TRIPLE BASEMENT UNDERGROUND PARKING Classic Schedule Layout 22-Jun-20 13:02

Activity ID Activity Name Original Start Finish Remarks 2020 2021


Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Dharahara01-2 TRIPLE BASEMENT UNDERGROUND 374d 05-Jun-20
PARKING 28-Jun-21 28-Jun-21, Dharahara01-2 TRIPLE BASEMENT

383d
Dharahara01-2.1 GENERAL REQUIREMENTS & PRELIMINARIES 05-Jun-20 28-Jun-21 28-Jun-21, Dharahara01-2.1 GENERAL REQUIR

Dharahara01-2.1.1 PROJECT MILESTONES 90d 29-Mar-21 28-Jun-21 28-Jun-21, Dharahara01-2.1.1 PROJECT MILES
TB1000 Handover 0d 28-Jun-21 Handover,
TB1010 Basement Structural Works Complete 0d 29-Mar-21 Basement Structural Works Complete,
Dharahara01-2.1.2 PRELIMINARIES 30d 05-Jun-20 05-Jul-20 05-Jul-20, Dharahara01-2.1.2 PRELIMINARIES
TB1030 Site Clearence 30d 05-Jun-20 05-Jul-20 Site Clearence
Dharahara01-2.2 CONSTRUCTION WORKS 374d 05-Jun-20 28-Jun-21 28-Jun-21, Dharahara01-2.2 CONSTRUCTION W

Dharahara01-2.2.1 DISMANTLE WORKS 36d 05-Jun-20 11-Jul-20 11-Jul-20, Dharahara01-2.2.1 DISMANTLE WORKS
TB1040 Existing PCC & Foundation Removal 32d 08-Jun-20 11-Jul-20 Existing PCC & Foundation Removal
TB1050 Sanchyakos Building 30d 05-Jun-20 05-Jul-20 Sanchyakos Building
Dharahara01-2.2.2 SUBSTRUCTURE 301d 05-Jun-20 13-Apr-21 13-Apr-21, Dharahara01-2.2.2 SUBSTRUCTURE
Dharahara01-2.2.2.1 PROTECTION WORKS 60d 04-Jul-20 05-Sep-20 05-Sep-20, Dharahara01-2.2.2.1 PROTECTION WORKS
TB1060 RCC Protection Pile 14d 04-Jul-20 19-Jul-20 Work depends on return of manpower
RCC Protection Pile
TB1064 West side 6d 04-Jul-20 11-Jul-20 West side
TB1065 North side 5d 14-Jul-20 19-Jul-20 North side
TB1070 Micropile Works 20d 22-Jul-20 11-Aug-20 Micropile Works
TB1080 Skin Wall 20d 25-Jul-20 14-Aug-20 Skin Wall
TB1090 Shoring Works 40d 26-Jul-20 05-Sep-20 Shoring Works
TB1100 Pile Cap 6d 20-Jul-20* 26-Jul-20 Pile Cap
Dharahara01-2.2.2.2 EARTH WORK 263d 20-Jul-20 13-Apr-21 13-Apr-21, Dharahara01-2.2.2.2 EARTH WORK
TB1130 Excavation for Foundation 31d 20-Jul-20 20-Aug-20 Excavation for Foundation
TB1140 Disposal Work 38d 20-Jul-20 27-Aug-20 Disposal Work
TB1150 Backfilling at gaps between Skinwall & Shearwall 15d 29-Mar-21 13-Apr-21 Backfilling at gaps between Skinwall & Shearwall
TB1160 Anti -Termite Spray 42d 24-Jul-20 05-Sep-20 Anti -Termite Spray
TB1170 Gravel Sand Mixture(60:40) 42d 24-Jul-20 05-Sep-20 Gravel Sand Mixture(60:40)
Dharahara01-2.2.2.3 DEWATERING WORK 144d 20-Jul-20 13-Dec-20 13-Dec-20, Dharahara01-2.2.2.3 DEWATERING WORK
TB1180 Dewatering 144d 20-Jul-20* 13-Dec-20 Dewatering
Dharahara01-2.2.2.4 SUBSTRUCTURE WATER PROOFING WROK 303d 05-Jun-20 08-Apr-21 08-Apr-21, Dharahara01-2.2.2.4 SUBSTRUCTURE WATER PROOFING W
TB1190 Horizontal Waterproofing Membrane 108d 05-Jun-20 22-Sep-20 Horizontal Waterproofing Membrane
TB1200 Vertical Waterproofing Membrane 120d 07-Dec-20 08-Apr-21 Vertical Waterproofing Membrane
TB1210 Water Stops for all constructio n jo ints 201d 17-Jun-20* 06-Jan-21 Water Stops for all constructio n jo in ts
Dharahara01-2.2.2.5 PART-1 40% 149d 05-Jun-20 07-Nov-20 07-Nov-20, Dharahara01-2.2.2.5 PART-1 40%
Dharahara01-2.2.2.5.8 RAFT FOUNDATION 17d 05-Jun-20 22-Jun-20 22-Jun-20, Dharahara01-2.2.2.5.8 RAFT FOUNDATION
TB1220 Concrete Casting for Raft Foundation 17d 05-Jun-20* 22-Jun-20 Concrete Casting for Raft Foundation
Dharahara01-2.2.2.5.9 BASEMENT NO 02 (2B) 46d 17-Jun-20 02-Aug-20 02-Aug-20, Dharahara01-2.2.2.5.9 BASEMENT NO 02 (2B)
TB1230 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
20d 17-Jun-20 07-Jul-20 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
TB1240 Slab & Beam Reif, Formwork & Concrete Casting for 1B 25d 08-Jul-20 02-Aug-20 Slab & Beam Reif, Formwork & Concrete Casting for 1B
Dharahara01-2.2.2.5.10 BASEMENT NO 01 (1B) 46d 03-Aug-20 19-Sep-20 19-Sep-20, Dharahara01-2.2.2.5.10 BASEMENT NO 01 (1B)
TB1250 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
20d 03-Aug-20 24-Aug-20 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
TB1260 Slab & Beam Reif, Formwork & Concrete Casting for 2B 25d 25-Aug-20 19-Sep-20 Slab & Beam Reif, Formwork & Concrete Casting for 2B
Dharahara01-2.2.2.5.11 UPPER BASEMENT (UB) 46d 20-Sep-20 07-Nov-20 07-Nov-20, Dharahara01-2.2.2.5.11 UPPER BASEMENT (UB)
TB1270 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
20d 20-Sep-20 10-Oct-20 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
TB1280 Slab & Beam Reif, Formwork & Concrete Casting for UB 25d 12-Oct-20 07-Nov-20 Slab & Beam Reif, Formwork & Concrete Casting for UB
Dharahara01-2.2.2.6 PART-2 60% 219d 15-Jul-20 27-Feb-21 27-Feb-21, Dharahara01-2.2.2.6 PART-2 60%
Dharahara01-2.2.2.6.8 RAFT FOUNDATION 72d 15-Jul-20 26-Sep-20 26-Sep-20, Dharahara01-2.2.2.6.8 RAFT FOUNDATION
TB1290 100mm thick PCC for foundation 50d 15-Jul-20 04-Sep-20 100mm thick PCC for foundation
TB1300 Steel Reinforcement for Raft 60d 22-Jul-20 21-Sep-20 Steel Reinforcement for Raft
TB1310 Formwork for Raft Foundation 60d 22-Jul-20 21-Sep-20 Formwork for Raft Foundation
TB1320 Concrete Casting for Raft Foundation 35d 21-Aug-20 26-Sep-20 Concrete Casting for Raft Foundation

