Documente Academic
Documente Profesional
Documente Cultură
Part One
Power and Distribution Transformers Sizing Calculations – part one
http://www.electrical-knowhow.com/2017/11/power-and-distribution-transformers-sizing-calculations.html
Today, we will start explaining the Power and Distribution Transformers sizing calculations in details
and I’d like to from all of you to review our course “EP-3: Electrical Procurement – Transformers
Course” to be more familiar with the contents of our new articles about the Power and Distribution
Transformers sizing calculations.
The contents of our articles for Power and Distribution Transformers sizing calculations will include
the following points:
The following points were explained before ( or will be explained) in our course “EP-3: Electrical
Procurement – Transformers Course” :
So, we will not go through these points here, we will focus only on the following two points:
Now, we will start with the first point; Glossary of Sizing Power and Distribution Transformers.
Glossary of Sizing Power and Distribution Transformers
Term Explanation
The following points were explained before ( or will be explained) in our course “EP-3:Electrical
Procurement – Transformers Course” :
So, we will not go through these points here, we will focus only on the following two points:
And we already explained the Glossary of Sizing Power and Distribution Transformers in Article
“Power and Distribution Transformers sizing calculations – part One” , today we will explain the
second point; Power and Distribution Transformers sizing calculations.
Note:
I’d like from all of you to review our course “EP-3:Electrical Procurement – Transformers Course” to
be more familiar with the contents of our new articles about the Power and Distribution Transformers
sizing calculations.
Power and Distribution Transformers sizing calculations
Our study for the Power and Distribution Transformers sizing calculations will include the
explanations of the following points:
• The Resources used in our study to calculate basic ratings of power and distribution
transformers will be the ANSI/IEEE Standard C57 (Distribution, Power, and Regulating Transformers).
• We will go through the important points in the ANSI/IEEE Standard C57 that will lead to the
accurate sizing of power and distribution transformers as follows:
1. C57.12.00 specifies the following service conditions for liquid-immersed distribution and power
transformers:
2. C57.12.00 lists the following preferred continuous kVA ratings for liquid immersed power and
distribution transformers (Table-1).
750
Table-1: Standard Transformer kVA Ratings (Liquid-Filled)
3. C57.12.00 lists the following basic dielectric insulation levels (BIL) for liquid-immersed transformers
(Table-2).
kV Flashover kV
kV kV
crest rms
rms Crest sec
below Distribution
4. C57.12.00 specifies that the angular placement for three-phase transformers shall be in
accordance with Figure-1.
5. C57.12.00 list four categories for the rating of transformers (Table -3):
a :Category I shall include distribution transformers manufactured in accordance with ANSI C57.12.20
[B3] up through 500 kVA, single phase or three phase. In addition, autotransformers of 500 equivalent
two winding kVA or less, which are manufactured as distribution transformers in accordance with
ANSI C57.12.20 [B3], shall be included in Category I, even though their nameplate kVA may exceed
500.
6. C57.12.00 specifies that power transformers that are rated 200 kVA and below, and that have high
voltage ratings 8660 volts and below, shall have additive polarity. All other single-phase transformers
shall have subtractive polarity.
7. C57.12.00 specifies that the average winding temperature rise above ambient temperature shall
not exceed 650C when measured by resistance and that the winding hottest-spot temperature rise
shall not exceed 800C.
8. C57.92 lists the following derating factors for 550C or 650C rise transformers that are being
operated at ambient temperatures above or below 300C (Table-4).
Note: Table-4 is valid for temperatures that range from 00C to 500C.
9. C57.12.10 lists the following OA/FA ratings for power transformers that are rated 750 - 12,500 kVA
(Table-5).
OA First-Stage Second-Stage
11. C57.12.01 specifies the same usual service conditions for dry-type transformers as for liquid-filled
transformers.
12. C57.12.01 lists the following continuous kVA ratings for dry-type power and distribution
transformers (Table-7):
50 2500 25,000
75
3333 33,333
100
13. C57.12.01 lists the following limits of temperature and temperature rise ratings for dry-type
transformers (Table-8).
60 130
80 150
115 185
130 200
150 220
Table-8: Limits of Temperature and Temperature Rise Ratings for Dry-Type Transformers
14. C57.12.01 lists the same categories of dry-type transformers as liquid-filled transformers, except
that Category IV does not exist for dry-type transformers.
15. C57.12.01 lists the following BIL ratings for dry-type transformers (Table-9).
Insulation Minimum
Time To
Level
kV kV crest Flashover
kV rms kV crest
Sec
kV crest
below
2.4 20 10 20 20 1.0
4.16 30 12 30 30 1.0
13.8 60 19 60 60 1.5
Self-Cooled Forced-Air-Cooled
(kVA) (kVA)
750 1000
1000 1333
1500 2000
2000 2667
2500 3333
3750 5000
5000 6667
7500 10000
In the next article, we will focus on the other points in Power and Distribution Transformers sizing
calculations which are:
• Selection Factors,
• Special cases,
• Calculations procedures.
So, please keep following.
Power and Distribution Transformers Sizing Calculations –
Part Three
In Article “Power and Distribution Transformers sizing calculations – part One”, we indicate that the contents of our
articles for Power and Distribution Transformers sizing calculations will include the following points:
The following points were explained before ( or will be explained) in our course “EP-3:Electrical Procurement –
Transformers Course” :
So, we will not go through these points here, we will focus only on the following two points:
And we already explained the Glossary of Sizing Power and Distribution Transformers in Article “Power and Distribution
Transformers sizing calculations – part One” .
Also, in Article “Power and Distribution Transformers Sizing Calculations – Part Two” , we indicate that Our study for the
Power and Distribution Transformers sizing calculations will include the explanations of the following points:
And we explained in this article the Resources used to calculate basic ratings of power and distribution transformers,
today we will explain Selection Factors for Power and Distribution Transformers sizing calculations.
Note: I’d like from all of you to review our course “EP-3: Electrical Procurement – Transformers Course” to be more
familiar with the contents of our new articles about the Power and Distribution Transformers sizing calculations.
Selection Factors for Power and Distribution Transformers sizing calculations
Before going through the equations and calculations for sizing power and distribution transformers, we must know the
factors which must be considered before making these calculations. Noting that without fulfilling these factors, your
calculations will not be so accurate. These factors we called them the selection factors which are:
1. Voltage class,
2. Load type,
3. Ambient Temperature,
4. Standard Sizes,
5. Cooling Classes,
6. Temperature Rise,
7. Altitude.
First: Voltage class:
There are three classes of voltage: low, medium, and high voltage.
