Activities
General excavation
General Backfilling of Areas/Roads
Subbase preparation under paving
Limited excavation up to 1.5 m
Limited Excavation (Over 1.5m depth)
Reinf concrete pit for sewer
Installation of PVC drainage system
Installation of Cast Iron Drainage
Laying of Sand for Pipe Prot.
Lay of slabs/bricks Cables
Road (Base course+ subbase)
Asphalting of Roads
Lean Concrete
Reinforced Concrete up to +1.0 M
Reinforced Concrete +1.0M/+ 7.0 M
Reinforced Concrete for Paving
Concrete for Piping support
Foundation Protection
Execution of expansion joints
PR / Lay light items (Real V)
Fire Proofing
Grouting Operation
Und. Fibreg. Pip. On S.PN14 (6In)
P/E FiberGl. Pip. On S.PN6 (6In)
Hydrotest Resin Pip on Site
GOSP 3
Activities
General excavation
General Backfilling of Areas/Roads
Subbase preparation under paving
Limited excavation up to 1.5 m
Limited Excavation (Over 1.5m depth)
Reinf concrete pit for sewer
Installation of PVC drainage system
Installation of Cast Iron Drainage
Laying of Sand for Pipe Prot.
Lay of slabs/bricks Cables
Road (Base course+ subbase)
Asphalting of Roads
Lean Concrete
Reinforced Concrete up to +1.0 M
Reinforced Concrete +1.0M/+ 7.0 M
Reinforced Concrete for Paving
Concrete for Piping support
Foundation Protection
Execution of expansion joints
PR / Lay light items (Real V)
Fire Proofing
Grouting Operation
Und. Fibreg. Pip. On S.PN14 (6In)
P/E FiberGl. Pip. On S.PN6 (6In)
Hydrotest Resin Pip on Site
GOSP 4
Activities
General excavation
General Backfilling of Areas/Roads
Subbase preparation under paving
Limited excavation up to 1.5 m
Limited Excavation (Over 1.5m depth)
Reinf concrete pit for sewer
Installation of PVC drainage system
Installation of Cast Iron Drainage
Laying of Sand for Pipe Prot.
Lay of slabs/bricks Cables
Road (Base course+ subbase)
Asphalting of Roads
Lean Concrete
Reinforced Concrete up to +1.0 M
Reinforced Concrete +1.0M/+ 7.0 M
Reinforced Concrete for Paving
Concrete for Piping support
Foundation Protection
Execution of expansion joints
PR / Lay light items (Real V)
Fire Proofing
Grouting Operation
Und. Fibreg. Pip. On S.PN14 (6In)
P/E FiberGl. Pip. On S.PN6 (6In)
Hydrotest Resin Pip on Site
INLET / OUTLET
Activities
General excavation
General Backfilling of Areas/Roads
Subbase preparation under paving
Limited excavation up to 1.5 m
Limited Excavation (Over 1.5m depth)
Reinf concrete pit for sewer
Installation of Cast Iron Drainage
Laying of Sand for Pipe Prot.
Lay of slabs/bricks Cables
Road (Base course+ subbase)
Asphalting of Roads
Lean Concrete
Reinforced Concrete UP TO +1.0 M
Reinforced Concrete +1.0M/+ 7.0 M
Reinforced Concrete for Paving
Concrete for Piping support
Foundation Protection
Execution of expansion joints
PR / Lay light items (Real V)
Grouting Operation
Und. Fibreg. Pip. On S.PN14 (6In)
Hydrotest Resin Pip on Site
COMMON
Activities
14 31 30 31 30 31 31 30 31 30 31 31 29 31 30 31 30 31 31 30 31 30 31 31 28
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
1,269.00 102.00 cu.m 0.082% 23-Jan-10 15-Feb-10 21.00 6.7% 18.9% 18.3% 18.9% 18.9% 18.3% 100.0% 100.0%
8,340.00 1,218.00 cu.m 0.975% 10-Feb-10 13-Feb-10 12.00 9.5% 10.2% 9.9% 10.2% 9.9% 10.2% 10.2% 9.9% 10.2% 10% 100.0% 100.0%
43,659.00 4,066.00 sq.m. 3.255% 5-May-10 16-May-10 10.00 8.9% 8.3% 8.9% 8.6% 8.9% 8.6% 8.9% 8.9% 8.6% 8.8% 8.6% 4.3% 100.0% 100.0%
4,570.00 sq.m. 3.658% 15-Feb-10 19-Feb-10 5.00 280.0% 620.0% 600.0% 620.0% 600.0% 620.0% 620.0% 600.0% 620.0% 600.0% 620.0% 620.0% 580.0% 620.0% 600.0% 620.0% 600.0% 620.0% 620.0% 600.0% 620.0% 12500.0% 12500.0%
44.52 2,680.00 cu.m 2.145% 22-Feb-10 22-Feb-10 1.00
225.10 1,757.00 sq.m. 1.406% 23-Feb-10 2-Mar-10 13.00 230.8% 238.5% 238.5% 230.8% 238.5% 230.8% 238.5% 238.5% 215.4% 2100.0% 2100.0%
2,400.00 480.00 m 0.384% 3-Mar-10 3-Mar-10 1.00 ### 3100.0% 3000.0% 3100.0% 3000.0% 3100.0% 3100.0% 2900.0% 3100.0% 3000.0% 3100.0% -64000.0% -64000.0%
107.00 535.00 m 0.428% 4-Mar-10 14-Mar-10 10.00 300.0% 310.0% 610.0%
163.00 108.00 cu.m 0.086% 16-Mar-10 16-Mar-10 1.00 3100.0% 3000.0% 3100.0% 3000.0% 3100.0% 3100.0% 2900.0% 3100.0% 3000.0% 3100.0% 3000.0% ### 3100.0% 3000.0% 3100.0% 3000.0% 48800.0% 48800.0%
238.00 38.00 sq.m. 0.030% 26-Apr-10 4-May-10 6.00 483.3% 516.7% 500.0% 516.7% 500.0% 2516.7% 2516.7%
10,202.00 1,226.00 cu.m. 0.981% 17-May-10 25-May-10 8.00 387.5% 387.5% 375.0% 387.5% 375.0% 1912.5% 1912.5%
20,634.00 774.00 sq.m. 0.620% 17-Mar-10 30-Apr-10 20.00 155.0% 150.0% 155.0% 150.0% 155.0% 765.0% 765.0%
508.00 750.00 cu.m 0.600% 1-Apr-10 29-Apr-10 1.00 800.0% 3100.0% 3000.0% 3100.0% 3000.0% ### 3100.0% 3000.0% 3100.0% 3000.0% 3100.0% 3100.0% 34500.0% 34500.0%
6,259.00 38,046.00 cu.m 30.455% 26-May-10 12-Jun-10 15.00 193.3% 200.0% 206.7% 200.0% 206.7% 206.7% 200.0% 206.7% 200.0% 206.7% 206.7% 186.7% 2420.0% 2420.0%
185.00 626.00 cu.m 0.501% 13-Jun-10 13-Jun-10 1.00 800.0% 3000.0% ### 3100.0% 3000.0% 3100.0% 3000.0% 3100.0% 22200.0% 22200.0%
24,211.00 8,335.00 sq.m. 6.672% 30-Jun-10 5-Jul-10 5.00 580.0% 620.0% 600.0% 620.0% 600.0% 620.0% 620.0% 600.0% 620.0% 5480.0% 5480.0%
294.00 1,456.00 cu.m. 1.166% 25-Apr-10 28-Apr-10 6.00 516.7% 516.7% 483.3% 516.7% 500.0% 516.7% 500.0% 516.7% 4066.7% 4066.7%
40,516.00 9,088.00 sq.m. 7.275% 26-Aug-10 4-Sep-10 8.00 375.0% 387.5% 387.5% 375.0% 387.5% 375.0% 387.5% 387.5% 362.5% 387.5% 375.0% 387.5% 375.0% 387.5% 387.5% 375.0% 387.5% 375.0% 6862.5% 6862.5%
12,105.00 2,421.00 m 1.938% 2-Sep-10 18-Sep-10 14.00 207.1% 221.4% 214.3% 221.4% 214.3% 221.4% 221.4% 214.3% 221.4% 1957.1% 1957.1%
111.00 261.00 cu.m. 0.209% 6-Jul-10 13-Jul-10 7.00 414.3% 442.9% 428.6% 1285.7% 1285.7%
120.00 4,730.00 cu.m 3.786% 14-Jul-10 21-Jul-10 7.00 414.3% 442.9% 428.6% 442.9% 428.6% 442.9% 442.9% 428.6% 442.9% 3914.3% 3914.3%
46.00 8,879.00 cu.m. 7.108% 15-Aug-10 25-Aug-10 10.00 310.0% 300.0% 310.0% 310.0% 290.0% 310.0% 300.0% 310.0% 300.0% 310.0% 310.0% 300.0% 310.0% 300.0% 310.0% 200.0% 4780.0% 4780.0%
44,023.00 31,156.00 Kg 24.940% 29-Aug-10 1-Sep-10 4.00 400.0% 775.0% 775.0% 725.0% 775.0% 750.0% 775.0% 750.0% 775.0% 775.0% 750.0% 775.0% 750.0% 9550.0%
31.00 19.00 Kg 0.015% 6-Sep-10 16-Sep-10 10.00 280.0% 310.0% 290.0% 310.0% 300.0% 310.0% 300.0% 2100.0%
4,790.00 1,603.00 m 1.283% 26-Aug-10 4-Sep-10 8.00 362.5% 387.5% 375.0% 387.5% 375.0% 387.5% 387.5% 375.0% 387.5% 375.0% 3800.0%
124,924.00 13.02% 100.000% 27-Jul-10 11-Aug-10 14.00 0.0% 0.0%
26-Aug-10 11-Sep-10 14.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
12-Sep-10 26-Sep-10 10.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
14-Sep-10 26-Sep-10 8.00
13-Mar-10 26-Jul-10 5.00
22-Jul-10 2-Aug-10 10.00
27-Jul-10 7-Aug-10 10.00
3-Aug-10 14-Aug-10 10.00
26-Aug-10 6-Sep-10 10.00
29-Aug-10 6-Sep-10 8.00
29-Aug-10 5-Sep-10 7.00
14-Sep-10 16-Sep-10 3.00
13-Mar-10 27-Jul-10 5.00
26-Aug-10 31-Aug-10 5.00
14-Sep-10 19-Sep-10 5.00
13-Mar-10 27-Jul-10 5.00
28-Jul-10 2-Aug-10 5.00
3-Aug-10 8-Aug-10 5.00
6-Jul-10 21-Jul-10 14.00
31-Jul-10 15-Aug-10 14.00
16-Aug-10 26-Aug-10 10.00
13-Jun-10 15-Jun-10 3.00
26-Jun-10 12-Aug-10 42.00
3-Feb-10 11-Apr-10 10.00
17-Mar-10 24-Jun-10 20.00
14-Jun-10 21-Jun-10 7.00
8-Jul-10 17-Aug-10 35.00
22-Jul-10 31-Aug-10 35.00
28-Aug-10 12-Sep-10 14.00
13-Sep-10 27-Sep-10 10.00
13MAR10A 14-Sep-10 7.00
28-Aug-10 7-Sep-10 10.00
5-Mar-10 10-Mar-10 7.00
1-May-10 2-May-10 2.00
1-May-10 4-May-10 4.00
3-Jul-10 19-Jul-10 15.00
12-Mar-10 14-Mar-10 2.00
15-Mar-10 15-Mar-10 1.00
18-Mar-10 19-Mar-10 7.00
20-Mar-10 20-Mar-10 1.00
21-Mar-10 23-Mar-10 6.00
23-Mar-10 23-Mar-10 1.00
24-Mar-10 5-Apr-10 12.00
5-Apr-10 5-Apr-10 2.00
3-May-10 5-May-10 3.00
5-May-10 10-May-10 5.00
6-May-10 6-May-10 1.00
11-May-10 11-May-10 1.00
12-May-10 16-May-10 4.00
16-May-10 17-May-10 2.00
18-May-10 25-May-10 7.00
26-May-10 27-May-10 2.00
26-May-10 2-Jun-10 7.00
3-Jun-10 3-Jun-10 1.00
16-Jun-10 27-Jun-10 10.00
30-Jun-10 1-Jul-10 2.00
8-May-10 15-May-10 7.00
5-Jun-10 12-Jun-10 7.00
13-Jun-10 20-Jun-10 7.00
12-Jul-10 13-Jul-10 2.00
12-Jul-10 14-Jul-10 3.00
15-Jul-10 17-Jul-10 2.00
2-Jun-10 19-Jun-10 15.00
2-Jun-10 19-Jun-10 15.00
6-Jun-10 29-Jun-10 21.00
28-Jun-10 29-Jun-10 2.00
30-Jun-10 11-Jul-10 10.00
6-Jul-10 8-Jul-10 3.00
6-Jul-10 8-Jul-10 3.00
12-Jul-10 15-Aug-10 30.00
15-Mar-10 24-May-10 14.00
13-May-10 24-May-10 10.00
25-May-10 1-Jun-10 7.00
25-May-10 30-May-10 5.00
2-Jun-10 12-Jun-10 9.00
20-Jun-10 30-Jun-10 10.00
1-Jul-10 12-Jul-10 10.00
10-Aug-10 21-Aug-10 10.00
25-Aug-10 5-Sep-10 10.00
5-Sep-10 25-Sep-10 15.00
8-Sep-10 28-Sep-10 15.00
8-Sep-10 28-Sep-10 15.00
16-Sep-10 30-Sep-10 10.00
8-Sep-10 28-Sep-10 15.00
15-Feb-10 22-Feb-10 12.00
9-Mar-10 6-May-10 10.00
23-Feb-10 23-Feb-10 5.00
24-Feb-10 24-Feb-10 1.00
25-Feb-10 27-Feb-10 13.00
28-Feb-10 28-Feb-10 1.00
1-Mar-10 3-Mar-10 10.00
4-Mar-10 4-Mar-10 1.00
6-Mar-10 5-May-10 6.00
8-May-10 16-May-10 8.00
16-Feb-10 25-May-10 20.00
18-Apr-10 25-May-10 1.00
30-May-10 15-Jun-10 15.00
16-Jun-10 16-Jun-10 1.00
4-Jul-10 8-Jul-10 5.00
22-Aug-10 6-Sep-10 14.00
5-Sep-10 11-Sep-10 6.00
12-Sep-10 23-Sep-10 8.00
10-Jul-10 17-Jul-10 7.00
21-Jul-10 28-Jul-10 7.00
3-Aug-10 14-Aug-10 10.00
17-Aug-10 21-Aug-10 4.00
19-Aug-10 1-Sep-10 12.00
17-Aug-10 25-Aug-10 8.00
29-Jul-10 14-Aug-10 14.00
15-Aug-10 30-Aug-10 14.00
21-Aug-10 31-Aug-10 10.00
30-Aug-10 7-Sep-10 8.00
13-Mar-10 2-Aug-10 5.00
29-Jul-10 9-Aug-10 10.00
3-Aug-10 14-Aug-10 10.00
10-Aug-10 21-Aug-10 10.00
15-Aug-10 25-Aug-10 10.00
17-Aug-10 25-Aug-10 8.00
17-Aug-10 24-Aug-10 7.00
4-Sep-10 6-Sep-10 3.00
13-Mar-10 3-Aug-10 5.00
17-Aug-10 22-Aug-10 5.00
28-Aug-10 1-Sep-10 5.00
13-Mar-10 3-Aug-10 5.00
4-Aug-10 9-Aug-10 5.00
10-Aug-10 15-Aug-10 5.00
10-Jul-10 25-Jul-10 14.00
3-Aug-10 18-Aug-10 14.00
19-Aug-10 30-Aug-10 10.00
30-May-10 1-Jun-10 3.00
26-Jun-10 24-Jul-10 25.00
23-Feb-10 22-Apr-10 10.00
29-Mar-10 10-Jun-10 20.00
17-Jun-10 24-Jun-10 7.00
28-Jul-10 25-Aug-10 25.00
9-Aug-10 6-Sep-10 25.00
15-Aug-10 30-Aug-10 14.00
31-Aug-10 11-Sep-10 10.00
13-Mar-10 9-Sep-10 10.00
31-Aug-10 7-Sep-10 7.00
1-May-10 5-May-10 5.00
1-May-10 5-May-10 5.00
6-May-10 23-May-10 15.00
8-Mar-10 14-Mar-10 7.00
24-May-10 25-May-10 2.00
24-May-10 27-May-10 4.00
4-Aug-10 19-Aug-10 14.00
15-Mar-10 18-Mar-10 2.00
19-Mar-10 19-Mar-10 1.00
20-Mar-10 24-Mar-10 7.00
25-Mar-10 25-Mar-10 1.00
26-Mar-10 26-Mar-10 6.00
26-Mar-10 26-Mar-10 1.00
27-Mar-10 29-Mar-10 12.00
30-Mar-10 30-Mar-10 2.00
26-May-10 29-May-10 3.00
30-May-10 30-May-10 1.00
8-Jun-10 9-Jun-10 2.00
10-Jun-10 17-Jun-10 7.00
19-Jun-10 20-Jun-10 2.00
19-Jun-10 26-Jun-10 7.00
27-Jun-10 27-Jun-10 1.00
22-Jul-10 24-Jul-10 2.00
25-Jul-10 29-Jul-10 5.00
31-Jul-10 31-Jul-10 1.00
1-Aug-10 4-Aug-10 4.00
31-May-10 7-Jun-10 7.00
25-Jul-10 1-Aug-10 7.00
2-Aug-10 9-Aug-10 7.00
6-Sep-10 7-Sep-10 2.00
26-Aug-10 29-Aug-10 3.00
21-Aug-10 22-Aug-10 2.00
28-Jun-10 21-Jul-10 21.00
