Documente Academic
Documente Profesional
Documente Cultură
Bridges
Asset Class
Strategy
Generational Level
1 2 3 4
52
24 – 44 45 – 69 70 – 94 95 – 100
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 91
BRIDGES STRATEGY
Approval
Amendment Record
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 2 of 91
BRIDGES STRATEGY
Table of Contents
8. Risk......................................................................................................... 66
a. Enterprise Risks ....................................................................................................... 66
Identified Risks & Proposed Controls ....................................................................... 66
b. Asset Management System Target Risks ................................................................ 69
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 3 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 4 of 91
BRIDGES STRATEGY
List of Tables
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 5 of 91
BRIDGES STRATEGY
List of Figures
Figure 1 - Bridge Asset Management Framework ................................................................................ 16
Figure 2 - Metro Asset Management Document Structure .................................................................... 16
Figure 3 - Underbridge .......................................................................................................................... 17
Figure 4 - Overbridge ............................................................................................................................ 17
Figure 5 - Footbridge ............................................................................................................................. 17
Figure 6 - Subway ................................................................................................................................. 17
Figure 7 - Flyover .................................................................................................................................. 17
Figure 8 - Bridge Deck ........................................................................................................................... 18
Figure 9 - Girder .................................................................................................................................... 18
Figure 10 - Pier ...................................................................................................................................... 18
Figure 11 - Wing Wall ............................................................................................................................ 18
Figure 12 - Bearings .............................................................................................................................. 18
Figure 13 - Abutment ............................................................................................................................. 18
Figure 14 - Paint .................................................................................................................................... 19
Figure 15 - Crash Beam ........................................................................................................................ 19
Figure 16 - Functional Block Diagram ................................................................................................... 20
Figure 17 - Maintenance Responsibility Owner .................................................................................... 23
Figure 18 - MTM Bridge Types - Detailed ............................................................................................. 23
Figure 19 - MTM Bridge Types - Simplified ........................................................................................... 24
Figure 20 - Bridge Type by Network Group........................................................................................... 25
Figure 21 - Substructure Type by Group ............................................................................................... 27
Figure 22 - Superstructure Type by Group ............................................................................................ 27
Figure 23 - Ellipse Asset Hierarchy ....................................................................................................... 28
Figure 24 - Structures & Facilities Asset Conditions ............................................................................. 42
Figure 25 - Bridges Asset Condition Index Summary - Network Wide ................................................. 43
Figure 26 - Average ACI Degradation ................................................................................................... 44
Figure 27 - Bridges Asset Condition Index - Network Group ................................................................ 45
Figure 28 - ESCi Average by Component ............................................................................................. 46
Figure 29 - Napier St Bridge Strikes per Year ....................................................................................... 50
Figure 30 - ACI, Hi & POF v Time ......................................................................................................... 51
Figure 31 - Tonnage Criticality Distribution by Rail Group .................................................................... 52
Figure 32 - Average Bridge ACI by Year ............................................................................................... 55
Figure 33 - Bridge Maintenance Expenditure ........................................................................................ 56
Figure 34 - Bridge Renewals Expenditure ............................................................................................. 57
Figure 35 - Structures & Facilities Retrospective Yearly Spend ........................................................... 58
Figure 36 - Risk Profile over Time ......................................................................................................... 72
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 6 of 91
BRIDGES STRATEGY
1. Executive Summary
Asset Class Bridges
Generational
2
Level
Summary of Assess all bridges individually by applying life cycle cost
Strategy modelling, choosing a renewals approach that constitutes
the best value for money
Complete life cycle cost modelling for all bridge assets on
the network
Where superstructure renewal is recommended,
consideration is to be given to improvements in
clearances and track quality (eg. increased ballast depth,
road clearance and overhead heights)
Gradual and continued installation of secondary fall
protection on crash beams lacking such a prevention
system
In the medium term, improvements in bridge condition
data are to be sought through the use of load capacity
assessments on critical bridges
Business Impact S&F account for 1.2% of Infrastructure PWMs.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 7 of 91
BRIDGES STRATEGY
Percent Life Zero (as per valuation in June 2015). Approximately 10% of
Expired bridges are nominally life expired, as they are over 100 years
old, however these bridges have been life extended through
maintenance and renewals works and are still safe for
operation.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 8 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 9 of 91
BRIDGES STRATEGY
2. Introduction
Metro commenced its franchisee lease in November 2009. One of its key
commitments was to achieve PAS 55 (Publicly Available Specification PAS 55 2008)
accreditation by December 31st 2013. In order to achieve this goal, alignment
between the asset management policy, strategy and objectives was required to
ensure the ‘on ground’ completion of tasks could be readily achievable. This
accreditation was achieved and asset class strategies proved to be the conduit to
achieve this aim.
Asset Class Strategies (ACS’s) encompass assets of high, medium and low network
criticality. They guide prioritisation of renewal works and aid in the optimisation of
maintenance works to ensure assets perform to the required level.
The objective of this ACS is to set a strategic approach for the maintenance and
renewal of bridge assets, in order to optimise performance as a whole. It provides a
justified and evidence-based strategy that is used to forecast volumes, intervention
type and associated costs considered necessary to maintain the asset in the same
condition or better than was received at the start of the franchise.
This document sets out:
The types and volumes of Bridge assets on the network
The status of these assets in terms of their current and historic performance and
their criticality
The chosen approach to managing the specific asset types including the planning
of work volumes to deliver the business objectives and levels of service for the
lowest whole life cost
The information requirements to support current and future decision making and
plans for their development.
