RESUMEN GENERAL DEL PRESUPUESTO ANALÍTICO

FUENTE DE FTO : RECURSOS ORDINARIOS


UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE CAYNARACHI
FUNCION : TRANSPORTE
PROGRAMA : TRANSPORTE TERRESTRE
SUB-PROGRAMA :CAMINOS VECINALES
PROYECTO :"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO VECINAL EMP.PE. SNB. KM 60+680-SANTA ROSA DEL
TIOYACU-DISTRITO DE CAYNARACHI-LAMAS"

GASTOS GASTOS DE ELABORACION DE LIQUIDACION DE


CODIGO ESPECIFICA DE GASTOS COSTO DIRECTO EXPEDIENTE COSTO TOTAL
GENERALES SUPERVISION TECNICO OBRA

2.6.22.43 PERSONAL 28,156.27 23,100.00 23,800.00 15,514.00 4,333.33 94,903.60


2.6.22.44 BIENES 154,707.35 17,073.47 190.00 488.20 412.15 172,871.17
2.6.22.45 SERVICIOS 221,166.00 2,147.38 181.25 4,150.00 0.00 227,644.63
2.6.22.46 OTROS 0.00 0.00 0.00 0.00 0.00 0.00
TOTAL 404,029.62 42,320.85 24,171.25 20,152.20 4,745.48 495,419.40
% 10.47468995% 5.98254405% 4.98780263% 1.17453765%
RESUMEN PRESUPUESTO ANALÍTICO - COSTO DIRECTO

FTE.FTO : RECURSOS ORDINARIOS


UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE CAYNARACHI
FUNCION : TRANSPORTE
PROGRAMA : TRANSPORTE TERRESTRE
SUB-PROGRAMA :CAMINOS VECINALES
PROYECTO :"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO
VECINAL EMP.PE. SNB. KM 60+680-SANTA ROSA DEL TIOYACU-DISTRITO DE
CAYNARACHI-LAMAS"

CÓDIGO ESPECIFICA DE GASTOS C. DIRECTO

2.6.22.43 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - PERSONAL 28,156.27

2.6.22.44 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - BIENES 154,707.35

2.6.22.45 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - SERVICIOS 221,166.00

2.6.22.46 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - OTROS 0.00

TOTAL COSTO DIRECTO 404,029.62

DESAGREGADO DEL PRESUPUESTO ANALÍTICO

COSTO DIRECTO
RETRIBUCIONES COMPLEMENTARIAS-CONTRATOS A PLAZO FIJO S/. 28,156.27

01 JORNAL
DEL EMPLEADO EVENTUAL

:"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO VECINAL EMP.PE. SNB. KM 60+680-SANTA ROSA DEL
TIOYACU-DISTRITO DE CAYNARACHI-LAMAS" 28,156.27
CAPATAZ hh 133.3851 24.00 3,201.24
OPERARIO hh 100.0000 21.83 2,183.00
OFICIAL hh 26.7727 13.14 351.79
PEON hh 1,368.2206 15.96 21,836.80
TOPOGRAFO hh 24.3100 24.00 583.44
TOTAL MANO DE OBRA 28,156.27
RESUMEN PRESUPUESTO ANALÍTICO - COSTO DIRECTO

FTE.FTO : RECURSOS ORDINARIOS


UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE CAYNARACHI
FUNCION : TRANSPORTE
PROGRAMA : TRANSPORTE TERRESTRE
SUB-PROGRAMA :CAMINOS VECINALES
PROYECTO :"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO
VECINAL EMP.PE. SNB. KM 60+680-SANTA ROSA DEL TIOYACU-DISTRITO DE
CAYNARACHI-LAMAS"

CÓDIGO ESPECIFICA DE GASTOS C. DIRECTO

2.6.22.43 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - PERSONAL 28,156.27

2.6.22.44 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - BIENES 154,707.35

2.6.22.45 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - SERVICIOS 221,166.00