20-Jul-10 21-Jul-10 2.00
1-Aug-10 11-Aug-10 10.00
5-Aug-10 29-Aug-10 21.00
5-Aug-10 22-Aug-10 15.00
5-Aug-10 22-Aug-10 15.00
7-Aug-10 9-Aug-10 3.00
7-Aug-10 9-Aug-10 3.00
13-Mar-10 12-Aug-10 14.00
2-Aug-10 12-Aug-10 10.00
14-Aug-10 18-Aug-10 5.00
14-Aug-10 21-Aug-10 7.00
22-Aug-10 26-Aug-10 5.00
23-Aug-10 2-Sep-10 10.00
23-Aug-10 2-Sep-10 10.00
28-Aug-10 1-Sep-10 5.00
30-Aug-10 9-Sep-10 10.00
6-Sep-10 26-Sep-10 15.00
4-Sep-10 23-Sep-10 15.00
28-Aug-10 13-Sep-10 15.00
28-Aug-10 13-Sep-10 15.00
28-Aug-10 13-Sep-10 15.00
10-Mar-10 17-Mar-10 7.00
15-May-10 17-Jun-10 30.00
26-May-10 29-Jun-10 30.00
17-May-10 14-Jun-10 25.00
23-May-10 29-May-10 6.00
15-Jun-10 1-Jul-10 15.00
3-Jul-10 13-Jul-10 10.00
14-Jul-10 25-Jul-10 10.00
26-Jul-10 5-Aug-10 10.00
26-May-10 29-Jun-10 30.00
13-Jun-10 5-Jul-10 20.00
7-Jun-10 13-Jun-10 6.00
14-Jun-10 24-Jun-10 10.00
19-Jul-10 24-Jul-10 5.00
13-Jul-10 29-Jul-10 15.00
4-Aug-10 10-Aug-10 6.00
31-Jul-10 16-Aug-10 15.00
15-Apr-10 30-Jun-10 6.00
17-Apr-10 29-Apr-10 10.00
1-Jul-10 12-Jul-10 10.00
26-Jun-10 1-Jul-10 6.00
3-Jul-10 13-Jul-10 10.00
14-Jul-10 25-Jul-10 10.00
14-Jul-10 25-Jul-10 10.00
7-Aug-10 17-Aug-10 10.00
17-Aug-10 28-Aug-10 10.00
16-Jun-10 8-Jul-10 20.00
3-Jul-10 25-Jul-10 20.00
28-Jul-10 19-Aug-10 20.00
21-Aug-10 28-Aug-10 7.00
28-Aug-10 0.00
30-Sep-10 0.00
14 31 30 31 30 31 31 30 31 30 31 31 29 31 30 31 30 31 31 30 31 30 31 31 28
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Qty DMHS Unit Relative %
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
1,269.00 102.00 cu.m 0.088% 4/20/2007 9/30/2007 164.00 6.7% 18.9% 18.3% 18.9% 18.9% 18.3% 100.0% 100.0%
8,429.00 1,123.00 cu.m 0.964% 2/1/2008 11/30/2008 304.00 9.5% 10.2% 9.9% 10.2% 9.9% 10.2% 10.2% 9.9% 10.2% 9.9% 100.0% 100.0%
43,659.00 4,066.00 sq.m. 3.492% 1/1/2008 12/15/2008 350.00 8.9% 8.3% 8.9% 8.6% 8.9% 8.6% 8.9% 8.9% 8.6% 8.9% 8.6% 4.3% 100.0% 100.0%
11,131.00 4,452.00 cu.m 3.823% 2/15/2007 10/31/2008 625.00 280.0% 620.0% 600.0% 620.0% 600.0% 620.0% 620.0% 600.0% 620.0% 600.0% 620.0% 620.0% 580.0% 620.0% 600.0% 620.0% 600.0% 620.0% 620.0% 600.0% 620.0% 12500.0% 12500.0%
2,486.00 2,619.00 cu.m 2.249% 4/20/2007 10/30/2008 560.00 1100.0% 3100.0% 3000.0% ### 3100.0% 3000.0% 3100.0% 3000.0% 3100.0% 3100.0% 2900.0% 3100.0% 3000.0% 3100.0% 3000.0% ### 3100.0% 3000.0% 3000.0% 56000.0% 56000.0%
185.00 1,353.00 cu.m 1.162% 6/1/2007 2/28/2008 273.00 230.8% 238.5% 238.5% 230.8% 238.5% 230.8% 238.5% 238.5% 215.4% 2100.0% 2100.0%
80.00 16.00 m 0.014% 7/15/2007 5/31/2008 322.00 5.3% 3100.0% 3000.0% 3100.0% 3000.0% 3100.0% 3100.0% 2900.0% 3100.0% 3000.0% 3100.0% 30505.3% 30505.3%
107.00 535.00 m 0.459% 4/1/2008 5/31/2008 61.00 300.0% 310.0% 610.0%
75.00 50.00 cu.m 0.043% 8/1/2007 11/30/2008 488.00 3100.0% 3000.0% 3100.0% 3000.0% 3100.0% 3100.0% 2900.0% 3100.0% 3000.0% 3100.0% 3000.0% ### 3100.0% 3000.0% 3100.0% 3000.0% 48800.0% 48800.0%
150.00 24.00 sq.m. 0.021% 2/1/2008 6/30/2008 151.00 483.3% 516.7% 500.0% 516.7% 500.0% 2516.7% 2516.7%
10,716.00 1,288.00 cu.m. 1.106% 7/1/2008 11/30/2008 153.00 387.5% 387.5% 375.0% 387.5% 375.0% 1912.5% 1912.5%
21,676.00 813.00 sq.m. 0.698% 8/1/2008 12/31/2008 153.00 155.0% 150.0% 155.0% 150.0% 155.0% 765.0% 765.0%
383.00 416.00 cu.m 0.357% 2/21/2007 1/31/2008 345.00 2.3% 3100.0% 3000.0% 3100.0% 3000.0% ### 3100.0% 3000.0% 3100.0% 3000.0% 3100.0% 3100.0% 33702.3% 33702.3%
6,284.00 35,345.00 cu.m 30.353% 3/3/2007 2/28/2008 363.00 193.3% 200.0% 206.7% 200.0% 206.7% 206.7% 200.0% 206.7% 200.0% 206.7% 206.7% 186.7% 2420.0% 2420.0%
185.00 581.00 cu.m 0.499% 5/24/2007 12/31/2007 222.00 3.6% 3000.0% ### 3100.0% 3000.0% 3100.0% 3000.0% 3100.0% 21403.6% 21403.6%
24,211.00 8,335.00 sq.m. 7.158% 2/1/2008 10/31/2008 274.00 580.0% 620.0% 600.0% 620.0% 600.0% 620.0% 620.0% 600.0% 620.0% 5480.0% 5480.0%
294.00 1,456.00 cu.m. 1.250% 12/1/2007 7/31/2008 244.00 516.7% 516.7% 483.3% 516.7% 500.0% 516.7% 500.0% 516.7% 4066.7% 4066.7%
40,152.00 5,074.00 sq.m. 4.357% 6/1/2007 11/30/2008 549.00 375.0% 387.5% 387.5% 375.0% 387.5% 375.0% 387.5% 387.5% 362.5% 387.5% 375.0% 387.5% 375.0% 387.5% 387.5% 375.0% 387.5% 375.0% 6862.5% 6862.5%
12,105.00 2,421.00 m 2.079% 2/1/2008 10/31/2008 274.00 207.1% 221.4% 214.3% 221.4% 214.3% 221.4% 221.4% 214.3% 221.4% 1957.1% 1957.1%
70.00 142.00 cu.m. 0.122% 2/1/2008 4/30/2008 90.00 414.3% 442.9% 428.6% 1285.7% 1285.7%
120.00 4,730.00 cu.m 4.062% 2/1/2008 10/31/2008 274.00 414.3% 442.9% 428.6% 442.9% 428.6% 442.9% 442.9% 428.6% 442.9% 3914.3% 3914.3%
46.00 9,709.00 cu.m. 8.338% 10/1/2007 1/20/2009 478.00 310.0% 300.0% 310.0% 310.0% 290.0% 310.0% 300.0% 310.0% 300.0% 310.0% 310.0% 300.0% 310.0% 300.0% 310.0% 200.0% 4780.0% 4780.0%
45,482.00 30,261.00 Kg 25.987% 11/15/2007 11/30/2008 382.00 400.0% 775.0% 775.0% 725.0% 775.0% 750.0% 775.0% 750.0% 775.0% 775.0% 750.0% 775.0% 750.0% 9550.0%
10.00 12.00 Kg 0.010% 12/4/2007 6/30/2008 210.00 280.0% 310.0% 290.0% 310.0% 300.0% 310.0% 300.0% 2100.0%
4,431.00 1,522.00 m 1.307% 2/1/2008 11/30/2008 304.00 362.5% 387.5% 375.0% 387.5% 375.0% 387.5% 387.5% 375.0% 387.5% 375.0% 3800.0%
116,445.00 12.13% 100.000% 0.0% 0.0%
10.71% 93.46% 119.11% 167.27% 195.84% ### 204.13% 197.54% 229.96% 326.49% 437.85% 422.70% 451.04% 418.90% 406.77% 419.79% 404.45% ### 416.71% 403.26% 414.46% 248.04% 27.08% 16.68% 0.00% 4122.21%
10.71% 104.18% 223.29% 390.55% 586.40% ### 992.90% ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 10778.89%
14 31 30 31 30 31 31 30 31 30 31 31 29 31 30 31 30 31 31 30 31 30 31 31 28
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Qty DMHS Unit Relative %
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
1,269.00 102.00 cu.m 0.087% 5/20/2007 10/30/2007 164.00 7.3% 18.3% 18.9% 18.9% 18.3% 18.3% 100.0% 100.0%
8,337.00 1,111.00 cu.m 0.944% 3/2/2008 12/31/2008 305.00 9.8% 9.8% 10.2% 9.8% 10.2% 10.2% 9.8% 10.2% 9.8% 10.2% 100.0% 100.0%
43,659.00 4,066.00 sq.m. 3.456% 2/1/2008 1/31/2009 366.00 7.9% 8.5% 8.2% 8.5% 8.2% 8.5% 8.5% 8.2% 8.5% 8.2% 8.5% 8.5% 100.0% 100.0%
11,313.00 4,525.00 cu.m 3.847% 3/17/2007 11/30/2008 625.00 2.4% 4.8% 5.0% 4.8% 5.0% 5.0% 4.8% 5.0% 4.8% 5.0% 5.0% 4.6% 5.0% 4.8% 5.0% 4.8% 5.0% 5.0% 4.8% 5.0% 4.8% 100.0% 100.0%
2,535.00 2,626.00 cu.m 2.232% 5/20/2007 11/30/2008 561.00 2.1% 5.3% 5.5% 5.5% 5.3% 5.5% 5.3% 5.5% 5.5% 5.2% 5.5% 5.3% 5.5% 5.3% 5.5% 5.5% 5.3% 5.5% 5.3% 100.0% 100.0%
228.00 1,476.00 cu.m 1.255% 7/1/2007 3/30/2008 274.00 11.3% 11.3% 10.9% 11.3% 10.9% 11.3% 11.3% 10.6% 10.9% 100.0% 100.0%
960.00 192.00 m 0.163% 8/15/2007 6/30/2008 321.00 5.3% 9.3% 9.7% 9.3% 9.7% 9.7% 9.0% 9.7% 9.3% 9.7% 9.3% 100.0% 100.0%
107.00 535.00 m 0.455% 5/1/2008 6/30/2008 61.00 50.8% 49.2% 100.0%
163.00 108.00 cu.m 0.092% 9/1/2007 12/30/2008 487.00 6.2% 6.4% 6.2% 6.4% 6.4% 6.0% 6.4% 6.2% 6.4% 6.2% 6.4% 6.4% 6.2% 6.4% 6.2% 6.2% 100.0% 100.0%
205.00 33.00 sq.m. 0.028% 3/1/2008 7/31/2008 153.00 20.3% 19.6% 20.3% 19.6% 20.3% 100.0% 100.0%
10,176.00 1,222.00 cu.m. 1.039% 8/1/2008 12/31/2008 153.00 20.3% 19.6% 20.3% 19.6% 20.3% 100.0% 100.0%
20,584.00 772.00 sq.m. 0.656% 9/1/2008 1/31/2009 153.00 19.6% 20.3% 19.6% 20.3% 20.3% 100.0% 100.0%
441.00 576.00 cu.m 0.490% 3/23/2007 2/28/2008 343.00 2.6% 8.7% 9.0% 8.7% 9.0% 9.0% 8.7% 9.0% 8.7% 9.0% 9.0% 8.2% 100.0% 100.0%
6,304.00 35,635.00 cu.m 30.293% 4/2/2007 3/30/2008 364.00 8.0% 8.5% 8.2% 8.5% 8.5% 8.2% 8.5% 8.2% 8.5% 8.5% 8.0% 8.2% 100.0% 100.0%
185.00 581.00 cu.m 0.494% 6/23/2007 1/30/2008 222.00 3.6% 14.0% 14.0% 13.5% 14.0% 13.5% 14.0% 13.5% 100.0% 100.0%
24,211.00 8,335.00 sq.m. 7.085% 3/1/2008 11/30/2008 275.00 11.3% 10.9% 11.3% 10.9% 11.3% 11.3% 10.9% 11.3% 10.9% 100.0% 100.0%
294.00 1,456.00 cu.m. 1.238% 1/1/2008 8/31/2008 244.00 12.7% 11.9% 12.7% 12.3% 12.7% 12.3% 12.7% 12.7% 100.0% 100.0%
40,468.00 5,135.00 sq.m. 4.365% 7/1/2007 12/30/2008 549.00 5.6% 5.6% 5.5% 5.6% 5.5% 5.6% 5.6% 5.3% 5.6% 5.5% 5.6% 5.5% 5.6% 5.6% 5.5% 5.6% 5.5% 5.5% 100.0% 100.0%
12,105.00 2,421.00 m 2.058% 3/1/2008 11/30/2008 275.00 11.3% 10.9% 11.3% 10.9% 11.3% 11.3% 10.9% 11.3% 10.9% 100.0% 100.0%
91.00 200.00 cu.m. 0.170% 3/1/2008 5/31/2008 92.00 33.7% 32.6% 33.7% 100.0% 100.0%
120.00 4,730.00 cu.m 4.021% 3/2/2008 11/30/2008 274.00 10.9% 10.9% 11.3% 10.9% 11.3% 11.3% 10.9% 11.3% 10.9% 100.0% 100.0%
47.00 9,920.00 cu.m. 8.433% 11/1/2007 2/28/2009 486.00 6.2% 6.4% 6.4% 6.0% 6.4% 6.2% 6.4% 6.2% 6.4% 6.4% 6.2% 6.4% 6.2% 6.4% 6.4% 5.8% 100.0% 100.0%
45,564.00 30,336.00 Kg 25.788% 12/15/2007 12/30/2008 382.00 4.2% 8.1% 7.6% 8.1% 7.9% 8.1% 7.9% 8.1% 8.1% 7.9% 8.1% 7.9% 8.1% 100.0%
15.00 18.00 Kg 0.015% 1/3/2008 7/30/2008 210.00 13.3% 13.8% 14.8% 14.3% 14.8% 14.3% 14.8% 100.0%
4,439.00 1,525.00 m 1.296% 3/2/2008 12/30/2008 304.00 9.9% 9.9% 10.2% 9.9% 10.2% 10.2% 9.9% 10.2% 9.9% 9.9% 100.0%
117,636.00 12.26% 100.000% 0.0% 0.0%
0.00% 0.11% 2.64% 2.87% 2.88% 3.41% 3.42% 3.32% 3.43% 3.83% 5.04% 6.20% 6.01% 8.05% 5.27% 5.67% 5.43% 5.37% 5.57% 5.37% 5.55% 5.37% 3.73% 0.96% 0.49% 73.33%
0.00% 0.11% 2.75% 5.62% 8.49% 11.90% 15.32% 18.65% 22.08% 25.91% 30.94% 37.15% 43.16% 51.22% 56.48% 62.16% 67.59% 72.96% 78.53% 83.90% 89.45% 94.82% 98.55% 99.51% 100.00% 173.33%
14 31 30 31 30 31 31 30 31 30 31 31 29 31 30 31 30 31 31 30 31 30 31 31 28
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Qty DMHS Unit Relative %
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
1,269.00 102.00 cu.m 0.086% 5/20/2007 10/30/2007 164.00 7.3% 18.3% 18.9% 18.9% 18.3% 18.3% 100.0% 100.0%
8,645.00 1,148.00 cu.m 0.971% 3/2/2008 12/31/2008 305.00 9.8% 9.8% 10.2% 9.8% 10.2% 10.2% 9.8% 10.2% 9.8% 10.2% 100.0% 100.0%
43,659.00 4,066.00 sq.m. 3.441% 2/1/2008 1/31/2009 366.00 7.9% 8.5% 8.2% 8.5% 8.2% 8.5% 8.5% 8.2% 8.5% 8.2% 8.5% 8.5% 100.0% 100.0%
11,189.00 4,475.00 cu.m 3.787% 3/17/2007 11/30/2008 625.00 2.4% 4.8% 5.0% 4.8% 5.0% 5.0% 4.8% 5.0% 4.8% 5.0% 5.0% 4.6% 5.0% 4.8% 5.0% 4.8% 5.0% 5.0% 4.8% 5.0% 4.8% 100.0% 100.0%
2,512.00 2,645.00 cu.m 2.238% 5/20/2007 11/30/2008 561.00 2.1% 5.3% 5.5% 5.5% 5.3% 5.5% 5.3% 5.5% 5.5% 5.2% 5.5% 5.3% 5.5% 5.3% 5.5% 5.5% 5.3% 5.5% 5.3% 100.0% 100.0%
173.00 1,305.00 cu.m 1.104% 7/1/2007 3/30/2008 274.00 11.3% 11.3% 10.9% 11.3% 10.9% 11.3% 11.3% 10.6% 10.9% 100.0% 100.0%
480.00 96.00 m 0.081% 8/15/2007 6/30/2008 321.00 5.3% 9.3% 9.7% 9.3% 9.7% 9.7% 9.0% 9.7% 9.3% 9.7% 9.3% 100.0% 100.0%
107.00 535.00 m 0.453% 5/1/2008 6/30/2008 61.00 50.8% 49.2% 100.0%
75.00 50.00 cu.m 0.042% 9/1/2007 12/30/2008 487.00 6.2% 6.4% 6.2% 6.4% 6.4% 6.0% 6.4% 6.2% 6.4% 6.2% 6.4% 6.4% 6.2% 6.4% 6.2% 6.2% 100.0% 100.0%
150.00 24.00 sq.m. 0.020% 3/1/2008 7/31/2008 153.00 20.3% 19.6% 20.3% 19.6% 20.3% 100.0% 100.0%
12,593.00 1,512.00 cu.m. 1.279% 8/1/2008 12/31/2008 153.00 20.3% 19.6% 20.3% 19.6% 20.3% 100.0% 100.0%
25,471.00 956.00 sq.m. 0.809% 9/1/2008 1/31/2009 153.00 19.6% 20.3% 19.6% 20.3% 20.3% 100.0% 100.0%