1- Low Voltage, Three-Wire:
Volt Application
Volt Application
Kilo-Volt Application
2.4
4.16
4.8
Voltages in this class are used to distribute large blocks
6.9
of power and as a utilization voltage for large motors
13.8
(isolated neutral).
23
34.5
46
69
4-High Voltage, Three phase, Three-Wire:
Kilo-Volt Application
115
138 Nominal system voltages within this class to transmit
161 large blocks of power over long distances.
230
1- Normal Load:
It means that the minimum self-cooled kVA rating of each OA/FA transformer shall be equal to the maximum normal
operating load plus projected future load.
2- Emergency Load:
Transformers may be operated under emergency conditions at ratings above normal load ratings. However, there will be
some sacrifice of life expectancy. ANSI/IEEE Standard C57.91 and C57.92 provide methods for determining the life
expectancy of power transformers when they are operated at loads above their listed ratings.
It means that for self-cooled transformers (OA or AA) only, a 10% load growth factor should be added to the calculated
load (normal maximum operating load plus projected future load).
It is a known load that will be added in the future. Projected future load should not be confused with the 10% load growth
factor that was discussed in the immediate previous paragraph.
• The temperature rise ratings of transformers are all based on an ambient temperature of 300C averaged over a
24-hour period, and the temperature not to exceed 400C at any time.
• If the transformer is operated at rated load and at temperatures greater than an average ambient temperature of
300C, some decrease in life expectancy will occur.
• To avoid this decrease in life, ANSI/IEEE Standard C57 requires that the transformer be de-rated as follows:
liquid-filled power
transformers the average ambient temperature
1.5% for each 10C over 300C
exceeds 300C
750
50 2500 25,000
75
3333 33,333
100
Table- lists the cooling classes for liquid-filled transformers and Figure 55 lists the cooling classes for dry-type
transformers.
Liquid-immersed, self-cooled
OA
Liquid-immersed, self-cooled/forced-air-cooled
OA/FA
Liquid-immersed, self-cooled/forced-air-cooled/forced-
OA/FA/FA aircooled
Liquid-immersed, self-cooled/forced-air-forced-liquid-
OA/FA/FOA
cooled
Table- : Cooling Classes for Liquid-Filled Transformers
Class Code Method Of Cooling
Ventilated, self-cooled
AA
Ventilated, forced-air-cooled
AFA
AA/FA
Ventilated, self-cooled/forced-air-cooled
ANV Non-ventilated, self-cooled
GA Sealed, self-cooled
The rated kVA of a transformer is the kVA output that can be delivered for a specified time, at rated secondary voltage and
rated frequency, without exceeding the specified temperature rise under prescribed conditions.
• In liquid-filled power transformers, the specified time is continuous operation. The rated secondary voltage and
frequency are as stated on the transformer nameplate.
• The specified temperature rise is the average rise of temperature in the windings, which is either 550C or 650C
and is stated on the nameplate.
• The corresponding hottest spot winding temperatures are 650C and 800C and are not stated on the nameplate.
• Sixty-five degrees average rise is the “preferred” rating specified for modern transformer designs.
• Some transformers have a dual temperature rise rating of 550/650C, with a corresponding dual kVA rating
specified on the nameplate.
• Prescribed conditions are an ambient temperature not to exceed 300C averaged over a 24 hour period and not to
exceed 400C at any time.
• The kVA ratings of outdoor transformers account for the warming effects of full sunlight during daytime hours.
The kVA ratings for dry type transformers have the same ambient temperature basis as for liquid-filled transformers.
Seventh: Altitude
To allow for reduced cooling at higher elevations de-rate the transformer nameplate kVA by 0.3% for each 330 feet over
3300 feet above sea level.
In the next article, we will focus on the other points in Power and Distribution Transformers sizing calculations which are:
• Calculations procedures,
• Special cases.
Power And Distribution Transformers Sizing Calculations –
Part Four
In Article “Power and Distribution Transformers Sizing Calculations – Part One”, we indicate that the contents of our
articles for Power and Distribution Transformers sizing calculations will include the following points:
The following points were explained before (or will be explained) in our course “EP-3:Electrical Procurement –
Transformers Course”:
So, we will not go through these points here, we will focus only on the following two points:
And we already explained the Glossary of Sizing Power and Distribution Transformers in Article “Power and Distribution
Transformers Sizing Calculations – Part One”.
Also, in Article “Power and Distribution Transformers Sizing Calculations – Part Two” , we indicate that Our study for the
Power and Distribution Transformers sizing calculations will include the explanations of the following points:
And we explained in this article the Resources used to calculate basic ratings of power and distribution transformers while
we explained the selection factors for the Power and Distribution Transformers in article “Power and Distribution
Transformers Sizing Calculations – Part Three”
Today we will explain the calculations procedures for sizing of Power and Distribution Transformers.
Note: I’d like from all of you to review our course “EP-3: Electrical Procurement – Transformers Course” to be more
familiar with the contents of our new articles about the Power and Distribution Transformers sizing calculations.
Calculations Procedures For
Sizing Of Power And Distribution Transformers.
In power systems, there are many devices whose proper size is critical to the design of a power delivery system. One of
the most important is the power transformer.
There are several factors involved in the process of sizing a transformer which were explained in article “Power and
Distribution Transformers Sizing Calculations – Part Three”, these factors can be used to determine if a transformer can
handle its required operating load or not. Inadequately sized transformers may shorten the equipment's operating life or
cause overloading failures.
Now, we will explain step by step the accurate sizing calculations of Power and Distribution Transformers which will
include the following:
Step# 1
Selected data:
• Power or Distribution?
• Liquid-Filled or Dry-Type?
Select power or distribution transformer based on given information then select a liquid-filled or a
dry-type.
Selection Guide:
• Power transformer: used between the generator and the distribution circuits and these are
usually rated at 500 kVA and above. Power transformers are available for step-up operation, primarily
used at the generator and referred to as generator step-up (GSU) transformers, and for step-down
operation, mainly used to feed distribution circuits. See Fig.1
Fig.1
Fig.2
How to select between Liquid-Filled or Dry-Type Transformers?
