Heading:- 0.0/5.5/9.5 m
Benching:-0.4/3.7/9.5m
▪Dewatering
▪Housekeeping
CP 24/25-04(CP-07)
Heading: 0.0/9.6/9.6 m
Benching:- 0.4/7.3/9.6 m
▪Dewatering
▪Housekeeping
CP 25/26-01(CP-08)
Heading:- 0.0/9.5/9.5
Benching:- 0.0/9.5/9.5
Activity
Dewatering
▪Housekeeping
CP 25/26-02(CP-09)
Page 1 of 17
Mumbai Metro Line 3
Heading: 0/9.5/9.5
Benching: 0/9.5/9.5
Activities
CP 25/26-03 (CP10)
Heading 0/9.5/9.5
Benching: 0.0/9.56/9.6
▪Dewatering
▪Housekeeping
CP 25/26-04(CP-11)
Excavation MTDL -
Page 2 of 17
Mumbai Metro Line 3
Cross passages -
**Benching. – 46.8/93.6 RM
--------------------------------------------------------------------------------------------
Overt Concrete:
LATTICE GIRDER
0/9 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/270.4
Second Layer wire-mesh: 0/283.5
Page 3 of 17
Mumbai Metro Line 3
D) JUNCTION DEVELOPMENT
HEADING Excavation (Mtr)
Today/Cumulative/Total Scope:0.0/10.7/10.7 (Completed 4/5/19)
BENCHING Excavation (Mtr)
Today/Cumulative/Total Scope: 0/0/10.7
E) CP-16 (East Side) Breaking started on 24.04.2019
& Junction Development
FORE-POLING: 76mm SDA (Mtr.):
0/180/180 (24 Nos.)(Started on 30.3.19 and completed 11.4.2019)
HEADING Excavation (Mtr)
Today/Cumulative/Total Scope :0/16.7/16.70
SHOTCRETE
Sealing :0/121
First Layer :00/176
Second Layer :0/183
WIREMESH FIXING
First layer (Sqm): 0/176
Second Layer (Sqm): 0/176
LATTICE GIRDER
0/5/5 Numbers
SN ROCK BOLTS 25mm 4m long :
5/55/65 (2nos. mock-up)
Glass Fibre ROCK BOLTS (Nos) :0/0/16
Page 4 of 17
Mumbai Metro Line 3
Excavation: 0/34.45
segment Dismantle: 0/246- numbers
LATTICE GIRDER
0/31 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/1177
Second Layer wire-mesh: 00/1111
SHOTCRETE
Sealing Shotcrete: 0/1177
First Layer shotcrete: 00/1111
Second Layer Shotcrete:0/1111
SN ROCK BOLTS (Nos): 0/375
Forepoling 32 mm dia. : 0/37
H) CP-04(West Side)
CONSOLIDATION GROUTING:
51mm dia. 4m Long : 0/14/22
76mm SDA (Mtr.): (SDA Started on 02.06.19)
00/180/180 m Drilling finished 06-06-2019)
Grouting 0/24/24 (grouting Finished 08-06-2019)
EXCAVATION
Excavation :00/16.45/16.45( 1 meter excavated in the box excavation.)
LATTICE GIRDER
0/5/5 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/229
Second Layer wire-mesh: 0/165
SHOTCRETE
Sealing Shotcrete: 0/200
First Layer shotcrete: 0/198
Second Layer Shotcrete:0/165
SN ROCK BOLTS (Nos):0/53
Drainage holes 0/10
Consolidation grouting 5 hole
Page 5 of 17
Mumbai Metro Line 3
Excavation :0.0/37.8
segment Dismantle; 0/168 numbers
LATTICE GIRDER
0/24 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/550
Second Layer wire-mesh: 00/550
SHOTCRETE
Sealing Shotcrete: 00/550
First Layer shotcrete:00/550
Second Layer Shotcrete: 00/550
SN ROCK BOLTS (Nos): 0/140
Forepoling 0/61
Cement grouting bags 0/6
Excavation : 0.0/0.0
segment Dismantle; 0/75 numbers
LATTICE GIRDER
1/34 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing:0/956
Second Layer wire-mesh: 0/956
SHOTCRETE
Sealing Shotcrete: 0/956
First Layer shotcrete: 0/956
Second Layer Shotcrete: 0/956
SN ROCK BOLTS (Nos): 0/380
Cement grouting bags: 0/0
Consolidation grouting:
SDA Forepoling: 00/39
Forepoling : 0/278
K) CP13
Page 6 of 17
Mumbai Metro Line 3
Excavation :
segment Dismantle; 1/54 numbers
LATTICE GIRDER
0/13 Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/784
Second Layer wire-mesh: 0/784
SHOTCRETE
Page 7 of 17
Mumbai Metro Line 3
Q) CP 10
FORE-POLING: 51mm SDA (Mtr.):
24/169/180 m Drilling Finished)
SDA Grouting 0/11/24 nos. (Grouting Completed)
R) CP 05
FORE-POLING: 76mm SDA (Mtr.):
0/180/180 m Drilling Finished)
SDA Grouting 12/12/24 nos. (Grouting Completed)
S) CP 12
FORE-POLING: 76mm SDA (Mtr.):
13/46/180 m Drilling Finished)
SDA Grouting 0/0/24 nos. (Grouting Completed)
T) CP11
FORE Polling : SDA installation
/33/180 m Drilling .
