Aux. Transformer

MV Switchgear

Transformer

Inverter
Aux. Equipment
DC Disconnection
and Protection Panel
Images reproduced courtesy of Power Electronics

13
Battery storage

During the non-statutory


consultation, we asked for views
on whether the Battery Energy
Storage Systems (BESS) should be
concentrated in specific locations
or spread across different locations
across all the sites.

Typical battery storage compound configuration


(Image reproduced courtesy of Fluence Energy)

A majority of people who responded to the consultation said that the BESS should Each will consist of containers that will house the batteries. The containers will
be concentrated. A number of responses also emphasised that the BESS should be a maximum of 6m in height. Images with the indicative appearance of these
be located away from homes and well screened. containers are shown here.

We are now proposing that the BESS is concentrated at three locations marked on Locating the BESS together means we are better able to screen them from the
the plans on pages 9, 11 and 15. These are: outside. We have looked to locate the BESS away from homes, select appropriate
colours, and screen them with planting.
• Sunnica East Site A – within the area marked E33

• Sunnica East Site B – within the area marked E18 We were asked at our public exhibitions last year about how safe the BESS would be,
particularly with regards to fire risk. We take the risk of a potential fire very seriously.
• Sunnica West Site A – within the area marked W17
Each container would be isolated and would contain an automatic fire control
system. If approved, the Scheme would be subject to a Battery Fire Safety Plan.

14
C
" 11m
E07 C
"

File Name:C:\Users\Anna.Dilieto\AECOM Directory\Sunnica Energy Farm - GIS - General\Layout\PEIR\Chapter_3_Scheme_Description\200907_SunnicaEnergyFarm_PEIR_Figure 3-1_Sunni


C C C
" C
"
C
" C
" E24 C
"
" "
C
" C
" C
"
E30 C
"
E31
566000 C
"
567000 10m 568000 569000 570000 571000 E28 E29
13m C
" C
" C
" C C
" FOR THEC
"TO BE USED ONLY "PURPOS
E12 THIS DRAWING IS

BESS Locations – Sunnica East Site A and Site B E25 C


14m ISSUE THAT IT WAS ISSUED FOR AND IS SUBJECT TO AMEN
3m
4m " 13m
7m
4m 6m C
" C
" C
" LEGEND
275000

4m

8m
6m
14m
7m E13 Scheme Boundary
7m C
" C
"
14m
14m Public Highway within Scheme
8m

Proposed Scheme Plan


11m 39m
6m
4m 4m

272000
C
" 3m
4m
E01 " E02
C 9m Developable Area
11m

C
" E14 Boundary Fence
12m
8m
C BESS and Substation
4m
9m
7m
"
C
"
C
" 12m
6m
E15 Compound Area (Permanent)
C
"
7m
C
"
E04
C
"
C
" E17 Solar PV Array
C
" C
" 26m

E16 C
"
566000 E03 567000 C
" 568000 569000 17m
Illustrative Locations of Solar
C
" C
" C
"
Station
8m 8m
THIS DRAWING IS TO BE USED ONLY FOR THE PURPOSE OF 9m
ISSUE THAT IT WAS ISSUED FOR AND IS SUBJECT TO AMENDMENT
C
" C
" C
" C
"
13m
C
" 14m Proposed Road
274000

LEGEND
7m E18
9m

E33 6m
Scheme Boundary Green Infrastructure
E05
12m
Woodstore - 20m Buffer C
" Native Grassland Planting wit
Office/Warehouse
8m 17m
17m 19m
18m
9m
C
" C
" C
" 18m
Proposed Scheme Plan Archaeological Mitigation Area
E08 10m
Developable Area E197m C
"
C E20 Native Grassland Planting
271000

"
C
" 12m
14m
Boundary Fence
C
" C
"
18m
Proposed Woodland (new
8m BESS and Substation
17m

C
" E09 E10 Compound Area (Permanent) E21 planting or infilling of existing
C
" 9m
C
12m C
" C
" 9m
9m Solar PV Array
6m " vegetation)
Retained Woodland
8m
13m
Illustrative Locations of Solar
16m C
"
C
8m "
Station E22
16m
19m 18m
Proposed Hedgerow (new
8m
Proposed Road planting or infilling of existing
18m
Green Infrastructure vegetation)
21m
Native Grassland Planting within
Potential Provision of Permiss
19m 12m 19m
18m
17m Archaelogical Mitigation Areas
16m Route
273000

16m 9m
18m

C
" Native Grassland/Wetland 18m
0 500 1,000m
E11
14m Copyright:
C C E27
E23 Native Grassland Planting 11m
22m " "
C
"
11m E26 Contains OS data © Crown copyright and database right 2019
566000 567000 568000
Heritage Offset with additional 569000 570000 Contains public sector information licensed under the Open Gov
E07 C C C C
" C
"
C
" Licence v3.0
" " planting along The Avenue E24 C " C"

BESS Location – Sunnica West Site A


18m
C C
" C
"
12m
" W13 C
" Proposed Woodland (new
"
C
" C
"
Sheet Layout

C planting or infilling of existing E30 E32


C " C
"
C
"
"
vegetation) E28 E29 E31
10m
C
" 13m C
" C
" C
" C" Retained Woodland
21m
W14 E12
C
" C
" C
" C
"
C
" C
"
14m
Proposed Hedgerow (new E25 C "
planting or infilling of existing
24m 13m
22m
C
" C
" C
" C"
vegetation)
C
"
Potential Provision of Permissive
8m 14m
E13
7m
C
" C
" Route
14m

" W10
14m
C C
" Purpose of Issue

PEIR
22m 39m
C
"
m
C
"
272000

Copyright:
C
" Contains OS data © Crown copyright and database right 2019
9m
C
" W16 Contains public sector information licensed under the Open Government
Client

W11 Licence v3.0


C
" C
" C
" SUNNICA LTD
W08 12m
C
"
C
" E14 Sheet Layout
37m

8m C
"
9m W15 C
"
C
" C
" Project Title
C
" C
" 12m

C
" C
" E15
W17 C
" W12 C
" C
" C
" C
"
W03 C
"
C
" E17
22m
C
" C
" C
" 26m
C
" C
"
E16 C
"
C
" C
" C
" 17m
C
"
C
" C
"
W06 C
"
W09
C
"
Drawing Title
C
" 14m
C
" E18 Purpose of Issue FIGURE 3-1
C
" PEIR
SUNNICA EAST SITE A AND B
C
C PARAMETER PLAN
12m
17m " C
"
" 19m
Client
17m
C
" W07 SUNNICA LTD
C
"
E19 C
"
C
" E20
271000

20m
C
"
C
" C
" 14m 18m Drawn Checked Approved Date
12m Project Title AD DW NC 07/09/2
W04 C
"
Office/Warehouse
18m
C
" C
" 17m AECOM Internal Project No. Scale @ A3
C
" C
" C
" E21 19m
60589004 1:18,000
C
"
W05 THIS DOCUMENT HAS BEEN PREPARED PURSUANT TO AND SUBJECT
TERMS OF AECOM'S APPOINTMENT BY ITS CLIENT. AECOM ACCEPTS NO
C
" 16m C
"
FOR ANY USE OF THIS DOCUMENT OTHER THAN BY ITS ORIGINAL CLIE
FOLLOWING AECOM'S EXPRESS AGREEMENT TO SUCH USE, AND ONLY
C
" 28m
C
" E22 Drawing Title 19m 18m
PURPOSES FOR WHICH IT WAS PREPARED AND PROVIDED.

