Sunteți pe pagina 1din 7

Preparation and Benefits of Electrical Load

Schedule
5 Comments

Preparing a load schedule helps in determining the amount of


power required for an installation. This information is then used by electrical
engineers to properly size conductors, conduits and determine the proper
overload and other protection and control systems.
Let your fellow member A.N tell you about it and don’t hesitate to send us
a mail if you want to be published in the blog too!
The load schedule, which should be done at the installation design stage, is
determined through calculations. In some cases, this should be done with the
future in mind, especially if there are foreseen additional loads.

Preparing the schedule requires a list all the equipment or loads together and all
associated ratings and parameters.

Typical steps in preparing load schedule


Below are some of the typical steps that may be used when preparing the load
schedule for an industrial plant for the first time.

1. Create a list of all expected loads in the installation or facility. Specify


whether they are process or non process loads.
2. Get the electrical characteristics for each of the loads, including voltage,
current, nominal ratings, absorbed ratings, efficiency, power factors, etc
3. Classify each equipment by load duty, load criticality and switchboard
location
4. Calculate expected consumed load for each load
5. Calculate the operating, peak and design loads for each switchboard and
then for the overall installation.
A sample typical load summary | image: www.slideshare.net/wiwitpur/load-list-calculation

Calculating the operating load, peak load and design load


Once you have the information, calculate the expected consumed load, operating
load, peak and design load.

Consumed load
Consumed load: this is the amount of power equipment is expected to consume.
The active and reactive power is calculated from the formula:
This can be done according to the load duty to find out the individual and total
consumed load during intermittent, standby and continuous load.

Operating load
Operating load refers to the expected power consumption during the normal
operations and calculated from:

Peak load
This is the expected maximum load that may occur during the normal operations. It
usually lasts for a short duration, such as when standby loads are operated during
testing of the systems, changing over machines or any other scenario that puts
more stress on the installation.

Design load
The design load is what is used for electrical studies, equipment sizing and
calculated from whichever is the larger of the following
The design load is intentionally made larger to accommodate errors that may have
occurred during load estimation, or due to additional unforeseen load which may
not have been included during design phase. The design load should also be higher
to cater for future load growth. This results to over-sized equipment to take care of
the extra load. The peak load may sometimes be used for design purposes; in such
as case, the design load is calculated from DL = 1.2 X PL.

A typical summary of loads is as shown in the table below:

Benefits of a load schedule


 Gives a good estimate of electrical load during the normal and the peak
loading

 Allows the design to include provisions for additional load or at least advise
building owners of requirements to accommodate any extra load or expansion

 By understanding the load, and when peak consumption is likely to occur, it


is possible to implement an informed power management scheme that ensures
that the load is average most of the time, and eliminate cases of alternating
between very low and very high peak consumption periods.

 With proper management, it not only brings down the electricity bill charged
at the peak times, but also benefits the generating company who now can
generate less energy.

 It enables the design to cater for future loads.

 The estimate helps in selecting the collect size of conductors, conduits and
control and protection gear.

Load Schedules for different operating schedules


It may be necessary to get the operating, peak and design loads for each circuit on
the switchboard. The individual circuits are then added together to give the overall
load for the system. Different load schedules may be prepared to find out the
operating and peak as well as design loads for different classes of loads such as for
the process and non-process loads, when in standby, intermittent or continuous
operation. Further these may need to be prepared for situations when all critical
loads are operating at peak.

Several other schemes may be evaluated under different conditions to determine


the amount of power required and associated installation requirements. In
particular, determining the peak critical load may be necessary in a medical facility,
airport or any other sensitive installations. Determining this helps in selecting the
proper backup generator or UPS.

A load schedule for different operating scenarios will show when peak consumption
occurs and provide an opportunity to find out if all the high loads must operate at
this time. Analyzing the process and non process loads can help design a power
management scheme where only what is critical for the efficient operation is
powered on during peak tariffs. The loads which can be scheduled to run during
the off-peak tariff or when the total load is not as high can then be configured to do
so as long as they do not impact on the production. This helps in spreading out the
energy use and saving on the electricity bills.

Conclusion
Preparing a load schedule helps in determining the amount of power required for
an installation. The load schedule helps electrical engineers to properly size
conductors, conduits and protection systems.

In addition, it helps designers to properly size the power backup generators or


other alternative power sources.

Thanks for reading,


A.N.

S-ar putea să vă placă și