Upgrades to bridges are funded through capital expenditure provided by the state and
maintained by Infrastructure Delivery.
The following strategy outlines the optimum M&R approach based on current
knowledge of the asset, however it is recognised that delivering this approach is
constrained due to resourcing and other factors detailed within this document.
a. Note on Purpose
This document does not contain detailed notes to explain the purpose of each
section. For this explanation, please see the Asset Class Strategy, L1-AMS-PLA-001.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 10 of 91
BRIDGES STRATEGY
b. Generational Level
This issue of the Bridges ACS was assessed as a 2nd Generation Asset Class
Strategy, as per the guidelines contained in the Asset Management Strategy (L1-
AMS-PLA-001).
Information
Systems & Data 6 2 2 2
Quality
Accuracy of
Condition
Assessments & 3 2 1
Fault/Defect
History
Level of Service
2 2
(LoS) Definition
Knowledge of
5 2 2 1
Criticality
Depth of Risk
3 2 1
Assessment
Group Analysis
3 2 1
Life Cycle
6 2 2 2
Modelling
Planning Period 2 2
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 11 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 12 of 91
BRIDGES STRATEGY
d. Definitions
Definition Description
Bridges, properties, buildings, vehicles and other items
that have a distinct value to the organisation. Inclusive of
Asset
any software code that is critical to the delivery of the
function of the asset
An ACS Generation is a classification assigned by good
asset management practice that identifies the maturity of
an asset class strategy. Early Generation strategies (e.g.
Generation 1) are immature and typically reflect a strategy
Asset Class that is guided by non-rigorous or incomplete asset
Strategy condition and performance data. Later Generation
strategies (e.g. 2 to 5) are improvements on earlier
Generation Generations as asset data is fed back in to the strategy.
Generation 1 strategies are integral in guiding asset
managers in identifying gaps in current asset management
practice.
Head of Network Asset Management or their delegated
Asset Custodian
representative
A list of assets that are to be managed and
Asset Register
maintained
The status of an element when compared to as new
Condition condition due to weathering and wear and tear items such
as corrosion, shrinkage
Horizontal structural member protecting a bridge from the
Crash Beams
impact of vehicles
MTM’s chosen enterprise resource planning system for
Ellipse managing infrastructure maintenance scheduling, fault
recording, finance reporting and asset database.
Flyover Bridge that carries railway traffic over a railway line
Footbridge A bridge that carries pedestrians over the railway line
Area bounded by Up ends of North Melbourne, Richmond
Inner Suburban Area
and Jolimont station platforms.
A surveillance task to determine the condition of an
asset. The data collected may be qualitative and
quantitative dependant on the level of inspection. When
performed as a scheduled maintenance task a condition
Inspection
rating is required to provide a record of the structures
condition and to identify whether the asset should continue
to perform satisfactorily until the next scheduled
inspection
The joint MTM and PTV panel that conducts monthly
Maintenance and
meetings to discuss and review MTM’s maintenance and
Renewal Review
review performance including claims. The M&RRG is also
Group
a forum for proposing and approving changes to the AMP
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 13 of 91
BRIDGES STRATEGY
Definition Description
Section closure granting sole occupancy of the line/s for
Occupation maintenance or construction purposes and requiring
suspension of train services.
Overbridge A bridge that carries road traffic over the railway line
Computer based GIS detailing Victorian train and tram
infrastructure assets and condition. Used for displaying
PASS Assets
and managing DOT controlled assets and linked to
Ellipse for transfer of asset configuration details.
Preventive, surveillance or event-initiated maintenance
Preventive
performed at predetermined intervals. The scope and
Maintenance
frequency of the scheduled task is predetermined
Work performed in response to a defect or deficiency in
an asset that requires an action outside of those covered
Reactive
by scheduled maintenance. The scope and frequency
Maintenance
varies depending on the nature of the defects or
deficiencies identified as requiring action
The right of way set aside for the construction, operation
Reserve
and maintenance access of the operating railway
A quantitative based assessment to determine the strength
and suitability of an asset in its current state and condition,
Structural
as defined by inspection. Assumptions and qualitative
Assessment
assessment may be included by the structural engineer
where data is insufficient
A subway carries pedestrian traffic under the railway
Subway
track
Technical Maintenance Plan sets out the preventive
TMP maintenance policy for assets in regards to the inspection,
assessment and maintenance tasks
A tabulation of the scheduled maintenance requirements
TMP Schedule for each asset class or system. The TMP Schedule is an
attachment to this document
A bridge that carries rail traffic over an obstacle,
Underbridge
waterway, road, railway or path
A specific task to be performed by either an Inspector or
Work Order
Foreman generated from Ellipse.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 14 of 91
BRIDGES STRATEGY
e. Relevant Standards
A number of specifications and procedures have been published that relate to various
aspects of bridge maintenance and renewal activities. A summary table of the various
components of track and their related specifications is available on request from the
asset development team.