16m AECOM
C
"
18m
FIGURE 3-2 Unit 1 Wellbrook Court,
Girton, 15
SUNNICA WEST A AND B Cambridge, CB3 0NA
United Kingdom
19m 12m
PARAMETER PLAN 19m Telephone (01223) 488000
Grid connection

The electricity generated and stored by the Scheme will be imported


and exported to the National Grid via underground cables from the
onsite substations to the Burwell National Grid Substation.

To achieve this, we are proposing to install a 132 methods further, prior to the submission of our DCO
kilovolt (kV) cable to connect Sunnica East Site A, application. This amended option is reflected on the
Sunnica East Site B, Sunnica West Site A, and Sunnica plans here and shows a width of up to 50m to allow
West Site B to the Burwell National Grid Substation. for survey work and local conditions. To install the
The proposed route of this cable is shown on the red cable itself, we anticipate that we will use a trench
line boundary plan, running between each of our sites with a width of approximately 1.2m and a depth of
and the grid connection. approximately 2m.

During the non-statutory consultation, we set out two We have also continued our discussions with National
possible options for the route of the cable connecting Grid about the upgrade required to Burwell National
Sunnica East, Sunnica West Site A, and Sunnica West Grid Substation to accommodate the connection. This
Site B to Burwell National Grid Substation. At the time, will involve a small extension to the substation to
we did not know exactly where the cable would be able house a new transformer.
to cross the railway line between Fordham and Snailwell.
We have identified three areas as suitable options
Following consultation with Network Rail, we are for this extension. Each option remains under
now proposing to use the more northern of the two consideration and each is shown on the plan. The three
options – which we referred to as option 1 during the areas identified for Burwell National Grid Substation
last consultation. This has also allowed us to confirm extension are currently agricultural fields. The preferred
the route of the cable through the industrial area and location is within National Grid land ownership to the
across the A142 Fordham Road. east of the existing substation, adjacent to Weirs Drove,
approximately 200m west of Burwell. The alternative
In proceeding with this option, we have made minor two locations are to the north and north-west of the
amendments, including widening its path to allow existing substation approximately 450 and 650m from
for further survey work to be undertaken. This will Burwell, respectively.
enable us to refine our proposed route and tunnelling

16
Cable Route
560000 565000 570000
THIS DRAWING IS TO BE USED ONLY FOR THE PURPOSE OF
ISSUE THAT IT WAS ISSUED FOR AND IS SUBJECT TO AMENDMENT

LEGEND
Grid Connection Red Line Boundary
558000
THIS DRAWING IS TO BE USED ONLY FOR THE PURPOSE OF
Maximum Area for Sunnica East Site A
Maximum Area for Sunnica East Site B
ISSUE THAT IT WAS ISSUED FOR AND IS SUBJECT TO AMENDMENT

LEGEND

Maximum Area for Sunnica West Site A


Scheme Boundary
Maximum Area for Burwell
National Grid Substation
Extension
Potential Area for Alternative
Maximum Area for Sunnica West Site B
Substation
Cable Route A
275000

Cable Route B
Burwell Substation
Option 2

Option 3
File Name:C:\Users\Anna.Dilieto\AECOM Directory\Sunnica Energy Farm - GIS - General\Layout\PEIR\Chapter_3_Scheme_Description\200907_SunnicaEnergyFarm_PEIR_Figure 3-19_PreferredAlternativeLocation_BurwellSubstation.mxd

Burwell National
Burwell Substation

Grid Substation
Copyright:
Ne Contains OS data © Crown copyright and database right 2019
w nha
Contains public sector information licensed under the Open Government
Licence v3.0
mD
rove

Sunnica East Site A


Option 1 Purpose of Issue

PEIR
Client

SUNNICA LTD
ve

Project Title
s Dro
Weir

Sunnica East Site B


FIGURE 3-19
Drawing Title

PREFERRED AND ALTERNATIVE


LOCATIONS FOR BURWELL
NATIONAL GRID SUBSTATION
Scheme Boundary Drawn
EXTENSION
Checked Approved Date
AD DW NC 07/09/2020
267000

AECOM Internal Project No. Scale @ A3


60589004 1:2,500

Preferred Area for Burwell THIS DOCUMENT HAS BEEN PREPARED PURSUANT TO AND SUBJECT TO THE
TERMS OF AECOM'S APPOINTMENT BY ITS CLIENT. AECOM ACCEPTS NO LIABILITY
FOR ANY USE OF THIS DOCUMENT OTHER THAN BY ITS ORIGINAL CLIENT OR

National Grid Substation


FOLLOWING AECOM'S EXPRESS AGREEMENT TO SUCH USE, AND ONLY FOR THE
PURPOSES FOR WHICH IT WAS PREPARED AND PROVIDED.

AECOM

±
Unit 1 Wellbrook Court,
Girton,
Cambridge, CB3 0NA
United Kingdom
2m Telephone (01223) 488000
www.aecom.com

Drawing Number Rev

60589004_PEIR_SD_027 0
NOTE:
0 500m
558000

Public highways run through the Sunnica East Site,


which are not part of the site boundary. These have
been digitised based on the 1:1250 scale OS
270000

Mastermap.
Copyright:
Contains OS data © Crown copyright and database right 2018
File Name:C:\Users\Anna.Dilieto\AECOM Directory\Sunnica Energy Farm - GIS - General\Layout\Communications_Team\200909_SunnicaEnergyFarm_Comms_RLB.mxd

Sunnica West Site B

Purpose of Issue

CONSULTATION
Client

SUNNICA LTD
Sunnica West Site A
Burwell National Project Title

Grid Substation

Drawing Title

RED LINE BOUNDARY


265000

Drawn Checked Approved Date


AD CH NC 09/09/2020
AECOM Internal Project No. Scale @ A3
60589004 1:50,000
THIS DOCUMENT HAS BEEN PREPARED PURSUANT TO AND SUBJECT TO THE
TERMS OF AECOM'S APPOINTMENT BY ITS CLIENT. AECOM ACCEPTS NO LIABILITY
FOR ANY USE OF THIS DOCUMENT OTHER THAN BY ITS ORIGINAL CLIENT OR
FOLLOWING AECOM'S EXPRESS AGREEMENT TO SUCH USE, AND ONLY FOR THE
PURPOSES FOR WHICH IT WAS PREPARED AND PROVIDED.