2.6.22.46 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - OTROS 0.00

TOTAL COSTO DIRECTO 404,029.62

02 MATERIALES DE CONSTRUCCION S/. 13,516.06


:"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO VECINAL EMP.PE. SNB. KM 60+680-SANTA ROSA DEL
TIOYACU-DISTRITO DE CAYNARACHI-LAMAS" 13,516.06
CLAVOS PARA MADERA C/C 3" kg 125.0000 5.50 687.50
CALAMINA pln 120.0000 18.00 2,160.00
MADERA TORNILLO p2 1,250.0000 3.50 4,375.00
ESTACAS DE MADERA p2 6.6300 4.50 29.84
TRIPLAY DE 4X8X8 mm pln 75.0000 22.50 1,687.50
PINTURA ESMALTE gal 0.5525 48.00 26.52
ALMACEN DE OBRA glb 3.0000 1,000.00 3,000.00
PLANTONES und 930.0000 1.50 1,395.00
WINCHA DE 30m und 2.2100 70.00 154.70

TOTAL MATERIALES 13,516.06

03 HERRAMIENTAS Y EQUIPOS S/. 141,191.29

:"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO VECINAL EMP.PE. SNB. KM 60+680-SANTA ROSA DEL
TIOYACU-DISTRITO DE CAYNARACHI-LAMAS" 141,191.29
NIVEL TOPOGRAFICO día 2.2100 6.50 14.37
ESTACION TOTAL día 2.9500 120.00 353.59
HERRAMIENTAS MANUALES %mo 877.31
RODILLO LISO VIBR AUTOP 70-100 HP 7-9 T. hm 159.5700 160.00 25,531.30 MAQUI. PROPIA
CARGADOR S/LLANTAS 125-155 HP 3 YD3. hm 11.0000 250.00 2,749.85 MAQUI PROPIA
TRACTOR DE ORUGAS DE 190-240 HP hm 112.3800 330.00 37,086.42
MOTONIVELADORA DE 125 HP hm 159.6600 220.00 35,124.94 MAQUI PROPIA
CAMION VOLQUETE DE 15 m3 hm 194.7300 180.00 35,050.77 MAQUI PROPIA
CAMION CISTERNA hm 29.3500 150.00 4,402.74

TOTAL HERRAMIENTAS Y EQUIPOS 141,191.29


TODAS LAS HORAS Y SU COSTO TOTAL DE MAQUINARIA PROPIA SERA CONVERTIDO ADQUISICION DE REPUESTO INSUMOS
LUBRICANTES, COMBUSTIBLE, LO CUAL SE INDICA EN EL CUADRO DESAGREGADO DE COSTOS OPERATIVOS DE EQUIPO PROPIO
04 SUB - CONTRATOS S/. 221,166.00

:"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO VECINAL EMP.PE. SNB. KM 60+680-SANTA ROSA DEL
TIOYACU-DISTRITO DE CAYNARACHI-LAMAS" 221,166.00
SC.ADQUISISCION Y COLOCACION DE CARTEL DE OBRA 2.4mX3.60m und 1.0000 2,500.00 2,500.00
SC.ADQUISICION E INSTALACION DE HITOS KILOMETRICOS und 3.0000 750.00 2,250.00
SC . ADQUISICION E INSTALACION DE SEÑAL INFORMATIVA und 2.0000 1,000.00 2,000.00
SC.ADQUISICION E INSTALACION DE SEÑAL REGLAMENTARIA und 1.0000 1,000.00 1,000.00
SC.ADQUI E INSTAL.DE SEÑAL PREVENTIVA und 2.0000 1,000.00 2,000.00
SC.MATERIAL LIGANTE P/ AFIRMADO m3 491.0400 60.00 29,462.40
SC.MATERIAL GRANULAR FINO/P AFIRMADO m3 927.5200 60.00 55,651.20
SC.MATERIAL GRANULAR MEDIO P/ AFIRMADO m3 927.5200 60.00 55,651.20
SC.METERIAL GRANULAR GRUESO P/ AFIRMADO m3 927.5200 60.00 55,651.20
SC.MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb 1.0000 15,000.00 15,000.00
TOTAL SUB CONTRATOS 221,166.00