g. Related Documents
The Bridges ACS sets the high level strategy for the maintenance and renewals of
Bridges across the network. Renewals are nominated through the ACS then fed into
the Renewals Prioritisation Tool (RPT) for prioritisation of funding allocation. Bridge
maintenance activities are carried out in accordance with the Structures TMP, as well
as associated standards, procedures and specifications, as detailed in Figure 1:
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 15 of 91
BRIDGES STRATEGY
This Asset Class Strategy forms part of a suite of related Metro asset management
documents as detailed in Figure 2:
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 16 of 91
BRIDGES STRATEGY
Figure 3 - Underbridge
Figure 4 - Overbridge
Figure 5 - Footbridge
Figure 6 - Subway
Figure 7 - Flyover
Note: tunnels are covered separately in a dedicated ACS and therefore are not
included within the scope of this strategy.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 17 of 91
BRIDGES STRATEGY
Beams or compound
Girders structures used to carry load
between substructures
Figure 9 - Girder
Figure 10 - Pier
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 18 of 91
BRIDGES STRATEGY
Figure 14 - Paint
Horizontal structural member
positioned at the face of a
vulnerable bridge, providing
Crash Beams protection from the impact of
vehicles or their loads, which
exceed the structure’s Figure 15 - Crash Beam
vertical clearance.
Each of these components is assessed for condition when bridge inspections take
place. For an understanding of the quality of these components, please refer to
Section 5a, Asset Criticality.
There are additional components detailed in asset hierarchy; however the
components listed in Table 2 are typically the key drivers of bridge condition.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 19 of 91
BRIDGES STRATEGY
Currently, work-orders for faults are managed external to Ellipse using MS Excel
work-order register managed by Structures and Facilities group. NAM and
Infrastructure are working with AMS to develop Ellipse to capture scheduled
inspections and maintenance repair tasks.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 20 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 21 of 91
BRIDGES STRATEGY
External Interfaces
In addition to internal interfaces, MTM has the franchise obligation to interface with a
number of external stakeholders. These are:
Public Transport Victoria (PTV)
VicTrack
Transport Safety Victoria (TSV)
Vic Roads
Local Government Authorities
V/line
Yarra Trams
ARTC
Other ARO’s
Pacific National
Queensland Rail
Tourist & Heritage Rail Operators
These interfaces are managed in co-operation with business units within MTM. There
are regular Audits and Compliance meetings to manage this interface.
d. Asset Base
Currently there are a total of 650 bridges located around the network. However
MTM’s responsibility for the maintenance of bridges does not extend across the entire
asset base. Figure 17 shows the breakdown of bridge assets network wide, by
responsible authority:
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 22 of 91
BRIDGES STRATEGY
As shown, MTM has the responsibility to maintain a total of 521 bridges across the
network and this number will form the basis of analysis for this asset class strategy.
These MTM managed bridges can then be broken down by bridge type:
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 23 of 91
BRIDGES STRATEGY
Figure 18 (above) shows that the majority bridge type across the network is the
Underbridge (rail over road, rail over waterway, service under rail), with a total of 247
bridges. The other simplified bridge types and their totals are listed in Figure 19:
Bridges listed as ‘other’ are non-typical bridges that are maintained by MTM.
Examples of such bridges are station concourses and passenger access ramps.
Figure 20 provides a breakdown of different bridge types by group, with the Burnley
group showing the greatest dependency on the quality of bridge assets:
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 24 of 91
BRIDGES STRATEGY
The 521 bridges can be further broken down by Substructure and Superstructure
type, as seen in Table 4:
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 25 of 91
BRIDGES STRATEGY
From this table, we can see that Mild Steel is easily the most represented
superstructure type, with use in over 50% of all bridges. Substructure types are a bit
more varied, with brick, concrete and reinforced concrete being the most popularly
used on the network.
Note that 105 bridges are listed in this table as N/A for substructure and
superstructure type. These assets are subways and therefore do not have separate
substructure and superstructure components.
The table also shows that 13 bridges have an unknown component. This is
something to be rectified and it represents an improvement area in asset knowledge.
Substructure and superstructure type can then be plotted across the different network
groups in Figure 21 and in Figure 22:
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 26 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 27 of 91
BRIDGES STRATEGY
In addition, the components listed in Table 5 feed into the bridges class in our asset
management system. The hierarchy is a flat structure, as these components all sit at
the same level and are linked up to their parent asset.
Table 5 - Bridge Asset Components
Comp Comp
Component Component
No. No.
S001 Abutment S045 Paintwork / Protection System
S002 Arch S047 Pier
S003 Arch Barrel / Voussoir Stones S048 Pile Waling
S004 Arch Key Stone S057 Railing/Barrier/Parapet
S005 Batter Protection S060 Ramp Wall
S006 Beam S061 Retaining Wall
S007 Bearing S062 Road
S017 Box Culvert S066 Services
S035 Box Girder S067 Signage
S008 Bracing S068 Sill Beam
S010 CB Fall Arrest System S069 Spandrel Wall
S011 CB Support S072 Stringer
S012 Cladding S076 Transom
S013 Columns or Piles S077 Transverse Beam
S015 Corbel S078 Trestle Bracing
S036 Cross Girder S079 Truss Bottom Chord
S024 Deck S080 Truss Bracing
S025 Diaphragm S081 Truss Diagonal Member
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 28 of 91
BRIDGES STRATEGY
Comp Comp
Component Component
No. No.
