Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date 07/10/2020

Prepared By: NATM Approved By:


Ashish khare Mainak Roy
Representative CRE
Contractors Activities
Cross
Passage/Activities
CP 24/25-03(CP-06)

Heading:- 0.0/5.5/9.5 m
Benching:-0.4/3.7/9.5m

1. Benching excavation is in progress.

▪Dewatering
▪Housekeeping

CP 24/25-04(CP-07)

Heading: 0.0/9.6/9.6 m
Benching:- 0.4/7.3/9.6 m

1. Benching excavation is in progress.

▪Dewatering
▪Housekeeping

CP 25/26-01(CP-08)

Heading:- 0.0/9.5/9.5
Benching:- 0.0/9.5/9.5

Activity

1. Invert concrete curing is in progress.


2. Overt rebar shifting and tying is in progress.

Dewatering
▪Housekeeping

CP 25/26-02(CP-09)

Page 1 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020

Heading: 0/9.5/9.5
Benching: 0/9.5/9.5

Activities

1) Overt and invert Waterproofing is in progress.

CP 25/26-03 (CP10)

Heading 0/9.5/9.5

Benching: 0.0/9.56/9.6

1) Overt concrete curing is in progress.


2) Scaffolding erection is done for temporary ring beam dismantling at U/L
side.
3) Temporary Ring beam dismentinng is in progress.

▪Dewatering
▪Housekeeping

CP 25/26-04(CP-11)

1) Overt curing is in progress.


2) Temporary Ring beam shifting is in progress to PG.

NATM, Marol Naka /


Activities Excavation MTUL-
**Heading - 263.52/263.52 (completed)
**Benching – 0.0/190.50 RM

Excavation MTDL -

Page 2 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020

**Heading -263.52/263.52 RM (Completed)


**Benching – 2.0/80.0 RM

Cross passages -

**Heading - 84.0/84.0 (Completed)

**Benching. – 46.8/93.6 RM
--------------------------------------------------------------------------------------------

Total Heading excavation = 611/611 (Completed)


-------------------------------------------------------------------------------------------
Invert Concrete:
Upline tunnel – 0/165.30
Down line tunnel - 0/52.0

Overt Concrete:

Upline tunnel - 0.0/41.7 m

A) CP-1 (West Side) Breaking started on 18.02.2019


HEADING Excavation (Mtr)
Today/Cumulative/Total :0/5.85/5.85 (Completed on 13.04.19)
BENCHING Excavation (Mtr)
Today/Cumulative/Total Scope :0/0/5.85

B) Main Platform Tunnel Excavation (towards CSIA 09.5.19)


Excavation : 0/12.78/12.78
Ring segment Dismantle; 0/60/60 numbers

LATTICE GIRDER
0/9 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/270.4
Second Layer wire-mesh: 0/283.5

Page 3 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020
SHOTCRETE
Sealing Shotcrete: 0/225.4
First Layer shotcrete: 0/283.5
Second Layer Shotcrete: 0/283.5
SN ROCK BOLTS (Nos): 0/120

C) Main Platform Tunnel Excavation (towards Pali Ground 19-06-19)


Excavation :0.0/49.45
Segment Dismantle; 0/186
LATTICE GIRDER
1/43 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 22/954
Second Layer wire-mesh: 22/954
SHOTCRETE
Sealing Shotcrete: 22/954
First Layer shotcrete:22/954
Second Layer Shotcrete: 00/932
SN ROCK BOLTS (Nos): 14/305
Consolidated grouting cement used :0/12
Fore poling 32mm dia 4mtr long 0/107

