m VERDANT DUPLEX
AWARD COST
DESCRIPTION OF PAY ITEM OLD BUDGET REVISED OLD
OFM COST
I SUB-STRUCTURE 59,742.06 59,742.06 17,150.24
II GROUND FLOOR RC WALL 66,764.06 66,764.06 19,364.29
III SECOND FLOOR SUSPENDED SLA 47,218.49 47,218.49 16,194.05
IV SECOND FLOOR RC WALL 74,797.68 74,797.68 22,400.56
VA STEEL FRAMING WORKS 24,558.75 24,558.75 0.00
VB ROOFING & ACCESSORIES 26,576.59 27,037.14 15,144.50
VC MISCELLANEOUS CONCRETE 15,652.69 15,652.69 5,718.27
VD MASONRY FINISHES 81,254.49 81,254.49 28,058.19
VI SLAB-ON-FILL 33,482.63 33,482.63 9,916.33
VII CARPENTRY 79,421.69 87,148.52 50,193.18
VIIIA FINISHING WORKS 64,365.19 64,365.19 6,953.37
VIIIB MOVE-IN WORKS 68,909.24 68,909.24 33,606.28
233,235.99
FROM PROJECT : ORCHARD PLACE RESIDENCES
PERIOD COVERED :
CONTRACTOR :
DATE : October 26, 2020