AECOM
Unit 1 Wellbrook Court,
Girton,

±
Cambridge, CB3 0NA
United Kingdom
Telephone (01223) 488000
www.aecom.com

Drawing Number Rev

0 1,000 2,000 3,000 4,000m 1 0


560000 565000 570000

17
Landscape and visual impact

Assessment Summary
We have assessed potential impacts of the Scheme on the local landscape, the landscape character Several viewpoints close to the Development Consent
areas, views into and out of the site, and visual amenity. This process has involved looking at the Order (DCO) site are anticipated to experience significant
impact of our design proposals from a number of different landscape and visual receptors that effects on their landscape character and visual amenity
have been agreed with the local authorities, including different parts of the Scheme, during the during construction. This is due to the visual appearance
construction, operation, and decommissioning of the Scheme. The selection of viewpoints has of construction works on land that is currently used as
included residential and commercial properties, heritage receptors (Chippenham Park, for example), farmland. This effect will only last for the duration of the
road users, and public rights of ways. construction works.

Assessment outcome and mitigation Some significant effects are expected to occur on
landscape and visual amenity during operation. The effect
The Landscape and Visual Impact Assessment (LVIA) has informed the iterative design process, with
will be less once mitigation planting has been established,
the aim of minimising the effects of the Scheme through design principles which have been embedded
reducing most of these significant visual effects to minor
into our proposals. The embedded mitigation covers the siting, scale, and mass of structures, as
significance. There is only a single viewpoint that is
well as proposed Green Infrastructure (mitigation planting) to improve the landcover and vegetation
anticipated to experience a significant visual effect once
patterns, as well as reducing the visibility of the Scheme, as described in Chapter 3 of the PEI Report
the Green Infrastructure has established. This is the Users
and shown on the Parameter Plans. An Outline Landscape and Ecology Management Plan has been
of the Gallops viewpoint.
drafted and included within the consultation materials (Appendix 10I of the PEI Report) to demonstrate
how the proposed mitigation measures will be delivered. The decommissioning phase is expected to lead to similar
effects to construction, although it would benefit from
These measures reduce the significance of effect of the Scheme from many viewpoints and locations.
the Green Infrastructure shielding some views into the
Some significant adverse effects on landscape and visual receptors are currently predicted to
site and therefore lessening some effects. The long-term
occur during the construction phase, due to temporary changes in landcover and the presence of
effects of the operational Scheme would be reversed
construction machinery. This is inevitable from locations where there are views into the site, from
following decommissioning and reinstatement, albeit the
which there will be an obvious change in the landscape from farmland to a solar farm development.
Green Infrastructure planting would remain.
Some significant adverse effects are also initially predicted to occur during the early years of operation
of the Scheme until the proposed planting and screening measures become established. Full details of
More information
these effects are included in Chapter 10 (Landscape and Visual Assessment) of the PEI Report.
See Chapter 3 (Scheme Description), Chapter 10 (Landscape
It is expected that over time there would be a reduction in the effects on the landscape and visual and Visual Assessment) of the PEI Report, Figures 3-16 and
receptors due to the long-term establishment of the Green Infrastructure, and this would remain 3-17 and Parameter Plan Figures 3-1 and 3-2.
following the eventual removal of the solar panels and associated structures.

18
Ecology

Assessment within the Scheme design for creation of biodiverse habitats to mitigate the loss of existing habitats.
The ecology assessment proposes measures to minimise These mitigation and enhancement areas include at least three nesting plots for stone-curlew, acid
potential impacts and effects of the Scheme on ecology grassland creation/restoration, marshy grassland creation/restoration, and planting of seed-bearing
and nature conservation (biodiversity) during construction, species for overwintering farmland birds.
operation, and decommissioning.
The Scheme has been designed to ensure that existing woodland, treelines, and the majority of
Our assessment has been informed by existing data hedgerows are retained and will be protected during construction of the Scheme, and extensive
sources, a series of habitat assessments, and ecological additional woodland and hedgerow planting throughout the Scheme is embedded within the Scheme
surveys which have been carried out on the site and on design, as shown on the Parameter Plans. In addition, the following embedded mitigation has been
other ecological sites in the surrounding area, and which incorporated into the design:
will continue as necessary up to submission of the DCO • Undeveloped buffers of at least 5m from existing boundary features have been retained
application. throughout the Scheme

• Existing designated sites within the Scheme have been retained and will not be impacted
Assessment outcome and mitigation
The main impact on ecology from the Scheme is expected • The crossing of watercourses where the presence of otter and water vole have been determined,
to be some habitat loss from within the site itself, although as well as the River Kennett, River Snail, Lee Brook, New River, and Burwell Lode, will be
overall the Scheme is being designed to provide biodiversity undertaken using underground methods that do not disturb the watercourse, with appropriate
enhancement. In addition, any disturbance of protected setbacks from the top of the banks (depending on habitats and other individual ecological
species and off-site ecological receptors will be prevented constraints)
and controlled through various control measures. • Throughout the Scheme, the use of motion detection security lighting to avoid permanent lighting
will be utilised and a sensitive lighting scheme will be developed ensuring inward distribution of
Primary mitigation measures are embedded within the
light and avoiding light spill onto existing boundary features
Scheme. These are documented within the draft Outline
Landscape and Ecology Management Plan (LEMP) which A Construction and Environment Management Plan (CEMP) will be used to manage the environmental
outlines the management and mitigation measures to be effects of the Scheme during construction. The CEMP will include control measures such as:
implemented for the Scheme to successfully integrate avoiding the spread of invasive non-native species; no working within 10m of watercourses to
within the context of the site. prevent hazards such as chemical and soils spills into the watercourses; vegetation clearance to be
undertaken at an appropriate time of year so as to avoid harming protected species and the nesting
A total of 214 hectares of embedded mitigation and bird period; and avoidance of protected species’ habitats using certain construction techniques.
biodiversity enhancement areas have been included

19
Where protected species are at risk of being affected, we will use mitigation
strategies and, where required, apply for species licences from Natural England
for translocation of animals away from construction areas sufficiently in
advance of the works to meet with the optimum time for mitigation and to
minimise any changes to the construction programme.

Summary
There are minor adverse impacts predicted on habitats and species as a
result of the construction, operation, and decommissioning of the Scheme.
However, given the embedded mitigation measures provided for the Scheme,
no significant residual adverse effects on ecological features are predicted and
the Scheme is aiming to achieve a net gain in biodiversity value.

More information
See Chapter 8 of the PEI Report.

