BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Monday, March 09, 2020 DAILY SITE PHOTO

Activities Location Description of works Remarks

FOUNDATION Bored Pile


Piling work in progress.
total completed to date: 128 nos.
total Number foundation Bored Piles 128 nos. 100.00%
Structural work

CONTIGUOUS Bored Pile ( CBP )

total completed to date: 137 nos.


Total number of contiguous Bored Piles 141 nos. 97.16%

GROUT PILES
3CBP CAST TODAY 9 MARCH 2020 PLUS 1 TC1-1
total completed to date: 71 nos. TOWER CRANE PILE SUPPORT
Total number of GROUT Piles 141 nos. 50.35%
Grout Pile " 0" Progress Today
Architectural
work
M & E Work

INSTALL REBAR CAGE FOR TOWER CRANE CBP 11 800MM DIAMETER @DEPTH FROM TOP
SUPPORT OF STEEL CASING TO PILE TOE DEPTH OF 15.3

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY METERS


ATTENDANCE
P Manager 1 Supervisor 2 Generator 3
Site Supervisor 3 Safety officer 1 Excavator 2
08:30 17:30 Safety officer 1 Pil Rig Operator 2 Piling Rig 1
Site engineer 1 Safety office 1 MINI BREAKER 1
RTO 1 Rigger Worker 4 MINI EXCAVATOR 2
REMARKS Administrator 1 hacking team 4 vibro hammer 1
Coordinator 1 gen Worker 4 80T crawler crane 1
G Worker 7
New Piling Rig 1
Weather

FAIR

Manpower
8:30 18:00 TOTAL : 16 TOTAL : 18 TOTAL : 0 TOTAL : 0 34 CBP 42 800MM DIAMETER @DEPTH FROM CBP 46 800MM DIAMETER @DEPTH FROM TOP
TOP OF STEEL CASING TO PILE TOE DEPTH OF STEEL CASING TO PILE TOE DEPTH 21.1

Housekeeping work inprogress, OF 21.3 METERS METERS

TOTAL OF3 NOS. OF CONTIGUOUS BORED PILES(CBP) DONE TODAY ( 9 MARCH 2020) CBP PILES @97.16%
COMPLETED , MSCP FOUNDATION PILES IS 100 % completed

CBP 11 800MM DIAMETER @DEPTH FROM TOP OF STEEL CASING TO PILE TOE DEPTH OF 15.3 METERS

CBP 42 800MM DIAMETER @DEPTH FROM TOP OF STEEL CASING TO PILE TOE DEPTH OF 21.3 METERS

CBP 46 800MM DIAMETER @DEPTH FROM TOP OF STEEL CASING TO PILE TOE DEPTH 21.1 METERS

TC1-1 600MM DIAMETER @DEPTH FROM TOP OF STEEL CASING TO PILE TOE DEPTH OF 28.9 METERS

INSTALL REBAR CAGE FOR TOWER CRANE SUPPORT

REMARKS : TC1-1 600MM DIAMETER @DEPTH FROM


TOP OF STEEL CASING TO PILE TOE DEPTH
OF 28.9 METERS

0 Grout Piles Done today 9 MARCH 2020

Balance of 4 Numbers of CBP Piles Comprising of 800mm diameter of CBP piles at lower deck PLUS 3 Nos. of 600mm
diameter FOR Tower Crane Support

noise level reading: Does not Exceed for the entire duration of work