D) JUNCTION DEVELOPMENT
HEADING Excavation (Mtr)
Today/Cumulative/Total Scope:0.0/10.7/10.7 (Completed 4/5/19)
BENCHING Excavation (Mtr)
Today/Cumulative/Total Scope: 0/0/10.7
E) CP-16 (East Side) Breaking started on 24.04.2019
& Junction Development
FORE-POLING: 76mm SDA (Mtr.):
0/180/180 (24 Nos.)(Started on 30.3.19 and completed 11.4.2019)
HEADING Excavation (Mtr)
Today/Cumulative/Total Scope :0/16.7/16.70
SHOTCRETE
Sealing :0/121
First Layer :00/176
Second Layer :0/183
WIREMESH FIXING
First layer (Sqm): 0/176
Second Layer (Sqm): 0/176
LATTICE GIRDER
0/5/5 Numbers
SN ROCK BOLTS 25mm 4m long :
5/55/65 (2nos. mock-up)
Glass Fibre ROCK BOLTS (Nos) :0/0/16

F) CP-16 Main D/L Platform Tunnel Excavation (towards CSIA 09.7.19)

Page 4 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020
Excavation :0/12.7
segment Dismantle; 0/48 numbers
LATTICE GIRDER
0/8 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/264
Second Layer wire-mesh: 0/231
SHOTCRETE
Sealing Shotcrete: 0/226
First Layer shotcrete: 0/227
Second Layer Shotcrete: 0/231
SN ROCK BOLTS (Nos):0/82

G) CP-16 Main D/L Platform Tunnel Excavation (towards PALI GROUND)

Excavation: 0/34.45
segment Dismantle: 0/246- numbers
LATTICE GIRDER
0/31 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/1177
Second Layer wire-mesh: 00/1111
SHOTCRETE
Sealing Shotcrete: 0/1177
First Layer shotcrete: 00/1111
Second Layer Shotcrete:0/1111
SN ROCK BOLTS (Nos): 0/375
Forepoling 32 mm dia. : 0/37

H) CP-04(West Side)
CONSOLIDATION GROUTING:
51mm dia. 4m Long : 0/14/22
76mm SDA (Mtr.): (SDA Started on 02.06.19)
00/180/180 m Drilling finished 06-06-2019)
Grouting 0/24/24 (grouting Finished 08-06-2019)
EXCAVATION
Excavation :00/16.45/16.45( 1 meter excavated in the box excavation.)
LATTICE GIRDER
0/5/5 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/229
Second Layer wire-mesh: 0/165
SHOTCRETE
Sealing Shotcrete: 0/200
First Layer shotcrete: 0/198
Second Layer Shotcrete:0/165
SN ROCK BOLTS (Nos):0/53
Drainage holes 0/10
Consolidation grouting 5 hole

Page 5 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020
0/24/32

I) CP-04 Main U/L Platform Tunnel Excavation (towards CSIA )

Excavation :0.0/37.8
segment Dismantle; 0/168 numbers
LATTICE GIRDER
0/24 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/550
Second Layer wire-mesh: 00/550
SHOTCRETE
Sealing Shotcrete: 00/550
First Layer shotcrete:00/550
Second Layer Shotcrete: 00/550
SN ROCK BOLTS (Nos): 0/140
Forepoling 0/61
Cement grouting bags 0/6

J) CP04 Towards Pali Ground side

Excavation : 0.0/0.0
segment Dismantle; 0/75 numbers
LATTICE GIRDER
1/34 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing:0/956
Second Layer wire-mesh: 0/956
SHOTCRETE
Sealing Shotcrete: 0/956
First Layer shotcrete: 0/956
Second Layer Shotcrete: 0/956
SN ROCK BOLTS (Nos): 0/380
Cement grouting bags: 0/0
Consolidation grouting:
SDA Forepoling: 00/39
Forepoling : 0/278

K) CP13

segment Dismantle; 0/102 numbers


LATTICE GIRDER
0/32 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/1081
Second Layer wire-mesh: 0/1081
SHOTCRETE

Page 6 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020
Sealing Shotcrete: 0/1081
First Layer shotcrete: 0/1081
Second Layer Shotcrete: 0/1081
SN ROCK BOLTS (Nos): 0/367
Cement grouting bags: 0/10
Forepoling 0/215

L) CP13 Junction Development

segment Dismantle; 0/0 numbers


LATTICE GIRDER
0/5 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 20/50
Second Layer wire-mesh: 20/50
SHOTCRETE
Sealing Shotcrete: 20/50
First Layer shotcrete: 0/30
Second Layer Shotcrete: 0/30
SN ROCK BOLTS (Nos): 0/5
Cement grouting bags 0/3

