palacio

 arquitectos
PERU  RAIL  /  BELMOND  BAE  PROJECT
Oct  24  2016
TIME  TABLE

BAE  PROJECT  TIMETABLE


OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL MAY
WAGONS WEEK  7 WEEK  8 WEEK  9 WEEK  10 WEEK  11 WEEK  12 WEEK  13 WEEK  14 WEEK  15 WEEK  16 WEEK  17 WEEK  18 WEEK  19 WEEK  20 WEEK  21 WEEK  22 WEEK  23 WEEK  24 WEEK  25 WEEK  26 WEEK  27 WEEK  28 WEEK  29 WEEK  30 WEEK  31 WEEK  32 WEEK  33 WEEK  34 WEEK  35 WEEK  36
PREVIOUS MON   24 MON   31 MON   7 MON   14 MON   21 MON   28 MON   5 MON   12 MON   19 MON   26 MON   2 MON   9 MON   16 MON   23 MON   30 MON   6 MON   13 MON   20 MON   27 MON   6 MON   13 MON   20 MON   27 MON   3 MON   10 MON   17 MON   24 MON   1 MON   8

CARPET SPECS&PURCHASING EX-­‐WORK FREIGHT  &  CUSTOM CUSCO

1831 Commissioners  Car


INSTAL.

1843 Luxury  /  Family  Car


TODAY   INSTAL.

1859 Deluxe  Car


INSTAL.

1860 Deluxe  Car


INSTAL.

1841 Luxury  /  Family  Car


INSTAL.

1834 Luxury  /    Suites  Car


TODAY

INSTAL.

1824 Deluxe  PWD  Car

PRELIMINARY  CONVOY  RELEASE


INSTAL.

CONVOY  RELEASE
1847 Luxury  /    Suites  Car
INSTAL.

1852 Dining  Car

1830 Observatory  Car


TODAY

1838 Dining  /  Boutique  Car

1839 Lounge  Car


INSTAL.

1850 Luxury  /  Spa  Car


INSTAL.

1853 Staff  Car


TODAY

INSTAL.

1854 Staff  Car


INSTAL.

1836 Galley  Car


FF&E  &  SPARE  PARTS  PURCHASING  AND  OVERSEAS  DELIVERY KITCHEN  EQUIPMENT  INSTALLATION INSTAL.
BACK  UP  WAGONS

1826 Luxury  /  Family  Car


INSTAL.
TODAY

1825 Deluxe  Car


INSTAL.

1858 Deluxe  Car


INSTAL.

KEY: TECHNICHAL  AND  PRELIMINARY  WORKS FF&E:  PURCHASING  &  OVERSEAS  DELIVERIES CARPET

REMODELING  WORKS FF&E:  PRODUCTION

EXTERIOR  PAINT FF&E:  INSTALLATION