S030 Footbridge Roof Sheeting S082 Truss End Post
S031 Footbridge Stair Treads S083 Truss Portal
S032 Footbridge Veranda Structure S084 Truss Top Chord
S033 Footing S085 Truss Vertical Member
S039 Guard Rail S090 Walkway/Refuge
S040 Headstock / Cross Head S089 Walkway
S041 Impost S092 Waterway
S044 Kerb S093 Wearing Surface
S037 Main/Top Girder S094 Wing Wall
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 29 of 91
BRIDGES STRATEGY
Provide bridge
assets in a
To reduce condition that
Preventable
preventable does not hinder
passenger
passenger track
injuries per 2.7
injuries due to 2.0 2.0 maintenance,
million (Jun 2014)
asset failures or therefore aiding
passenger
lack of ‘fit for quality of track
journeys
purpose’ assets geometry and
comfort of
passenger ride
Train services
arriving within
To reduce the
4’59’ of the 92%
number of trains 95% Target of zero
daily timetable (Dec 2013) 95%
delayed beyond (Network train delays for
measured at 93% (all lines)
4’59” due to asset average) bridge assets
prescribed (Jun 2014)
failures
monitoring
points
To reduce the
Delivery of Target of zero
number of trains
train services 98.5% train
cancelled due to 99.5% 99.5%
as per daily (Jun 2014) cancellations for
asset failures
timetable bridge assets
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 30 of 91
BRIDGES STRATEGY
In
Asset Strategic Guidance Bridges
Franchise
Management Measure Target Target ACS
Strategic
Objective 2017 Dec 2024 Target
Targets
Maintenance
and Renewal
escrow
To deliver the
invoiced and
Infrastructure $1.877 billion LY7 – Deliver
accrued
Annual Works over the -5% 60% of the
(2017) -
Plan within period of the +0% Annual Works
allocated funding franchise Plan
Deviation of
actual spend
from agreed
budget (2024)
To deliver the
Rolling Stock
Deviation of
Preventative
actual spend
Maintenance +5% +5%
from agreed N/A
Budget and +0% +0%
budget
Reliability Growth
Plan within
allocated funding
4.5 Threshold
(Jun 2013) 4.2 Threshold 3.8
Lost Time
Infra (Infra) (Infra)
Injury N/A
Frequency
To undertake 3 Threshold Threshold 2.0
Rate (LTIFR)
asset (Jun 2013) 2.8 (Roll Stock)
management Roll Stock (Roll Stock)
activities in a
manner that 41 Threshold
increases worker (Jun 2013) 39 Threshold 35
safety. Lost Time Infra (Infra) (Infra)
Injury Severity N/A
Rate (LTISR) 90 Threshold Threshold 25
(Jun 2013) 45 (Roll Stock)
Roll Stock (Roll Stock)
Noise and
1.699 Target 17 no. in
To undertake vibration
by Dec 2013 2015
asset complaints
(5% decrease 1.384 0.966 (5% reduction
management from public
on 2012 from 2014 figure
activities in a per million
figure) of 18)
manner that passengers
reduces
environmental Soil/water 17 11 5
damage and non- contamination by Dec 2013
compliances (reported (10% 11 5 0
spills) decrease on
2012 figure)
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 31 of 91
BRIDGES STRATEGY
In
Asset Strategic Guidance Bridges
Franchise
Management Measure Target Target ACS
Strategic
Objective 2017 Dec 2024 Target
Targets
Achieve
Certification
certification to
to, and
PAS55 (Dec
maintenance
2013)
of, an
To gain and Maintain PAS
internationally Maintain ISO Maintain ISO Develop asset
maintain 55
recognised 55001 55001 lifecycle
certification to Certification
Asset Certification Certification modelling
internationally (Nov 2016)
Management
recognised Asset Achieve ISO
Standard or
Management 55001
Specification
Standard or Certification
Specification (Nov 2016)
Close out
Asset
improvement
Management 70% 75%
actions through
Maturity (PAS 55) (GFMAM)
completion of
ACS revision 2
To return the
assets at
completion of
franchise in a Pass Pass
Assessment Bridges asset
condition no independent independent
of asset class pass
worse than in - audit of asset audit of asset
condition independent
which they were condition condition
audit
accepted at start
of franchise
allowing for fair
wear and tear
b. Group Requirements
A number of key route sections have been highlighted as high criticality due to the
impact if they are unavailable for use as a result of infrastructure failure. The high
critical sections have been summarised in Table 6.
Table 6 - Critical Line Sections
Route
Group Route Section Impact
Strategy ID
No access to FSS for the
Burnley to Box Hill –
Burnley BYBOX majority of the Burnley
More than one track
Group.
Track 1 Jolimont to
Clifton Hill FSS01 No Alternative FSS platform
FSS
No effective access to FSS
Clifton Hill JLCHL Jolimont to Clifton Hill
for CHL group
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 32 of 91
BRIDGES STRATEGY
Route
Group Route Section Impact
Strategy ID
Caulfield Local RMJ No effective access to FSS
Dandenong CLCFD
to Caulfield for DNG group
Measure of fault severity per = #P1 faults for LY(x) / #P1 faults for LY(x-1)
asset type by comparing number = #P2 faults for LY(x) / #P2 faults for LY(x-1)
of faults year-on-year = #(P1+P2) faults for LY(x) / #(P1+P2) faults for LY(x-1)
% Completed maintenance
=# inspections completed / # inspections scheduled
inspections per annum
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 33 of 91
BRIDGES STRATEGY
a. Asset Criticality
Through regular visual inspections conducted across the network on all bridge
assets, an Asset Condition Index (ACI) is calculated for all bridges. This index value,
combined with component condition assessment, forms the basis for ranking the
critical bridge assets by condition and also promotes MTM’s ability to trend asset
condition over time.
