Documente Academic
Documente Profesional
Documente Cultură
Project ID P6TEST
DEFAULTS:
1
1.2 Create the following WBS:
2
1.4 Add the following relationships:
100 200 SS
200 300 SS 20
200 400 SS 30
200 500 FS
600 300 FS
600 400 FS
600 500 FS
600 700 FS
700 800 FF
Activity ID Constraint
3
1.6 Assign ‘TERRACAL’ Resource to Activity 300 (Budgeted Units =1000, Bell Shaped
curve)
1.7 Design the following layout and save it using your full name:
Group by WBS
Sort by Activity ID
Columns Activity ID
Activity Name
Start
Finish
Original Duration
Remaining Duration
Total Float
Physical % Complete
4
1.8 Schedule and view the schedule log contents
1.11 Re‐status the Project using the above Data Date, analyze the schedule and provide
the following information:
Information Answer
5
1.12 Print‐preview the Gantt chart
Timescale Quarter/Month
Relationships Off