Documente Academic
Documente Profesional
Documente Cultură
2
Negotiate and sign 5 The purchase department will be involved in order to Purchase Cannot be reduced.
contracts for PTM office negotiate the office rental fee and to sign the contract. department 20%
3 Once the contract for the new office will be signed, it will be Abeer 40% Cannot be reduced.
possible to identify the furniture needed. Iksha 15%
Define furniture for PTM
Labeeb 15%
Office
Purchase Dept.
10%
2 The proposed duration takes into consideration the scenario Purchase Cannot be reduced.
Buy furniture
with standard and immediately available piece of furniture. department 20%
2 The proposed duration takes into consideration the scenario Furniture Supplier Cannot be reduced.
with standard piece of furniture. In addition, a short lag of 3 100%
Install furniture days must be considered if you consider furniture Abeer 30%
immediately available (the lag can be up to 30 days for
custom made furniture).
5 In order to perform this activity in the best way, we should Abeer 50% Cannot be reduced.
wait that all the PTM operators will be trained. Labeeb 70%
Unfortunately, the agreement that has been already made 10 PTM Operators
Define functionalities of PTMs
with the branches does not permit to wait until that event. at 10%
Functionalities will be thus decided with a minor involvement
of future PTM operators.
4 The new office for the PTM operators will need IT systems. Purchase Cannot be reduced.
Hardware will be standard while software will only ask some department 20%
Buy IT systems
license extension and some configuration made by the PTM Labeeb 10%
supplier (see two activities below).
20 After having bought IT systems, their implementation can Labeeb 60% It can be reduced to 15 days. Every day of
start. PC, printers, software and network will be installed. reduction requires 10% of Albert.
Implement IT systems
This activity cannot finish until installing furniture is not
finished.
10 Configurations can be made after having completed the PTM supervisor Cannot be reduced.
Configure PTMs software for
implementation of IT systems. 100%
Operators
Labeeb 20%
3 Order PTMs. After a negotiation with the supplier, it has been Labeeb 10% Cannot be reduced.
agreed that delivery is guarantee in 30 days for standard Purchase Dept.
Buy PTMs PTMs (no configurations that asks for custom code). They can 20%
be ordered once the needed functionalities have been
decided.
20 This activity can be performed after having selected the 4 test Purchase Dept. Cannot be reduced.
Select renovation company branches. 20%
Abeer 5%
Renovation of branches 30 Masonry work in selected branches. Based on previous Abeer 10% It can be reduced to 20 days by adding 5000
experiences, this activity can start 40 days after having Renovation Euros per day of schedule compression.
3
selected the renovation company. This lag is due to obtaining Supplier 90%
legal permits.
10 This activity can be performed in parallel with “Renovation ofPTM Supervisor Cannot be reduced.
the branches” (starting from its second half) but it cannot 100%
Install PTMs in selected finish until renovations are not completed. Renovation
branches Supplier 10%
Labeeb 10%
Abeer 10%
3 This activity can be performed when all the pieces of the Abeer 50% Cannot be reduced.
puzzle will be available (PTM operators selected and trained, Labeeb 100%
PTM office with running systems, PTMs installed in the 4 All (20) PTM
Test of the PTMs services
branches). Operators 100%
PTM Supervisor
100%
Service inauguration
5 This activity has no real predecessors apart having knowledge Communication Cannot be reduced.
Define list of guests of what PTMs are (useful to invite the right guests and to Dept. 1 person at
convey to them the right messages). 40%.
5 Once defined the list of guests the details of the event can be Communication Cannot be reduced.
Define the characteristics of
defined. Dept. 2 persons at
the event
20%.
2 It means sending letters/emails and calling them. Communication Cannot be reduced.
Invite guests
Dept. 1 person at
100%.
10 Given the high number of events that the bank does, there Communication Cannot be reduced.
Manage the supply chain are internal suppliers that can support doing the event. Dept. 1 person at
30%.
1 Final milestone. This task can be performed after having All internal Cannot be reduced.
completed and tested the PTMs installation. team100%
Run the event (Project End) Communication
Dept. 1 person at
100%