Step# 2
Selected data:
• Primary Voltage?
• Secondary Voltage?
Select the primary and secondary voltage ratings from Table-1 and the given information.
For three-phase transformers, assume 3Ø, 3-wire, delta-connected primaries and 3Ø, 4-wire, wye-
connected secondaries.
120/240 V 1Ø 3
480 V 3
3Ø
208Y/120 V 4
3Ø
480Y/277 V 4
3Ø
2400 V*
3Ø 3
4160 V
3Ø 3
6900 V*
3Ø 3
13,800 V
3Ø 3
34,500 V*
3Ø 3
69,000 V
3Ø 3
115,000 V
3Ø 3
230,000 V
3Ø 3
Step# 3
Selected data:
Select the BIL Rating for the transformer from Table-2 for liquid-filled transformers, or from Table-
3 for dry-type transformers.
Sec
kV rms kV kV crest kV crest kV crest
0.48 and 10 4 10 10 1.0
below
2.4 20 10 20 20 1.0
4.16 30 12 30 30 1.0
13.8 60 19 60 60 1.5
Step# 4
Calculated Data:
A- Calculate the load kW for each load or combination of loads at rated utilization voltage.
Note: Include any projected (known) future loads.
kWload = 3 x kV x I x p.f. or
B- Calculate the load kVAR for each load or combination of loads at rated utilization voltage.
Note: Include any projected (known) future loads.
D- Calculate the adjusted site kVA after derating for temperature from Table-4.
Example-1:
Then:
kVA (adjusted) = kVA (site)/0.94 for dry-type transformers with 1500C insulation,
kVA (adjusted) = kVA (site)/0.96 for dry-type transformers with 2200C insulation.
Step# 5
Selected data:
Note:
750
50 2500 25,000
75
3333 33,333
100
Step# 6
Selected data:
• From Table-7 for liquid-filled transformers that are rated 750 - 12,500 kVA or
• From Table-8 for liquid-filled transformers that are Greater Than 12.5 MVA and
• From Table-9 for dry-type transformers.
Table-7: The Cooling Class kVA Ratings For Liquid-Filled Transformers (750 - 12,500 KVA)
OA First-Stage Second-Stage
Table-8: The Cooling Class kVA Ratings For Liquid-Filled Transformers Greater Than 12.5 MVA
Self-Cooled Forced-Air-Cooled
(AA) Ratings (AA/FA) Ratings
(kVA) (kVA)
750 1000
1000 1333
1500 2000
2000 2667
2500 3333
3750 5000
5000 6667
7500 10000
Notes:
• The forced-cooled kVA ratings of each transformer serving a double-ended substation shall
be capable of feeding the entire load of both buses with the bus tie breaker closed.
• Forced-air cooling shall be provided on all transformers that are rated 2500 kVA and larger.
Power And Distribution Transformers Sizing Calculations –
Part Five
In Article “Power and Distribution Transformers sizing calculations – part One”, we indicate that the contents of our
articles for Power and Distribution Transformers sizing calculations will include the following points:
The following points were explained before (or will be explained) in our course “EP-3:Electrical Procurement –
Transformers Course”:
So, we will not go through these points here, we will focus only on the following two points:
Also, in Article “Power and Distribution Transformers Sizing Calculations – Part Two” ,we indicate that Our study for the
Power and Distribution Transformers sizing calculations will include the explanations of the following points:
And we explained in this article the Resources used to calculate basic ratings of power and distribution transformers while
we explained the selection factors for the Power and Distribution Transformers in article “Power and Distribution
Transformers Sizing Calculations – Part Three”
In article “Power And Distribution Transformers Sizing Calculations – Part Four”, we indicted that the accurate sizing
calculations of Power and Distribution Transformers will include the following:
Note: I’d like from all of you to review our course “EP-3: Electrical Procurement – Transformers Course” to be
more familiar with the contents of our new articles about the Power and Distribution Transformers sizing
calculations.
Step# 1:
Step# 2:
Ep/Np = Es/Ns
Then:
Ep = (Np/Ns) x Es
Es = (Ns/Np) x Ep
And:
Np = (Ep/Es) x Ns
Ns = (Es/Ep) x Np
Step# 3:
Then:
Ip = (Ns/Np) x Is
Is = (Np/Ns) x Ip
And:
Np = (Is/Ip) x Np
Ns = (Ip/Is) x Np
Step# 4:
VAin = VAout
Ep x Ip = Es x Is (for single-phase transformers)
3 x Ep x Ip = 3 x Es x Is (for three-phase transformers)
Or
kVAin = kVAout
kVp x Ip = kVs x Is (for single-phase transformers)
3 x kVp x Ip = 3 x kVs x Is (for three-phase transformers)
Where:
Ep or KVp : Primary Voltage,
Es or KVs: Secondary Voltage,
Ip: Primary Current,
Is: Secondary Current,
Np: Primary Turns Number,
Ns: Secondary Turns Number.
Note:
Efficiency is calculated by dividing the output real power by the input real power. The efficiency will
vary depending on the amount of load because the copper losses of a transformer vary with load.
Step# 1:
Determine the transformer kVA, total copper losses, and total iron losses.
Step# 2:
Calculate the output power of the transformer at the given power factor.
Step# 3:
Step# 4:
Note:
As a transformer becomes loaded, the voltage at the secondary terminals of the transformer
decreases. This decrease in voltage is caused by the voltage drop across the internal impedance of the
transformer. The higher the transformer impedance, the higher the voltage drop.
Step# 1:
Determine the voltage (E full-load) of the transformer at the secondary terminals under full-load
conditions.
Step# 2:
Some factors must be taken in consideration in some cases when sizing the power and distribution transformers
these are the special cases which will be as follows:
1. Secondary Unit Substations,
2. Paralleled Transformers,
3. K-Factor Transformers,
4. Transformers with Large Motor Loads.
A secondary unit substation, sometimes called a power center, is a close-coupled assembly consisting
of three-phase power transformers, enclosed high voltage incoming line sections, and enclosed
secondary low voltage outgoing sections encompassing the following electrical ratings:
• Transformer kVA: 112.5 thru 2500 kVA (self-cooled rating), liquid-filled, dry-type, or cast coil
• Primary Voltages: 2.4 kV thru 34.5 kV
• Secondary Voltages: 208, 240, 480, or 600 Volt (maximum)
As a result of locating power transformers and their close-coupled secondary switchboards as close as
possible to the areas of load concentration, the secondary distribution cables or busways are kept to
minimum lengths. This concept has obvious advantages such as:
• primary switchgear, for example, power fuses, medium voltage circuit breakers, or
interrupters,
• the transformer (liquid-filled or dry type),
• The secondary distribution section (main and feeder low voltage power circuit breakers).
