RENDIMIENTOS DE TRANSPORTE

PROYECTO ESTUDIO DEFINITIVO DE MEJORAMIENTO Y CONSTRUCCION DE LA CARRETERA RUTA 10


TRAMO HUAMACHUCO - PUENTE PALLAR - JUANJUI
SECTOR HUAMACHUCO - SACSACOCHA - PUENTE PALLAR

TRANSPORTE DE MATERIAL TRANSPORTE TRANSPORTE TRANSPORTE DE MEZCLA TRANSPORTE DE MATERIAL TRANSPORTE DE MATERIAL
GRANULAR Y DE RELLENO ASFÁLTICA EXCEDENTE A DME TRANSPORTE DE TRANSPORTE TRANSPORTE TRANSPORTE DE DERRUMBES A DME
INTERNO AGREGADOS AGUA PARA LA
BASES DE CALCULO UND MATERIAL PARA MATERIAL PIEDRA PARA PIEDRA
(Cantera a planta CONCRETO, OBRA
ACCESOS EXCEDENTE GAVION MEDIANA
de agregados) FILTRO
D<=1km D>1km D<=1km D>1km D<=1km D>1km D<=1km D>1km

DISTANCIA MEDIA PONDERADA km 1.00 1.00 0.30 15.23 1.00 1.00 1.00 1.00 4.13 2.83 4.81 1.37 10.29 1.00 1.00
VELOCIDAD CARGADO km/h 15 20 15 20 20 25 15 20 15 15 15 15 15 15 20
VELOCIDAD DESCARGADO km/h 20 25 20 25 25 30 20 25 20 20 25 25 25 20 25
TIEMPO DE CARGA min 6.86 8.57 8.57 12.00 6.86 10 8.57 8.57 8.57 8.57 6.86
TIEMPO DE DESCARGA min 2.00 2.00 2.00 6.00 2.00 25 2.00 2.00 2.00 2.00 2.00
TIEMPO RECORRIDO CARGADO fórmula 60 d / 15 60 d / 20 60 d / 15 60 d / 20 60 d / 20 60 d / 25 60 d / 15 60 d / 20 60 d / 15 60 d / 15 60 d / 15 60 d / 15 60 d / 15 60 d / 15 60 d / 20
TIEMPO RECORRIDO DESCARGADO fórmula 60 d / 20 60 d / 25 60 d / 20 60 d / 25 60 d / 25 60 d / 30 60 d / 20 60 d / 25 60 d / 20 60 d / 20 60 d / 25 60 d / 25 60 d / 25 60 d / 20 60 d / 25
TIEMPO RECORRIDO min 7.00 5.40 7.00 5.40 5.40 4.40 7.00 5.40 7.00 7.00 6.40 6.40 6.40 7.00 5.40
CICLO fórmula 8.86 + 7.00d 0.00 + 5.40d 10.57 + 7.00d 10.57 + 5.40d 18.00 + 5.40d 0.00 + 4.40d 8.86 + 7.00d 0.00 + 5.40d 10.00 + 7.00d 10.57 + 7.00d 10.57 + 6.40d 10.57 + 6.40d 10.57 + 6.40d 8.86 + 7.00d 0.00 + 5.40d
CICLO min 15.86 5.40 12.67 92.81 23.40 4.40 15.86 5.40 63.91 30.38 41.35 19.34 76.43 15.86 5.40
TIEMPO TRABAJADO POR DIA min 480 480 480 480 480 480 480 480 480 480 480 480 480 480 480
EFICIENCIA % 90.00% 90.00% 90.00% 90.00% 75.00% 75.00% 90.00% 90.00% 90.00% 90.00% 90.00% 90.00% 90.00% 90.00% 90.00%
TIEMPO UTIL TRABAJADO min 432 432 432 432 360 360 432 432 432 432 432 432 432 432 432
VOLUMEN DEL VOLQUETE m3 15 15 15 15 15 15 15 15 15 15 15 15 15 15
VOLUMEN DEL CAMION CISTERNA gln 3,000.00
RENDIMIENTO DEL CARGADOR m3/día 1050 840 840 1050 840 840 840 840 1050
INCIDENCIA DEL CARGADOR hm 0.39 0.61 0.09 0.39 0.25 0.18 0.39 0.11 0.39
NUMERO DE VIAJES AL DIA u 27 80 34 5 15 82 27 80 7 14 10 22 6 27 80
VOLUMEN TRANSPORTADO POR DIA m3 405 1200 510 75 225 1230 405 1200 79 210 150 330 90 405 1200
ESPONJAMIENTO 1.20 1.20 1.20 1.20 1.30 1.30 1.30 1.30 1.20 1.30 1.35 1.35 1.35 1.35

RENDIMIENTO m3/dia 338.00 1,000.00 425.00 63.00 173.00 946.00 312.00 923.00 79.00 175.00 115.00 244.00 67.00 300.00 889.00