TOTAL COSTO DIRECTO S/. 404,029.62


RESUMEN PRESUPUESTO ANALÍTICO - GASTOS GENERALES

FTE.FTO : RECURSOS ORDINARIOS


UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE CAYNARACHI
FUNCION : TRANSPORTE
PROGRAMA : TRANSPORTE TERRESTRE
SUB-PROGRAMA :CAMINOS VECINALES
PROYECTO
:"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO VECINAL
EMP.PE. SNB. KM 60+680-SANTA ROSA DEL TIOYACU-DISTRITO DE CAYNARACHI-LAMAS"

CÓDIGO ESPECIFICA DE GASTOS G. GENERALES

2.6.22.43 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - PERSONAL 23,100.00

2.6.22.44 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - BIENES 17,073.47

2.6.22.45 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - SERVICIOS 2,147.38

2.6.22.46 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - OTROS 0.00

TOTAL GASTOS GENERALES 42,320.85

DESAGREGADO DEL PRESUPUESTO ANALÍTICO

GASTOS GENERALES
RETRIBUCIONES COMPLEMENTARIAS-CONTRATOS A PLAZO FIJO

01 JORNAL
DEL EMPLEADO EVENTUAL S/. 23,100.00
% DE PARTICIPACION
CARGO N° DE PERSONAS MESES COSTO SUB TOTAL
RESIDENTE DE PROYECTOS DE INVERSION 1.00 2.50 4,500.00 11,250.00
ASISTENTE TECNICO DE OBRA 1.00 2.50 3,500.00 8,750.00
ALMACENERO 1.00 2.50 1,240.00 3,100.00
TOTAL 23,100.00

07 BIENES, SERVICIOS Y OTROS

VESTUARIO Y ELEMENTOS DE SEGURIDAD S/. 1,000.00

DESCRIPCIÓN UND. CANTIDAD P.U. SUB TOTAL


CASCOS DE PROTECCION TIPO KW COLOR BLANCO UND 2.00 50.00 100.00
CASCOS DE PROTECCION TIPO KW COLOR UND 10.00 25.00 250.00
BOTAS DE JEBE PAR 10.00 25.00 250.00
CHALECO DRYLL DE TRABAJO UND 10.00 25.00 250.00
PONCHOS DE LLUVIA UND 10.00 15.00 150.00
TOTAL 1,000.00

COMBUSTIBLE Y LUBRICANTES S/. 15,562.00

DESCRIPCIÓN UND. CANTIDAD P.U. SUB TOTAL


PETROLEO (CAMIONETA PICK UP 4X4) GLN 726.00 12.00 8,712.00
ALQUILER DE CAMIONETA 4x4 DIA 44.00 150.00 6,600.00
GASOLINA 84 OCT GLN 20.00 12.50 250.00
TOTAL 15,562.00

08 BIENES DE CONSUMO S/. 511.47

MATERIALES MEDICOS Y MEDICINAS

DESCRIPCIÓN UND. CANTIDAD P.U. SUB TOTAL


AGUA OXIGENADA FRASCO 1.00 4.00 4.00
ALCOHOL LTS 1.00 8.00 8.00
PASTILLAS PARA LA GRIPE UND. 10.00 1.00 10.00
PASTILLAS ANTIHISTAMINICOS UND. 24.00 1.00 24.00
ALGODON X 250 GR. PQTE 2.00 4.24 8.47
GASA FRACCIONADA X 10 PZAS. PQTE 5.00 2.00 10.00
YODO LTS 1.00 15.00 15.00
ACIDO BORICO UND 1.00 4.00 4.00
ANTIBIOTICOS/ANTINFLAMATORIOS/ANALGESICOS GLB 1.00 50.00 50.00
VENDAS UND 3.00 8.00 24.00
GASA QUIRURGICA ESTERIL 10X40 PQT 2.00 5.00 10.00
ESPARADRAPO RLL 1.00 15.00 15.00
JERINGAS 10ML UND 10.00 0.50 5.00
VENDITAS ADHESIVAS CJAS 8.00 3.00 24.00
TOTAL 211.47