Types of Secondary Unit Substations
1. Single-Ended Substations
2. Double-Ended Substations
1- Single-Ended Substations:
Figure-1 shows the one-line diagram and physical layout of a secondary unit substation that uses a radial system
arrangement. This type of radial substation arrangement is called a single-ended substation because there is only one
incoming line section at the one end (west) of the unit (prepackaged) assembly.
Figure-2 shows the one-line diagram and physical layout of a secondary unit substation that uses a secondary
selective system arrangement. This type of arrangement, the secondary selective system, overcomes the major
disadvantage of the radial system in that it provides duplicate paths of supply to the secondary bus of each load
center. This selective system has two step-down transformers, each with its own incoming primary feeder. The
secondary bus associated with each transformer is connected through a tie breaker. Normally, the system is operated
with the tie connection open, that is, as two separate radial systems operating independently of each other.
With the loss of one of the primary feeders and/or transformers, the main secondary breaker for that circuit can be
opened and the tie breaker closed, allowing the one remaining primary feeder and transformer to energize all of the
secondary bus. The service to one-half of the load is momentarily interrupted during this transition period.
The selection of kVA and impedance ratings of unit substation transformers is very critical to the
levels of available fault current on the secondary main bus side of the substation. This available fault
current on the secondary side of the transformer, assuming that there are no other fault current
sources on the secondary side, is called The Transformer Let-Through Current.
Procedures For Calculating Transformer Let-Through Current
Transformer impedance dictates how much fault current a transformer can supply to a fault for a
given kVA size. The higher the impedance, the lower the available fault current. Sometimes
transformer impedances are used to limit the let-through current (sometimes called the infinite bus
fault current calculations).
By calculating the transformer let-through current, you can estimate the available fault current at the
secondary terminals of a transformer. Transformer let-through current can be calculated using the
following steps:
Step#1:
Step#2:
Determine % Z from Table-1 for single-phase transformers and Table-2 for three-phase transformers.
%Z=
Step#3:
Impedance (%Z)
• The impedance (%Z) of the transformer, which is based on the self-cooled (OA) rating of the
transformer, is the main factor in limiting the magnitude of the fault current available on the low
voltage section of the system, especially at points close to the substation secondary bus.
• Because of the importance of the transformer impedance in limiting the available fault
current, unit substation transformers are designed on purpose to have impedances values of at least
5.0%, with a typical value being 5.75%. This higher impedance value is obtained by increasing the
leakage reactance of the transformer windings, rather than increasing the winding resistance. Higher-
resistance windings would increase the heat losses in the transformer, which is not desirable.
PRIMARY NOMINAL
RATING IMPEDANCE
VOLTAGE
kVA %
kV
2.4 2.2
3
13.8 2.8
2.4 2.2
10 13.8 2.4
34.5 5.5
2.4 2.5
25 13.8 2.3
34.5 5.5
2.4 2.4
13.8 2.5
50
34.5 5.5
69.0 6.5
2.4 5.5
100
69.0 6.5
2.4 3.7
13.8 3.8
167
34.5 5.5
69.0 6.5
Example:
Referring to Figure 56, what is the transformer let-through current (ILT) at the secondary bus? What is
ILT if the impedance of the transformer is specified at 5% versus 5.75%? What is ILT if the impedance of
the transformer is specified at 7% versus 5.75%?
Answer:
In the next article, we will continue discussing other special cases for Power and Distribution Transformers sizing
calculations which are:
Power And Distribution Transformers Sizing Calculations –
Part Six
Glossary of Sizing Power and Distribution Transformers, Power and Distribution Transformers sizing
calculations – part One
Resources used to calculate basic ratings of power and Power and Distribution Transformers Sizing
distribution transformers Calculations – Part Two
the selection factors for the Power and Distribution Power and Distribution Transformers Sizing
Transformers Calculations – Part Three
Applicable calculations procedures for sizing of power Power And Distribution Transformers Sizing
and distribution transformers Calculations – Part Four
1-Applicable procedures for calculating power and Power And Distribution Transformers Sizing
distribution transformer ratios, Calculations – Part Five
2-Applicable procedures for calculating power
transformer efficiency,
3-Applicable procedures for calculating power
transformer voltage regulation,
4-Special Cases In Transformers Sizing Calculations:
Secondary Unit Substations
Note: I’d like from all of you to review our course “EP-3: Electrical Procurement – Transformers Course” to be
more familiar with the contents of our new articles about the Power and Distribution Transformers sizing
calculations.
Today, we will explain other special cases for Power and Distribution Transformers sizing calculations; Paralleled
Transformers.
2- Paralleled Transformers
Here we will explain the limiting conditions of connecting transformers in parallel and loading/sizing
considerations that must be followed. Firstly, let’s see what is meant by Paralleled Transformers?
If two or more transformers are connected to a same supply on the primary side and to a same load
on the secondary side, then it is called as Paralleled transformers.
Figure-1 shows two transformers connected in parallel. The transformers are connected in parallel by
connecting the similarly marked terminals together. For example, terminal X1 of T1 to terminal X1 of
T2, terminal X2 of T1 to X2 of T2, etc.
Importance for using Paralleled Transformers
1- Increased Load:
When load is increased and it exceeds the capacity of existing transformer, another transformer may
be connected in parallel with the existing transformer to supply the increased load.
2- Non-availability of large transformer:
If a large transformer is not available which can meet the total requirement of load, two or more
small transformers can be connected in parallel to increase the capacity.
3- Increased reliability:
If multiple transformers are running in parallel, and a fault occurs in one transformer, then the other
parallel transformers still continue to serve the load and the faulty transformer can be taken out for
the maintenance.
4- Transportation is easier for small transformers:
If installation site is located far away, then transportation of smaller units is easier and may be
economical.
The paralleling of the secondaries of transformers increases the short circuit current available, and, therefore
necessitates higher interrupting capacity and more expensive secondary switchgear (bus, breakers, etc.).