M) CP06 and Main Tunnel Towards CSIA(20-10-2019)

segment Dismantle; 0/159 numbers


LATTICE GIRDER
0/20 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/1208
Second Layer wire-mesh: : 0/1208
SHOTCRETE
Sealing Shotcrete: 0/1208
First Layer shotcrete: : 0/1208
Second Layer Shotcrete: 0/1208
SN ROCK BOLTS (Nos): 0/364
GFRP -0/12
Cement grouting bags 0/10

N) CP06 and Main Tunnel Towards pali ground side(20-10-2019)

Excavation :
segment Dismantle; 1/54 numbers
LATTICE GIRDER
0/13 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/784
Second Layer wire-mesh: 0/784
SHOTCRETE

Page 7 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020
Sealing Shotcrete: 0/784
First Layer shotcrete: 0/784
Second Layer Shotcrete:0/784
SN ROCK BOLTS (Nos): 0/276
GFRP -0/0
Cement grouting bags 0/0

O) CP-03 (West Side) Started on 14.05.2019


FORE-POLING: 76mm SDA (Mtr.):
00/180/180 m
Grouting done for 0/24/24 Nos. Completed on 23.5.2019.
P) CP-14 (East Side)
FORE-POLING: 76mm SDA (Mtr.): (SDA Started on 23.4.19)
00/180/180 m Drilling Finished 28.5.2019)
SDA Grouting 0/24/24 nos. (Grouting Completed 31.5.19)
Note- 1.6m Excavation in CP-1 already excavated during station box excavation.
1.2m left side and 0.8m right side excavation in CP-16 already done during station
box A excavation.

Q) CP 10
FORE-POLING: 51mm SDA (Mtr.):
24/169/180 m Drilling Finished)
SDA Grouting 0/11/24 nos. (Grouting Completed)

R) CP 05
FORE-POLING: 76mm SDA (Mtr.):
0/180/180 m Drilling Finished)
SDA Grouting 12/12/24 nos. (Grouting Completed)

S) CP 12
FORE-POLING: 76mm SDA (Mtr.):
13/46/180 m Drilling Finished)
SDA Grouting 0/0/24 nos. (Grouting Completed)
T) CP11
FORE Polling : SDA installation
/33/180 m Drilling .
U) CP11
Excavation :0.0/0.0
Segment Dismantle :
LATTICE GIRDER :
2/31 numbers

WIREMESH FIXING :
First layer wire mesh fixing: 0/1146
Second layer wire mesh fixing:0/1146

SHOTCRETE :
Sealing shotcrete : 0/1169
First layer shotcrete : 0/1146
Second layer shotcrete:0/1146
Page 8 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020

SN ROCK BOLTS (Nos): 27/386

V) CP12 :

Sealing shotcrete : 6cum


First shotcrete : 17cum

W) CP01 MTUL Benching from CSIA side:

CP1 invert
Sealing shotcret - 30cum
1st layer shotcret - 108cum

X) CP02:

Excavation : 0.0/0.0
segment Dismantle; 0/0 numbers
LATTICE GIRDER
1/5Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/97
Second Layer wire-mesh: 0/97
SHOTCRETE
Sealing Shotcrete:0/97
First Layer shotcrete: 0/97
Second Layer Shotcrete: 0/97
SN ROCK BOLTS (Nos): 0/18
Fore poling 4 m. long 0/34

Y) CP03

Excavation : 0.0/0.0
segment Dismantle; 0/0 numbers
LATTICE GIRDER
5 nos.
WIREMESH FIXING
First Layer Wire-mesh fixing:0/73
Second Layer wire-mesh: 24/92
SHOTCRETE
Sealing Shotcrete:0/33
First Layer shotcrete: 0/73
Second Layer Shotcrete: 24/92
SN ROCK BOLTS (Nos): 0/22
Fore poling 4 m. long 0/0
Channel fixing mtr : 0/22

Page 9 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020

Invert :