The Asset Condition Index (ACI) is an indexed score that enables each asset to be
ranked in order from very poor to very good condition. The score has been derived
using the following equation:
4
𝐹𝐸
𝐴𝐶𝐼 = ∑ 𝐸𝑆𝐶𝑖 × 𝑆𝑖 × 𝑀𝑖
𝑛
𝑖=1
Where:
A summary of element condition index is included in Section 5a, Asset Criticality. For
further detail on how this index is compiled, as well as the other factors in the ACI
equation, see externally managed bridge ACI evaluation database.
The ACI is used as a tool for effective asset management but not necessarily used as
a ranking tool for asset renewal. A low ACI, combined with a bridge’s individual
component assessment, should be used to identify bridges requiring some level of
renewal to the whole bridge or part of a bridge.
The Asset Condition Index is broken into condition classes to give the score a
tangible meaning. The classes and their descriptions are detailed in Table 8:
Table 8 - Asset Condition Index
Condition
Rating ACI Condition Description
State
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 34 of 91
BRIDGES STRATEGY
Condition
Rating ACI Condition Description
State
The main factor influencing the ACI of a bridge is the Elemental Structural Condition
Index (ESCi), which is calculated for the individual components of the bridge using
the following formula:
Where:
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 35 of 91
BRIDGES STRATEGY
b. Network Criticality
Early in 2015, the Network Strategy team developed a route section criticality ranking.
This ranking was a detailed iteration of the strategic route sections (SRS) developed
as a part of the Renewals Prioritisation Tool version 1(RPT1). This ranking defines
locations that represent the highest risk to the performance of the network if failure
occurs.
The criticality ranking is presented with the intent to be used as a practical guide for
day to day maintenance decision making when prioritising fault rectification. Route
sections across the network have been assessed and the impact of disruption to
these sections has been ranked 0 - 4 with the consequence detailed in Table 9 (Note:
TPH = trains per hour).
Table 9 - Route Criticality Rankings
Rating Impact
0 No Impact
1 Single route blocked less than 4 TPH or restricted routing
2 Single route blocked greater than 4 TPH includes loop
3 No effective service some routes
4 No effective service entire/majority of group
Table 10 outlines the high critical route sections for each of the five rail groups. These
route criticalities should be considered when prioritising maintenance activities.
Criticality ranking for all route sections across the network is available on request
from the asset development team.
Table 10 - High Critical Route Sections
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 36 of 91
BRIDGES STRATEGY
c. Combined Criticality
Using ACI values, combined with criticality of network location; and by conducting a
review of the condition and criticality of defects on the worst performing bridge assets,
a list of the most critical bridges on the network has been compiled. Table 11 shows a
list of the 20 most critical bridges on the network based on these criteria:
Timber Deck
Elizabeth St Flinders St to
Significant deterioration to top flange of
Rail Bridge Hurstbridge
main girders
Timber Deck
Johnson St Flinders St to
Deterioration of main girders
Rail Bridge Hurstbridge
Leaning and deformation of Abutment 1
Bearing sill timbers in poor condition
Aitken Creek Broadmeadows Timber deck in poor condition
Rail Bridge to Donnybrook Significant deterioration with section loss to
top flange
Stafford St Rail Flinders St to Significant movement and deformation of
Bridge Hurstbridge substructure
Gipps St Rail Flinders St to
Superstructure in poor condition
Bridge Hurstbridge
General
Caulfield to
Motors Bridge redundant and no longer used
Pakenham
Footbridge
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 37 of 91
BRIDGES STRATEGY
North
Racecourse
Melbourne - Timber Deck
Rd Rail Bridge
Upfield
Timber deck in poor condition
Malcolm Creek Broadmeadows
Deterioration and section loss to top flange
Rail Bridge to Donnybrook
of main girders
Timber deck in poor condition
Blackburn Rd Burnley to Glen
– Up Track Waverley Deterioration and section loss to top flange
of main girders
North
Phoenix St Timber Deck in moderate to poor condition
Melbourne to
Footbridge Handrails and guardrails in poor condition
Upfield
Westgarth Timber Deck in poor condition
Flinders St to
Station
Hurstbridge Section loss and corrosion to top flange of
Footbridge main girders
Yarra River
Richmond to
Bridge, Bridge bearings in poor condition
South Yarra
Cremorne
Maribyrnong North
River Truss Melbourne to Cross girders in poor condition
Bridge Footscray
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 38 of 91
BRIDGES STRATEGY
These bridges are considered to be the highest priority on the network and have
therefore been subjected to a more comprehensive analysis of the different options
available. This analysis includes:
Establishment of the structural condition of each structure (ACI)
Determination of the asset risk profile, based on observed defects and the
probability of failure versus the consequence of the event (example provided in
Appendix B, otherwise found in detail in Sterling Group Bridge Report: J15-
313_RPT_V0.1 Life Cycle Cost Analysis)
Assessment of alternative engineering options for the remediation of each
structure (found in Sterling Group Bridge Report: J15-313_RPT_V0.1 Life Cycle
Cost Analysis)
Completion of a Life Cycle Cost analysis for each of these options (Section 9,
Planning and Costing Scenarios)
Recommendations based on the outcomes of the analysis (Section 11c, Critical
Bridges Strategy & Tactics)
In addition to the 20 locations listed above, there is a selection of examples of bridge
assets on the network for which the maintenance and/or renewal of the structure is on
such a scale that they require large scale investment and input from the PTV. These
assets are as follows:
Table 12 - Major Project Bridges
Name Line Section Major Defects / Issues
U-frame struts in poor condition
Paint protection system requires
Old Viaduct Inner City reinstatement
Girders and deck members identified
to be nearing the end of fatigue life
Significant structural defects
Degraves & Elizabeth
Ground water penetration
St Subways, Inner City
Flinders St Station Significant cracking in the subway
walls
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 39 of 91
BRIDGES STRATEGY
Therefore, each of the assets listed above in Table 12 require a dedicated strategy.