Example#1:
Fig-2
Referring to Figure-2, what is the total transformer let-through current at the secondary bus?
Answer:
If the Mandatory Conditions for Optimal Parallel Operation do not exist, circulating currents will flow
between and through the secondary windings of both transformers.
Definitions:
The circulating current is the current flowing at no load in the high and low voltage windings,
excluding exciting currents.
Full load current is the current flowing in the transformer with a load connected, absent of exciting
and circulating currents.
Disadvantages of Circulating Currents:
• Lower the transformer efficiency
• Reduce the maximum amount of load that the combined transformers can carry.
The magnitude of the circulating current that flows depends on which of the above optimal
conditions do not exist. Let’s consider each of these optimal conditions to determine what occurs if
they do not exist as follows:
A circulating current flows even if there is no load on the transformers. This circulating current flows
because the voltage is different on the secondary side of the transformer. In figure-1, if transformer
T1 has a higher turns ratio than transformer T2, then T1 will have a lower secondary voltage than T2.
Transformers will not equally share the load. Current will divide between the two transformers, but
not necessarily equally. . In figure-1, if transformer T1 has a higher impedance than transformer T2,
then more current will flow through T2 than T1. This is the same principle as the principle of current
dividing between two paralleled impedances. If unequal impedances exist, one transformer can easily
overload.
Paralleling two transformers with different phase shifts (e.g., Δ-Δ to Δ-Y) or different polarities (e.g.,
subtractive to additive) will cause large secondary circulating currents to flow.
3- Limiting kVA
Two dissimilar transformers (where one of the Mandatory Conditions for Optimal Parallel Operation
doesn’t exist) may be operated in parallel, but the following two conditions must be met:
1. The circulating current should not exceed 10% percent of the full load rated current
of either transformer.
2. The total load (combination of the circulating currents and full load current) should
be limited to a value below the full rated current in either transformer. This total load limit is
called the limiting kVA or the maximum kVA load of two transformers that are being
operated in parallel.
Example#2:
Referring to Figure-1, what is the circulating current magnitude that flows between the paralleled
transformers, and what is the limiting kVA of the two transformers that are being operated in
parallel?
Answer:
Where:
• kV1 and kV2 are the kV secondary voltages for transformers T1 and T2 at no-load.
• Z1 and Z2 are the percent impedances for transformers T1 and T2.
• I1 and I2 are the full load current for transformers T1 and T2.
The circulating current must be less than 10% of the smaller of I1 or I2.
kVAlimit = Zmin x [(kVA1/Z1) + (kVA2/Z2)] x 0.9 = 8 x [(12000/9) + (1000/8)] x 0.9 = 18600 kVA = 18.6
MVA
So, Total power supplied to the secondary bus cannot exceed 18.6 MVA. If more than 18.6 MVA of
load is connected, transformer T2 will overload resulting in possible damage.
• If paralleling two transformers with load tap changers, the automatic sensing relay which
controls the tap position of the transformers must be set up in a master/slave configuration. Both
load tap changers must “stay in step” (stay on the same taps). The master/slave configuration system
should allow one transformer’s sensing relay to control the tap changer on both transformers.
• If paralleling transformers that have a high secondary current, consider the impedance of the
cables or bus that is used to parallel the secondary windings. Small changes in impedance may have a
large effect on load sharing.
Summary for Parallel Transformers Connections
Transformer
Equal Unequal Overloading Circulating
Parallel Recommended
Loading Loading Concerns Currents
Connection Types paralleling Connection
Equal
impedances—
Yes No No No Yes
Equal ratios—
Same kVA
Equal
impedances—
No Yes No No Yes but Not Optimal
Equal ratios—
Different kVA
Unequal
impedances—
No Yes Yes No Not Optimal
Equal ratios—
Same kVA
Unequal
impedances—
No Yes Yes No Not Optimal
Equal ratios—
Different kVA
Unequal
impedances—
Yes No Yes Yes Not Optimal
Unequal ratios—
Same kVA
Unequal
impedances—
No Yes Yes Yes Not Optimal
Unequal ratios—
Different kVA
Different Phase
shift— Not allowed
Different polarity
Power And Distribution Transformers Sizing Calculations –
Part Seven
Glossary of Sizing Power and Distribution Transformers, Power and Distribution Transformers sizing
calculations – part One
Resources used to calculate basic ratings of power and Power and Distribution Transformers Sizing
distribution transformers Calculations – Part Two
the selection factors for the Power and Distribution Power and Distribution Transformers Sizing
Transformers Calculations – Part Three
Applicable calculations procedures for sizing of power Power And Distribution Transformers Sizing
and distribution transformers Calculations – Part Four
1- Applicable procedures for calculating power and Power And Distribution Transformers Sizing
distribution transformer ratios, Calculations – Part Five
2- Applicable procedures for calculating power
transformer efficiency,
3- Applicable procedures for calculating power
transformer voltage regulation,
4- Special Cases In Transformers Sizing Calculations:
Secondary Unit Substations
Special Cases In Transformers Sizing Calculations: Power And Distribution Transformers Sizing
Paralleled Transformers Calculations – Part Six
Note: I’d like from all of you to review our course “EP-3: Electrical Procurement – Transformers Course” to be
more familiar with the contents of our new articles about the Power and Distribution Transformers sizing
calculations.
Today, we will explain other special cases for Power and Distribution Transformers sizing calculations; K-Factor
Transformers.
3- K-Factor Transformers
Linear Loads:
A load that does not affect the input waveform, which is a pure sinewave, composed of a
fundamental frequency (e.g. 60 hz) component with no multiple frequencies. Typical linear loads are
resistive heating and induction motors.
Nonlinear Loads:
A load that distorts the input sinewave such that the resultant waveform is composed of a
fundamental frequency (e.g. 60 hz) component and multiple frequency components (e.g. 120 hz, 180
hz,..etc) called harmonics. Examples of these loads used in offices are: computers, fax machines,
copiers, printers, cash registers, UPS systems, and solid-state ballasts. In industrial plants, nonlinear
loads are such as variable speed drives, HID lighting, solid-state starters and solid-state
instruments. See Fig.1
As defined by ANSI / IEEE Std. 519, Harmonics are voltages or currents at frequencies that are integer
multiples of the fundamental (60 Hz) frequency: 120 Hz, 180 Hz, 240 Hz, 300 Hz, etc. which called odd
harmonics (3rd, 5th, 7th ,..., 25th,...). See Table-1.