Actual Level of Effort Critical Remaining Work Page 1 of 3 TASK filter: All Activities
Actual Work Milestone Note: All the works depends upon site condition, return of the workers from their residence, longitivity of EPIDEMIC COVID 19 and earliest issuance of drawings. © GIETC-RAMAN JV
Remaining Work summary
TRIPLE BASEMENT UNDERGROUND PARKING Classic Schedule Layout 22-Jun-20 13:02
Activity ID Activity Name Original Start Finish Remarks 2020 2021
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Dharahara01-2.2.2.6.9 BASEMENT NO 02 (2B) 50d 25-Sep-20 15-Nov-20 15-Nov-20, Dharahara01-2.2.2.6.9 BASEMENT NO 02 (2B)
TB1330 Steel Reinforcement, Formwork & Concrete Casting for Retaining Wall
21d& Columns
25-Sep-20 16-Oct-20 Steel Reinforcement, Formwork & Concrete Casting for Retaining Wall & Columns
TB1340 Slab & Beam Reif, Formwork & Concrete Casting for 2B 28d 17-Oct-20 15-Nov-20 Slab & Beam Reif, Formwork & Concrete Casting for 2B
Dharahara01-2.2.2.6.10 BASEMENT NO 01 (1B) 50d 16-Nov-20 05-Jan-21 05-Jan-21, Dharahara01-2.2.2.6.10 BASEMENT NO 01 (1B)
TB1350 Steel Reinforcement. Formwork & Concrete Casting for Retaining Wall
21d& Columns
16-Nov-20 07-Dec-20 Steel Reinforcement. Formwork & Concrete Casting for Retaining Wall & Columns
TB1360 Slab & Beam Reif, Formwork & Concrete Casting for 1B 28d 08-Dec-20 05-Jan-21 Slab & Beam Reif, Formwork & Concrete Casting for 1B
Dharahara01-2.2.2.6.11 UPPER BASEMENT (UB) 49d 06-Jan-21 27-Feb-21 27-Feb-21, Dharahara01-2.2.2.6.11 UPPER BASEMENT (UB)
TB1370 Steel Reinforcement, Formwork & Concrete Casting for Retaining Wall
21d& Columns
06-Jan-21 28-Jan-21 Steel Reinforcement, Formwork & Concrete Casting for Retaining Wall & Columns
TB1380 Slab & Beam Reif, Formwork & Concrete Casting for UB 28d 30-Jan-21 27-Feb-21 Slab & Beam Reif, Formwork & Concrete Casting for UB
Dharahara01-2.2.3 SUPERSTRUCTURE 28d 28-Feb-21 29-Mar-21 29-Mar-21, Dharahara01-2.2.3 SUPERSTRUCTURE
Dharahara01-2.2.3.1 GROUND FLOOR (GF) 28d 28-Feb-21 29-Mar-21 29-Mar-21, Dharahara01-2.2.3.1 GROUND FLOOR (GF)
TB1390 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 12d 28-Feb-21 12-Mar-21 Steel Reinf,Formwork & Concrete Casting for Walls & Columns
TB1400 Slab & Beam Reif, Formwork & Concrete Casting for GF 15d 13-Mar-21 29-Mar-21 Slab & Beam Reif, Formwork & Concrete Casting for GF
Dharahara01-2.2.4 ROUGH FINISHES INTERNAL 155d 09-Dec-20 16-May-21 16-May-21, Dharahara01-2.2.4 ROUGH FINISHES INTERNA
Dharahara01-2.2.4.1 BASEMENT NO 02 (2B) 45d 09-Dec-20 24-Jan-21 24-Jan-21, Dharahara01-2.2.4.1 BASEMENT NO 02 (2B)
TB1410 Masonary Work 20d 09-Dec-20 29-Dec-20 Masonary Work
TB1420 Plastering Work 20d 14-Dec-20 03-Jan-21 Plastering Work
TB1430 Flooring Work & Threshold(Granite, Checkered Tiles) 15d 08-Jan-21 24-Jan-21 Flooring Work & Threshold(Granite, Checkered Tiles)
TB1440 Wall fin ishes & Skirtin g ( Granite) 7d 17-Jan-21 24-Jan-21 Wall fin ishes & Skirtin g ( Granite)
TB1450 Floor Screed and Water proofing at Wet Areas 15d 24-Dec-20 08-Jan-21 Floor Screed and Water proofing at Wet Areas