20
Environmental Landscape Masterplan Sunnica East and West

570000
THIS DRAWING IS TO BE USED ONLY FOR THE PURPOSE OF
ISSUE THAT IT WAS ISSUED FOR AND IS SUBJECT TO AMENDMENT

E01
E02 LEGEND
Scheme Boundary
E04 County Boundary
E03 District Boundary
Public Highway within Scheme
E33 Proposed Scheme Plan
E05 Developable Area
E08
Native Grassland Planting within
E09 E10 Archaelogical Mitigation Areas
Native Grassland/Wetland
Native Grassland Planting
E06 Heritage Offset with additional
planting along The Avenue
E11 Landscape Offset
E27
E23 E24 E26 Proposed Woodland (new planting or
E07 infilling of existing vegetation)
E30 E32 Retained Woodland
E28 E29
Sunnica East Site A E12 E25 E31 Sunnica Chalk Grassland
Potential Provision of Permissive
E13 East Site B Route
Proposed Hedgerow (new planting or
infilling of existing vegetation)
E14

E15 E17
E16
E18

E19 E20
File Name:C:\Users\Anna.Dilieto\AECOM Directory\Sunnica Energy Farm - GIS - General\Layout\Communications_Team\200910_SunnicaEnergyFarm_Comms_LandscapeMasterplan_SunnicaEastWest.mxd

E21

E22
Copyright:
Contains OS data © Crown copyright and database right 2018
Contains public sector information licensed under the Open Government
Licence v3.0
270000

Purpose of Issue

CONSULTATION
Client

SUNNICA LTD
Sunnica West
W01 W02
Site B Project Title

Sunnica West W13

Site A W14
Drawing Title
W10
LANDSCAPE MASTERPLAN
W16 SUNNICA EAST AND WEST
W11
W08
W15
Drawn Checked Approved Date
W03 W17 W12 AD RH NC 10/09/2020
AECOM Internal Project No. Scale @ A3
W06 W09 60589004 1:32,000
THIS DOCUMENT HAS BEEN PREPARED PURSUANT TO AND SUBJECT TO THE
TERMS OF AECOM'S APPOINTMENT BY ITS CLIENT. AECOM ACCEPTS NO LIABILITY
FOR ANY USE OF THIS DOCUMENT OTHER THAN BY ITS ORIGINAL CLIENT OR
FOLLOWING AECOM'S EXPRESS AGREEMENT TO SUCH USE, AND ONLY FOR THE
W07 PURPOSES FOR WHICH IT WAS PREPARED AND PROVIDED.

AECOM
W04 Unit 1 Wellbrook Court,
Girton,

±
W05 Cambridge, CB3 0NA
United Kingdom
Telephone (01223) 488000
www.aecom.com

Drawing Number Rev

0 1,000 2,000m 0
570000

21
Environmental Landscape Masterplan Burwell Substation
560000
THIS DRAWING IS TO BE USED ONLY FOR THE PURPOSE OF
ISSUE THAT IT WAS ISSUED FOR AND IS SUBJECT TO AMENDMENT

LEGEND
Scheme Boundary
County Boundary
District Boundary
Public Highway within Scheme
Proposed Scheme Plan
Developable Area
270000

Native Grassland Planting within


Archaelogical Mitigation Areas
Native Grassland/Wetland
Retained Woodland
Proposed Hedgerow (new planting or
infilling of existing vegetation)
File Name:C:\Users\Anna.Dilieto\AECOM Directory\Sunnica Energy Farm - GIS - General\Layout\PEIR\Chapter_10_Landscape\200902_SunnicaEnergyFarm_Figure10-14b_LandscapeMasterplan_CableRouteBurwellSubstation.mxd

W01

Copyright:
Contains OS data © Crown copyright and database right 2018
Contains public sector information licensed under the Open Government
Licence v3.0

Purpose of Issue

PEIR
Client

SUNNICA LTD
Burwell National Project Title

Grid Substation

Drawing Title

FIGURE 10-14B
LANDSCAPE MASTERPLAN
CABLE ROUTE CORRIDOR
TO BURWELL SUBSTATION
Drawn Checked Approved Date
AD RH NC 02/09/2020
AECOM Internal Project No. Scale @ A3
60589004 1:20,000
THIS DOCUMENT HAS BEEN PREPARED PURSUANT TO AND SUBJECT TO THE
TERMS OF AECOM'S APPOINTMENT BY ITS CLIENT. AECOM ACCEPTS NO LIABILITY
FOR ANY USE OF THIS DOCUMENT OTHER THAN BY ITS ORIGINAL CLIENT OR
FOLLOWING AECOM'S EXPRESS AGREEMENT TO SUCH USE, AND ONLY FOR THE
PURPOSES FOR WHICH IT WAS PREPARED AND PROVIDED.

AECOM
Unit 1 Wellbrook Court,
Girton,

±
Cambridge, CB3 0NA
United Kingdom
Telephone (01223) 488000
www.aecom.com

Drawing Number Rev

0 1,000 2,000m 60589004_PEIR_LSP_030 0


560000

22
Environmental Landscape Viewpoints

Photomontages showing specific views of the site, from different locations, can be downloaded from the scheme website: www.sunnica.co.uk/downloads
Alternatively, physical copies are available on request by calling Freephone 0808 168 7925 and speaking to a member of the project team.
560000 570000
THIS DRAWING IS TO BE USED ONLY FOR THE PURPOSE OF
ISSUE THAT IT WAS ISSUED FOR AND IS SUBJECT TO AMENDMENT

LEGEND
Scheme Boundary
Suffolk County Boundary
County District Boundary
2km Study Area


!
A Representative Viewpoint
A
!


1

A
! 2k m


2b
A


 3
!A
2a
!

A
!
A
4 A

!

!
 
5 12

 
A
!
 26b
A

 !A
!
Cambridgeshire


6

!
12a
A ! A
A!

! A
County

14 14a

East
 


A!
11
! !
A 23a

!
A
24 26a
  A

10
Cambridgeshire
!A


 !


!
A
12b


7

A
25
District 15  !
A

!
A

! 23

! A
13

!
9 15a

A
!
! 
A 22

A
A A


!
15b

8

A
!

 

17 16

A
!
File Name:C:\Users\Anna.Dilieto\AECOM Directory\Sunnica Energy Farm - GIS - General\Layout\PEIR\Chapter_10_Landscape\200902_SunnicaEnergyFarm_Figure10-12_VisualReceptorPlan_Overview.mxd



21

!
18

A
Sunnica East Site A A
Sunnica East Site B
!

!
21a
A
!  19

!A
!
49

A

A
20 27 Copyright:
Contains OS data © Crown copyright and database right 2018


28 Contains public sector information licensed under the Open Government

!
A
Licence v3.0
270000

A
!
A
!  29


30
A
!
31


A
! 
!A !

48

  Sunnica West
47a Purpose of Issue

 PEIR

A
!
A
!

!


A
Site B

A 51 !
32 34

!
!
A 

 

Client
47
A

54

A  

A
!
!


52
46
A
! !
A 35a
36 SUNNICA LTD

AA! A
 
!!A
35

!
A

!

42 33a
50 45
A

A! 
44 !
A 33
! 37b
Project Title

Sunnica West

A

A
!

