Documente Academic
Documente Profesional
Documente Cultură
METHOD STATEMENT
of
for
PACKAGE V202
CONSTRUCTION AND COMPLETION OF VIADUCT GUIDEWAY AND OTHER
ASSOCIATED WORKS FROM PERSIARAN DAGANG TO JINJANG
Contractor
Table of Contents
1) SCOPE OF WORK
1.3 Materials
Material used as approval
- Crusher Run
- Concrete Grade C32/40-20
- 12mm thick Plywood
- Timber pf 1” x 3” and 2” x 4”
- Formwork release agent (Estoform OB)
- Curing Compound (Estocure)
- Steel Wire (reinforcement ties)
- High Tensile Steel Bar
1.5 Manpower
1.5.1 All site personnel to compulsory to attend Blue Card Training for Safety Passport Assurance
1.5.2 All site personnel shall have KVRMT Grey Card Passport subject to working method and
machinery involved this is to enhance safety in workplace. In additional backhoe operator only
require Blue Card.
1.5.3 PIC to submit Participant Particular form to WPC of each site personnel together enclosed
- Identification Card / Passport Card
- Valid Cidb Card
- Work Permit for Expatriate/Foreign
1.6.1.1 PIC to ensure using construction drawing or shop drawing that WPC has submitted to PDP/SC
1.6.1.2 PIC to ensure using material that have submitted by WPC to PDP/SC prior to procurement and
usage.
1.6.1.3 PIC shall apply Permit to Work (PTW) form relevant parties before commence work.
1.6.1.4 PIC to ensure followed Traffic Management Plan implemented by WPC
1.6.1.5 PIC to ensure working area is barricade properly according to safety and health plan
1.6.2.1 WPC surveyor shall set-out the position of RCUD alignment for center line of drain at 20 meter
interval and sump location
1.6.2.2 PIC shall ensure the invert level and gradient is based on approved drawings
1.6.3.1 PIC to ensure the specified materials for reinforcement work such rebar and plywood shall be
stored at designated area for safety reason and providing timber support at bottom to avoid any
contact with ground surface and properly covered from weather as to avoid factors that can
accelerate rusting process.
1.6.3.2 All material delivered to site shall be inspected during delivery and before commencing work
and shall be properly storage to avoid any deterioration or damage.
1.6.3.3 All material shall be stacked properly for easy identification and lifting.
geotextile.
Excavation trenches to be provided temporary rigid perimeter fencing red and white painted
and to be 1.5-meter height from ground.
- providing safe access to trenches
PIC to provide sturdy temporary safe access in and out for emergency event such slope collapse
or others using steel ladders from scaffold or any and providing handrails to allow safe 3-point
contact.
- Excavation surface and bedding
Area shall be firm and even. Free from water, soft layer and loose material.
Bedding material shall used approved material and thickness
1.6.4.2 Machineries
All machine such as backhoe and lory use for excavation and transporting soil must go through
inspection by main conc.
PIC to prepare the lorry or the backhoe condition physically accordingly to the requirement
require by client that stipulated in the Inspection Machinery Checklist
Construction Joints –
1.6.10 Curing
- Applied approved curing compound to exposed surface after removal of the formwork
- Worker shall aware contact number for emergency event and pic contact number shall be
display properly at site.
- PIC to ensure worker aware of assembly point
- PIC is to ensure the emergency first aid kit is available on site
PIC to understand the Environmental execution plan and applied to the job site
- Daily inspected on the condition of machinery before work start
- Make sure the there no contamination prior to scheduled waste
- Ensure the cleanliness by creating awarenss to workers on the important of hygiene practice
- To minimize noise and dust pollution