Dharahara01-2.2.4.2 BASEMENT NO 01 (1B) 45d 30-Jan-21 16-Mar-21 16-Mar-21, Dharahara01-2.2.4.2 BASEMENT NO 01 (1B)
TB1460 Masonary Work 20d 30-Jan-21 19-Feb-21 Masonary Work
TB1470 Plastering Work 20d 04-Feb-21 24-Feb-21 Plastering Work
TB1480 Flooring Work & Threshold(Granite, Checkered Tiles,Vitrified Flooring) 15d 01-Mar-21 16-Mar-21 Flooring Work & Threshold(Granite, Checkered Tiles,Vitrified Flooring)
TB1490 Wall fin ishes & Skirtin g (Granite) 7d 09-Mar-21 16-Mar-21 Wall fin ishes & Skirtin g (Granit e)
TB1500 Floor Screed and Water proofing at Wet Areas 15d 14-Feb-21 01-Mar-21 Floor Screed and Water proofing at Wet Areas
Dharahara01-2.2.4.3 UPPER BASEMENT (UB) 45d 24-Mar-21 08-May-21 08-May-21, Dharahara01-2.2.4.3 UPPER BASEMENT (UB)
TB1510 Masonary Work 20d 24-Mar-21 13-Apr-21 Masonary Work
TB1520 Plastering Work 20d 29-Mar-21 18-Apr-21 Plastering Work
TB1530 Flooring Work & Threshold(Granite, Checkered Tiles) 15d 23-Apr-21 08-May-21 Flooring Work & Threshold(Granite, Checkered Tiles)
TB1540 Wall fin ishes & Skirtin g ( Granite) 7d 01-May-21 08-May-21 Wall fin ishes & Skirtin g ( Granite)
TB1550 Floor Screed and Water proofing at Wet Areas 15d 08-Apr-21 23-Apr-21 Floor Screed and Water proofing at Wet Areas
Dharahara01-2.2.4.4 GROUND FLOOR (GF) 29d 16-Apr-21 16-May-21 16-May-21, Dharahara01-2.2.4.4 GROUND FLOOR (GF)
TB1560 Masonary Work 15d 16-Apr-21 01-May-21 Masonary Work
TB1570 Plastering Work 15d 18-Apr-21 03-May-21 Plastering Work
TB1580 Flooring Work & Threshold(Granite) 7d 09-May-21 16-May-21 Flooring Work & Threshold(Granite)
TB1590 Wall fin ishes & Skirtin g ( Granite) 4d 12-May-21 16-May-21 Wall fin ishes & Skirtin g ( Granite)
TB1600 Floor Screed and Water proofing at Wet Areas 10d 26-Apr-21 06-May-21 Floor Screed and Water proofing at Wet Areas
Dharahara01-2.2.4.5 ROOF FLOOR 12d 03-May-21 16-May-21 16-May-21, Dharahara01-2.2.4.5 ROOF FLOOR
TB1610 Masonary Work 7d 03-May-21 10-May-21 Masonary Work
TB1620 Plastering Work 7d 05-May-21 13-May-21 Plastering Work
TB1630 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble)7d 09-May-21 16-May-21 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio
TB1640 Wall fin ishes & Skirtin g ( Gla zed Ceramic Tile & Staturio Marble) 2d 14-May-21 16-May-21 Wall fin ishes & Skirtin g ( Gla zed Ceramic Tile & Staturio Marble
Dharahara01-2.2.5 FINAL FINISHES INTERNAL 160d 03-Jan-21 15-Jun-21 15-Jun-21, Dharahara01-2.2.5 FINAL FINISHES INT
Dharahara01-2.2.5.1 BASEMENT NO 02 (2B) 37d 03-Jan-21 10-Feb-21 10-Feb-21, Dharahara01-2.2.5.1 BASEMENT NO 02 (2B)
TB1650 Paint Work 20d 03-Jan-21 24-Jan-21 Paint Work
TB1660 Metal Works 7d 18-Jan-21 25-Jan-21 Metal Works
TB1670 Doors & Windows (Wood & Alluminium) 15d 25-Jan-21 10-Feb-21 Doors & Windows (Wood & Alluminium)
TB1680 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing)
7d 25-Jan-21 01-Feb-21 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing)
Dharahara01-2.2.5.2 BASEMENT NO 01 (1B) 37d 24-Feb-21 02-Apr-21 02-Apr-21, Dharahara01-2.2.5.2 BASEMENT NO 01 (1B)