MATERIALES IMPRESIÓN Y FOTOGRÁFICOS


RESUMEN PRESUPUESTO ANALITICO - SUPERVISION

FTE.FTO : RECURSOS ORDINARIOS


UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE CAYNARACHI
FUNCION : TRANSPORTE
PROGRAMA : TRANSPORTE TERRESTRE
SUB-PROGRAMA :CAMINOS VECINALES
PROYECTO :"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO
VECINAL EMP.PE. SNB. KM 60+680-SANTA ROSA DEL TIOYACU-DISTRITO DE
CAYNARACHI-LAMAS"

CÓDIGO ESPECIFICA DE GASTOS G. SUPERVISION

2.6.22.43 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - PERSONAL 23,800.00

2.6.22.44 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - BIENES 190.00

2.6.22.45 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - SERVICIOS 181.25

2.6.22.46 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - OTROS 0.00

TOTAL GASTOS DE SUPERVISION 24,171.25

DESAGREGADO DEL PRESUPUESTO ANALÍTICO

GASTOS DE SUPERVISION
RETRIBUCIONES COMPLEMENTARIAS-CONTRATOS A PLAZO FIJO

01 JORNAL S/. 23,800.00


DEL EMPLEADO EVENTUAL

CARGO N° DE PERSONAS MESES COSTO SUB TOTAL


INSPECTOR DE OBRA 1.00 2.50 6,000.00 15,000.00
ASISTENTE TECNICO 1.00 2.50 3,520.00 8,800.00
TOTAL 23,800.00

06 BIENES, SERVICIOS Y OTROS


VESTUARIO S/. 190.00

DESCRIPCION UND CANTIDAD P.U. SUB TOTAL


CASCOS DE PROTECCION TIPO KW COLOR BLANCO UND 2.00 50.00 100.00
BOTAS DE JEBE PAR 2.00 30.00 60.00
PONCHOS DE LLUVIA UND 2.00 15.00 30.00
TOTAL 190.00

MATERIALES DE ESCRITORIO S/. 181.25

DESCRIPCIÓN UND. CANTIDAD P.U. SUB TOTAL


ANILLOS DE 5/8" UND 4.00 0.50 2.00
ARCHIVADOR DE LOMO ANCHO PARA FORMATO A-4 UND 4.00 10.00 40.00
CINTA MASKING 2" UND 1.00 4.00 4.00
CLIP WINGO PEQUEÑO X 100 UNID CJA 1.00 1.00 1.00
CORRECTOR UND 1.00 5.00 5.00
ESPIRALES DE 7 MM UND 4.00 0.50 2.00
FASTENERX50 UND CJA 0.50 6.00 3.00
FILES UND 4.00 0.50 2.00
LAPICERO AZUL/NEGRO 031 FABER CASTELL UND 4.00 0.50 2.00
LIBRETA DE CAMPO UND 2.00 3.50 7.00
PAPEL BOND 80 GR A-4 MLL 2.00 25.00 50.00
PEGAMENTO EN BARRA UND 1.00 4.50 4.50
PLUMON INDELEBLE DELGADO DIFER. COLORES UND 3.00 3.00 9.00
PLUMON INDELEBLE GRUESO DIFER. COLORES UND 3.00 5.00 15.00
PORTAMINAS UND 1.00 10.00 10.00
POST IT CUADRADO COLORES PZA 3.00 4.75 14.25
REPUESTOS PARA PORTAMINAS UND 3.00 1.50 4.50
RESALTADOR UND 3.00 2.00 6.00
TOTAL 181.25

TOTAL GASTOS DE SUPERVISION S/. 24,171.25


RESUMEN PRESUPUESTO ANALITICO - EXPEDIENTE TECNICO

FTE.FTO : RECURSOS ORDINARIOS


UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE CAYNARACHI
FUNCION : TRANSPORTE
PROGRAMA : TRANSPORTE TERRESTRE
SUB-PROGRAMA :CAMINOS VECINALES
PROYECTO :"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO
VECINAL EMP.PE. SNB. KM 60+680-SANTA ROSA DEL TIOYACU-DISTRITO DE
CAYNARACHI-LAMAS"