43

!

A!

41

Site A
A
!

37a 

!
A

A


55 53
37

!
A Drawing Title

 
37c

 A
!  

FIGURE 10-12
VISUAL RECEPTOR PLAN

! A

A


A
! ! OVERVIEW
!
A

57 56

A
!
37d
 !A

58 40

Drawn Checked Approved Date


39 AD RH NC 02/09/2020

 
! West Suffolk
AECOM Internal Project No.
60589004
Scale @ A3
1:50,000

A
!

THIS DOCUMENT HAS BEEN PREPARED PURSUANT TO AND SUBJECT TO THE


39a 38 TERMS OF AECOM'S APPOINTMENT BY ITS CLIENT. AECOM ACCEPTS NO LIABILITY
A

FOR ANY USE OF THIS DOCUMENT OTHER THAN BY ITS ORIGINAL CLIENT OR
FOLLOWING AECOM'S EXPRESS AGREEMENT TO SUCH USE, AND ONLY FOR THE
PURPOSES FOR WHICH IT WAS PREPARED AND PROVIDED.

AECOM
Unit 1 Wellbrook Court,
Girton,

±
Cambridge, CB3 0NA
United Kingdom

East Telephone (01223) 488000


www.aecom.com

Cambridgeshire Drawing Number Rev

0 2,000 4,000 6,000m District 60589004_PEIR_LSP_017 0


560000 570000

23
Environmental Landscape Viewpoints

560000 570000
280000

THIS DRAWING IS TO BE USED ONLY FOR THE PURPOSE OF


ISSUE THAT IT WAS ISSUED FOR AND IS SUBJECT TO AMENDMENT

LEGEND
Scheme Boundary
2km Study Area
Barriers
Building
Woodland
Zone of Theoretical Visibility - with
Barriers
Sunnica West Site Visible Only
Sunnica East Site Visible Only
Both Sites Visible

2k m

NOTES
Generated using Ordnance Surveys Terrain 5 Dataset which is based on 5m
Sunnica East Site A resolution Digital Terrain Model (DTM), incorporating the proposed Solar PV
panels modelled across the site to a maximum anticipated height of 2.5m, and the
proposed substations, modelled to a maximum anticipated height of 8.5m.
Proposed scheme is derived from the proposed Red Line Boundary (RLB) areas
dated 02/09/2020 with reference points included every 20m on a grid across the
full extent of the RLB site. The ZTVS do not include associated buildings which are
not known at this stage.
Sunnica East Site B ZTV calculated using ArcGIS 10.6.1 Viewshed tool with observer eye height 1.7m
above ground.
Visual barriers on the Combined with Barriers ZTV were defined within the
immediate site context up to 5km from the RLB. Woodland areas were derived
from Forestry Commission National Forestry Inventory (NFI), modelled at 10m,
File Name:C:\Users\Anna.Dilieto\AECOM Directory\Sunnica Energy Farm - GIS - General\Layout\PEIR\Chapter_10_Landscape\200902_SunnicaEnergyFarm_Figure10-11f_ZTV_withBarriers_Combined.mxd

and the National Tree Map, using the maximum tree height value, and buildings
were derived from OS MasterMap using the accurate OS Building Height Attribute
(BHA) data. For buildings outside the BHA coverage, heights were modelled at
8m, and the dataset extracted from OS Open Local vector based building layers.

Copyright:
Contains OS data © Crown copyright and database right 2018
Contains public sector information licensed under the Open Government Licence v3.0
This map uses data that is public sector information from Suffolk County Council. The data is
270000

licensed on terms equivalent to the Ordnance Survey OpenData Licence. The date of this
data is 09.10.2018
Contains Natural England data ©. Contains Historic England data ©. Contains Environment
Agency data ©. Contains NTM data 2019 ©.

Sheet Layout

Sunnica West Site B

Purpose of Issue

PEIR
Sunnica West Site A Client

SUNNICA LTD

Project Title

Drawing Title
FIGURE 10-11F
COMBINED WITH BARRIERS
ZONE OF THEORETICAL
VISIBILITY FOR THE DCO SITE
Drawn Checked Approved Date
AD RH NC 02/09/2020
AECOM Internal Project No. Scale @ A3
60589004 1:72,000
THIS DOCUMENT HAS BEEN PREPARED PURSUANT TO AND SUBJECT TO THE
TERMS OF AECOM'S APPOINTMENT BY ITS CLIENT. AECOM ACCEPTS NO LIABILITY
FOR ANY USE OF THIS DOCUMENT OTHER THAN BY ITS ORIGINAL CLIENT OR
FOLLOWING AECOM'S EXPRESS AGREEMENT TO SUCH USE, AND ONLY FOR THE
PURPOSES FOR WHICH IT WAS PREPARED AND PROVIDED.

AECOM
Unit 1 Wellbrook Court,
Girton,

±
Cambridge, CB3 0NA
United Kingdom
Telephone (01223) 488000
www.aecom.com

Drawing Number Rev

0 5,000 10,000m 60589004_PEIR_LSP_016 0


560000 570000

24
Other environmental
considerations

We have set out information about other potential environmental impacts


we have assessed in the table below. This includes the outcomes of our
assessments and proposed mitigation.

Assessment Assessment outcome and mitigation Summary More information

Climate We have assessed potential The overall impact of the Scheme is beneficial While the Scheme is anticipated to have See Chapter 6 of
Change impacts of the Scheme on the due to the Scheme providing low carbon solar minor adverse impacts during construction, the PEI Report.
climate via a lifecycle greenhouse energy to help the UK achieve its net zero operation (including maintenance), and
gas (GHG) impact assessment and target. There are likely to be some unavoidable decommissioning, these are offset by the
also considered the resilience of GHG emissions resulting from the Scheme as net positive impact of the Scheme on GHG
the Scheme to physical impacts materials, energy and fuel use, and transport will emissions and the UK’s ability to meet its
of climate change via a Climate be required, but these are small relative to the carbon targets. The GHG savings achieved
Change Resilience (CCR) review. operational benefits of the Scheme. There are throughout the assessed lifetime of the
embedded climate resilience mitigation measures Scheme demonstrate the role solar energy
in the design, including the use of sustainable generation has to play in the transition to,
drainage systems and no loss of floodplain and longer-term maintenance of, a low
storage, to protect the Scheme from potential carbon economy.
climate change impacts.
The CCR review has considered the
measures, including in relation to flood
risk, which have been integrated into the
Scheme design and these are considered
adequate protection against potential
climate change impacts.