Actual Level of Effort Critical Remaining Work Page 2 of 3 TASK filter: All Activities
Actual Work Milestone Note: All the works depends upon site condition, return of the workers from their residence, longitivity of EPIDEMIC COVID 19 and earliest issuance of drawings. © GIETC-RAMAN JV
Remaining Work summary
TRIPLE BASEMENT UNDERGROUND PARKING Classic Schedule Layout 22-Jun-20 13:02
Activity ID Activity Name Original Start Finish Remarks 2020 2021
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
TB1690 Paint Work 20d 24-Feb-21 16-Mar-21 Paint Work
TB1700 Metal Works 7d 11-Mar-21 18-Mar-21 Metal Works
TB1710 Doors & Windows (Wood & Alluminium) 15d 18-Mar-21 02-Apr-21 Doors & Windows (Wood & Alluminium)
TB1720 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing)
7d 18-Mar-21 25-Mar-21 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing)
Dharahara01-2.2.5.3 UPPER BASEMENT (UB) 37d 18-Apr-21 25-May-21 25-May-21, Dharahara01-2.2.5.3 UPPER BASEMENT (UB
TB1730 Paint Work 20d 18-Apr-21 08-May-21 Paint Work
TB1740 Metal Works 7d 03-May-21 10-May-21 Metal Works
TB1750 Doors & Windows (Wood & Alluminium) 15d 10-May-21 25-May-21 Doors & Windows (Wood & Alluminium)
TB1760 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing)
7d 10-May-21 17-May-21 Staircase finishing (Balustrades,Handrails & Marble for Tread, R
Dharahara01-2.2.5.4 GROUND FLOOR (GF) 37d 09-May-21 15-Jun-21 15-Jun-21, Dharahara01-2.2.5.4 GROUND FLOOR (
TB1770 Paint Work 20d 09-May-21 29-May-21 Paint Work
TB1780 Metal Works 7d 23-May-21 30-May-21 Metal Works
TB1790 Doors & Windows (Wood & Alluminium) 15d 30-May-21 15-Jun-21 Doors & Windows (Wood & Alluminium)
TB1800 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing)
7d 30-May-21 06-Jun-21 Staircase finishing (Balustrades,Handrails & Marble for Tr
Dharahara01-2.2.5.5 ROOF FLOOR 22d 13-May-21 03-Jun-21 03-Jun-21, Dharahara01-2.2.5.5 ROOF FLOOR
TB1810 Paint Work 7d 13-May-21 20-May-21 Paint Work
TB1820 Metal Works 5d 16-May-21 21-May-21 Metal Works
TB1830 Doors & Windows (Wood & Alluminium) 4d 30-May-21 03-Jun-21 Doors & Windows (Wood & Alluminium)
Dharahara01-2.2.6 EXTERNAL FINISHES 75d 13-Apr-21 28-Jun-21 28-Jun-21, Dharahara01-2.2.6 EXTERNAL FINIS
Dharahara01-2.2.6.1 Parking Area & Side Walk 75d 13-Apr-21 28-Jun-21 28-Jun-21, Dharahara01-2.2.6.1 Parking Area & S
TB1840 Parking Area & Side Walk, Plinth Protection Works 30d 13-Apr-21 13-May-21 Parking Area & Side Walk, Plinth Protection Works
TB1850 Asphalt Work / Pavement Reinstatement 30d 13-May-21 13-Jun-21 Asphalt Work / Pavement Reinstatement
TB1860 Interlock & Curb Stone Pavement 15d 13-Jun-21 28-Jun-21 Interlock & Curb Stone Pavement
Dharahara01-2.2.6.2 Elevation Finishing Work 75d 13-Apr-21 28-Jun-21 28-Jun-21, Dharahara01-2.2.6.2 Elevation Finish
TB1870 Pavillion Structures 60d 13-Apr-21 13-Jun-21 Pavillion Structures
TB1880 Musical Fountain 20d 15-May-21 04-Jun-21 Musical Fountain
TB1890 Landscaping works 60d 28-Apr-21 28-Jun-21 Landscaping works
TB1900 Bus Stands 15d 13-Jun-21 28-Jun-21 Bus Stands
Dharahara01-2.3 CONVEYING SYSTEM 30d 16-Apr-21 16-May-21 16-May-21, Dharahara01-2.3 CONVEYING SYSTEM