U) CP11
Excavation :0.0/0.0
Segment Dismantle :
LATTICE GIRDER :
2/31 numbers
WIREMESH FIXING :
First layer wire mesh fixing: 0/1146
Second layer wire mesh fixing:0/1146
SHOTCRETE :
Sealing shotcrete : 0/1169
First layer shotcrete : 0/1146
Second layer shotcrete:0/1146
Page 8 of 17
Mumbai Metro Line 3
V) CP12 :
CP1 invert
Sealing shotcret - 30cum
1st layer shotcret - 108cum
X) CP02:
Excavation : 0.0/0.0
segment Dismantle; 0/0 numbers
LATTICE GIRDER
1/5Numbers
WIREMESH FIXING
First Layer Wire-mesh fixing: 0/97
Second Layer wire-mesh: 0/97
SHOTCRETE
Sealing Shotcrete:0/97
First Layer shotcrete: 0/97
Second Layer Shotcrete: 0/97
SN ROCK BOLTS (Nos): 0/18
Fore poling 4 m. long 0/34
Y) CP03
Excavation : 0.0/0.0
segment Dismantle; 0/0 numbers
LATTICE GIRDER
5 nos.
WIREMESH FIXING
First Layer Wire-mesh fixing:0/73
Second Layer wire-mesh: 24/92
SHOTCRETE
Sealing Shotcrete:0/33
First Layer shotcrete: 0/73
Second Layer Shotcrete: 24/92
SN ROCK BOLTS (Nos): 0/22
Fore poling 4 m. long 0/0
Channel fixing mtr : 0/22
Page 9 of 17
Mumbai Metro Line 3
Invert :
Z) CP15
LATTICE GIRDER
0 nos.
WIREMESH FIXING
First Layer Wire-mesh fixing:0/34
Second Layer wire-mesh: 0/34
SHOTCRETE
Sealing Shotcrete:0/55
First Layer shotcrete: 11/55
Second Layer Shotcrete: 21/55
SN ROCK BOLTS (Nos): 0/22
Fore poling 4 m. long 0/0
Channel fixing mtr : 0/2
AA) CP12
Invert:
CP01 invert
CP02 invert
CP16 invert
CP03 invert
Page 10 of 17
Mumbai Metro Line 3
Page 11 of 17
Mumbai Metro Line 3
2) Excavation work is going on more than 1mtr in each cycle which is not as per the
approved drawing.
Quality & Technical 1) CJV is continuously doing the excavation without following the excavation
Issues sequences (heading and benching) given in MS and drawings. Formal CSR
and NCR have also raised - NATM Marol Naka.
2) The CJV is not providing the nailing in the wiremesh properly due to which
gaps can be observed between the wiremesh and the surface behind it.
3) The CJV is not removing the water at the corners of the lattice girder before
installing them.
4) The CJV is not installing thickness pin at every location.
5) Some of the Lattice Girders that are installed are damaged.
Environmental 1) Proper ventilation arrangement should be provided for dust control during dry
Issues shotcreting.
NCR / Observations 1) GCC-UGC07-LET-001699-A00: Waviness in primary support(shotcrete) where
Lattice girder installed.
2) GCC-UGC07-LET-001379-A00: Improper/incomplete primary support at Marol
Naka Box-A NATM work area.
3) GCC-UGC07-LET-001392-A00: Non -Adherence of Approved drawing and Poor
quality of work at Marol Naka NATM.
PHOTOGRAPHS
Page 12 of 17
Mumbai Metro Line 3
Page 13 of 17
Mumbai Metro Line 3
Invert excavation is in progress at Downline tunnel. Overt rebar work is in progress 11th panel Upline tunnel.
Page 14 of 17
Mumbai Metro Line 3
Invert wiremesh fixing is in progress junction area of Down line invert panel 6th concreting done. Total qty- 34
CP08 U/L tunnel. cum.
Page 15 of 17
Cross Passage Location
CP23/24-01
CP23/24-02
Page 1 of 17