405.00 456.00 cu.m 0.386% 3/23/2007 2/28/2008 343.00 2.6% 8.7% 9.0% 8.7% 9.0% 9.0% 8.7% 9.0% 8.7% 9.0% 9.0% 8.2% 100.0% 100.0%
6,340.00 35,648.00 cu.m 30.165% 4/2/2007 3/30/2008 364.00 8.0% 8.5% 8.2% 8.5% 8.5% 8.2% 8.5% 8.2% 8.5% 8.5% 8.0% 8.2% 100.0% 100.0%
185.00 581.00 cu.m 0.492% 6/23/2007 1/30/2008 222.00 3.6% 14.0% 14.0% 13.5% 14.0% 13.5% 14.0% 13.5% 100.0% 100.0%
24,211.00 8,335.00 sq.m. 7.053% 3/1/2008 11/30/2008 275.00 11.3% 10.9% 11.3% 10.9% 11.3% 11.3% 10.9% 11.3% 10.9% 100.0% 100.0%
294.00 1,456.00 cu.m. 1.232% 1/1/2008 8/31/2008 244.00 12.7% 11.9% 12.7% 12.3% 12.7% 12.3% 12.7% 12.7% 100.0% 100.0%
40,203.00 5,077.00 sq.m. 4.296% 7/1/2007 12/30/2008 549.00 5.6% 5.6% 5.5% 5.6% 5.5% 5.6% 5.6% 5.3% 5.6% 5.5% 5.6% 5.5% 5.6% 5.6% 5.5% 5.6% 5.5% 5.5% 100.0% 100.0%
12,105.00 2,421.00 m 2.049% 3/1/2008 11/30/2008 275.00 11.3% 10.9% 11.3% 10.9% 11.3% 11.3% 10.9% 11.3% 10.9% 100.0% 100.0%
70.00 140.00 cu.m. 0.118% 3/1/2008 5/31/2008 92.00 33.7% 32.6% 33.7% 100.0% 100.0%
120.00 4,730.00 cu.m 4.002% 3/2/2008 11/30/2008 274.00 10.9% 10.9% 11.3% 10.9% 11.3% 11.3% 10.9% 11.3% 10.9% 100.0% 100.0%
46.00 9,709.00 cu.m. 8.216% 11/1/2007 2/28/2009 486.00 6.2% 6.4% 6.4% 6.0% 6.4% 6.2% 6.4% 6.2% 6.4% 6.4% 6.2% 6.4% 6.2% 6.4% 6.4% 5.8% 100.0% 100.0%
50,207.00 31,165.00 Kg 26.371% 12/15/2007 12/30/2008 382.00 4.2% 8.1% 7.6% 8.1% 7.9% 8.1% 7.9% 8.1% 8.1% 7.9% 8.1% 7.9% 8.1% 100.0%
10.00 12.00 Kg 0.010% 1/3/2008 7/30/2008 210.00 13.3% 13.8% 14.8% 14.3% 14.8% 14.3% 14.8% 100.0%
4,450.00 1,533.00 m 1.297% 3/2/2008 12/30/2008 304.00 9.9% 9.9% 10.2% 9.9% 10.2% 10.2% 9.9% 10.2% 9.9% 9.9% 100.0%
118,177.00 12.31% 100.000% 0.0% 0.0%
0.00% 0.10% 2.62% 2.85% 2.85% 3.37% 3.37% 3.27% 3.38% 3.76% 4.99% 6.18% 5.99% 8.02% 5.26% 5.66% 5.44% 5.38% 5.64% 5.46% 5.65% 5.46% 3.84% 0.98% 0.47% 73.33%
0.00% 0.10% 2.72% 5.57% 8.42% 11.79% 15.16% 18.43% 21.81% 25.57% 30.56% 36.74% 42.73% 50.75% 56.01% 61.67% 67.11% 72.49% 78.13% 83.60% 89.24% 94.70% 98.55% 99.53% 100.00% 173.33%
14 31 30 31 30 31 31 30 31 30 31 31 29 31 30 31 30 31 31 30 31 30 31 31 28
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Qty DMHS Unit Relative %
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
80.00 6.00 cu.m 0.003% 4/22/2007 6/6/2007 46.00 19.6% 67.4% 13.0% 100.0% 100.0%
7,480.00 1,075.00 cu.m 0.499% 1/15/2008 9/30/2008 260.00 6.5% 11.2% 11.9% 11.5% 11.9% 11.5% 11.9% 11.9% 11.5% 100.0% 100.0%
38,047.00 3,544.00 sq.m. 1.645% 1/31/2008 6/30/2008 152.00 0.7% 19.1% 20.4% 19.7% 20.4% 19.7% 100.0% 100.0%
9,613.00 3,846.00 cu.m 1.785% 5/1/2007 6/30/2008 427.00 7.3% 7.0% 7.3% 7.3% 7.0% 7.3% 7.0% 7.3% 7.3% 6.8% 7.3% 7.0% 7.3% 7.0% 100.0% 100.0%
2,301.00 2,879.00 cu.m 1.336% 6/7/2007 11/28/2007 175.00 13.7% 17.7% 17.7% 17.1% 17.7% 16.0% 100.0% 100.0%
169.00 1,335.00 cu.m 0.620% 8/1/2007 1/31/2008 184.00 16.8% 16.3% 16.8% 16.3% 16.8% 16.8% 100.0% 100.0%
88.00 440.00 m 0.204% 3/1/2008 6/30/2008 122.00 25.4% 24.6% 25.4% 24.6% 100.0%
311.00 207.00 cu.m 0.096% 11/15/2007 7/30/2008 259.00 6.2% 12.0% 12.0% 11.2% 12.0% 11.6% 12.0% 11.6% 11.6% 100.0% 100.0%
740.00 118.00 sq.m. 0.055% 10/14/2007 6/2/2008 233.00 7.7% 12.9% 13.3% 13.3% 12.4% 13.3% 12.9% 13.3% 0.9% 100.0% 100.0%
12,858.00 1,543.00 cu.m 0.716% 8/5/2008 11/17/2008 105.00 25.7% 28.6% 29.5% 16.2% 100.0% 100.0%
26,009.00 975.00 sq.m. 0.452% 10/26/2008 1/14/2009 81.00 7.4% 37.0% 38.3% 17.3% 100.0% 100.0%
293.00 379.00 cu.m 0.176% 5/15/2007 1/31/2008 262.00 6.5% 11.5% 11.8% 11.8% 11.5% 11.8% 11.5% 11.8% 11.8% 100.0% 100.0%
3,063.00 18,898.00 cu.m 8.770% 5/15/2007 2/28/2008 290.00 5.9% 10.3% 10.7% 10.7% 10.3% 10.7% 10.3% 10.7% 10.7% 9.7% 100.0% 100.0%
11.00 44.00 cu.m 0.020% 7/1/2007 8/31/2008 428.00 7.2% 7.2% 7.0% 7.2% 7.0% 7.2% 7.2% 6.8% 7.2% 7.0% 7.2% 7.0% 7.2% 7.2% 100.0% 100.0%
21,139.00 7,166.00 sq.m. 3.326% 3/18/2008 8/4/2008 140.00 10.0% 21.4% 22.1% 21.4% 22.1% 2.9% 100.0% 100.0%
142.00 703.00 cu.m 0.326% 6/1/2008 10/31/2008 153.00 19.6% 20.3% 20.3% 19.6% 20.3% 100.0% 100.0%
35,769.00 4,278.00 sq.m. 1.985% 7/15/2007 10/31/2008 475.00 3.6% 6.5% 6.3% 6.5% 6.3% 6.5% 6.5% 6.1% 6.5% 6.3% 6.5% 6.3% 6.5% 6.5% 6.3% 6.5% 100.0% 100.0%
10,570.00 2,114.00 m 0.981% 5/4/2008 8/16/2008 105.00 26.7% 28.6% 29.5% 15.2% 100.0% 100.0%
52.00 110.00 cu.m 0.051% 7/31/2008 9/27/2008 59.00 1.7% 52.5% 45.8% 100.0% 100.0%
17.00 2,795.00 cu.m 1.297% 11/15/2007 7/15/2008 244.00 6.6% 12.7% 12.7% 11.9% 12.7% 12.3% 12.7% 12.3% 6.1% 100.0% 100.0%
643,352.00 155,062.00 Kg 71.962% 10/1/2007 12/30/2008 457.00 6.8% 6.6% 6.8% 6.8% 6.3% 6.8% 6.6% 6.8% 6.6% 6.8% 6.8% 6.6% 6.8% 6.6% 6.6% 100.0%
19,614.00 7,960.00 m 3.694% 1/15/2008 7/30/2008 198.00 8.6% 14.6% 15.7% 15.2% 15.7% 15.2% 15.2% 100.0%
215,477.00 22.45% 100.000% 0.0%
0.0000% 0.0000% 0.0005% 0.6570% 1.2364% ### 1.5600% 1.5097% 6.4457% 6.3165% 6.3884% 6.7490% 6.7394% 6.6834% 6.8586% 7.3489% 7.1963% ### 5.5936% 5.1989% 5.3221% 5.0075% 4.8972% 0.0782% 0.0000% 24.1395%
0.0000% 0.000% 0.001% 0.658% 1.894% 3.291% 4.851% 6.361% 12.807% 19.123% 25.511% 32.260% 39.000% 45.683% 52.542% 59.891% 67.087% ### 79.496% 84.695% 90.017% 95.025% 99.922% ### ###
14 31 30 31 30 31 31 30 31 30 31 31 29 31 30 31 30 31 31 30 31 30 31 31 28
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Qty DMHS Unit Relative %
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
1,272.00 102.00 cu.m 0.038% 10/1/2007 11/30/2007 61.00 50.8% 49.2% 100.0% 100.0%
197,296.00 15,784.00 cu.m 5.910% 4/30/2007 5/30/2008 397.00 0.3% 7.8% 7.6% 7.8% 7.8% 7.6% 7.8% 7.6% 7.8% 7.8% 7.3% 7.8% 7.6% 7.6% 100.0% 100.0%
1,098.00 5,218.00 cu.m 1.954% 12/2/2007 4/7/2008 128.00 23.4% 24.2% 22.7% 24.2% 5.5% 100.0% 100.0%
37,667.00 12,555.00 cu.m 4.701% 2/1/2008 7/1/2008 152.00 19.1% 20.4% 19.7% 20.4% 19.7% 0.7% 100.0% 100.0%
37,667.00 12,555.00 cu.m 4.701% 1/1/2008 5/31/2008 152.00 20.4% 19.1% 20.4% 19.7% 20.4% 100.0% 100.0%
20,996.00 8,398.00 cu.m 3.144% 11/1/2007 9/30/2008 335.00 9.0% 9.3% 9.3% 8.7% 9.3% 9.0% 9.3% 9.0% 9.3% 9.3% 9.0% 100.0% 100.0%
18,871.00 7,548.00 cu.m 2.826% 11/1/2007 5/31/2008 213.00 14.1% 14.6% 14.6% 13.6% 14.6% 14.1% 14.6% 100.0% 100.0%
58,872.00 95,736.00 cu.m 35.844% 12/15/2007 9/30/2008 291.00 5.8% 10.7% 10.0% 10.7% 10.3% 10.7% 10.3% 10.7% 10.7% 10.3% 100.0% 100.0%
6,425.00 10,448.00 cu.m 3.912% 11/1/2007 5/31/2008 213.00 14.1% 14.6% 14.6% 13.6% 14.6% 14.1% 14.6% 100.0% 100.0%
785.00 5,360.00 cu.m 2.007% 10/1/2007 5/31/2008 244.00 12.7% 12.3% 12.7% 12.7% 11.9% 12.7% 12.3% 12.7% 100.0% 100.0%
329.00 2,246.00 cu.m 0.841% 12/1/2007 4/30/2008 152.00 20.4% 20.4% 19.1% 20.4% 19.7% 100.0% 100.0%
672.00 134.00 m 0.050% 1/1/2008 6/30/2008 182.00 17.0% 15.9% 17.0% 16.5% 17.0% 16.5% 100.0% 100.0%
1,629.00 326.00 m 0.122% 1/1/2008 5/30/2008 151.00 20.5% 19.2% 20.5% 19.9% 19.9% 100.0% 100.0%
999.00 666.00 cu.m 0.249% 11/15/2007 9/30/2008 321.00 5.0% 9.7% 9.7% 9.0% 9.7% 9.3% 9.7% 9.3% 9.7% 9.7% 9.3% 100.0% 100.0%
8,281.00 5,521.00 cu.m 2.067% 11/1/2007 5/31/2008 213.00 14.1% 14.6% 14.6% 13.6% 14.6% 14.1% 14.6% 100.0% 100.0%
1,253.00 200.00 sq.m. 0.075% 2/14/2008 4/30/2008 77.00 20.8% 40.3% 39.0% 100.0% 100.0%
1,494.00 239.00 sq.m. 0.089% 2/1/2008 3/25/2008 54.00 53.7% 46.3% 100.0% 100.0%
15,610.00 1,957.00 cu.m 0.733% 3/1/2008 6/24/2008 116.00 26.7% 25.9% 26.7% 20.7% 100.0% 100.0%
29,311.00 1,184.00 sq.m. 0.443% 4/1/2008 7/31/2008 122.00 24.6% 25.4% 24.6% 25.4% 100.0% 100.0%
89,923.00 9,588.00 sq.m. 3.590% 7/1/2008 9/30/2008 92.00 33.7% 33.7% 32.6% 100.0% 100.0%
89,923.00 9,588.00 sq.m. 3.590% 4/18/2008 6/20/2008 64.00 20.3% 48.4% 31.3% 100.0% 100.0%
2,095.00 262.00 m 0.098% 7/1/2008 8/31/2008 62.00 50.0% 50.0% 100.0% 100.0%
4,000.00 4,002.00 m 1.498% 6/19/2008 10/30/2008 134.00 9.0% 23.1% 23.1% 22.4% 22.4% 100.0% 100.0%
118.00 234.00 cu.m 0.088% 12/1/2007 3/31/2008 122.00 25.4% 25.4% 23.8% 25.4% 100.0% 100.0%
960.00 1,907.00 cu.m 0.714% 12/1/2007 2/28/2008 90.00 34.4% 34.4% 31.1% 100.0% 100.0%
448.00 4,043.00 cu.m 1.514% 10/1/2007 1/30/2008 122.00 25.4% 24.6% 25.4% 24.6% 100.0% 100.0%
415.00 3,744.00 cu.m 1.402% 10/30/2007 4/1/2008 155.00 1.3% 19.4% 20.0% 20.0% 18.7% 20.0% 0.6% 100.0% 100.0%
5,958.00 1,986.00 sq.m. 0.744% 3/1/2008 6/30/2008 122.00 25.4% 24.6% 25.4% 24.6% 100.0% 100.0%
57.00 284.00 cu.m 0.106% 1/1/2008 4/30/2008 121.00 25.6% 24.0% 25.6% 24.8% 100.0% 100.0%
6,897.00 11,821.00 sq.m. 4.426% 1/1/2008 6/5/2008 157.00 19.7% 18.5% 19.7% 19.1% 19.7% 3.2% 100.0% 100.0%
1,936.00 3,318.00 sq.m. 1.242% 1/1/2008 3/5/2008 65.00 47.7% 44.6% 7.7% 100.0% 100.0%
5,992.00 6,337.00 sq.m. 2.373% 12/25/2007 3/3/2008 70.00 10.0% 44.3% 41.4% 4.3% 100.0% 100.0%
133.00 391.00 cu.m 0.146% 1/8/2008 3/31/2008 84.00 28.6% 34.5% 36.9% 100.0% 100.0%
28.00 82.00 cu.m 0.031% 1/1/2008 3/13/2008 73.00 42.5% 39.7% 17.8% 100.0% 100.0%
3.00 388.00 cu.m 0.145% 2/1/2008 4/30/2008 90.00 32.2% 34.4% 33.3% 100.0% 100.0%
90,528.00 21,819.00 Kg 8.169% 9/15/2007 4/30/2008 229.00 7.0% 13.5% 13.1% 13.5% 13.5% 12.7% 13.5% 13.1% 100.0%
2,760.00 1,120.00 m 0.419% 1/2/2008 4/22/2008 112.00 26.8% 25.9% 27.7% 19.6% 100.0%
267,091.00 27.83% 100.000%
0.0000% 0.0000% 0.0149% 0.4615% 0.4466% ### 0.4615% 1.0173% 2.2444% 3.9599% 7.3126% ### ### ### ### ### 6.7765% ### 5.7388% 5.5062% 0.3355% 0.0000% 0.0000% 0.0000% 0.0000% 91.4115%
Total DMHS = 959,750.00 100% 0.0000% 0.000% 0.015% 0.476% 0.923% 1.384% 1.846% 2.863% 5.108% 9.068% 16.380% 28.887% 41.252% 53.168% 64.584% 75.761% 82.537% ### 94.158% 99.665% ### ### ### ### ###
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
Monthly Percentage accomplishment = #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Monthly Cumulative % Accomplishment = #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Project : Khurais Crude Facilities 0.00001751
Location : Khurais Saudi Arabia Ramon: MONTHLY PROGRESS PLAN
GOSP 1 11.55 inserted column Ramon:
0.22 to derive DMHS inserted column Ramon: 14 31 30 31 30 31 31 30 31 30 31 31 29 31 30 31 30 31 31
this becomes Date start Date finish Duration to derive total Validation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Activities Qty DMHS Unit Relative %
Productivity sum of DMHS 28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08
Rate
General excavation 1,269.00 102.00 0.08 cu.m 0.082% 4/20/2007 9/30/2007 164.00 102.00 - 7 19 19 19 19 19
85 240 232 240 240 232
397063 6.7% 18.9% 18.3% 18.9% 18.9% 18.3%
General Backfilling of Areas/Roads 8,340.00 1,218.00 0.15 cu.m 0.975% 2/1/2008 11/30/2008 304.00 1,218.00 - 116 124 120 124 120 124 124
Subbase preparation under paving 43,659.00 4,066.00 0.09 sq.m. 3.255% 1/1/2008 12/15/2008 350.00 4,066.00 - 360 337 360 349 360 349 360 360
Limited excavation up to 1.5 m 11,424.00 4,570.00 0.40 cu.m 3.658% 2/15/2007 10/31/2008 625.00 4,570.00 - 102 227 219 227 219 227 227 219 227 219 227 227 212 227 219 227 219 227 227