Sealing shotcrete 12 cum

First layer shotcrete 27cum

Z) CP15

LATTICE GIRDER
0 nos.
WIREMESH FIXING
First Layer Wire-mesh fixing:0/34
Second Layer wire-mesh: 0/34
SHOTCRETE
Sealing Shotcrete:0/55
First Layer shotcrete: 11/55
Second Layer Shotcrete: 21/55
SN ROCK BOLTS (Nos): 0/22
Fore poling 4 m. long 0/0
Channel fixing mtr : 0/2

AA) CP12

Sealing layer 7cum


1st layer 17 cum

Invert:

CP01 invert

Sealing shotcrete: 33cum

1st layer: 118cum

CP02 invert

Sealing shotcrete 4cum

1st layer shotcrete 7cum

CP16 invert

Sealing shotcrete 39cum

1st layer shotcrete 116cum

CP03 invert

Page 10 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020

Sealing shotcrete 12cum

1st layer shotcrete 70cum

I&M Progress status CP 23/24-01:


Completed
Tunnel Array installation
Building Instruments Completed
Convergence monitoring inside Installation Completed,
Tunnel
CP 23/24-02:
Completed
Tunnel Array
installation
Building Completed
Instruments
Convergence Installation Completed,
monitoring inside
Tunnel
CP 23/24-03:
Tunnel Array Completed
installation
Building Completed
Instruments
Convergence Under progress
monitoring inside
Tunnel
CP-01& 16, NATM Marol Naka:
Surface 1. Above Ground completed as per station
Instrumentation approved I&M drawings.
Building Completed as per Station approved I&M
Instruments drawings
Convergence Installed.
monitoring inside
Tunnel
Areas of Concern

Page 11 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020
Safety Issues 1) Excavated muck is filled in bag and left unattended near Cross passage working
area.

2) Excavation work is going on more than 1mtr in each cycle which is not as per the
approved drawing.

Quality & Technical 1) CJV is continuously doing the excavation without following the excavation
Issues sequences (heading and benching) given in MS and drawings. Formal CSR
and NCR have also raised - NATM Marol Naka.
2) The CJV is not providing the nailing in the wiremesh properly due to which
gaps can be observed between the wiremesh and the surface behind it.
3) The CJV is not removing the water at the corners of the lattice girder before
installing them.
4) The CJV is not installing thickness pin at every location.
5) Some of the Lattice Girders that are installed are damaged.
Environmental 1) Proper ventilation arrangement should be provided for dust control during dry
Issues shotcreting.
NCR / Observations 1) GCC-UGC07-LET-001699-A00: Waviness in primary support(shotcrete) where
Lattice girder installed.
2) GCC-UGC07-LET-001379-A00: Improper/incomplete primary support at Marol
Naka Box-A NATM work area.
3) GCC-UGC07-LET-001392-A00: Non -Adherence of Approved drawing and Poor
quality of work at Marol Naka NATM.

4) GCC-UGC07-LET -0001492-A00 : Delay in primary support at NATM area below


the MMOPL-1.

5) GCC-UGC07-LET -0001669-A00: Unsafe activity at NATM work area.

PHOTOGRAPHS

Page 12 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020
TUNNEL CROSS PASSAGES

Obvert reinforcement is in progress at CP-08.

Heading core cutting in progress at CP-06.

Waterproofing work started at CP-09.

Benching excavation in progress at CP-07.

Page 13 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020

MAROL NAKA NATM CROSS PASSAGES

Invert excavation is in progress at Downline tunnel. Overt rebar work is in progress 11th panel Upline tunnel.

Page 14 of 17
Mumbai Metro Line 3

CRE SITE DAILY REPORT


Contractor L&T-STEC JV Mumbai (UGC-07) Date
07/10/2020
Invert excavation is in progress at Downline tunnel. Overt rebar work is in progress 11th panel Upline tunnel.

Invert wiremesh fixing is in progress junction area of Down line invert panel 6th concreting done. Total qty- 34
CP08 U/L tunnel. cum.

Page 15 of 17
Cross Passage Location
CP23/24-01

CP23/24-02

Page 1 of 17