These strategies are defined in Section 11c, Critical Bridges Strategy & Tactics.
In future, MTM plan to produce a criticality list for all bridge assets on the network.
This represents a key improvement and is recommended to assess each bridge
regarding consequence of failure, network location, bridge length, condition, etc.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 40 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 41 of 91
BRIDGES STRATEGY
As this summary shows, as of June 2015, there are zero life expired bridges on the
network. While approximately 10% of bridges are nominally life expired, as they are
over 100 years old, these bridges have been life extended through maintenance and
renewals works, and are still safe for operation.
As an average across the network, remaining bridge life in years is 52. The Stony
Point line is in the best condition, as it has just one bridge which is new; while the
Newport to Williamstown line has the lowest average quality of bridge asset. With the
exception of the Stony Point line, bridge assets across the network have an average
remaining life of between 31 and 75 years.
b. Asset Condition
Figure 24 provides us with an initial understanding of bridge condition in comparison
with other Structures and Facilities assets:
In comparison with the other main assets managed by the S&F department, bridges
are in relatively good condition, with culvert, retaining walls and overhead structures
showing the lowest levels of overall condition. This goes some way to explaining
recent trends in reduced budgets for bridge maintenance and renewal. For further
detail on maintenance and renewals expenditure for bridges, see Sections 6g and 6h.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 42 of 91
BRIDGES STRATEGY
With an understanding of bridge condition against only key S&F asset classes,
condition of bridges can now be put under further scrutiny. Through calculating a
value for ACI (as detailed in Section 5a) and by conducting a frequency based
inspection regime of bridge assets, MTM has a clear picture of the condition of
bridges across the network.
Figure 25 summarises asset condition index of bridge assets network wide from, as
per the condition descriptions in Table 8.
The overwhelming majority of bridge assets are in a fair condition, while almost 20%
of bridges are currently in good condition. Just 1% of bridges listed as being in poor
condition and zero bridges on the network receiving a very poor index. The bridges of
poor condition are listed in Section 5a, addressing asset criticality and again in
Section 11, which covers the strategy to manage these critical bridges.
Using these values of ACI, it’s possible to show a depiction of expected average
degradation of bridges for their nominal 100 year life against ACI. As can be seen in
Figure 26, Bridge assets experience fast and slow exponential decay. Slow decay is
experienced in the earlier stages of asset life where as rapid deterioration occurs later
in the asset’s life. This is also called a double exponential decay model (y= abx + cdx).
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 43 of 91
BRIDGES STRATEGY
A more detailed understanding of bridge structural condition across the network, the
following shows the percentage of ACI condition by network group (Figure 27):
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 44 of 91
BRIDGES STRATEGY
From this graph it is observed that only the Clifton Hill and Dandenong groups have
bridges in poor condition. However, overall asset quality of bridges is actually the
lowest on the Burnley group. Bridges on the Inner City group are a stand out for being
of the highest quality.
Table 14 provides further breakdown of bridge condition data:
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 45 of 91
BRIDGES STRATEGY
The ESCi average for each component is also shown in the following graphs by
network group:
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 47 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 48 of 91
BRIDGES STRATEGY
Currently crash beams are not assessed as part of frequency based inspections of
bridge assets. This is an improvement area that is to be addressed in the short term.
Dedicated reports have been compiled on crash beam renewal criticality though and
a summary of the ten most critical locations is shown below in Table 15. These crash
beams are to be listed for renewal and prioritised through the Renewals Prioritisation
Tool. For additional information on crash beams strategy, see Section 11.
Table 15 - Crash Beam Renewal Prioritisation
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 49 of 91
BRIDGES STRATEGY
A number of measures have been used to assess and rank criticality of the crash
beams. These include: the presence of secondary supports used to prevent collapse;
structural compliance to the VROIGS standard; the robustness of the substructure;
whether the beams span the entire road; and the number of bridge/crash beam
strikes on record. A summary of the most commonly struck bridges on the network
over the past nine years is shown in Table 16:
Table 16 - Most Frequently Struck Bridges/Crash Beams
Number of Strikes
Ranking Bridge Name
over 9 Years
1 Napier St, Footscray 57
2 Racecourse Rd, Newmarket 39
3 Warrigal Rd, Holmesglen 32
4 Merri Parade, Merri 31
5 Warrandyte/Bedford Road, Ringwood 25
6 Racecourse Rd, Flemington Bridge 23
7 John St, Lilydale 19
8 Spencer St & Flinders St, Melbourne 18
9 New St, Ringwood 17
10 Wantirna Rd, Ringwood 16
11 Hull Rd, Mooroolbark 14
12 Alexandra Avenue, South Yarra 13
13 Mt Alexander Rd, Essendon 13
14 Victoria St Middle, Footscray 10
Napier St Bridge in Footscray is the most commonly struck bridge on the network. In
Oct 2010 the road on the west approach was re-aligned. Prior to this re-alignment the
bridge strike rate was 3.33 per year, following the re-alignment the strike rate
increased to 9.25 per year.
