Memo
Additional scope
Justification: As it's not possible to isolate and repair the flange leak in normal operation, hence it's requested to do during T/I.
Originator Comments: Job can be attended during TA. To replace the gasket only.
Scope location
Location : Area-4
Unit : 051-Mild Hydrocracker
Equipment Number : FV0242
Elevation : 1.50m apprx.
WP holder
* U-051 FV-0242 DOWNSTREAM 2ND 1/V DOWNSTREAM FLANGE HAS MINOR LEAK.
* To replace the gasket of the flange.
Justification description
Justification: As it's not possible to isolate and repair the flange leak in normal operation, hence it's requested to do during T/I.
* U-051 FV-0242 DOWNSTREAM 2ND 1/V DOWNSTREAM FLANGE HAS MINOR LEAK.
* To replace the gasket of the flange.
No. Job description / resources Job no. Lib no. Job discipline / circumstances
001 OBTAIN WORK PERMIT _0EXN A020 OPERATIONS
> Refer to SATORP Work Permit System Procedure to apply a work permit and detailed job safety analysis JSA. Conduct Tool-Box Talk
in Work location, prior to start the job.
MECHANICAL
TR-2 Static Exec. BLOCK-C/4_AYTB
SUPERVISOR
002 BREAKING OF FLANGE CONNECTION _0EXO H067 PIPING
Breaking the flange connection.
MECHANICAL
HELPER/IND
TR-2 Static Exec. BLOCK-C/4_AYTB
CLEANER/LAB
OR
PIPE FITTER TR-2 Static Exec. BLOCK-C/4_AYTB
003 INSPECTION AS OPEN CONDITION _0EXP D887 MECHANICAL
Inspection will issue recommendation if required
MECHANICAL
HELPER/IND
TR-2 Static Exec. BLOCK-C/4_AYTB
CLEANER/LAB
OR
PIPE FITTER TR-2 Static Exec. BLOCK-C/4_AYTB
PIPE
TR-2 Static Exec. BLOCK-C/4_AYTB
FABRICATOR
WELDER
TR-2 Static Exec. BLOCK-C/4_AYTB
PIPING
MECHANICAL
TR-2 Static Exec. BLOCK-C/4_AYTB
SUPERVISOR
Show jobs:
SCOPE:
24H - 0:00 A4-Scope Execution Start PAU_AA-051-S0 - MHC
24H - 0:00 U051-Scope Execution Start PAU_AA-051-S0 - M
24H - 0:00 System Isolation Complete / Ready For Mainten
24H - 0:00 A4-Scope Execution Finish PAU_AA-051-S0 - MH
24H - 0:00 U051-Scope Execution Finish PAU_AA-051-S0 - M
24H - 0:00 System Hand Over Complete / Ready For Commi
SCOPE: 2021092 - U051-FV-0242 downstream 2nd I/V downstream fla
_0EXN 24TA - 1:00 OBTAIN WORK PERMIT
_0EXO 24TA - 2:00 BREAKING OF FLANGE CONNECTION
_0EXP 24TA - 1:00 INSPECTION AS OPEN CONDITION
_0EXQ 24TA - 12:00 REPAIR IF ANY
_0EXR 24TA - 2:00 INSPECTION ON REPAIRS
_0EXS 24TA - 2:00 MAKING OF FLANGE CONNECTION
_0EXT 24TA - 1:00 CLOSE WORK PERMIT
Subtotal: 0 69 0 0 0
Total: 69 0