Limited Excavation (Over 1.5m depth) 2,620.00 2,680.00 1.02 cu.m 2.145% 4/20/2007 10/30/2008 560.00 2,680.00 - 53 148 144 148 148 144 148 144 148 148 139 148 144 148 144 148 148
Reinf concrete pit for sewer 293.00 1,757.00 6.00 cu.m 1.406% 6/1/2007 2/28/2008 273.00 1,757.00 - 193 200 200 193 200 193 200 200 180
Installation of PVC drainage system 2,400.00 480.00 0.20 m 0.384% 7/15/2007 5/31/2008 322.00 480.00 - 25 46 45 46 45 46 46 43 46 45 46
Installation of Cast Iron Drainage 107.00 535.00 5.00 m 0.428% 4/1/2008 5/31/2008 61.00 535.00 - 263 272
Laying of Sand for Pipe Prot. 163.00 108.00 0.66 cu.m 0.086% 8/1/2007 11/30/2008 488.00 108.00 - 7 7 7 7 7 7 6 7 7 7 7 7 7
Lay of slabs/bricks Cables 238.00 38.00 0.16 sq.m. 0.030% 2/1/2008 6/30/2008 151.00 38.00 - 7 8 8 8 8
Road (Base course+ subbase) 10,202.00 1,226.00 0.12 cu.m. 0.981% 7/1/2008 11/30/2008 153.00 1,226.00 - 248 248
Asphalting of Roads 20,634.00 774.00 0.04 sq.m. 0.620% 8/1/2008 12/31/2008 153.00 774.00 - 157
Lean Concrete 508.00 750.00 1.48 cu.m 0.600% 2/21/2007 1/31/2008 345.00 750.00 - 17 67 65 67 65 67 67 65 67 65 67 67
Reinforced Concrete up to +1.0 M 38,046.00 6,259.00 38,046.00 6.08 cu.m 30.455% 3/3/2007 2/28/2008 363.00 38,046.00 - 3,039 3,144 3,249 3,144 3,249 3,249 3,144 3,249 3,144 3,249 3,249 2,935
6.00 2.00 3.00
Reinforced Concrete +1.0M/+ 7.0 M 626.00 185.00 626.00 3.38 cu.m 0.501% 5/24/2007 12/31/2007 222.00 626.00 - 23 85 87 87 85 87 85 87
Reinforced Concrete for Paving 24,211.00 8,335.00 0.34 sq.m. 6.672% 2/1/2008 10/31/2008 274.00 8,335.00 - 882 943 913 943 913 943 943
Concrete for Piping support 294.00 1,456.00 4.95 cu.m. 1.166% 12/1/2007 7/31/2008 244.00 1,456.00 - 185 185 173 185 179 185 179 185
Foundation Protection 40,516.00 9,088.00 0.22 sq.m. 7.275% 6/1/2007 11/30/2008 549.00 9,088.00 - 497 513 513 497 513 497 513 513 480 513 497 513 497 513 513
Execution of expansion joints 12,105.00 2,421.00 0.20 m 1.938% 2/1/2008 10/31/2008 274.00 2,421.00 - 256 274 265 274 265 274 274
PR / Lay light items (Real V) 111.00 261.00 2.35 cu.m. 0.209% 2/1/2008 4/30/2008 90.00 261.00 - 84 90 87
Fire Proofing 120.00 4,730.00 39.42 cu.m 3.786% 2/1/2008 10/31/2008 274.00 4,730.00 - 501 535 518 535 518 535 535
Grouting Operation 46.00 8,879.00 193.02 cu.m. 7.108% 10/1/2007 1/20/2009 478.00 8,879.00 - 576 557 576 576 539 576 557 576 557 576 576
Und. Fibreg. Pip. On S.PN14 (6In) 44,023.00 31,156.00 0.71 Kg 24.940% 11/15/2007 11/30/2008 382.00 31,156.00 - 1,305 2,528 2,528 2,365 2,528 2,447 2,528 2,447 2,528 2,528
P/E FiberGl. Pip. On S.PN6 (6In) 31.00 19.00 0.61 Kg 0.015% 12/4/2007 6/30/2008 210.00 19.00 - 3 3 3 3 3 3 3
Hydrotest Resin Pip on Site 4,790.00 1,603.00 0.33 m 1.283% 2/1/2008 11/30/2008 304.00 1,603.00 - 153 163 158 163 158 163 163
124,924.00 13.02% 100.000%
120 3,334 3,574 3,973 4,598 4,776 4,804 4,649 5,121 6,260 7,836 8,109 9,411 6,731 6,777 6,913 6,382 6,833 6,804
120 3,453 7,027 11,000 15,598 20,374 25,178 29,827 34,948 41,208 49,045 57,154 66,565 73,296 80,073 86,986 93,368 100,200 107,005
GOSP 2
14 31 30 31 30 31 31 30 31 30 31 31 29 31 30 31 30 31 31
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Activities Qty DMHS Unit Relative %
28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08
General excavation 1,269.00 102.00 0.08 cu.m 0.088% 4/20/2007 9/30/2007 164.00 102.00 - 7 19 19 19 19 19
General Backfilling of Areas/Roads 8,429.00 1,123.00 0.13 cu.m 0.964% 2/1/2008 11/30/2008 304.00 1,123.00 - 107 115 111 115 111 115 115
Subbase preparation under paving 43,659.00 4,066.00 0.09 sq.m. 3.492% 1/1/2008 12/15/2008 350.00 4,066.00 - 360 337 360 349 360 349 360 360
Limited excavation up to 1.5 m 11,131.00 4,452.00 0.40 cu.m 3.823% 2/15/2007 10/31/2008 625.00 4,452.00 - 100 221 214 221 214 221 221 214 221 214 221 221 207 221 214 221 214 221 221
Limited Excavation (Over 1.5m depth) 2,486.00 2,619.00 1.05 cu.m 2.249% 4/20/2007 10/30/2008 560.00 2,619.00 - 51 145 140 145 145 140 145 140 145 145 136 145 140 145 140 145 145
Reinf concrete pit for sewer 185.00 1,353.00 7.31 cu.m 1.162% 6/1/2007 2/28/2008 273.00 1,353.00 - 149 154 154 149 154 149 154 154 139
Installation of PVC drainage system 80.00 16.00 0.20 m 0.014% 7/15/2007 5/31/2008 322.00 16.00 - 1 2 1 2 1 2 2 1 2 1 2
Installation of Cast Iron Drainage 107.00 535.00 5.00 m 0.459% 4/1/2008 5/31/2008 61.00 535.00 - 263 272
Laying of Sand for Pipe Prot. 75.00 50.00 0.67 cu.m 0.043% 8/1/2007 11/30/2008 488.00 50.00 - 3 3 3 3 3 3 3 3 3 3 3 3 3
Lay of slabs/bricks Cables 150.00 24.00 0.16 sq.m. 0.021% 2/1/2008 6/30/2008 151.00 24.00 - 5 5 5 5 5
Road (Base course+ subbase) 10,716.00 1,288.00 0.12 cu.m. 1.106% 7/1/2008 11/30/2008 153.00 1,288.00 - 261 261
Asphalting of Roads 21,676.00 813.00 0.04 sq.m. 0.698% 8/1/2008 12/31/2008 153.00 813.00 - 165
Lean Concrete 383.00 416.00 1.09 cu.m 0.357% 2/21/2007 1/31/2008 345.00 416.00 - 10 37 36 37 36 37 37 36 37 36 37 37
Reinforced Concrete up to +1.0 M 6,284.00 35,345.00 5.62 cu.m 30.353% 3/3/2007 2/28/2008 363.00 35,345.00 - 2,824 2,921 3,018 2,921 3,018 3,018 2,921 3,018 2,921 3,018 3,018 2,726
Reinforced Concrete +1.0M/+ 7.0 M 185.00 581.00 3.14 cu.m 0.499% 5/24/2007 12/31/2007 222.00 581.00 - 21 79 81 81 79 81 79 81
Reinforced Concrete for Paving 24,211.00 8,335.00 0.34 sq.m. 7.158% 2/1/2008 10/31/2008 274.00 8,335.00 - 882 943 913 943 913 943 943
Concrete for Piping support 294.00 1,456.00 4.95 cu.m. 1.250% 12/1/2007 7/31/2008 244.00 1,456.00 - 185 185 173 185 179 185 179 185
Foundation Protection 40,152.00 5,074.00 0.13 sq.m. 4.357% 6/1/2007 11/30/2008 549.00 5,074.00 - 277 287 287 277 287 277 287 287 268 287 277 287 277 287 287
Execution of expansion joints 12,105.00 2,421.00 0.20 m 2.079% 2/1/2008 10/31/2008 274.00 2,421.00 - 256 274 265 274 265 274 274
PR / Lay light items (Real V) 70.00 142.00 2.03 cu.m. 0.122% 2/1/2008 4/30/2008 90.00 142.00 - 46 49 47
Fire Proofing 120.00 4,730.00 39.42 cu.m 4.062% 2/1/2008 10/31/2008 274.00 4,730.00 - 501 535 518 535 518 535 535
Grouting Operation 46.00 9,709.00 211.07 cu.m. 8.338% 10/1/2007 1/20/2009 478.00 9,709.00 - 630 609 630 630 589 630 609 630 609 630 630
Und. Fibreg. Pip. On S.PN14 (6In) 45,482.00 30,261.00 0.67 Kg 25.987% 11/15/2007 11/30/2008 382.00 30,261.00 - 1,267 2,456 2,456 2,297 2,456 2,377 2,456 2,377 2,456 2,456
P/E FiberGl. Pip. On S.PN6 (6In) 10.00 12.00 1.20 Kg 0.010% 12/4/2007 6/30/2008 210.00 12.00 - 2 2 2 2 2 2 2
Hydrotest Resin Pip on Site 4,431.00 1,522.00 0.34 m 1.307% 2/1/2008 11/30/2008 304.00 1,522.00 - 145 155 150 155 150 155 155
116,445.00 12.13% 100.000%
109 3,082 3,229 3,462 3,834 3,963 3,967 3,839 4,577 5,697 7,220 7,499 8,819 6,365 6,423 6,588 6,111 6,569 6,548
109 3,191 6,421 9,882 13,717 17,680 21,647 25,486 30,063 35,760 42,980 50,478 59,298 65,663 72,085 78,673 84,784 91,353 97,901
GOSP 3
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Activities Qty DMHS Unit Relative %
28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08
General excavation 1,269.00 102.00 0.08 cu.m 0.087% 5/20/2007 10/30/2007 164.00 102.00 - 7 19 19 19 19 19
General Backfilling of Areas/Roads 8,337.00 1,111.00 0.13 cu.m 0.944% 3/2/2008 12/31/2008 305.00 1,111.00 - 109 109 113 109 113 113
Subbase preparation under paving 43,659.00 4,066.00 0.09 sq.m. 3.456% 2/1/2008 1/31/2009 366.00 4,066.00 - 322 344 333 344 333 344 344
Limited excavation up to 1.5 m 11,313.00 4,525.00 0.40 cu.m 3.847% 3/17/2007 11/30/2008 625.00 4,525.00 - 109 217 224 217 224 224 217 224 217 224 224 210 224 217 224 217 224 224
Limited Excavation (Over 1.5m depth) 2,535.00 2,626.00 1.04 cu.m 2.232% 5/20/2007 11/30/2008 561.00 2,626.00 - 56 140 145 145 140 145 140 145 145 136 145 140 145 140 145 145
Reinf concrete pit for sewer 228.00 1,476.00 6.47 cu.m 1.255% 7/1/2007 3/30/2008 274.00 1,476.00 - 167 167 162 167 162 167 167 156 162
Installation of PVC drainage system 960.00 192.00 0.20 m 0.163% 8/15/2007 6/30/2008 321.00 192.00 - 10 18 19 18 19 19 17 19 18 19 18
Installation of Cast Iron Drainage 107.00 535.00 5.00 m 0.455% 5/1/2008 6/30/2008 61.00 535.00 - 272 263
Laying of Sand for Pipe Prot. 163.00 108.00 0.66 cu.m 0.092% 9/1/2007 12/30/2008 487.00 108.00 - 7 7 7 7 7 6 7 7 7 7 7 7
Lay of slabs/bricks Cables 205.00 33.00 0.16 sq.m. 0.028% 3/1/2008 7/31/2008 153.00 33.00 - 7 6 7 6 7
Road (Base course+ subbase) 10,176.00 1,222.00 0.12 cu.m. 1.039% 8/1/2008 12/31/2008 153.00 1,222.00 - 248
Asphalting of Roads 20,584.00 772.00 0.04 sq.m. 0.656% 9/1/2008 1/31/2009 153.00 772.00 -
Lean Concrete 441.00 576.00 1.31 cu.m 0.490% 3/23/2007 2/28/2008 343.00 576.00 - 15 50 52 50 52 52 50 52 50 52 52 47
Reinforced Concrete up to +1.0 M 6,304.00 35,635.00 5.65 cu.m 30.293% 4/2/2007 3/30/2008 364.00 35,635.00 - 2,839 3,035 2,937 3,035 3,035 2,937 3,035 2,937 3,035 3,035 2,839 2,937
Reinforced Concrete +1.0M/+ 7.0 M 185.00 581.00 3.14 cu.m 0.494% 6/23/2007 1/30/2008 222.00 581.00 - 21 81 81 79 81 79 81 79
Reinforced Concrete for Paving 24,211.00 8,335.00 0.34 sq.m. 7.085% 3/1/2008 11/30/2008 275.00 8,335.00 - 940 909 940 909 940 940
Concrete for Piping support 294.00 1,456.00 4.95 cu.m. 1.238% 1/1/2008 8/31/2008 244.00 1,456.00 - 185 173 185 179 185 179 185 185
Foundation Protection 40,468.00 5,135.00 0.13 sq.m. 4.365% 7/1/2007 12/30/2008 549.00 5,135.00 - 290 290 281 290 281 290 290 271 290 281 290 281 290 290
Execution of expansion joints 12,105.00 2,421.00 0.20 m 2.058% 3/1/2008 11/30/2008 275.00 2,421.00 - 273 264 273 264 273 273
PR / Lay light items (Real V) 91.00 200.00 2.20 cu.m. 0.170% 3/1/2008 5/31/2008 92.00 200.00 - 67 65 67
Fire Proofing 120.00 4,730.00 39.42 cu.m 4.021% 3/2/2008 11/30/2008 274.00 4,730.00 - 518 518 535 518 535 535
Grouting Operation 47.00 9,920.00 211.06 cu.m. 8.433% 11/1/2007 2/28/2009 486.00 9,920.00 - 612 633 633 592 633 612 633 612 633 633
Und. Fibreg. Pip. On S.PN14 (6In) 45,564.00 30,336.00 0.67 Kg 25.788% 12/15/2007 12/30/2008 382.00 30,336.00 - 1,350 2,462 2,303 2,462 2,382 2,462 2,382 2,462 2,462
P/E FiberGl. Pip. On S.PN6 (6In) 15.00 18.00 1.20 Kg 0.015% 1/3/2008 7/30/2008 210.00 18.00 - 2 2 3 3 3 3 3
Hydrotest Resin Pip on Site 4,439.00 1,525.00 0.34 m 1.296% 3/2/2008 12/30/2008 304.00 1,525.00 - 150 150 156 150 156 156
117,636.00 12.26% 100.000%
- 124 3,107 3,375 3,385 4,014 4,024 3,909 4,039 4,503 6,003 7,299 7,076 9,474 6,195 6,674 6,393 6,316 6,554
- 124 3,230 6,605 9,990 14,004 18,028 21,937 25,975 30,478 36,481 43,780 50,856 60,330 66,525 73,199 79,592 85,907 92,461
GOSP 4
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Activities Qty DMHS Unit Relative %
28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08
General excavation 1,269.00 102.00 0.08 cu.m 0.086% 5/20/2007 10/30/2007 164.00 102.00 - 7 19 19 19 19 19
General Backfilling of Areas/Roads 8,645.00 1,148.00 0.13 cu.m 0.971% 3/2/2008 12/31/2008 305.00 1,148.00 - 113 113 117 113 117 117