25
Assessment Assessment outcome and mitigation Summary More information

Cultural We have assessed potential Archaeological assets that have been identified As a result of the Scheme, there are See Chapter 7 of
Heritage impacts of the Scheme on through geophysical surveys are being protected anticipated to be significant adverse the PEI Report.
designated heritage assets and through the Scheme design by removing the areas residual temporary effects on the setting
their setting, including scheduled from solar development. Where foundations are to of archaeological mounds and built
monuments, listed buildings be installed, work is being done to understand the heritage (Chippenham RPG and Triumphal
and conservation areas, and on archaeological sensitivity and prevent significant Arches). However, the embedded mitigation
non-designated assets, including effects. No direct impacts are anticipated on will minimise the visual intrusion of
archaeological remains and the surrounding built heritage assets (such as the Scheme on built heritage with the
historic buildings and historic Chippenham Registered Parks and Gardens and establishment of the proposed planting.
landscape. Triumphal Arches); however, they may, absent An additional programme of archaeological
mitigation, still experience significant temporary fieldwork is being undertaken prior to
adverse effects as a result of visual intrusion the submission of the Environmental
of the Scheme to their setting. Embedded Statement to mitigate the significant
mitigation is therefore proposed within the design, adverse effects on buried archaeology.
using screening to minimise visual intrusion.
Additional mitigation, including a programme of
archaeological fieldwork, will be implemented to
mitigate the significant adverse effects.

Water We have assessed potential Embedded mitigation in the design, the Through the use of embedded mitigation, See Chapter 9 of
Environment impacts of the Scheme on the implementation of good practice during there would be no significant effects on the PEI Report.
water environment. The water construction, and the implementation of a the water environment from the Scheme.
environment includes surface Surface Water Drainage Strategy to minimise
The flood risk assessment has concluded
water bodies (e.g. rivers, streams, flood risk will be implemented to minimise
that the flood risk is very low to low across
ditches, canals, lakes and ponds, adverse effect on the water environment. The
the majority of the Scheme with isolated
etc.), groundwater bodies, as well Surface Water Drainage Strategy has been
areas of medium to high risk. The Scheme
as flood risk and drainage. developed to mimic natural drainage as far as
will not increase the flood risk outside
practicable using Sustainable Drainage Systems,
of the site and the design included in
and to provide a number of other benefits to
the Surface Water Drainage Strategy will
ecological habitat creation.
improve flood risk both within and outside
of the Scheme area.

Noise and We have assessed noise impacts Embedded mitigation including best Although the construction and See Chapter 11 of
Vibration from the Scheme by comparing practice measures during construction and decommissioning activities may be the PEI Report.
the noise which may be generated decommissioning implemented via a CEMP, and audible, through the use of embedded
by construction, operation, the specification of operational plant with low mitigation, there are not anticipated
and decommissioning with the noise emissions are proposed to be implemented to be any significant noise effects
baseline noise environment at to minimise adverse noise and vibration effects. from the construction, operation or
noise-sensitive receptors near the decommissioning of the Scheme.
Scheme.

26
Assessment Assessment outcome and mitigation Summary More information

Socio- We have assessed potential The embedded mitigation that has been Through the use of embedded mitigation, Chapter 12 of the
Economics impacts of the Scheme on socio- implemented in the design of the Scheme as there is not anticipated to be any PEI Report.
economics and land use, including a result of the other technical assessments significant socio-economic effects
employment generation, gross has provided sufficient mitigation to avoid or associated with the Scheme.
value added during construction, minimise the socio-economic effects. The only
impact on the use of public rights potential significant adverse effect that has been
of way, and impact on residential identified is the temporary impact on users of
properties, businesses, and public rights of ways as a result of construction
community facilities. and decommissioning of the Scheme. The
temporary closures and diversions of the public
rights of ways will have clearly signed alternative
routes and where possible will be planned and
programmed to minimise disruption to the users.

Transport We have assessed the potential The main impact on traffic and transport is After mitigation, it is anticipated that See Chapter 13 of
impacts on traffic and transport likely to be from Heavy Good Vehicles and staff there would be no significant traffic and the PEI Report.
as a result of the construction vehicles during construction. These effects will transport impacts.
and decommissioning of the be prevented by managing arrival and departure
Scheme. times to ensure they are outside of the highway
peak period thereby not worsening the peak
The operational phase is likely
traffic; implementing central car parking for
to require five permanent staff
staff adjacent to the strategic road network
on site. As such, the operational
to minimise the use of the local road network;
impacts of the Scheme have been
encouraging staff to lift share; and implementing
scoped out of this assessment as
a car parking permit system to control the arrival
the increases in traffic are likely
and departure of vehicles from the site. These
to be minimal.
mitigation measures would be secured through
a Construction Traffic Management Plan and
Construction Worker Management Plan.

Air Quality We have assessed the potential Adverse dust effects on human and ecological After mitigation, there are not See Chapter 14 of
impacts on air quality as a receptors will be avoided through the use of anticipated to be any significant air quality the PEI Report.
result of the construction and good industry standard mitigation measures impacts. In addition, at this stage based
decommissioning of the Scheme. incorporated into the CEMP, including on previous experience of similar projects,
The operational impacts of the inspections, barriers, and planning of site layout. due to the predicted traffic volumes
Scheme have been scoped out of and the low total baseline nitrogen
this assessment as the effects are dioxide concentrations in the area, it is
likely to be minimal. not anticipated that there will be any
significant air quality effects from traffic
Dust impacts are considered in
sources; however, this will be confirmed at
the PEI Report; traffic air quality
the Environmental Statement stage.
impacts will be reported in the
Environmental Statement.

27
Assessment Assessment outcome and mitigation Summary More information

Glint and We have assessed the potential impacts There will be no impacts for RAF Mildenhall, RAF Lakenheath It is expected that with the See Chapter 16 of
Glare of glint and glare resulting from the or Cambridge Airport given their respective distances and proposed embedded and the PEI Report.
Scheme on surrounding receptors, locations. All other receptors will be significantly screened additional mitigation there
including aviation, railway, road, public by existing vegetation, vegetation proposed as part of the would be no significant
rights of way users, bridleway users embedded mitigation, and/or surrounding buildings and are impact from glint and glare
(including equestrian) and residential assessed as low impact and not considered to be significant. as a result of the Scheme.
receptors. Therefore, no additional mitigation requirement has been
identified once the embedded mitigation has established.
An assessment of the impact on railway and road
receptors, residential properties, public rights of way,
and bridleway receptors (including equestrian) has
been undertaken. All receptors, apart from road users
on a short section of the A14 (approximately 200m), are
assessed as not resulting in a significant effect due to the
location of the solar refection, reflections coinciding with
direct sunlight, and therefore, not resulting in a safety
hazard.
Mitigation will be provided for the road users on the A14
in the form of a temporary, solid hoarding that will be a
maximum of 2m in height. The hoarding would be located
on a short section, approximately 300m, of the Sunnica
West Site A boundary with a high percentage of evergreen
(native and non-native) species, planted adjacent to the
temporary hoarding in line with the indicative planting
strategy shown on the Parameter Plans.