Harmonic Frequency in Hz
fundamental 60
3rd 120
5th 300
7th 420
9th 540
11th 660
etc. etc.
Table-1: Harmonics
Nonlinear loads produce harmonic currents which flow from the load towards the power source
following the path of least impedances result in harmonic voltage drops which are observed as
harmonic voltage distortion. The voltage distortions could become very severe when the power
systems inductive and capacitive impedances become equal, a condition of parallel resonance.
1. Overheating of cables, especially the neutral conductor, but if normal wiring sizing
methods are employed, then the derating for wiring for harmonics is minimal and can be
ignored,
2. Overheating and vibration in induction motors,
3. Increased losses in transformers due to stray magnetic losses in the core, and eddy
current and resistive losses in the windings. eddy current losses are of most concern when
harmonics are present, because they increase approximately with the square of the
frequency,
4. Where power factor capacitors are fitted, harmonic currents can damage them and
care must be taken to avoid resonance with the supply inductance.
K-Factor
• When transformer supply a non-sinusoidal load current with the same rms value than rated
current, DC losses remain constant but winding eddy losses increase due to the higher frequency of
the harmonics, as a result, winding temperature rise increases and temperature limits can be exceed.
• So, K Factor rating is used to define the transformer’s ability to withstand the additional
heating generated by the harmonic current.
• K-Factor is a ratio between the additional losses due to harmonics and the eddy losses at 60
Hz. Note that K-Factor transformers do not eliminate harmonic distortion; they withstand the non-
linear load condition without overheating.
• K-Factor transformers are designed to be operated fully loaded with any harmonic
load having K-Factor equal to or less than its K-rating. For example, a K-13 transformer can
be fully loaded with any harmonic load having a K-Factor up to K-13. If the load has a K-Factor greater
than 13, then the transformer cannot be safely operated at full load and would require derating.
• The great advantage of a ‘K-rated’ transformer is that it will have been designed with
harmonic loads in mind and care will have been taken to keep losses low. For example:
1. Eddy current losses will have been reduced by the use of stranded conductors,
2. Magnetic losses will have been reduced by the use of low loss steels,
3. The neutral point connections are usually brought out individually, so that the star
point has a 300% current rating
• Standard Industry K-Factor Transformer Ratings:
K-4, K-9, K-13, K-20, K-30, K-40, K-50
• The larger the K Factor, the more harmonics are present. Linear loads, for example, have a K
Factor of 1.
• No UL listing for K Factor means transformer is rated only for linear loads.
• UL listing requires label stating: “Suitable for non-sinusoidal current loads with K Factor not
to exceed x ”. (x= 4, 9, 13, 20, 30, 40 or 50). See Fig.2.
In other words, the K-factor of the overall load is less than that which would be expected from
measurement of all the individual items. Similarly, when there are linear loads present, the overall K-
factor is reduced because the harmonic load is a smaller proportion of the total load.
K-Factor or Factor K?
There are two approaches in selecting a transformer feeding non-linear loads as follows:
1. In the United States, Underwriters Laboratories used to calculate the factor increase
in eddy current loss and specify a transformer designed to cope; this is known as ‘K-Factor’.
2. in Europe, transformer manufacturers used to estimate by how much a standard
transformer should be de-rated so that the total loss on harmonic load does not exceed the
fundamental design loss; this is known as ‘factor K’.
The figures produced by each method are numerically different; ‘factor K’ is a total rating factor while
‘K-factor’ is a multiplier (although a de-rating factor can be derived from it). The fact that both
methods use K as a designation can lead to confusion when talking to suppliers.
The use of de-rated standard transformers instead of K-Factor Transformers carries some
disadvantage as under:
1. The de-rated transformer nameplate indicates greater capacity. Initially, the
transformer may be operated at reduced loading. But in the future, additional loads may be
increased without reference back to the initial de-rating. This may lead to overloading and
consequent failure.
2. Because the transformer is oversized, the primary over-current protection level may
be too high to protect the secondary, but if the protection level is reduced, the inrush
current may cause tripping. Larger overcurrent protection may be required for the oversized
(de-rated) standard transformer resulting in larger conductor requirements with the
associated higher feeder costs.
3. The transformers designed specifically for nonlinear loads minimize losses due to
harmonic currents. They operate with the nonlinear loads more efficiently and generate less
heat that need to be dissipated.
4. There is also a potential maintenance problem for oversized (de-rated)
transformers.
We have three methods for Sizing Transformers for Non-Linear Loads as follows:
Method#1: ANSI / IEEE C57.110 has a procedure for de-rating standard distribution transformers for
non-linear loading but We will explain this method later since it is more complicated.
Method#2: Underwriters’ Laboratories method where the appropriate K-Factor for a transformer
with non-linear loads can be calculated as follows:
K = Σ (Ih)2 (h)2
Where:
Ih = RMS Current at Harmonic h
h = Harmonic Order, i.e. 3rd, 5th, 7th, etc.
Fig.4: K-factor calculations by UL
1- List the kVA value for each load category to be supplied. Next, assign a K-factor designation that
corresponds to the relative level of harmonics drawn by each type of load. Refer to Table-2.
2- Multiply the kVA of each load or load category times the Index of Load K-rating (ILK) that
corresponds to the assigned K-factor rating. This result is an indexed kVA-ILK value.
2- Tabulate the total connected load kVA for all load categories to be supplied.
4- Next, add-up the kVA-ILK values for all loads or load categories to be supplied by the transformer.
5- Divide the grand total kVA-ILK value by the total kVA load to be supplied. This will give an average
ILK for that combination of loads.
6- From Table-2 find the K-factor rating whose ILK is equal to or greater than the calculated ILK.
Description
K-Factor ILK
Incandescent Lighting
Electric Resistance Heating
Motors (without solid state drives)
K1 0.00
Control Transformers / Electromagnetic Control Devices
Motor-Generators (without solid state drives)
• The problem associated with calculating K- Factor is selecting the range of harmonic
frequencies that should be included. Some use up to 15th harmonic, others up to 25 th harmonic, and
still others include up to 50th harmonic.
• For the same load, each of these calculations can yield significantly different K-
Factors, because even very small current levels associated with higher harmonics, when multiplied by
the harmonic number squared, can yield significantly to the K-Factor.