Dharahara01-2.4 MEP WORKS 168d 09-Dec-20 29-May-21 29-May-21, Dharahara01-2.4 MEP WORKS

Dharahara01-2.5 TESTING AND COMMISSIONING 7d 29-May-21 05-Jun-21 05-Jun-21, Dharahara01-2.5 TESTING AND COMMISSI
TB2330 Mechanical / HVAC Work Commissioning 7d 29-May-21 05-Jun-21 Mechanical / HVAC Work Commissioning
TB2340 Electrical Work Commissioning 7d 29-May-21 05-Jun-21 Electrical Work Commissioning
TB2350 Plumbing Work Commissioning 7d 29-May-21 05-Jun-21 Plumbing Work Commissioning
TB2360 Fire Fighting Work Commissioning 7d 29-May-21 05-Jun-21 Fire Fighting Work Commissioning
Dharahara01-2.6 CLOSE OUT AND HANDING OVER 42d 16-May-21 28-Jun-21 28-Jun-21, Dharahara01-2.6 CLOSE OUT AND H
TB2370 Final Finished Closeout 0d 28-Jun-21 Final Finished Closeout,
TB2380 Mechanical / HVAC Work Closeout 0d 05-Jun-21 Mechanical / HVAC Work Closeout,
TB2390 Electrical Work Closeout 0d 05-Jun-21 Electrical Work Closeout,
TB2400 Plumbing Work Closeout 0d 05-Jun-21 Plumbing Work Closeout,
TB2410 Fire Fighting Work Closeout 0d 05-Jun-21 Fire Fighting Work Closeout,
TB2420 Conveying System Closeout 0d 16-May-21 Conveying System Closeout,

Actual Level of Effort Critical Remaining Work Page 3 of 3 TASK filter: All Activities
Actual Work Milestone Note: All the works depends upon site condition, return of the workers from their residence, longitivity of EPIDEMIC COVID 19 and earliest issuance of drawings. © GIETC-RAMAN JV
Remaining Work summary

S-ar putea să vă placă și