Ground We have assessed the ground Adverse effects will be avoided through the use of It is expected there would See Chapter 16 of
Conditions conditions of the Scheme to identify mitigation measures incorporated into the CEMP, including be no significant impact on the PEI Report and
any potentially significant contamination appropriate storage of chemicals and materials. In addition, ground conditions from the the Preliminary
source-pathway-receptor linkages. intrusive site investigation is proposed to be carried out Scheme. Environmental
prior to construction works to provide adequate geo- Risk Assessment
environmental data to evaluate soil and groundwater quality (PERA).
and further assess potential contamination linkages.

Human The assessment has been undertaken Adverse impacts are anticipated on air quality, noise, and The assessment has shown See Chapter 15 of
Health in accordance with the Healthy Urban public rights of way as a result of the Scheme. However, that with the primary the PEI Report.
Development Unit Rapid Health Impact with the embedded mitigation measures outlined for mitigation measures
Assessment Matrix and draws on transport, air quality, and noise, and vibration, these are embedded in the design
information presented in other chapters not anticipated to be significant. for other relevant topics,
of the PEI Report and assesses the namely transport, air quality,
potential impacts on human health and noise and vibration,
and wellbeing within the construction, there are no anticipated
operation, and decommissioning phases significant adverse impacts
of the Scheme. on health and wellbeing.

28
Assessment Assessment outcome and mitigation Summary More information

Major We have assessed potential impacts Minimising the risk of major accidents during construction After mitigation, it is See Chapter 16 of
Disaster of the Scheme on the risks of major and decommissioning will be addressed through anticipated that there the PEI Report.
accidents or disasters occurring. appropriate risk assessments which will be delivered would be no significant Also see Chapter
‘Accidents’ are an occurrence resulting through the CEMP. major accidents and 8 and 9 of the PEI
from uncontrolled developments in disasters effects from the Report.
An assessment of major accidents and disasters resulting
the course of construction, operation, Scheme.
from the Scheme has been undertaken, considering
and decommissioning (e.g. major
impacts from criminal damage, bird strike, fire, and
emission, fire or explosion). ‘Disasters’
rail accidents. With the implementation of embedded
are naturally occurring extreme weather
mitigation including best practice design measures and
events or ground related hazard events
a Battery Fire Safety Plan, no significant effects are
(e.g. subsidence, landslide, earthquake).
anticipated.

Telecoms We have assessed potential impacts The only potential impact from the Scheme is on existing After mitigation, it is See Chapter 16 of
of the Scheme on the surrounding utilities during construction. Embedded mitigation in the anticipated that there the PEI Report.
telecommunication infrastructure, design, including locating the Scheme outside of utilities’ would be no significant
television reception, and existing protected zones and the use of ground penetrating radar telecommunications effects
utilities. to identify unknown utilities, and the measures required from the Scheme.
in the CEMP would reduce the risk of impacting existing
utilities during construction of the Scheme.

Waste We have assessed the expected waste Given the nature of the Scheme, significant quantities After mitigation, it is See Chapter 16 of
streams from construction, operation, of waste are not anticipated. A Construction Resource anticipated that there the PEI Report.
and decommissioning of the Scheme. Management Plan (CRMP) and a CEMP will be prepared for would be no significant
the construction and decommissioning phases. These will waste effects from the
include measures to control and manage waste onsite. Scheme.
Waste arisings will be prevented and designed out where
possible. Opportunities to re-use material resources will
be sought where practicable. Where re-use and prevention
are not possible, waste arisings will be managed in line
with the Waste Hierarchy.

29
Construction
Should we receive development consent, we expect construction
to take around 24 months. The proposed Sunnica Energy Farm
involves several different elements and we expect to work on
them at different times in this period. The construction of some
of these elements would happen in parallel.

We anticipate that working hours onsite will run from 7am to 7pm, Monday to Saturday. Working days will be
one 12-hour shift. We anticipate reaching our construction peak 11 months into the construction period. At
this point, an average of 1,260 staff per day would be required to work across the entire Scheme. This is a
maximum amount. Staff numbers would decrease at other times during the construction phase.

In terms of construction traffic, we anticipate 841 staff vehicles will travel to the scheme sites per day
during the peak of construction. To mitigate the impact of these vehicle movements on the highways
network, construction staff would be expected to arrive on site between 6am and 7am. They would be
expected to leave the site between 7pm and 8pm every day. Additionally, workers will arrive at two sites
and be bussed to other sites where appropriate. This means that construction staff traffic during peak
periods across all four sites will be zero. We are proposing to reduce the potential impact of HGV deliveries
by managing the arrival and departure times of HGVs travelling to the scheme sites. This will minimise the
number of HGVs travelling to the site during highway peak hours. For this reason, we anticipate that any
change in vehicle movements during the peak period will be minimal.

We recognise the potential impact of construction on our neighbours and will put in place a plan designed
to ensure potential impacts are managed and properly communicated. To aid this, we will include a draft
Construction Environmental Management Plan (CEMP) and Construction Traffic Management Plan (CTMP) with
our DCO application. This will set out the principles, controls, and measures we will use to manage potential
environmental impacts during construction. These are both available at www.sunnica.co.uk/downloads.

Anticipated key dates for each stage of work include:

Start of construction: Scheme operational:


Autumn/Winter 2022 Spring 2025
30
Construction at Sunnica Constructing the Battery Constructing the cable route
East Site A, Sunnica East Energy Storage System We would construct the cable route in sections;
Site B, Sunnica West Site A, (BESS) each section would take four months to
and Sunnica West Site B To construct the BESS, the following activities
construct. To install the cable, we propose using
a single trench of approximately 1.2m in width
would be required:
The first step in the construction process would and 2m in depth. To construct the trenching and
be to prepare the land for construction. This • Import the components to each of the install the cable we will require a working width
may require localised site levelling. Other initial three sites of up to 35m depending on local conditions.
construction activities would include the import
• Construction of the foundations
of construction materials, plant, and equipment To install the cable, jointing pits will be required
to each site; the installation of a perimeter fence; • Installation of the electrical cabling every 500m to 2,000m to allow the construction
construction of internal access roads; and the team to join each section of the cable together.
• Installation of the transformers,
establishment of construction compounds. The distance between each jointing pit will be
batteries, inverters, and switchgear
determined through the design process and will
Installation of the solar PV panels would take into account existing infrastructure, cable
include piling and the erection of the module specification, and delivery options.
mounting structures. Following this, the panels
would be mounted to the structures by hand. The cable route will need to cross a range of
Localised trenching would be required to install existing infrastructure including roads, tracks,
the electric cabling required to transport the underground utilities, a railway, rivers, and drains.
electricity generated from the panels to the solar We will primarily use open cut trenching for such
stations and onwards to the substations and grid crossings. Where this is not possible we will use
connection cable. The solar stations and control boring, micro-tunnelling, or moling methods.
systems would also be installed at this stage. Further details of these methods are provided in
the PEI Report.