• Based on the underlying assumptions of ANSI / IEEE C57.II0, it seems reasonable to limit
the K-Factor calculation to harmonic currents less than 25 th harmonic.
• In establishing standard transformer K-Factor rating; UL chose ratings of 1, 4, 9, 13, 20, 30, 40
and 50. From a practical viewpoint individual loads with K-Factors greater than 20 are infrequent.
• For example, At best office areas with some nonlinear loads and large
computer rooms normally have observed K-Factors of 4 to 9. Areas with
high concentrations of single phase computers and terminals have observed K- Factors of 13 to 17.
Power And Distribution Transformers Sizing Calculations –
Part Eight
Glossary of Sizing Power and Distribution Transformers, Power and Distribution Transformers sizing
calculations – part One
Resources used to calculate basic ratings of power and Power and Distribution Transformers Sizing
distribution transformers Calculations – Part Two
the selection factors for the Power and Distribution Power and Distribution Transformers Sizing
Transformers Calculations – Part Three
Applicable calculations procedures for sizing of power Power And Distribution Transformers Sizing
and distribution transformers Calculations – Part Four
1-Applicable procedures for calculating power and Power And Distribution Transformers Sizing
distribution transformer ratios, Calculations – Part Five
2-Applicable procedures for calculating power
transformer efficiency,
3-Applicable procedures for calculating power
transformer voltage regulation,
4-Special Cases In Transformers Sizing
Calculations: Secondary Unit Substations
Special Cases In Transformers Sizing Calculations: K- Power And Distribution Transformers Sizing
Factor Transformers Calculations – Part Seven
Note: I’d like from all of you to review our course “EP-3: Electrical Procurement – Transformers Course” to be
more familiar with the contents of our new articles about the Power and Distribution Transformers sizing
calculations.
Today, we will explain other special cases for Power and Distribution Transformers sizing calculations; K-
Factor/Factor K Calculator and Spreadsheet.
K-Factor/Factor K Calculators
Here we will study the programs and excel spreadsheets used for calculation of K-Factor/Factor K
used in sizing transformers with non-linear loads, these programs and excel spreadsheets are:
1. K-Factor/Factor K Calculator,
2. Transformer Calculations Spreadsheet.
1- K-Factor / Factor K Calculator
Note:
This program is designed to assist in the calculation of K Factors. It should be used for reference
purposes only and users should verify that the results are valid for their particular circumstances.
Introduction
This software calculates the K-Factor of a load from the harmonic content according to US and
European practice. The results can be used to select transformers or to determine suitable de-rating
factors for transformers.
How to use?
We will explain the following points to show how this program can be used in the calculation of K-
Factor / Factor K:
• First: Installation,
• Second: Running The Program,
• Third: The Main Window,
• Forth: Making New Calculation File,
• Fifth: Examples for K-Factor,
• Sixth: Examples for Factor K.
First: Installation
1. Double click the K-Factor-Calculation.exe file to install it.
2. The program will be installed to the following directory:
C:\Program Files (x86)\Copper Development Association\K-Factor Calculator\
Second: Running The Program
• From the start menu, click on the file KFC.exe to open it,
• Once the program opens, you will find the option to select the user’s language from English and Francais,
B- Output Data:
In case of K-Factor calculations: the output data will be as follows:
1. RMS Current,
2. K-Rating.
In case of Factor K calculations: the output data will be as follows:
1. Fundamental Eddy Current Loss,
2. Eddy current loss exponent,
3. RMS Current,
4. Factor K de-rate to.
Fifth: Examples for K-Factor
here are some examples for using this calculator to find K-Factor:
Sixth: Examples for Factor K
here are some examples for using this calculator to find Factor K:
2- Transformer Calculations Spreadsheet
The Transformer Calculations Spreadsheet consists of two parts:
Output data:
• Calculated RMS current, FLA in amps
• Calculated Harmonic Factors - K-Factor
• Calculated Harmonic Factors - FHL-Factor
Notes:
Note:
Non-registered members in Electrical-Knowhow website will not be able to open and use the program
and excel spreadsheet.
Glossary of Sizing Power and Distribution Transformers, Power and Distribution Transformers sizing
calculations – part One
Resources used to calculate basic ratings of power and Power and Distribution Transformers Sizing
distribution transformers Calculations – Part Two
the selection factors for the Power and Distribution Power and Distribution Transformers Sizing
Transformers Calculations – Part Three
Applicable calculations procedures for sizing of power Power And Distribution Transformers Sizing
and distribution transformers Calculations – Part Four
1-Applicable procedures for calculating power and Power And Distribution Transformers Sizing
distribution transformer ratios, Calculations – Part Five
2-Applicable procedures for calculating power
transformer efficiency,
3-Applicable procedures for calculating power
transformer voltage regulation,
4-Special Cases In Transformers Sizing Calculations:
Secondary Unit Substations
Special Cases In Transformers Sizing Calculations: Power And Distribution Transformers Sizing
Paralleled Transformers Calculations – Part Six
Special Cases In Transformers Sizing Calculations: K- Power And Distribution Transformers Sizing
Factor Transformers Calculations – Part Seven
Special Cases In Transformers Sizing Calculations, K- Power And Distribution Transformers Sizing
Factor/Factor K Calculators Calculations – Part Eight
Note: I’d like from all of you to review our course “EP-3: Electrical Procurement – Transformers Course” to be
more familiar with the contents of our new articles about the Power and Distribution Transformers sizing
calculations.
Today, we will explain other special cases for Power and Distribution Transformers sizing
calculations; Transformers with Large Motor Loads .
Special Cases In Transformers Sizing Calculations
4- Transformers with Large Motor Loads
introduction
Many engineers when sizing a transformer for some loads they care only about selecting a transformer larger than
the maximum demands they serve, or sometimes larger than the connected loads, so they do one of the following:
1. Add up the kVA loads and match the size of the Transformer to this summation (∑KVA
Loads).
2. Add up the kVA loads, add a percentage like 20% of the total, then match the size of the
Transformer to this summation (in this example, 1.20 X ∑KVA Loads).
Both above methods are non-professional, they can be used by non-specialist for the following reasons:
1. The first method ignores the characteristics of the loads, for example it does not take account of
inrush on Motor Loads, Lighting Loads, Harmonics and the like which can lead to premature failure of the
actual Transformer or large voltage dips, on motor startup.