Subbase preparation under paving 43,659.00 4,066.00 0.09 sq.m. 3.441% 2/1/2008 1/31/2009 366.00 4,066.00 - 322 344 333 344 333 344 344
Limited excavation up to 1.5 m 11,189.00 4,475.00 0.40 cu.m 3.787% 3/17/2007 11/30/2008 625.00 4,475.00 - 107 215 222 215 222 222 215 222 215 222 222 208 222 215 222 215 222 222
Limited Excavation (Over 1.5m depth) 2,512.00 2,645.00 1.05 cu.m 2.238% 5/20/2007 11/30/2008 561.00 2,645.00 - 57 141 146 146 141 146 141 146 146 137 146 141 146 141 146 146
Reinf concrete pit for sewer 173.00 1,305.00 7.54 cu.m 1.104% 7/1/2007 3/30/2008 274.00 1,305.00 - 148 148 143 148 143 148 148 138 143
Installation of PVC drainage system 480.00 96.00 0.20 m 0.081% 8/15/2007 6/30/2008 321.00 96.00 - 5 9 9 9 9 9 9 9 9 9 9
Installation of Cast Iron Drainage 107.00 535.00 5.00 m 0.453% 5/1/2008 6/30/2008 61.00 535.00 - 272 263
Laying of Sand for Pipe Prot. 75.00 50.00 0.67 cu.m 0.042% 9/1/2007 12/30/2008 487.00 50.00 - 3 3 3 3 3 3 3 3 3 3 3 3
Lay of slabs/bricks Cables 150.00 24.00 0.16 sq.m. 0.020% 3/1/2008 7/31/2008 153.00 24.00 - 5 5 5 5 5
Road (Base course+ subbase) 12,593.00 1,512.00 0.12 cu.m. 1.279% 8/1/2008 12/31/2008 153.00 1,512.00 - 306
Asphalting of Roads 25,471.00 956.00 0.04 sq.m. 0.809% 9/1/2008 1/31/2009 153.00 956.00 -
Lean Concrete 405.00 456.00 1.13 cu.m 0.386% 3/23/2007 2/28/2008 343.00 456.00 - 12 40 41 40 41 41 40 41 40 41 41 37
Reinforced Concrete up to +1.0 M 6,340.00 35,648.00 5.62 cu.m 30.165% 4/2/2007 3/30/2008 364.00 35,648.00 - 2,840 3,036 2,938 3,036 3,036 2,938 3,036 2,938 3,036 3,036 2,840 2,938
Reinforced Concrete +1.0M/+ 7.0 M 185.00 581.00 3.14 cu.m 0.492% 6/23/2007 1/30/2008 222.00 581.00 - 21 81 81 79 81 79 81 79
Reinforced Concrete for Paving 24,211.00 8,335.00 0.34 sq.m. 7.053% 3/1/2008 11/30/2008 275.00 8,335.00 - 940 909 940 909 940 940
Concrete for Piping support 294.00 1,456.00 4.95 cu.m. 1.232% 1/1/2008 8/31/2008 244.00 1,456.00 - 185 173 185 179 185 179 185 185
Foundation Protection 40,203.00 5,077.00 0.13 sq.m. 4.296% 7/1/2007 12/30/2008 549.00 5,077.00 - 287 287 277 287 277 287 287 268 287 277 287 277 287 287
Execution of expansion joints 12,105.00 2,421.00 0.20 m 2.049% 3/1/2008 11/30/2008 275.00 2,421.00 - 273 264 273 264 273 273
PR / Lay light items (Real V) 70.00 140.00 2.00 cu.m. 0.118% 3/1/2008 5/31/2008 92.00 140.00 - 47 46 47
Fire Proofing 120.00 4,730.00 39.42 cu.m 4.002% 3/2/2008 11/30/2008 274.00 4,730.00 - 518 518 535 518 535 535
Grouting Operation 46.00 9,709.00 211.07 cu.m. 8.216% 11/1/2007 2/28/2009 486.00 9,709.00 - 599 619 619 579 619 599 619 599 619 619
Und. Fibreg. Pip. On S.PN14 (6In) 50,207.00 31,165.00 0.62 Kg 26.371% 12/15/2007 12/30/2008 382.00 31,165.00 - 1,387 2,529 2,366 2,529 2,448 2,529 2,448 2,529 2,529
P/E FiberGl. Pip. On S.PN6 (6In) 10.00 12.00 1.20 Kg 0.010% 1/3/2008 7/30/2008 210.00 12.00 - 2 2 2 2 2 2 2
Hydrotest Resin Pip on Site 4,450.00 1,533.00 0.34 m 1.297% 3/2/2008 12/30/2008 304.00 1,533.00 - 151 151 156 151 156 156
118,177.00 12.31% 100.000%
- 119 3,095 3,363 3,374 3,980 3,985 3,864 3,992 4,444 5,979 7,306 7,082 9,474 6,212 6,691 6,430 6,363 6,663
- 119 3,214 6,577 9,951 13,931 17,916 21,780 25,772 30,216 36,195 43,501 50,583 60,057 66,270 72,961 79,391 85,754 92,417
INLET / OUTLET
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Activities Qty DMHS Unit Relative %
28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08
General excavation 80.00 6.00 0.08 cu.m 0.003% 4/22/2007 6/6/2007 46.00 6.00 - 1 4 1
General Backfilling of Areas/Roads 7,480.00 1,075.00 0.14 cu.m 0.499% 1/15/2008 9/30/2008 260.00 1,075.00 - 70 120 128 124 128 124 128 128
Subbase preparation under paving 38,047.00 3,544.00 0.09 sq.m. 1.645% 1/31/2008 6/30/2008 152.00 3,544.00 - 23 676 723 699 723 699
Limited excavation up to 1.5 m 9,613.00 3,846.00 0.40 cu.m 1.785% 5/1/2007 6/30/2008 427.00 3,846.00 - 279 270 279 279 270 279 270 279 279 261 279 270 279 270
Limited Excavation (Over 1.5m depth) 2,301.00 2,879.00 1.25 cu.m 1.336% 6/7/2007 11/28/2007 175.00 2,879.00 - 395 510 510 494 510 461
Reinf concrete pit for sewer 169.00 1,335.00 7.90 cu.m 0.620% 8/1/2007 1/31/2008 184.00 1,335.00 - 225 218 225 218 225 225
Installation of Cast Iron Drainage 88.00 440.00 5.00 m 0.204% 3/1/2008 6/30/2008 122.00 440.00 - 112 108 112 108
Laying of Sand for Pipe Prot. 311.00 207.00 0.67 cu.m 0.096% 11/15/2007 7/30/2008 259.00 207.00 - 13 25 25 23 25 24 25 24 24
Lay of slabs/bricks Cables 740.00 118.00 0.16 sq.m. 0.055% 10/14/2007 6/2/2008 233.00 118.00 - 9 15 16 16 15 16 15 16 1
Road (Base course+ subbase) 12,858.00 1,543.00 0.12 cu.m 0.716% 8/5/2008 11/17/2008 105.00 1,543.00 - 397
Asphalting of Roads 26,009.00 975.00 0.04 sq.m. 0.452% 10/26/2008 1/14/2009 81.00 975.00 -
Lean Concrete 293.00 379.00 1.29 cu.m 0.176% 5/15/2007 1/31/2008 262.00 379.00 - 25 43 45 45 43 45 43 45 45
Reinforced Concrete UP TO +1.0 M 3,063.00 18,898.00 6.17 cu.m 8.770% 5/15/2007 2/28/2008 290.00 18,898.00 - 1,108 1,955 2,020 2,020 1,955 2,020 1,955 2,020 2,020 1,825
Reinforced Concrete +1.0M/+ 7.0 M 11.00 44.00 4.00 cu.m 0.020% 7/1/2007 8/31/2008 428.00 44.00 - 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Reinforced Concrete for Paving 21,139.00 7,166.00 0.34 sq.m. 3.326% 3/18/2008 8/4/2008 140.00 7,166.00 - 717 1,536 1,587 1,536 1,587 205
Concrete for Piping support 142.00 703.00 4.95 cu.m 0.326% 6/1/2008 10/31/2008 153.00 703.00 - 138 142 142
Foundation Protection 35,769.00 4,278.00 0.12 sq.m. 1.985% 7/15/2007 10/31/2008 475.00 4,278.00 - 153 279 270 279 270 279 279 261 279 270 279 270 279 279
Execution of expansion joints 10,570.00 2,114.00 0.20 m 0.981% 5/4/2008 8/16/2008 105.00 2,114.00 - 564 604 624 322
PR / Lay light items (Real V) 52.00 110.00 2.12 cu.m 0.051% 7/31/2008 9/27/2008 59.00 110.00 - 2 58
Grouting Operation 17.00 2,795.00 164.41 cu.m 1.297% 11/15/2007 7/15/2008 244.00 2,795.00 - 183 355 355 332 355 344 355 344 172
Und. Fibreg. Pip. On S.PN14 (6In) 643,352.00 155,062.00 0.24 Kg 71.962% 10/1/2007 12/30/2008 457.00 155,062.00 - 10,518 10,179 10,518 10,518 9,840 10,518 10,179 10,518 10,179 10,518 10,518
Hydrotest Resin Pip on Site 19,614.00 7,960.00 0.41 m 3.694% 1/15/2008 7/30/2008 198.00 7,960.00 - 683 1,166 1,246 1,206 1,246 1,206 1,206
215,477.00 22.45% 100.000%
- - 1 1,416 2,664 3,010 3,361 3,253 13,889 13,611 13,766 14,543 14,522 14,401 14,779 15,835 15,506 14,686 12,053
- - 1 1,417 4,081 7,092 10,453 13,706 27,595 41,206 54,971 69,514 84,035 98,437 113,215 129,051 144,557 159,243 171,296
COMMON
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Activities Qty DMHS Unit Relative %
28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08
General excavation (Common) 1,272.00 102.00 0.08 cu.m 0.038% 10/1/2007 11/30/2007 61.00 102.00 - 52 50
General excavation (Pond) 197,296.00 15,784.00 0.08 cu.m 5.910% 4/30/2007 5/30/2008 397.00 15,784.00 - 40 1,233 1,193 1,233 1,233 1,193 1,233 1,193 1,233 1,233 1,153 1,233 1,193 1,193
General Backfilling of Areas/Roads (Ponds) 1,098.00 5,218.00 4.75 cu.m 1.954% 12/2/2007 4/7/2008 128.00 5,218.00 - 1,223 1,264 1,182 1,264 285
Embank bund walls by machine (Pond 2) 37,667.00 12,555.00 0.33 cu.m 4.701% 2/1/2008 7/1/2008 152.00 12,555.00 - 2,395 2,561 2,478 2,561 2,478 83
Embank bund walls by machine (Ponds) 37,667.00 12,555.00 0.33 cu.m 4.701% 1/1/2008 5/31/2008 152.00 12,555.00 - 2,561 2,395 2,561 2,478 2,561
Limited section excavation up to 1.5 m (Common) 20,996.00 8,398.00 0.40 cu.m 3.144% 11/1/2007 9/30/2008 335.00 8,398.00 - 752 777 777 727 777 752 777 752 777 777
Limited section excavation up to 1.5 m (Ponds) 18,871.00 7,548.00 0.40 cu.m 2.826% 11/1/2007 5/31/2008 213.00 7,548.00 - 1,063 1,099 1,099 1,028 1,099 1,063 1,099
Limited section excavation over 1.5 m (Common) 58,872.00 95,736.00 1.63 cu.m 35.844% 12/15/2007 9/30/2008 291.00 95,736.00 - 5,593 10,199 9,541 10,199 9,870 10,199 9,870 10,199 10,199
Limited section excavation over 1.5 m (Ponds) 6,425.00 10,448.00 1.63 cu.m 3.912% 11/1/2007 5/31/2008 213.00 10,448.00 - 1,472 1,521 1,521 1,422 1,521 1,472 1,521
Reinf concrete pit for sewer (Common) 785.00 5,360.00 6.83 cu.m 2.007% 10/1/2007 5/31/2008 244.00 5,360.00 - 681 659 681 681 637 681 659 681
Reinf concrete pit for sewer (Ponds) 329.00 2,246.00 6.83 cu.m 0.841% 12/1/2007 4/30/2008 152.00 2,246.00 - 458 458 429 458 443
Installation of PVC drainage system (Common) 672.00 134.00 0.20 m 0.050% 1/1/2008 6/30/2008 182.00 134.00 - 23 21 23 22 23 22
Installation of PVC drainage system (Ponds) 1,629.00 326.00 0.20 m 0.122% 1/1/2008 5/30/2008 151.00 326.00 - 67 63 67 65 65
Laying of Sand for Pipe Prot. (Common) 999.00 666.00 0.67 cu.m 0.249% 11/15/2007 9/30/2008 321.00 666.00 - 33 64 64 60 64 62 64 62 64 64
Laying of Sand for Pipe Prot. (Ponds) 8,281.00 5,521.00 0.67 cu.m 2.067% 11/1/2007 5/31/2008 213.00 5,521.00 - 778 804 804 752 804 778 804
Lay of slabs/bricks Cables (Common) 1,253.00 200.00 0.16 sq.m. 0.075% 2/14/2008 4/30/2008 77.00 200.00 - 42 81 78
Lay of slabs/bricks Cables (Ponds) 1,494.00 239.00 0.16 sq.m. 0.089% 2/1/2008 3/25/2008 54.00 239.00 - 128 111
Roadbed (Base course+ subbase) (Common) 15,610.00 1,957.00 0.13 cu.m 0.733% 3/1/2008 6/24/2008 116.00 1,957.00 - 523 506 523 405
Asphalting of Roads (Common) 29,311.00 1,184.00 0.04 sq.m. 0.443% 4/1/2008 7/31/2008 122.00 1,184.00 - 291 301 291 301
Ballasting of areas (Pond 2) 89,923.00 9,588.00 0.11 sq.m. 3.590% 7/1/2008 9/30/2008 92.00 9,588.00 - 3,231 3,231
Ballasting of areas (Ponds) 89,923.00 9,588.00 0.11 sq.m. 3.590% 4/18/2008 6/20/2008 64.00 9,588.00 - 1,948 4,644 2,996
Guard Rail Erection 2,095.00 262.00 0.13 m 0.098% 7/1/2008 8/31/2008 62.00 262.00 - 131 131
Fencing of Metal Post 4,000.00 4,002.00 1.00 m 1.498% 6/19/2008 10/30/2008 134.00 4,002.00 - 358 926 926
Lean Concrete (Common) 118.00 234.00 1.98 cu.m 0.088% 12/1/2007 3/31/2008 122.00 234.00 - 59 59 56 59
Lean Concrete (Ponds) 960.00 1,907.00 1.99 cu.m 0.714% 12/1/2007 2/28/2008 90.00 1,907.00 - 657 657 593
Reinforced Concrete UP TO +1.0 M (Common) 448.00 4,043.00 9.02 cu.m 1.514% 10/1/2007 1/30/2008 122.00 4,043.00 - 1,027 994 1,027 994
Reinforced Concrete UP TO +1.0 M (Ponds) 415.00 3,744.00 9.02 cu.m 1.402% 10/30/2007 4/1/2008 155.00 3,744.00 - 48 725 749 749 700 749 24
Reinforced Concrete for Paving (Common) 5,958.00 1,986.00 0.33 sq.m. 0.744% 3/1/2008 6/30/2008 122.00 1,986.00 - 505 488 505 488
Concrete for Piping support (Common) 57.00 284.00 4.98 cu.m 0.106% 1/1/2008 4/30/2008 121.00 284.00 - 73 68 73 70
Foundation Protection (Common) 6,897.00 11,821.00 1.71 sq.m. 4.426% 1/1/2008 6/5/2008 157.00 11,821.00 - 2,334 2,183 2,334 2,259 2,334 376
Foundation Protection (Ponds) 1,936.00 3,318.00 1.71 sq.m. 1.242% 1/1/2008 3/5/2008 65.00 3,318.00 - 1,582 1,480 255