CÓDIGO ESPECIFICA DE GASTOS G. LIQUIDACION

2.6.22.43 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - PERSONAL 15,514.00

2.6.22.44 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - BIENES 488.20

2.6.22.45 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - SERVICIOS 4,150.00

2.6.22.46 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - OTROS

TOTAL GASTOS EXPEDIENTE TECNICO 20,152.20

DESAGREGADO DEL PRESUPUESTO ANALÍTICO

GASTOS DE EXPEDIENTE TECNICO


RETRIBUCIONES COMPLEMENTARIAS-CONTRATOS A PLAZO FIJO

01 JORNAL

DEL EMPLEADO EVENTUAL S/. 15,514.00

CARGO N° DE PERSONAS MESES COSTO SUB TOTAL


ING.PROYECTISTA 1.00 1.50 5,500.00 8,250.00
TOPOGRAFO 1.00 1.00 2,050.00 2,050.00
ASISTENTE TECNICO 1.00 1.50 3,200.00 4,800.00
PEON 3.00 0.15 920.00 414.00
TOTAL 15,514.00

09 OTROS SERVICIOS DE TERCEROS S/. 4,150.00


OTROS SERVICIOS

DESCRIPCIÓN UND. CANTIDAD P.U. SUB TOTAL


ESTUDIO DE MECANICA DE SUELOS UND 8.00 400.00 3,200.00
ALQUILER DE ESTACION TOTAL (INCLUYE PRISMAS Y TRIPODE) DIA 5.00 120.00 600.00
ALQUILER DE GPS DIA 5.00 30.00 150.00
IMPRESIÓN DE PLANOS UND 20.00 10.00 200.00
TOTAL 4,150.00

MATERIALES DE ESCRITORIO S/. 488.20

DESCRIPCIÓN UND. CANTIDAD P.U. SUB TOTAL


ANILLOS DE 5/8" UND 3.00 0.50 1.50
ARCHIVADOR DE LOMO ANCHO PARA FORMATO A-4 UND 4.00 4.50 18.00
BORRADOR BR40 UND 1.00 0.50 0.50
CD RW REGRABABLES UND 3.00 1.00 3.00
CINTA MASKING 2" UND 2.00 4.00 8.00
CLIP WINGO PEQUEÑO X 100 UNID CJA 1.00 0.70 0.70
LIBRETA TOPOGRÁFICA FIELD BOOK UND 1.00 3.50 3.50
CORRECTOR UND 1.00 4.50 4.50
ESPIRALES DE 7 MM UND 15.00 0.25 3.75
FASTENERX50 UND CJA 1.00 6.00 6.00
FILES UND 5.00 1.00 5.00
LAPICERO AZUL/NEGRO 031 FABER CASTELL UND 3.00 2.00 6.00
LIBRETA DE CAMPO UND 1.00 3.50 3.50
MICA COLORES UND 6.00 2.00 12.00
PAPEL BOND 80 GR A-4 MLL 3.00 25.00 75.00
PEGAMENTO EN BARRA UND 2.00 4.50 9.00
PLUMON INDELEBLE DELGADO DIFER. COLORES UND 2.00 3.00 6.00
PLUMON INDELEBLE GRUESO DIFER. COLORES UND 2.00 5.00 10.00
PORTAMINAS UND 3.00 18.00 54.00
POST IT CUADRADO COLORES PZA 3.00 4.75 14.25
RESALTADOR UND 2.00 2.00 4.00
THONER HP LASERJET 1102 UND 1.00 240.00 240.00
TOTAL 488.20

TOTAL GASTOS DE EXPEDIENTE TECNICO S/. 20,152.20


RESUMEN PRESUPUESTO ANALITICO - SUPERVISION DE ESTUDIOS
FTE.FTO : RECURSOS ORDINARIOS
UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE CAYNARACHI
FUNCION : TRANSPORTE
PROGRAMA : TRANSPORTE TERRESTRE
SUB-PROGRAMA :CAMINOS VECINALES
PROYECTO :"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO VECINAL EMP.PE. SNB.
KM 60+680-SANTA ROSA DEL TIOYACU-DISTRITO DE CAYNARACHI-LAMAS"