2. The second method could unnecessarily increase the cost of the asset by over-compensating the
required Transformer size.
Note: for best selecting and sizing of a transformer, please review all the articles listed in above.
Importance of Short Circuit and Motor Starting Calculations in Transformer Sizing
Many engineers didn’t know that Short Circuit Calculations together with Motor Starting Calculations
are also used in Sizing Transformers and this what we will explain herein.
When sizing the transformer for motor loads, the fault current contribution from the
motors will not be a consideration for sizing. However, the motor contribution must be considered
when sizing all branch circuit fuses and circuit breakers. The interrupting capacity ratings of those
devices must equal or exceed the total short circuit capacity available at the point of application.
1. Inrush Current,
2. Motor starting KVA and Locked-Rotor Current,
3. Voltage and Frequency Variation.
1- Inrush Current
It is the initial input current drawn by an electrical device when first turned on. It usually applies to:
Inrush current is higher than the normal operating current or what is called “steady state” current.
An example of an electric motor inrush current is shown in Figure-1. It shows the peak current for the
first half cycle as being close to 30 amps and then decaying over subsequent half cycles as the motor
spools up.
Locked-rotor current is the steady-state current of a motor with the rotor locked and with rated
voltage applied at rated frequency. NEMA has designated a set of code letters to define locked-rotor
KVA/HP. This code letter appears on the nameplate of all AC squirrel-cage induction motors. KVA per
horsepower is calculated as follows:
A 0 - 3.15
B 3.15 – 3.55
C 3.55 – 4.0
D 4.0 – 4.5
E 4.5 – 5.0
F 5.0 – 5.6
G 5.6 – 6.3
H 6.3 – 7.1
J 7.1 – 8.0
K 8.0 – 9.0
L 9.0 - 10.0
M 10.0 - 11.2
N 11.2 - 12.5
P 12.5 - 14.0
R 14.0 - 16.0
S 16.0 - 18.0
T 18.0 - 20.0
U 20.0 - 22.4
V 22.4 - and up
Table-1: NEMA code letter designations (starting KVA’s)
The locked-rotor kilovolt-ampere-per-horsepower range includes the lower figure up to, but not
including, the higher figure. For example, 3.14 is letter “A” and 3.15 is letter “B”.
By manipulating the preceding equation for KVA/Hp for three-phase motors the following equation
can be derived for calculating locked-rotor current:
for example, the approximate starting current for a 7 1/2 Hp, 230 volt motor with a locked-rotor KVA
code letter G would be:
• all motors are designed to operate successfully with limited voltage and frequency
variations. However, voltage variation with rated frequency must be limited to ±10% and frequency
variations with rated voltage must be limited to ±5%. The combined variation of voltage and
frequency must be limited to the arithmetic sum of 10%.
• Variations are expressed as deviation from motor nameplate values, not necessarily system
nominal values. The allowable ±10% voltage variation is based upon the assumption that horsepower
will not exceed nameplate rating and that motor temperature may increase.
• Therefore, the voltage drop on inrush should not be allowed to drop more than -10% of the
rated voltage. This means 208v for 230v or 414v for 460 volt or 2.07 kV for 2.3 kV and 3.6 kV for 4.0
kV motors. It means that a 4 kV motor can still operate satisfactorily at 3,600 V.
So, Effect of variations in voltage:
An increase or decrease in voltage may result in increased heating at rated horsepower load. Under
extended operation this may accelerate insulation deterioration and shorten motor insulation
life. The affected motors may trip off as provided for by its protection – or if not, the motor burns.
We must determine the voltage dip caused by the motor inrush on start-up.
1. If the voltage dip within the allowable percentage of the system voltage. Then no
oversizing of the transformer is required.
2. If the voltage dip exceeds the operating requirement of the system, then the
transformer must provide extra kVA.
Note:
% Voltage Drop = (Motor Starting kVA) x 100 /(Motor Starting kVA + Short Circuit kVA)
Note: A voltage sag (U.S. English) equal to voltage dip (British English).
The following calculations will determine the extra kVA capacity required for a three
phase transformer that is used to feed a single three phase motor that is started with full voltage
applied to its terminals, or, "across-the-line."
The following precautions should be followed:
1. When one transformer is used to operate one motor, the running amperes of the
motor should not exceed 65% of the transformer’s full load ampere rating.
2. If any motor is started more than once per hour, add 20% to that motor's
minimum kVA rating to compensate for heat losses within the transformer.
Example:
A 7,500 kVA, 8.0% IZ, 69-4.16 kV transformer loaded with a single 2,000 hp, 4.16 kV, Code Letter J
motor. Check if this transformer size is adequate or not?
Answer:
1- from table-1 in above, Starting kVA of 2,000 hp Motor code letter J= 2,000 kVA x 7.6 = 15,200 kVA
2- Three-Phase Short Circuit Capacity of the 7,500 kVA transformer = transformer KVA X 100 /
transformer impedance= 7,500 KVA x 100 /8 = 93,750 kVA
Note: In this case, the 7.5 MVA transformer has a maximum of 93.75 MVA short circuit capability.
% Voltage dip = (Motor Starting kVA) x 100 /(Motor Starting kVA + Short Circuit kVA)
%VD at transformer Terminals = 15,200 x 100/(15,200 + 93,750) = 13.95% from the secondary voltage
4.16 KV
So, VD at transformer Terminals = 13.95% x 4.16 KV = 580 V
transformer Terminal Volts During Motor Start-Up = 4160 – 580 = 3,580 V
Result:
The transformer output voltage will drop more than 10%, so this 7.5 MVA transformer is small for a
2,000 hp motor!
The next higher standard size transformer at 10,000 kVA 8.0% impedance would have a short circuit
output capability of 125,000 kVA which will give %VD at transformer Terminals 10.84% . so, 12.5 MVA
transformer could be the choice which will have a short circuit output capability of 156,250 kVA which
will give %VD at transformer Terminals 8.865%.
The minimum transformer kVA is given by transformer manufacturers so that a transformer may be
sized properly for multiple motors.
If there are five motors on one transformer, add the minimum kVA ratings and then add transformer
capacity as necessary to accommodate the inrush current of the largest motor.
KVA transformer min = kVA ratings for all motors except largest + transformer KVA as necessary to
accommodate the inrush current of the largest motor (as in above Example)