Reinf. Concrete Road Channel (Common) 5,992.00 6,337.00 1.06 sq.m. 2.373% 12/25/2007 3/3/2008 70.00 6,337.00 - 634 2,806 2,625 272
PR / Lay light items (Real V) (Common) 133.00 391.00 2.94 cu.m 0.146% 1/8/2008 3/31/2008 84.00 391.00 - 112 135 144
PR / Lay light items (Real V) (Ponds) 28.00 82.00 2.93 cu.m 0.031% 1/1/2008 3/13/2008 73.00 82.00 - 35 33 15
Grouting Operation 3.00 388.00 129.33 cu.m 0.145% 2/1/2008 4/30/2008 90.00 388.00 - 125 134 129
Und. Fibreg. Pip. On S.PN14 (6In) 90,528.00 21,819.00 0.24 Kg 8.169% 9/15/2007 4/30/2008 229.00 21,819.00 - 1,524 2,954 2,858 2,954 2,954 2,763 2,954 2,858
Hydrotest Resin Pip on Site 2,760.00 1,120.00 0.41 m 0.419% 1/2/2008 4/22/2008 112.00 1,120.00 - 300 290 310 220
267,091.00 27.83% 100.000%
- - 40 1,233 1,193 1,233 1,233 2,717 5,995 10,577 19,531 33,404 33,027 31,826 30,492 29,852 18,100 15,711 15,328
Total DMHS = 959,750.00 100% - - 40 1,272 2,465 3,698 4,930 7,647 13,642 24,218 43,750 77,153 110,181 142,007 172,498 202,350 220,450 236,161 251,489
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08
Man Hour 229 6,659 13,045 16,822 19,047 20,976 21,374 22,231 37,612 45,092 60,335 78,159 79,937 78,271 70,878 72,553 58,922 56,477 53,950
Cum Man Hour 229 6,888 19,933 36,754 55,802 76,778 98,152 120,383 157,995 203,086 263,421 341,580 421,518 499,789 570,667 643,220 702,141 758,618 812,569
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Months 28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08
Manpower Requirement = 1 26 50 65 73 81 82 86 145 173 232 301 307 301 273 279 227 217 208
As Per COPr
footing
backfilling 112 m3 3 336 5 67.2
6.72 labours 100 86
81 82
73
65
50
50
26
1
-
Feb-07 Mar-07 Apr-07 May-07 Jun-07 Jul-07 Aug-07 Sep-07 Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Months 28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08
Manpower Requirement = 2 52 103 132 150 165 168 175 296 354 474 614 628 615 557 570 463 444 424
As Per BOQ 468 13609 26663 34382 38931 42873 43687 45438 76876 92163 123320 159751 163385 159980 144868 148292 120431 115434 110270
468 14078 40741 75123 114054 156927 200614 246052 322928 415091 538411 698162 861547 1021527 1166395 1314687 1435118 1550552 1660822
700
614 628 615
600 570
557
Manpower Requirement =
500 474 463
400
354
296
300
400
354
296
300
General Backfilling of Areas/Roads 0.15 0.13 0.13 0.13 General Backfilling of Areas/Roads 0.14 General Backfilling of Areas/Roads (Ponds) 4.75
Subbase preparation under paving 0.09 0.09 0.09 0.09 Subbase preparation under paving 0.09 Embank bund walls by machine (Pond 2) 0.33
Embank bund walls by machine (Ponds) 0.33
Limited excavation up to 1.5 m 0.40 0.40 0.40 0.40 Limited excavation up to 1.5 m 0.40 Limited section excavation up to 1.5 m (Common) 0.40
Limited Excavation (Over 1.5m depth) 1.02 1.05 1.04 1.05 Limited Excavation (Over 1.5m depth) 1.25 Limited section excavation up to 1.5 m (Ponds) 0.40
Reinf concrete pit for sewer 6.00 7.31 6.47 7.54 Reinf concrete pit for sewer 7.90 Reinf concrete pit for sewer (Common) 6.83
Reinf concrete pit for sewer (Ponds) 6.83
Installation of PVC drainage system 0.20 0.20 0.20 0.20 Installation of Cast Iron Drainage 5.00 Installation of PVC drainage system (Common) 0.20
Installation of Cast Iron Drainage 5.00 5.00 5.00 5.00 Installation of PVC drainage system (Ponds) 0.20
Laying of Sand for Pipe Prot. 0.66 0.67 0.66 0.67 Laying of Sand for Pipe Prot. 0.67 Laying of Sand for Pipe Prot. (Common) 0.67
Lay of slabs/bricks Cables 0.16 0.16 0.16 0.16 Lay of slabs/bricks Cables 0.16 Laying of Sand for Pipe Prot. (Ponds) 0.67
Lay of slabs/bricks Cables (Common) 0.16
Lay of slabs/bricks Cables (Ponds) 0.16
Road (Base course+ subbase) 0.12 0.12 0.12 0.12 Road (Base course+ subbase) 0.12 Roadbed (Base course+ subbase) (Common) 0.13
Asphalting of Roads 0.04 0.04 0.04 0.04 Asphalting of Roads 0.04 Asphalting of Roads (Common) 0.04
Lean Concrete 1.48 1.09 1.31 1.13 Lean Concrete 1.29 Lean Concrete (Common) 1.98
Lean Concrete (Ponds) 1.99
Reinforced Concrete up to +1.0 M 6.08 5.62 5.65 5.62 Reinforced Concrete UP TO +1.0 M 6.17 Reinforced Concrete UP TO +1.0 M (Common) 9.02
Reinforced Concrete +1.0M/+ 7.0 M 3.38 3.14 3.14 3.14 Reinforced Concrete +1.0M/+ 7.0 M 4.00 Reinforced Concrete UP TO +1.0 M (Ponds) 9.02
Reinforced Concrete for Paving 0.34 0.34 0.34 0.34 Reinforced Concrete for Paving 0.34 Reinforced Concrete for Paving (Common) 0.33
Concrete for Piping support 4.95 4.95 4.95 4.95 Concrete for Piping support 4.95 Concrete for Piping support (Common) 4.98
Reinf. Concrete Road Channel (Common) 1.06
Foundation Protection 0.22 0.13 0.13 0.13 Foundation Protection 0.12 Foundation Protection (Common) 1.71
Foundation Protection (Ponds) 1.71
Execution of expansion joints 0.20 0.20 0.20 0.20 Execution of expansion joints 0.20
PR / Lay light items (Real V) 2.35 2.03 2.20 2.00 PR / Lay light items (Real V) 2.12 PR / Lay light items (Real V) (Common) 2.94
PR / Lay light items (Real V) (Ponds) 2.93
Grouting Operation 193.02 211.07 211.06 211.07 Grouting Operation 164.41 Grouting Operation 129.33
Und. Fibreg. Pip. On S.PN14 (6In) 0.71 0.67 0.67 0.62 Und. Fibreg. Pip. On S.PN14 (6In) 0.24 Und. Fibreg. Pip. On S.PN14 (6In) 0.24
P/E FiberGl. Pip. On S.PN6 (6In) 0.61 1.20 1.20 1.20 Hydrotest Resin Pip on Site 0.41 Hydrotest Resin Pip on Site 0.41
Hydrotest Resin Pip on Site 0.33 0.34 0.34 0.34
Ballasting of areas (Pond 2) 0.11
Ballasting of areas (Ponds) 0.11
Guard Rail Erection 0.13
Fencing of Metal Post 1.00
Date Started: February 17, 2007
Target Date of Comp : Feb 2009
30 31 30 31 31 28
20 21 22 23 24 25
30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
102 1
1,269
100%
120 124 120 1,218 1
349 360 349 174 4,066 1
219 227 4,570 1
144 144 2,680 1
1,757 1
480 1
535 1
7 7 7 108 1
38 1
240 248 240 1,226 1
152 157 152 157 774 1
750 1
38,046 1
626 1
913 943 8,335 1
1,456 1
497 513 497 9,088 1
265 274 2,421 1
261 1
518 535 4,730 1
557 576 557 576 372 8,879 1
2,447 2,528 2,447 31,156 1
19 1
158 163 158 1,603 1
-
6,585 6,800 4,526 907 372 -
113,590 120,389 124,916 125,822 126,194 126,194
30 31 30 31 31 28
20 21 22 23 24 25
30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
102 1
111 115 111 1,123 1
349 360 349 174 4,066 1
214 221 4,452 1
140 140 2,619 1
1,353 1
16 1
535 1
3 3 3 50 1
24 1
253 261 253 1,288 1
159 165 159 165 813 1
416 1
35,345 1
581 1
913 943 8,335 1
1,456 1
277 287 277 5,074 1
265 274 2,421 1
142 1
518 535 4,730 1
609 630 609 630 406 9,709 1
2,377 2,456 2,377 30,261 1
12 1
150 155 150 1,522 1
-
6,337 6,544 4,288 969 406 -
104,239 110,782 115,070 116,039 116,445 116,445
20 21 22 23 24 25
30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
102 1
109 113 109 113 1,111 1
333 344 333 344 344 4,066 1
217 224 217 4,525 1
140 145 140 2,626 1
1,476 1
192 1
535 1
7 7 7 7 108 1
33 1
240 248 240 248 1,222 1
151 156 151 156 156 772 1
576 1
35,635 1
581 1
909 940 909 8,335 1
1,456 1
281 290 281 281 5,135 1
264 273 264 2,421 1
200 1
518 535 518 4,730 1
612 633 612 633 633 572 9,920 1
2,382 2,462 2,382 2,382 30,336 1
18 1
150 156 150 150 1,525 1
-
6,315 6,525 6,315 4,314 1,134 572
98,776 105,302 111,617 115,931 117,064 117,636
20 21 22 23 24 25
30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
102 1
113 117 113 117 1,148 1
333 344 333 344 344 4,066 1
215 222 215 4,475 1
141 146 141 2,645 1
1,305 1
96 1
535 1
3 3 3 3 50 1
24 1
296 306 296 306 1,512 1
187 194 187 194 194 956 1
456 1
35,648 1
581 1
909 940 909 8,335 1
1,456 1
277 287 277 277 5,077 1
264 273 264 2,421 1
140 1
518 535 518 4,730 1
599 619 599 619 619 559 9,709 1
2,448 2,529 2,448 2,448 31,165 1
12 1
151 156 151 151 1,533 1
-
6,456 6,671 6,456 4,460 1,157 559
98,873 105,544 112,001 116,460 117,618 118,177
20 21 22 23 24 25
30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
6 1
124 1,075 1
3,544 1
3,846 1
2,879 1
1,335 1
440 1
207 1
118 1
441 456 250 1,543 1
72 361 373 169 975 1
379 1
18,898 1
44 1
7,166 1
138 142 703 1
270 279 4,278 1
2,114 1
50 110 1
2,795 1
10,179 10,518 10,179 10,179 155,062 1
7,960 1
20 21 22 23 24 25
30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
102 1
15,784 1
5,218 1
12,555 1
12,555 1
752 8,398 1
7,548 1
9,870 95,736 1
10,448 1
5,360 1
2,246 1
134 1
326 1
62 666 1
5,521 1
200 1
239 1
1,957 1
1,184 1
3,127 9,588 1
9,588 1
262 1
896 896 4,002 1
234 1
1,907 1
4,043 1
3,744 1
1,986 1
284 1
11,821 1
3,318 1
6,337 1
391 1
82 1
388 1
21,819 1
1,120 1
14,706 896 - - - -
266,195 267,091 267,091 267,091 267,091 267,091
20 21 22 23 24 25
30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
2.04
20 21 22 23 24 25
30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
198 150 125 82 12 4
217
208
198
150
125
82
12
4
20 21 22 23 24 25
30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
406 306 255 167 25 9
105471 79517 66172 43335 6617 2311
1766292 1845809 1911981 1955316 1961933 1964244
444
424
406
306
255
167
444
424
406
306
255
167
25
9
General excavation 1,269 102 cu.m 0.082% 4/20/2007 9/30/2007 164.00 85 240 232 240 240 232 1,269
General Backfilling of Areas/Roads 8,340 1,218 cu.m 0.975% 2/1/2008 11/30/2008 304.00 796 850 823 850 823 850 850 823 850 823 8,340
Subbase preparation under paving 43,659 4,066 sq.m. 3.255% 1/1/2008 12/15/2008 350.00 3,867 3,617 3,867 3,742 3,867 3,742 3,867 3,867 3,742 3,867 3,742 1,871 43,659
Limited excavation up to 1.5 m 11,424 4,570 cu.m 3.658% 2/15/2007 10/31/2008 625.00 256 567 548 567 548 567 567 548 567 548 567 567 530 567 548 567 548 567 567 548 567 11,424
Limited Excavation (Over 1.5m depth) 2,620 2,680 cu.m 2.145% 4/20/2007 10/30/2008 560.00 51 145 140 145 145 140 145 140 145 145 136 145 140 145 140 145 145 140 140 2,620
Reinf concrete pit for sewer 293 1,757 cu.m 1.406% 6/1/2007 2/28/2008 273.00 32 33 33 32 33 32 33 33 30 293
Installation of PVC drainage system 2,400 480 m 0.384% 7/15/2007 5/31/2008 322.00 127 231 224 231 224 231 231 216 231 224 231 2,400
Installation of Cast Iron Drainage 107 535 m 0.428% 4/1/2008 5/31/2008 61.00 53 54 107
Laying of Sand for Pipe Prot. 163 108 cu.m 0.086% 8/1/2007 11/30/2008 488.00 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 163
Lay of slabs/bricks Cables 238 38 sq.m. 0.030% 2/1/2008 6/30/2008 151.00 46 49 47 49 47 238
Road (Base course+ subbase) 10,202 1,226 cu.m. 0.981% 7/1/2008 11/30/2008 153.00 2,067 2,067 2,000 2,067 2,000 10,202
Asphalting of Roads 20,634 774 sq.m. 0.620% 8/1/2008 12/31/2008 153.00 4,181 4,046 4,181 4,046 4,181 20,634
Lean Concrete 508 750 cu.m 0.600% 2/21/2007 1/31/2008 345.00 12 46 44 46 44 46 46 44 46 44 46 46 508
Reinforced Concrete up to +1.0 M 6,259 38,046 cu.m 30.455% 3/3/2007 2/28/2008 363.00 500 517 535 517 535 535 517 535 517 535 535 483 6,259