CÓDIGO ESPECIFICA DE GASTOS G. LIQUIDACION

2.6.22.43 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - PERSONAL 0.00

2.6.22.44 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - BIENES 0.00

2.6.22.45 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - SERVICIOS 0.00

2.6.22.46 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - OTROS 0.00

TOTAL GASTOS DE SUPERVISION DE ESTUDIOS 0.00

DESAGREGADO DEL PRESUPUESTO ANALÍTICO

GASTOS DE SUPERVISION DE ESTUDIOS

RETRIBUCIONES COMPLEMENTARIAS-CONTRATOS A PLAZO FIJO

01 JORNAL S/. 100.00

DEL EMPLEADO EVENTUAL


CARGO N° DE PERSONAS MESES COSTO SUB TOTAL
SUPERVISOR DE ESTUDIOS 1.00 0.05 2,000.00 100.00
TOTAL 100.00

02 VACACIONES TRUNCAS

DEL EMPLEADO EVENTUAL


CARGO N° DE PERSONAS MESES COSTO SUB TOTAL
SUPERVISOR DE ESTUDIOS 1.00 0.05 166.67 8.33
TOTAL 8.33

03 GASTOS VARIABLES Y OCASIONALES S/. 8.33


BENEFICIOS (COMPENSACION POR TIEMPO DE SERVICIOS)

DEL EMPLEADO EVENTUAL


CARGO N° DE PERSONAS MESES COSTO SUB TOTAL
SUPERVISOR DE ESTUDIOS 1.00 0.05 166.67 8.33
TOTAL 8.33

04 ESCOLARIDAD, AGUINALDOS Y GRATIFICACIONES S/. 4.17


AGUINALDOS POR FIESTAS PATRIAS Y NAVIDAD

DEL EMPLEADO EVENTUAL


CARGO N° DE PERSONAS MESES COSTO SUB TOTAL
SUPERVISOR DE ESTUDIOS 1.00 0.05 83.33 4.17
TOTAL 4.17

05 OBLIGACIONES DEL EMPLEADOR S/. 17.06


ESSALUD (9%)

DEL EMPLEADO EVENTUAL


CARGO N° DE PERSONAS MESES COSTO SUB TOTAL
SUPERVISOR DE ESTUDIOS 1.00 0.05 195.00 9.75
TOTAL 9.75

06 SEGURO COMPLEMENTARIO DE TRABAJO DE RIESGO (6.75%) S/. 7.31

DEL EMPLEADO EVENTUAL


CARGO N° DE PERSONAS MESES COSTO SUB TOTAL
SUPERVISOR DE ESTUDIOS 1.00 0.05 146.25 7.31
TOTAL 7.31

07 OTROS SERVICIOS DE TERCEROS S/. 0.00

MATERIALES DE ESCRITORIO S/. 523.45

DESCRIPCIÓN UND. CANTIDAD P.U. SUB TOTAL


RESUMEN PRESUPUESTO ANALITICO - LIQUIDACION DE OBRA

FTE.FTO : RECURSOS ORDINARIOS


UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE CAYNARACHI
FUNCION : TRANSPORTE
PROGRAMA : TRANSPORTE TERRESTRE
SUB-PROGRAMA :CAMINOS VECINALES
PROYECTO :"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO
VECINAL EMP.PE. SNB. KM 60+680-SANTA ROSA DEL TIOYACU-DISTRITO DE
CAYNARACHI-LAMAS"

CÓDIGO ESPECIFICA DE GASTOS G. LIQUIDACION

2.6.22.43 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - PERSONAL 4,333.33