12
10
4
Road
2
Alignment
changed
0
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 50 of 91
BRIDGES STRATEGY
c. Asset Health
The bridge class uses Asset Condition Index for determining maintenance and
renewal intervention, which is consistent with other Structures Management Systems
and can is electronically maintained by inspection management (internal or external).
Figure 30 shows a simplified representation of the relationship between Asset
Condition Index, Asset Health and the Probability of Failure over Time.
The representation demonstrates that as bridge assets slowly degrade over time
(decreasing ACI), the probability of failure increases exponentially. However, a close
understanding of network wide bridge asset health is something that to date has not
been achieved and constitutes a key improvement action.
MTM have a need to not only prioritise the renewal and/or maintenance of assets
based on condition, but to include key business factors such as network criticality and
tonnage condition, in order to have a more holistic approach to works prioritisation.
Such an approach would be managed via an Asset Health Index tool, with an
objective to prioritise maintenance and renewals activities, providing MTM with a best
for network approach that ensures infrastructure availability is maximised.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 51 of 91
BRIDGES STRATEGY
d. Asset Utilisation
Figure 31 details the tonnage distribution by rail group. It can be seen that the inner
rail suburban area has the highest tonnages with 66% being greater that 10MGT per
annum.
Asset utilisation is incorporated into the prioritisation of renewals through the RPT2.
Renewals with a high tonnage are weighted higher when optimisation is carried out.
Specific tonnage distributions across the network can be viewed in Error! Reference
ource not found..
e. Failure History
Throughout the Metro franchise there have been no reports of full functional failure of
bridge assets. A full functional failure would result from the collapse of an overbridge,
underbridge, footbridge, subway or flyover.
While not constituting a full functional failure, the restricted access to specific bridge
assets prohibits effective inspection, preventative and reactive maintenance of
service critical assets. This represents a risk to Metro’s capability to maintain reliable
train operations and highlights a failure of these assets to provide safe access to
maintenance staff.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 52 of 91
BRIDGES STRATEGY
For component specific failures, Structures and Facilities manages its work orders
through a spread sheet which breaks down work orders by structure type, line,
maintenance or renewal. The defects are reported in terms of P1 (highest priority),
P2, P3, P4 and P5 (lowest priority).
A monthly report details the status of work orders, which is the responsibility of the
Structures Maintenance Engineer. Currently, this report is managed through a spread
sheet and therefore work orders are not fully transparent to the business and are
difficult to track.
In addition, MTM are moving to implement a changed condition rating as part of the
latest revision of the Structures & Facilities Technical Maintenance Plan, which is
summarised in Table 17:
With the future implementation of these amended condition rating levels, it’s
important to also implement amendments to both the Ellipse database and the
externally managed defect reports. Both must align with the new ratings.
Improvement Action: Ensure that both the external bridge inspection database
and Ellipse condition information is amended to align with future condition rating
definitions.
f. Performance History
Bridges have performed well over the length of the MTM franchise with zero PWMs
having been recorded against all bridge assets. However, the nature of bridge assets
is that failures are rare, but the consequences are enormous for safety, operations,
cost, etc. For this reason, it’s important to have clearly defined strategy for dealing
with the most critical bridges on the network. The strategy for bridge assets as a
whole and for the most critical bridges is detailed in Section 11c, Critical Bridges
Strategy & Tactics.
For an overall understanding of bridge condition over time, we can plot the average
ACI value for all bridges on the network over recent years, in order to gain a broad
understanding of the trend of bridge condition. The graph in Figure 32 shows that
since 2012, average bridge ACI has reduced each year, meaning that degradation is
affecting bridge assets at a faster rate than MTM is improving bridge condition
through maintenance and renewals. The year 2012 is chosen as the starting point, as
prior to 2012, ACI was not calculated with the same metrics.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 54 of 91
BRIDGES STRATEGY
In the long term, a trend in ACI like that shown above is not sustainable. The strategy
developed for this ACS attempts to show the path towards arresting the negative
trend in ACI.
g. Maintenance Expenditure
Table 18 shows the breakdown of routine maintenance costs over the last three
franchise years. The total listed on the right of the table is the total over the six
completed years of the franchise.
Table 18 - Bridge Maintenance Expenditure
ROUTINE MAINTENANCE
Inspections $2,487,990 $2,254,720 $1,370,767 $11,973,041
Routine Maintenance
-$32,856 $2,280 $1,476,295
driven Renewals
Bridge Maintenance $1,024,257 $358,118 $710,759 $3,914,960
Sub-total $3,479,392 $2,615,118 $2,081,526 $17,364,296
As can be seen in this table and in Figure 33 (below), spend on maintenance has
decreased over time. This can be best explained by MTMs ‘best for network’
approach, which has led to funds being prioritised towards other Structures &
Facilities assets and for other Infrastructure disciplines.