Reinforced Concrete +1.0M/+ 7.0 M 185 626 cu.m 0.501% 5/24/2007 12/31/2007 222.00 7 25 26 26 25 26 25 26 185
Reinforced Concrete for Paving 24,211 8,335 sq.m. 6.672% 2/1/2008 10/31/2008 274.00 2,562 2,739 2,651 2,739 2,651 2,739 2,739 2,651 2,739 24,211
Concrete for Piping support 294 1,456 cu.m. 1.166% 12/1/2007 7/31/2008 244.00 37 37 35 37 36 37 36 37 294
Foundation Protection 40,516 9,088 sq.m. 7.275% 6/1/2007 11/30/2008 549.00 2,214 2,288 2,288 2,214 2,288 2,214 2,288 2,288 2,140 2,288 2,214 2,288 2,214 2,288 2,288 2,214 2,288 2,214 40,516
Execution of expansion joints 12,105 2,421 m 1.938% 2/1/2008 10/31/2008 274.00 1,281 1,370 1,325 1,370 1,325 1,370 1,370 1,325 1,370 12,105
PR / Lay light items (Real V) 111 261 cu.m. 0.209% 2/1/2008 4/30/2008 90.00 36 38 37 111
Fire Proofing 120 4,730 cu.m 3.786% 2/1/2008 10/31/2008 274.00 13 14 13 14 13 14 14 13 14 120
Grouting Operation 46 8,879 cu.m. 7.108% 10/1/2007 1/20/2009 478.00 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 46
Und. Fibreg. Pip. On S.PN14 (6In) 44,023 31,156 Kg 24.940% 11/15/2007 11/30/2008 382.00 1,844 3,573 3,573 3,342 3,573 3,457 3,573 3,457 3,573 3,573 3,457 3,573 3,457 44,023
P/E FiberGl. Pip. On S.PN6 (6In) 31 19 Kg 0.015% 12/4/2007 6/30/2008 210.00 4 5 4 5 4 5 4 31
Hydrotest Resin Pip on Site 4,790 1,603 m 1.283% 2/1/2008 11/30/2008 304.00 457 488 473 488 473 488 488 473 488 473 4,790
234,548 124,924 13.02% 100.000%
GOSP 2
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Activities Qty DMHS Unit Relative %
28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08 30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
General excavation 1,269 102 cu.m 0.088% 4/20/2007 9/30/2007 164.00 85 240 232 240 240 232 1,269
General Backfilling of Areas/Roads 8,429 1,123 cu.m 0.964% 2/1/2008 11/30/2008 304.00 804 860 832 860 832 860 860 832 860 832 8,429
Subbase preparation under paving 43,659 4,066 sq.m. 3.492% 1/1/2008 12/15/2008 350.00 3,867 3,617 3,867 3,742 3,867 3,742 3,867 3,867 3,742 3,867 3,742 1,871 43,659
Limited excavation up to 1.5 m 11,131 4,452 cu.m 3.823% 2/15/2007 10/31/2008 625.00 249 552 534 552 534 552 552 534 552 534 552 552 516 552 534 552 534 552 552 534 552 11,131
Limited Excavation (Over 1.5m depth) 2,486 2,619 cu.m 2.249% 4/20/2007 10/30/2008 560.00 49 138 133 138 138 133 138 133 138 138 129 138 133 138 133 138 138 133 133 2,486
Reinf concrete pit for sewer 185 1,353 cu.m 1.162% 6/1/2007 2/28/2008 273.00 20 21 21 20 21 20 21 21 19 185
Installation of PVC drainage system 80 16 m 0.014% 7/15/2007 5/31/2008 322.00 4 8 7 8 7 8 8 7 8 7 8 80
Installation of Cast Iron Drainage 107 535 m 0.459% 4/1/2008 5/31/2008 61.00 53 54 107
Laying of Sand for Pipe Prot. 75 50 cu.m 0.043% 8/1/2007 11/30/2008 488.00 5 5 5 5 5 5 4 5 5 5 5 5 5 5 5 5 75
Lay of slabs/bricks Cables 150 24 sq.m. 0.021% 2/1/2008 6/30/2008 151.00 29 31 30 31 30 150
Road (Base course+ subbase) 10,716 1,288 cu.m. 1.106% 7/1/2008 11/30/2008 153.00 2,171 2,171 2,101 2,171 2,101 10,716
Asphalting of Roads 21,676 813 sq.m. 0.698% 8/1/2008 12/31/2008 153.00 4,392 4,250 4,392 4,250 4,392 21,676
Lean Concrete 383 416 cu.m 0.357% 2/21/2007 1/31/2008 345.00 9 34 33 34 33 34 34 33 34 33 34 34 383
Reinforced Concrete up to +1.0 M 6,284 35,345 cu.m 30.353% 3/3/2007 2/28/2008 363.00 502 519 537 519 537 537 519 537 519 537 537 485 6,284
Reinforced Concrete +1.0M/+ 7.0 M 185 581 cu.m 0.499% 5/24/2007 12/31/2007 222.00 7 25 26 26 25 26 25 26 185
Reinforced Concrete for Paving 24,211 8,335 sq.m. 7.158% 2/1/2008 10/31/2008 274.00 2,562 2,739 2,651 2,739 2,651 2,739 2,739 2,651 2,739 24,211
Concrete for Piping support 294 1,456 cu.m. 1.250% 12/1/2007 7/31/2008 244.00 37 37 35 37 36 37 36 37 294
Foundation Protection 40,152 5,074 sq.m. 4.357% 6/1/2007 11/30/2008 549.00 2,194 2,267 2,267 2,194 2,267 2,194 2,267 2,267 2,121 2,267 2,194 2,267 2,194 2,267 2,267 2,194 2,267 2,194 40,152
Execution of expansion joints 12,105 2,421 m 2.079% 2/1/2008 10/31/2008 274.00 1,281 1,370 1,325 1,370 1,325 1,370 1,370 1,325 1,370 12,105
PR / Lay light items (Real V) 70 142 cu.m. 0.122% 2/1/2008 4/30/2008 90.00 23 24 23 70
Fire Proofing 120 4,730 cu.m 4.062% 2/1/2008 10/31/2008 274.00 13 14 13 14 13 14 14 13 14 120
Grouting Operation 46 9,709 cu.m. 8.338% 10/1/2007 1/20/2009 478.00 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 46
Und. Fibreg. Pip. On S.PN14 (6In) 45,482 30,261 Kg 25.987% 11/15/2007 11/30/2008 382.00 1,905 3,691 3,691 3,453 3,691 3,572 3,691 3,572 3,691 3,691 3,572 3,691 3,572 45,482
P/E FiberGl. Pip. On S.PN6 (6In) 10 12 Kg 0.010% 12/4/2007 6/30/2008 210.00 1 1 1 1 1 1 1 10
Hydrotest Resin Pip on Site 4,431 1,522 m 1.307% 2/1/2008 11/30/2008 304.00 423 452 437 452 437 452 452 437 452 437 4,431
233,736 116,445 12.13% 100.000% -
GOSP 3
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Activities Qty DMHS Unit Relative %
28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08 30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
General excavation 1,269 102 cu.m 0.087% 5/20/2007 10/30/2007 164.00 93 232 240 240 232 232 1,269
General Backfilling of Areas/Roads 8,337 1,111 cu.m 0.944% 3/2/2008 12/31/2008 305.00 820 820 847 820 847 847 820 847 820 847 8,337
Subbase preparation under paving 43,659 4,066 sq.m. 3.456% 2/1/2008 1/31/2009 366.00 3,459 3,698 3,579 3,698 3,579 3,698 3,698 3,579 3,698 3,579 3,698 3,698 43,659
Limited excavation up to 1.5 m 11,313 4,525 cu.m 3.847% 3/17/2007 11/30/2008 625.00 272 543 561 543 561 561 543 561 543 561 561 525 561 543 561 543 561 561 543 561 543 11,313
Limited Excavation (Over 1.5m depth) 2,535 2,626 cu.m 2.232% 5/20/2007 11/30/2008 561.00 54 136 140 140 136 140 136 140 140 131 140 136 140 136 140 140 136 140 136 2,535
Reinf concrete pit for sewer 228 1,476 cu.m 1.255% 7/1/2007 3/30/2008 274.00 26 26 25 26 25 26 26 24 25 228
Installation of PVC drainage system 960 192 m 0.163% 8/15/2007 6/30/2008 321.00 51 90 93 90 93 93 87 93 90 93 90 960
Installation of Cast Iron Drainage 107 535 m 0.455% 5/1/2008 6/30/2008 61.00 54 53 107
Laying of Sand for Pipe Prot. 163 108 cu.m 0.092% 9/1/2007 12/30/2008 487.00 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 163
Lay of slabs/bricks Cables 205 33 sq.m. 0.028% 3/1/2008 7/31/2008 153.00 42 40 42 40 42 205
Road (Base course+ subbase) 10,176 1,222 cu.m. 1.039% 8/1/2008 12/31/2008 153.00 2,062 1,995 2,062 1,995 2,062 10,176
Asphalting of Roads 20,584 772 sq.m. 0.656% 9/1/2008 1/31/2009 153.00 4,036 4,171 4,036 4,171 4,171 20,584
Lean Concrete 441 576 cu.m 0.490% 3/23/2007 2/28/2008 343.00 12 39 40 39 40 40 39 40 39 40 40 36 441
Reinforced Concrete up to +1.0 M 6,304 35,635 cu.m 30.293% 4/2/2007 3/30/2008 364.00 502 537 520 537 537 520 537 520 537 537 502 520 6,304
Reinforced Concrete +1.0M/+ 7.0 M 185 581 cu.m 0.494% 6/23/2007 1/30/2008 222.00 7 26 26 25 26 25 26 25 185
Reinforced Concrete for Paving 24,211 8,335 sq.m. 7.085% 3/1/2008 11/30/2008 275.00 2,729 2,641 2,729 2,641 2,729 2,729 2,641 2,729 2,641 24,211
Concrete for Piping support 294 1,456 cu.m. 1.238% 1/1/2008 8/31/2008 244.00 37 35 37 36 37 36 37 37 294
Foundation Protection 40,468 5,135 sq.m. 4.365% 7/1/2007 12/30/2008 549.00 2,285 2,285 2,211 2,285 2,211 2,285 2,285 2,138 2,285 2,211 2,285 2,211 2,285 2,285 2,211 2,285 2,211 2,211 40,468
Execution of expansion joints 12,105 2,421 m 2.058% 3/1/2008 11/30/2008 275.00 1,365 1,321 1,365 1,321 1,365 1,365 1,321 1,365 1,321 12,105
PR / Lay light items (Real V) 91 200 cu.m. 0.170% 3/1/2008 5/31/2008 92.00 31 30 31 91
Fire Proofing 120 4,730 cu.m 4.021% 3/2/2008 11/30/2008 274.00 13 13 14 13 14 14 13 14 13 120
Grouting Operation 47 9,920 cu.m. 8.433% 11/1/2007 2/28/2009 486.00 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 47
Und. Fibreg. Pip. On S.PN14 (6In) 45,564 30,336 Kg 25.788% 12/15/2007 12/30/2008 382.00 2,028 3,698 3,459 3,698 3,578 3,698 3,578 3,698 3,698 3,578 3,698 3,578 3,578 45,564
P/E FiberGl. Pip. On S.PN6 (6In) 15 18 Kg 0.015% 1/3/2008 7/30/2008 210.00 2 2 2 2 2 2 2 15
Hydrotest Resin Pip on Site 4,439 1,525 m 1.296% 3/2/2008 12/30/2008 304.00 438 438 453 438 453 453 438 453 438 438 4,439
233,820 117,636 12.26% 100.000% -
GOSP 4
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Activities Qty DMHS Unit Relative %
28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08 30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
General excavation 1,269 102 cu.m 0.086% 5/20/2007 10/30/2007 164.00 93 232 240 240 232 232 1,269
General Backfilling of Areas/Roads 8,645 1,148 cu.m 0.971% 3/2/2008 12/31/2008 305.00 850 850 879 850 879 879 850 879 850 879 8,645
Subbase preparation under paving 43,659 4,066 sq.m. 3.441% 2/1/2008 1/31/2009 366.00 3,459 3,698 3,579 3,698 3,579 3,698 3,698 3,579 3,698 3,579 3,698 3,698 43,659
Limited excavation up to 1.5 m 11,189 4,475 cu.m 3.787% 3/17/2007 11/30/2008 625.00 269 537 555 537 555 555 537 555 537 555 555 519 555 537 555 537 555 555 537 555 537 11,189
Limited Excavation (Over 1.5m depth) 2,512 2,645 cu.m 2.238% 5/20/2007 11/30/2008 561.00 54 134 139 139 134 139 134 139 139 130 139 134 139 134 139 139 134 139 134 2,512
Reinf concrete pit for sewer 173 1,305 cu.m 1.104% 7/1/2007 3/30/2008 274.00 20 20 19 20 19 20 20 18 19 173
Installation of PVC drainage system 480 96 m 0.081% 8/15/2007 6/30/2008 321.00 25 45 46 45 46 46 43 46 45 46 45 480
Installation of Cast Iron Drainage 107 535 m 0.453% 5/1/2008 6/30/2008 61.00 54 53 107
Laying of Sand for Pipe Prot. 75 50 cu.m 0.042% 9/1/2007 12/30/2008 487.00 5 5 5 5 5 4 5 5 5 5 5 5 5 5 5 5 75
Lay of slabs/bricks Cables 150 24 sq.m. 0.020% 3/1/2008 7/31/2008 153.00 30 29 30 29 30 150
Road (Base course+ subbase) 12,593 1,512 cu.m. 1.279% 8/1/2008 12/31/2008 153.00 2,552 2,469 2,552 2,469 2,552 12,593
Asphalting of Roads 25,471 956 sq.m. 0.809% 9/1/2008 1/31/2009 153.00 4,994 5,161 4,994 5,161 5,161 25,471
Lean Concrete 405 456 cu.m 0.386% 3/23/2007 2/28/2008 343.00 11 35 37 35 37 37 35 37 35 37 37 33 405
Reinforced Concrete up to +1.0 M 6,340 35,648 cu.m 30.165% 4/2/2007 3/30/2008 364.00 505 540 523 540 540 523 540 523 540 540 505 523 6,340
Reinforced Concrete +1.0M/+ 7.0 M 185 581 cu.m 0.492% 6/23/2007 1/30/2008 222.00 7 26 26 25 26 25 26 25 185
Reinforced Concrete for Paving 24,211 8,335 sq.m. 7.053% 3/1/2008 11/30/2008 275.00 2,729 2,641 2,729 2,641 2,729 2,729 2,641 2,729 2,641 24,211
Concrete for Piping support 294 1,456 cu.m. 1.232% 1/1/2008 8/31/2008 244.00 37 35 37 36 37 36 37 37 294
Foundation Protection 40,203 5,077 sq.m. 4.296% 7/1/2007 12/30/2008 549.00 2,270 2,270 2,197 2,270 2,197 2,270 2,270 2,124 2,270 2,197 2,270 2,197 2,270 2,270 2,197 2,270 2,197 2,197 40,203
Execution of expansion joints 12,105 2,421 m 2.049% 3/1/2008 11/30/2008 275.00 1,365 1,321 1,365 1,321 1,365 1,365 1,321 1,365 1,321 12,105
