DAILY SITE RECORD Monday, March 09, 2020 DAILY SITE PHOTO
GROUT PILES
3CBP CAST TODAY 9 MARCH 2020 PLUS 1 TC1-1
total completed to date: 71 nos. TOWER CRANE PILE SUPPORT
Total number of GROUT Piles 141 nos. 50.35%
Grout Pile " 0" Progress Today
Architectural
work
M & E Work
INSTALL REBAR CAGE FOR TOWER CRANE CBP 11 800MM DIAMETER @DEPTH FROM TOP
SUPPORT OF STEEL CASING TO PILE TOE DEPTH OF 15.3
FAIR
Manpower
8:30 18:00 TOTAL : 16 TOTAL : 18 TOTAL : 0 TOTAL : 0 34 CBP 42 800MM DIAMETER @DEPTH FROM CBP 46 800MM DIAMETER @DEPTH FROM TOP
TOP OF STEEL CASING TO PILE TOE DEPTH OF STEEL CASING TO PILE TOE DEPTH 21.1
TOTAL OF3 NOS. OF CONTIGUOUS BORED PILES(CBP) DONE TODAY ( 9 MARCH 2020) CBP PILES @97.16%
COMPLETED , MSCP FOUNDATION PILES IS 100 % completed
CBP 11 800MM DIAMETER @DEPTH FROM TOP OF STEEL CASING TO PILE TOE DEPTH OF 15.3 METERS
CBP 42 800MM DIAMETER @DEPTH FROM TOP OF STEEL CASING TO PILE TOE DEPTH OF 21.3 METERS
CBP 46 800MM DIAMETER @DEPTH FROM TOP OF STEEL CASING TO PILE TOE DEPTH 21.1 METERS
TC1-1 600MM DIAMETER @DEPTH FROM TOP OF STEEL CASING TO PILE TOE DEPTH OF 28.9 METERS
Balance of 4 Numbers of CBP Piles Comprising of 800mm diameter of CBP piles at lower deck PLUS 3 Nos. of 600mm
diameter FOR Tower Crane Support
noise level reading: Does not Exceed for the entire duration of work