31
Operations and
management
At our public exhibitions last year, we received a lot
of questions about how Sunnica Energy Farm would
operate once built. We were also asked about what
would happen at the end of Sunnica Energy Farm’s
operational lifecycle.

Operations Decommissioning
During its operational lifetime, Sunnica Energy Farm would be maintained The Scheme would be designed for an operating life of at least 40 years.
and operated by a designated management company on behalf of Sunnica Once the Scheme reaches the end of its operating life, it would be
Limited. The management of the Scheme would be overseen from a decommissioned in accordance with a decommissioning plan that will
number of offices that would be staffed and operational for the duration of need to be approved as part of the DCO. This would involve, for example,
the Scheme’s operating life. The locations of the offices are shown on the removing the solar panels and BESS and restoring the land to its previous
plans on pages 9 and 11. condition. This means farmland will not be permanently lost as a result
of our proposals. The solar panels and batteries would be recycled at this
During the operating life of the Scheme, activity across the sites would stage.
be minimal and largely restricted to monitoring, maintenance, and the
Decommissioning is expected to take between 12 and 24 months to
management of vegetation. We anticipate that there would be up to five
complete.
permanent members of staff onsite during the operational phase of the
Scheme. This number may rise during times of maintenance and cleaning.
Sunnica Limited would have a legal responsibility throughout the
operational life of the Sunnica Energy Farm to ensure that it complies with
the DCO and all other relevant legislation and regulations.

32
Community

The proposed Sunnica Energy Farm is a


Nationally Significant Infrastructure Project
(NSIP) and will help meet the urgent national
need for new renewable energy generation and
to cut carbon emissions by 2050 as set out in
government policy.

It will also bring a range of local benefits. Across the four sites, this will include
local pedestrian access, including three new permissive routes, and protection
for a number of areas of archaeological interest.

These areas of archaeological interest include:

• Land at Sunnica East Site A close to Isleham

• Land at Sunnica West Site A close to the A14

• Land at Sunnica West Site B close to Snailwell

Some of these sites came to light as a direct result of our geophysical land
investigations. Our proposals also include ecological enhancements which have
the potential to contribute to local biodiversity.

The Scheme will also create local economic benefits during the construction
process. These include use of local suppliers and businesses and a dedicated
skills programme for local people to be involved in the Scheme.

33
Timeline
Indicative Timeline

Look out for information in local


media and online. Development
WINTER 1. Pre-application of application, having regard to
2020
Thank you for your interest in consultation responses.

our proposals for Sunnica Energy The Planning Inspectorate (PINS) on


Farm. Following this statutory behalf of the Secretary of State, has 28
days to decide whether the application
consultation, we will consider all meets the required standards to proceed 2. Acceptance SPRING
2021
the views we receive and use them to examination, including whether our
consultation has been adequate.
to finalise our DCO application.
You can register as an interested
party: you will be kept informed of
The application will include a Consultation Report setting
SUMMER
3. Put forward progress and have opportunities to
out how we have had regard to the responses received 2021 your case put your case forward. Inspectors will
during this consultation. It will also include a summary hold a preliminary meeting and set
the timetable for examination.
of the non-statutory consultation. We expect to submit
our DCO application in spring 2021. If our application is
You can submit your comments in
accepted by PINS on behalf of the Secretary of State
writing. You can request to speak
for Business, Energy & Industrial Strategy, there will be
a further opportunity for you to make comments and
at a public hearing. The Planning 4. Examination SUMMER
Inspectorate (PINS) has six months to 2021
submissions as part of the process for determining the carry out the examination.
application.
A recommendation to the relevant
Secretary of State will be issued by
the Planning Inspectorate (PINS)
SUMMER 5. Decision within three months. The Secretary of
2022
State then has a further three months
to issue a decision on the proposal.

There is the opportunity


for legal challenge. 6. Post-decision AUTUMN
2022

34
Responding to the
consultation
We want as many people as possible to
share their views on our proposals as
part of this consultation.

We are consulting at a time when it is not possible to meet in person, due - Write to us at info@sunnica.co.uk or Sunnica Consultation, FREEPOST
to health and safety requirements for the ongoing COVID-19 pandemic. reference RTRB-LUUJ-AGBY, c/o Newgate Communications, Sky Light City
We are putting in place a detailed package of measures to ensure we can Tower, 50 Basinghall Street, London, EC2V 5DE
continue with the consultation.
Following the statutory consultation, we will have regard to the comments
received and continue to develop our design for the proposed Sunnica
We remain very aware of how important it is to make sure that anyone in
Energy Farm ahead of submitting our DCO application to the Secretary of
the community who wants to find out more or share their views on the
State. Our DCO application will include a Consultation Report setting out
proposals can do so. We are providing a range of ways to do this.
how we have considered all responses received.

Share your views Any comments received will be analysed by Sunnica Limited and any of
its appointed agents. Copies may be made available in due course to the
The consultation will take place between 22 September 2020 and 2
Secretary of State, the Planning Inspectorate, and other relevant statutory
December 2020. There are a number of ways you can respond:
authorities so that feedback can be considered as part of the DCO process.
- Complete a consultation questionnaire on our website: www.sunnica.co.uk We will request that any personal details are not placed on public record
but will be held securely by Sunnica Limited and its agents in accordance
- Complete a questionnaire (available on request through the contact
with the data protection law and will be used solely in connection with the
details below) and return it to info@sunnica.co.uk or Sunnica Consultation,
consultation process and subsequent DCO application and, except as noted
FREEPOST reference RTRB-LUUJ-AGBY, c/o Newgate Communications, Sky
above, will not be passed to third parties.
Light City Tower, 50 Basinghall Street, London, EC2V 5DE

35
Find out more

You can find out more about our proposals by:

• Viewing a virtual exhibition on our website: www.sunnica.co.uk

• Joining online webinars we will hold about our proposals. These will include presentations on
specific topics and will offer the opportunity to ask questions. You can find the dates of the
webinars and details of how to register at our website, www.sunnica.co.uk

• Booking an appointment to talk to us individually about the proposals, using the freephone
number detailed below. We will offer the opportunity to speak with members of our technical
team if you have questions about specific aspects of our proposals.

• Viewing consultation documents, including the PEI Report and the SoCC, on our website:
www.sunnica.co.uk

• Contacting us directly with any other questions, using the details below.

• Requesting copies of the materials on a memory stick or CD/DVD, using the contact details below.
If you would like a hard copy of the PEI Report and its non-technical summary please contact us
using the details in this booklet. A charge of £0.35 per page will be made for these materials.

Contact us

For further information, please contact us by:


Visiting our website: www.sunnica.co.uk | Calling: 0808 168 7925 (9am to 5pm, Monday to Friday)
Emailing: info@sunnica.co.uk | Writing to us at: Sunnica Consultation, FREEPOST reference RTRB-LUUJ-AGBY,
c/o Newgate Communications, Sky Light City Tower, 50 Basinghall Street, London, EC2V 5DE

S-ar putea să vă placă și