PR / Lay light items (Real V) 70 140 cu.m. 0.118% 3/1/2008 5/31/2008 92.00 24 23 24 70
Fire Proofing 120 4,730 cu.m 4.002% 3/2/2008 11/30/2008 274.00 13 13 14 13 14 14 13 14 13 120
Grouting Operation 46 9,709 cu.m. 8.216% 11/1/2007 2/28/2009 486.00 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 46
Und. Fibreg. Pip. On S.PN14 (6In) 50,207 31,165 Kg 26.371% 12/15/2007 12/30/2008 382.00 2,234 4,074 3,812 4,074 3,943 4,074 3,943 4,074 4,074 3,943 4,074 3,943 3,943 50,207
P/E FiberGl. Pip. On S.PN6 (6In) 10 12 Kg 0.010% 1/3/2008 7/30/2008 210.00 1 1 1 1 1 1 1 10
Hydrotest Resin Pip on Site 4,450 1,533 m 1.297% 3/2/2008 12/30/2008 304.00 439 439 454 439 454 454 439 454 439 439 4,450
244,969 118,177 12.31% 100.000% -
INLET / OUTLET
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Activities Qty DMHS Unit Relative %
28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08 30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
COMMON
Date start Date finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Activities Qty DMHS Unit Relative %
28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08 30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
General excavation (Common) 1,272 102 cu.m 0.038% 10/1/2007 11/30/2007 61.00 646 626 1,272
General excavation (Pond) 197,296 15,784 cu.m 5.910% 4/30/2007 5/30/2008 397.00 497 15,406 14,909 15,406 15,406 14,909 15,406 14,909 15,406 15,406 14,412 15,406 14,909 14,909 197,296
General Backfilling of Areas/Roads (Ponds) 1,098 5,218 cu.m 1.954% 12/2/2007 4/7/2008 128.00 257 266 249 266 60 1,098
Embank bund walls by machine (Pond 2) 37,667 12,555 cu.m 4.701% 2/1/2008 7/1/2008 152.00 7,186 7,682 7,434 7,682 7,434 248 37,667
Embank bund walls by machine (Ponds) 37,667 12,555 cu.m 4.701% 1/1/2008 5/31/2008 152.00 7,682 7,186 7,682 7,434 7,682 37,667
Limited section excavation up to 1.5 m (Common) 20,996 8,398 cu.m 3.144% 11/1/2007 9/30/2008 335.00 1,880 1,943 1,943 1,818 1,943 1,880 1,943 1,880 1,943 1,943 1,880 20,996
Limited section excavation up to 1.5 m (Ponds) 18,871 7,548 cu.m 2.826% 11/1/2007 5/31/2008 213.00 2,658 2,746 2,746 2,569 2,746 2,658 2,746 18,871
Limited section excavation over 1.5 m (Common) 58,872 95,736 cu.m 35.844% 12/15/2007 9/30/2008 291.00 3,439 6,272 5,867 6,272 6,069 6,272 6,069 6,272 6,272 6,069 58,872
Limited section excavation over 1.5 m (Ponds) 6,425 10,448 cu.m 3.912% 11/1/2007 5/31/2008 213.00 905 935 935 875 935 905 935 6,425
Reinf concrete pit for sewer (Common) 785 5,360 cu.m 2.007% 10/1/2007 5/31/2008 244.00 100 97 100 100 93 100 97 100 785
Reinf concrete pit for sewer (Ponds) 329 2,246 cu.m 0.841% 12/1/2007 4/30/2008 152.00 67 67 63 67 65 329
Installation of PVC drainage system (Common) 672 134 m 0.050% 1/1/2008 6/30/2008 182.00 114 107 114 111 114 111 672
Installation of PVC drainage system (Ponds) 1,629 326 m 0.122% 1/1/2008 5/30/2008 151.00 334 313 334 324 324 1,629
Laying of Sand for Pipe Prot. (Common) 999 666 cu.m 0.249% 11/15/2007 9/30/2008 321.00 50 96 96 90 96 93 96 93 96 96 93 999
Laying of Sand for Pipe Prot. (Ponds) 8,281 5,521 cu.m 2.067% 11/1/2007 5/31/2008 213.00 1,166 1,205 1,205 1,127 1,205 1,166 1,205 8,281
Lay of slabs/bricks Cables (Common) 1,253 200 sq.m. 0.075% 2/14/2008 4/30/2008 77.00 260 504 488 1,253
Lay of slabs/bricks Cables (Ponds) 1,494 239 sq.m. 0.089% 2/1/2008 3/25/2008 54.00 802 692 1,494
Roadbed (Base course+ subbase) (Common) 15,610 1,957 cu.m 0.733% 3/1/2008 6/24/2008 116.00 4,172 4,037 4,172 3,230 15,610
Asphalting of Roads (Common) 29,311 1,184 sq.m. 0.443% 4/1/2008 7/31/2008 122.00 7,208 7,448 7,208 7,448 29,311
Ballasting of areas (Pond 2) 89,923 9,588 sq.m. 3.590% 7/1/2008 9/30/2008 92.00 30,300 30,300 29,323 89,923
Ballasting of areas (Ponds) 89,923 9,588 sq.m. 3.590% 4/18/2008 6/20/2008 64.00 18,266 43,556 28,101 89,923
Guard Rail Erection 2,095 262 m 0.098% 7/1/2008 8/31/2008 62.00 1,048 1,048 2,095
Fencing of Metal Post 4,000 4,002 m 1.498% 6/19/2008 10/30/2008 134.00 358 925 925 896 896 4,000
Lean Concrete (Common) 118 234 cu.m 0.088% 12/1/2007 3/31/2008 122.00 30 30 28 30 118
Lean Concrete (Ponds) 960 1,907 cu.m 0.714% 12/1/2007 2/28/2008 90.00 331 331 299 960
Reinforced Concrete UP TO +1.0 M (Common) 448 4,043 cu.m 1.514% 10/1/2007 1/30/2008 122.00 114 110 114 110 448
Reinforced Concrete UP TO +1.0 M (Ponds) 415 3,744 cu.m 1.402% 10/30/2007 4/1/2008 155.00 5 80 83 83 78 83 3 415
Reinforced Concrete for Paving (Common) 5,958 1,986 sq.m. 0.744% 3/1/2008 6/30/2008 122.00 1,514 1,465 1,514 1,465 5,958
Concrete for Piping support (Common) 57 284 cu.m 0.106% 1/1/2008 4/30/2008 121.00 15 14 15 14 57
Foundation Protection (Common) 6,897 11,821 sq.m. 4.426% 1/1/2008 6/5/2008 157.00 1,362 1,274 1,362 1,318 1,362 220 6,897
Foundation Protection (Ponds) 1,936 3,318 sq.m. 1.242% 1/1/2008 3/5/2008 65.00 923 864 149 1,936
Reinf. Concrete Road Channel (Common) 5,992 6,337 sq.m. 2.373% 12/25/2007 3/3/2008 70.00 599 2,654 2,482 257 5,992
PR / Lay light items (Real V) (Common) 133 391 cu.m 0.146% 1/8/2008 3/31/2008 84.00 38 46 49 133
PR / Lay light items (Real V) (Ponds) 28 82 cu.m 0.031% 1/1/2008 3/13/2008 73.00 12 11 5 28
Grouting Operation 3 388 cu.m 0.145% 2/1/2008 4/30/2008 90.00 1 1 1 3
Und. Fibreg. Pip. On S.PN14 (6In) 90,528 21,819 Kg 8.169% 9/15/2007 4/30/2008 229.00 6,325 12,255 11,860 12,255 12,255 11,464 12,255 11,860 90,528
Hydrotest Resin Pip on Site 2,760 1,120 m 0.419% 1/2/2008 4/22/2008 112.00 739 715 764 542 2,760
742,701 267,091 27.83% 100.000%
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Project : Khurais Crude Facilities Date Started: February 17, 2007
Location : Khurais Saudi Arabia MONTHLY PROGRESS PLAN (QUANTITY) Target Date of Comp : Feb 2009
GOSP 1
14 31 30 31 30 31 31 30 31 30 31 31 29 31 30 31 30 31 31 30 31 30 31 31 28
Date start Date finish Duration
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Activities Qty DMHS Unit Relative %
28-Feb-07 31-Mar-07 30-Apr-07 31-May-07 30-Jun-07 31-Jul-07 31-Aug-07 30-Sep-07 31-Oct-07 30-Nov-07 31-Dec-07 31-Jan-08 29-Feb-08 31-Mar-08 30-Apr-08 31-May-08 30-Jun-08 31-Jul-08 31-Aug-08 30-Sep-08 31-Oct-08 30-Nov-08 31-Dec-08 31-Jan-09 28-Feb-09
Limited Excavation (Over 1.5m depth) 2,620 2,680 cu.m 2.145% 4/20/2007 10/30/2008 560.00 51 145 140 145 145 140 145 140 145 145 136 145 140 145 140 145 145 140 140 ###
General excavation 1,269 102 cu.m 0.082% 4/20/2007 9/30/2007 124.00 164.00 85 240 232 240 240 232 ###
General Backfilling of Areas/Roads 8,340 1,218 cu.m 0.975% 2/1/2008 11/30/2008 304.00 796 850 823 850 823 850 850 823 850 823 ###
FOUNDATION
Lean Concrete 508 750 cu.m 0.600% 2/21/2007 1/31/2008 6.00 345.00 12 46 44 46 44 46 46 44 46 44 46 46 ###
Reinforced Concrete up to +1.0 M 6,259 38,046 cu.m 30.455% 3/3/2007 2/28/2008 10.00 363.00 500 517 535 517 535 535 517 535 517 535 535 483 ###
Reinforced Concrete +1.0M/+ 7.0 M 185 626 cu.m 0.501% 5/24/2007 12/31/2007 82.00 222.00 7 25 26 26 25 26 25 26 ###
Foundation Protection 40,516 9,088 sq.m. 7.275% 6/1/2007 11/30/2008 8.00 549.00 2,214 2,288 2,288 2,214 2,288 2,214 2,288 2,288 2,140 2,288 2,214 2,288 2,214 2,288 2,288 2,214 2,288 2,214 ###
Grouting Operation 46 8,879 cu.m. 7.108% 10/1/2007 1/20/2009 122.00 478.00 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 ###
Fire Proofing 120 4,730 cu.m 3.786% 2/1/2008 10/31/2008 123.00 274.00 13 14 13 14 13 14 14 13 14 ###
UNDER GROUND FACILITIES
Reinf concrete pit for sewer 293 1,757 cu.m 1.406% 6/1/2007 2/28/2008 273.00 32 33 33 32 33 32 33 33 30 ###
Installation of PVC drainage system 2,400 480 m 0.384% 7/15/2007 5/31/2008 44.00 322.00 127 231 224 231 224 231 231 216 231 224 231 ###
Laying of Sand for Pipe Prot. 163 108 cu.m 0.086% 8/1/2007 11/30/2008 17.00 488.00 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 ###
Concrete for Piping support 294 1,456 cu.m. 1.166% 12/1/2007 7/31/2008 122.00 244.00 37 37 35 37 36 37 36 37 ###
Installation of Cast Iron Drainage 107 535 m 0.428% 4/1/2008 5/31/2008 122.00 61.00 53 54 ###
RTRP
Und. Fibreg. Pip. On S.PN14 (6In) 44,023 31,156 Kg 24.940% 11/15/2007 11/30/2008 106.00 382.00 1,844 3,573 3,573 3,342 3,573 3,457 3,573 3,457 3,573 3,573 3,457 3,573 3,457 ###
P/E FiberGl. Pip. On S.PN6 (6In) 31 19 Kg 0.015% 12/4/2007 6/30/2008 19.00 210.00 4 5 4 5 4 5 4 ###
Hydrotest Resin Pip on Site 4,790 1,603 m 1.283% 2/1/2008 11/30/2008 59.00 304.00 457 488 473 488 473 488 488 473 488 473 ###
PAVING
Subbase preparation under paving 43,659 4,066 sq.m. 3.255% 1/1/2008 12/15/2008 28.00 350.00 3,867 3,617 3,867 3,742 3,867 3,742 3,867 3,867 3,742 3,867 3,742 1,871 ###
Reinforced Concrete for Paving 24,211 8,335 sq.m. 6.672% 2/1/2008 10/31/2008 31.00 274.00 2,562 2,739 2,651 2,739 2,651 2,739 2,739 2,651 2,739 ###
Execution of expansion joints 12,105 2,421 m 1.938% 2/1/2008 10/31/2008 0.00 274.00 1,281 1,370 1,325 1,370 1,325 1,370 1,370 1,325 1,370 ###
ROAD WORKS
PR / Lay light items (Real V) 111 261 cu.m. 0.209% 2/1/2008 4/30/2008 90.00 36 38 37 ###
Lay of slabs/bricks Cables 238 38 sq.m. 0.030% 2/1/2008 6/30/2008 151.00 46 49 47 49 47 ###
Road (Base course+ subbase) 10,202 1,226 cu.m. 0.981% 7/1/2008 11/30/2008 151.00 153.00 2,067 2,067 2,000 2,067 2,000 ###
Asphalting of Roads 20,634 774 sq.m. 0.620% 8/1/2008 12/31/2008 31.00 153.00 4,181 4,046 4,181 4,046 4,181 ###
General Backfilling of Areas/Roads 0.15 0.13 0.13 0.13 General Backfilling of Areas/Roads
Subbase preparation under paving 0.09 0.09 0.09 0.09 Subbase preparation under paving
Limited excavation up to 1.5 m 0.40 0.40 0.40 0.40 Limited excavation up to 1.5 m
Limited Excavation (Over 1.5m depth) 1.02 1.05 1.04 1.05 Limited Excavation (Over 1.5m depth)
Reinf concrete pit for sewer 6.00 7.31 6.47 7.54 Reinf concrete pit for sewer
Installation of PVC drainage system 0.20 0.20 0.20 0.20 Installation of Cast Iron Drainage
Installation of Cast Iron Drainage 5.00 5.00 5.00 5.00
Laying of Sand for Pipe Prot. 0.66 0.67 0.66 0.67 Laying of Sand for Pipe Prot.
Lay of slabs/bricks Cables 0.16 0.16 0.16 0.16 Lay of slabs/bricks Cables
Road (Base course+ subbase) 0.12 0.12 0.12 0.12 Road (Base course+ subbase)
Asphalting of Roads 0.04 0.04 0.04 0.04 Asphalting of Roads
Reinforced Concrete up to +1.0 M 6.08 5.62 5.65 5.62 Reinforced Concrete UP TO +1.0 M
Reinforced Concrete +1.0M/+ 7.0 M 3.38 3.14 3.14 3.14 Reinforced Concrete +1.0M/+ 7.0 M
Reinforced Concrete for Paving 0.34 0.34 0.34 0.34 Reinforced Concrete for Paving
Concrete for Piping support 4.95 4.95 4.95 4.95 Concrete for Piping support
PR / Lay light items (Real V) 2.35 2.03 2.20 2.00 PR / Lay light items (Real V)
COMMON
0.08 General excavation (Common) 0.08
General excavation (Pond) 0.08
Cast Iron Drainage 5.00 Installation of PVC drainage system (Common) 0.20
Installation of PVC drainage system (Ponds) 0.20