2.6.22.44 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - BIENES 412.2

2.6.22.45 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - SERVICIOS 0.0

2.6.22.46 COSTO CONSTRUCCION POR ADMINISTRACION DIRECTA - OTROS 0.00

TOTAL GASTOS DE LIQUIDACION 4,745.48

DESAGREGADO DEL PRESUPUESTO ANALÍTICO

GASTOS DE LIQUIDACION
RETRIBUCIONES COMPLEMENTARIAS-CONTRATOS A PLAZO FIJO

01 JORNAL
DEL EMPLEADO EVENTUAL S/. 4,000.00

CARGO N° DE PERSONAS MESES COSTO SUB TOTAL


ING.LIQUIDADOR DE OBRA 1.00 1.00 2,500.00 2,500.00
LIQUIDADOR FINANCIERO 1.00 1.00 1,500.00 1,500.00
TOTAL 4,000.00

02 VACACIONES TRUNCAS
DEL EMPLEADO EVENTUAL S/. 333.33

CARGO N° DE PERSONAS MESES COSTO SUB TOTAL


ING.LIQUIDADOR DE OBRA 1.00 1.00 208.33 208.33
LIQUIDADOR FINANCIERO 1.00 1.00 125.00 125.00
TOTAL 333.33

MATERIALES DE ESCRITORIO S/. 412.15

DESCRIPCIÓN UND. CANTIDAD P.U. SUB TOTAL


ANILLOS DE 5/8" UND 6.00 0.50 3.00
ARCHIVADOR DE LOMO ANCHO PARA FORMATO A-4 UND 10.00 4.50 45.00
BORRADOR BR40 UND 2.00 0.50 1.00
CD RW REGRABABLES UND 2.00 9.00 18.00
CINTA MASKING 2" UND 2.00 4.00 8.00
CLIP WINGO PEQUEÑO X 100 UNID CJA 2.00 0.70 1.40
LIBRETA TOPOGRÁFICA FIELD BOOK UND 2.00 3.50 7.00
CORRECTOR UND 2.00 8.00 16.00
ESPIRALES DE 7 MM UND 3.00 0.25 0.75
FASTENERX50 UND CJA 2.00 6.00 12.00
FILES UND 6.00 1.00 6.00
LAPICERO AZUL/NEGRO 031 FABER CASTELL UND 6.00 2.00 12.00
MICA COLORES UND 12.00 2.00 24.00
PAPEL BOND 80 GR A-4 MLL 3.00 26.00 78.00
PEGAMENTO EN BARRA UND 2.00 4.50 9.00
PLUMON INDELEBLE DELGADO DIFER. COLORES UND 2.00 3.00 6.00
PLUMON INDELEBLE GRUESO DIFER. COLORES UND 2.00 5.00 10.00
PORTAMINAS UND 5.00 18.00 90.00
POST IT CUADRADO COLORES PZA 10.00 4.75 47.50
REPUESTOS PARA PORTAMINAS UND 5.00 1.50 7.50
RESALTADOR UND 5.00 2.00 10.00
TOTAL 412.15

TOTAL GASTOS DE LIQUIDACION S/. 4,745.48


HOJA RESUMEN
FTE.FTO : RECURSOS ORDINARIOS
UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE CAYNARACHI
FUNCION : TRANSPORTE
PROGRAMA : TRANSPORTE TERRESTRE
SUB-PROGRAMA :CAMINOS VECINALES
PROYECTO :"MEJORAMIENTO DEL CAMINO VECINAL A NIVEL DE AFIRMADO DEL CAMINO
VECINAL EMP.PE. SNB. KM 60+680-SANTA ROSA DEL TIOYACU-DISTRITO DE
CAYNARACHI-LAMAS"
ORGANO TECNICO : DIRECCION DE INFRAESTRUCTURA Y PLANEAMIENTO URBANO.

PRESUPUESTO BASE

Código Descripción Parcial (S/.)

A COSTO DIRECTO 404,029.62

(CD) S/. 404,029.62

B COSTO DIRECTO 404,029.62


C GASTOS GENERALES 10.47% 42,320.85
D GASTOS DE SUPERVISION 5.98% 24,171.25
E GASTOS DE LIQUIDACION DE OBRA 1.17% 4,745.48
F ELB. EXP. TECNICO 4.99% 20,152.20

G PRESUPUESTO TOTAL 495,419.40