While the trend of the maintenance spend of bridges is relatively accurate, the total
spend on bridge maintenance (show above) is actually inflated. This is because
inspection costs are currently captured as one large project, rather than separating
out individual inspections into bridges, overhead structures, culverts, etc. A key
improvement action for the next financial year is to ensure that inspection costs can
be attributed to individual assets.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 55 of 91
BRIDGES STRATEGY
Figure 34 shows bridge renewals expenditure, which has followed quite a different
trajectory over the length of the franchise:
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 56 of 91
BRIDGES STRATEGY
Year four saw a large rise in the renewals budget, as maintenance expenditure was
reducing. The more recent trend is to reduced renewals budget, an outcome of MTMs
‘best for network’ approach, which has led to funds being prioritised towards other
Structures & Facilities assets and for other Infrastructure disciplines. Figure 24 in
Section 6b, Asset Condition shows a summary of condition for each of the main asset
classes within Structures & Facilities and shows provides some indication of why
funds have been prioritised away from bridges in recent years. The reduction in
bridge spend is unsurprisingly matched by the reduction in average bridge ACI shown
by Figure 32 in Section 6f, Performance History.
As an overall picture of Structures & Facilities spend, the following retrospective
spend graph (Figure 35) shows the percentage and total spend on planned renewals,
reactive works, routine maintenance and inspections.
This graph shows that as a department, Structures & Facilities has shifted in a
positive direction towards planned renewals. As a percentage of the department
budget, reactive works has reduced by around half over four years and routine
maintenance by about 10% in the last year, while planned renewals have increased
by around 15% over the same period.
Figure 35 also shows that with FY 2014 as the exception, the budget for Structures &
Facilities has remained steady while the amount spent on maintenance and renewals
for bridges has declined. Once again, this is indicative of a focus on ‘best for network’
strategy, which has reprioritised funding.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 57 of 91
BRIDGES STRATEGY
Greater alignment between contractor managed work orders and Ellipse work
orders
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 58 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 59 of 91
BRIDGES STRATEGY
Potential
Potential to stop and
collapse of up to
significantly disrupt rail
two trains.
traffic on the area
Severe injuries affected.
Collapse or & Loss of Lives
Severe injuries / loss of
Column or practical to up to 600
Columns or lives & damages to third
Piles fail or collapse of people.
Piles parties on areas directly
partially fail columns or
Severe below the affected span.
piles
disturbance to
Severe disturbance to
the traffic on
the traffic on roads, rail
roads and public
and public areas below
areas below the
the structure.
structure.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 60 of 91
BRIDGES STRATEGY
The bearings
supporting
either end of Localised damage to
the girders other structural
have failed or elements
Failed or deformed. The Misalignment or
Enforcement of
Bearings deformed bearings are deformation of
temporary speed
bearings not performing the tracks
restrictions.
their role and
transferring No associated injuries or
the load to the loss of lives.
substructure
appropriately.
Failure of
bolted
connections Potential to stop Enforcement of
Collapse or temporary speed
and significantly
practical restrictions.
Bracing Buckling, disrupt rail traffic
collapse of
yield or on the area No associated injuries or
bracing
rupture of affected loss of lives.
bracing
members
Closure of the
Footbridge bridge until Closure of the bridge
Stair treads fail or partially fail
Stair repair/maintena until repair/maintenance
Treads nce works are works are completed.
completed.
Closure of the
Closure of the bridge
bridge until
Stringers fail or partially fail until
Stringers repairs/mainten
repairs/maintenance
ance works are
works are completed.
completed.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 61 of 91
BRIDGES STRATEGY
Collapse of up
Complete stop of all rail
to two trains.
traffic on the area
Severe injuries affected.
& Loss of Lives
Severe injuries / loss of
to up to 600
Truss Collapse of Collapse of lives & damages to third
people.
Bottom Truss Bottom Truss Bottom parties on areas directly
Chord Chord Chord Severe below the affected span.
disturbance to
Severe disturbance to
the traffic on
the traffic on roads and
roads and public
public areas below the
areas below the
structure.
structure.
Collapse of up
Complete stop of all rail
to two trains.
traffic on the area
Severe injuries affected.
& Loss of Lives
Severe injuries / loss of
to up to 600
Collapse of Collapse of lives & damages to third
Truss Top people.
Truss Top Truss Top parties on areas directly
Chord
Chord Chord Severe below the affected span.
disturbance to
Severe disturbance to
the traffic on
the traffic on roads and
roads and public
public areas below the
areas below the
structure.
structure.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 62 of 91
BRIDGES STRATEGY
Collapse of up
Complete stop of all rail
to two trains.
traffic on the area
Severe injuries affected.
& Loss of Lives
Severe injuries / loss of
Collapse of to up to 600
Truss Collapse of lives & damages to third
Truss people.
Vertical Truss Vertical parties on areas directly
Vertical
Member Member Severe below the affected span.
Member
disturbance to
Severe disturbance to
the traffic on
the traffic on roads and
roads and public
public areas below the
areas below the
structure.
structure.
Severe injury or
loss of life
Failure of the walkways Closure of the walkway
Walkway/ Damages to
including wearing surface, until repair/maintenance
Refuge third party
connections or beams works are completed.
properties (road
vehicles).
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 63 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 64 of 91
BRIDGES STRATEGY
8. Risk
a. Enterprise Risks
Risks are identified and assessed within Metro in accordance with Metro’s Enterprise
Risk Management Procedure (L0-SQE-PRO-031). A summary of this process,
including monitoring and review after completion of the risk assessment, is as follows:
Risk assessments are undertaken to determine whether there are any further
controls that can or should be applied to reduce an identified risk
Risks controls are identified and assessed in the workshop as being: a)
recommend to adopt; b) explore further; and/or c) reject
The workshop documentation (register and report, if one is needed) are sent to
corporate risk department within the Safety, Environment and Risk (SER) division
of Metro (risk@metrotrains.com.au)
The SER risk department reviews the risk assessment and determines the level
of escalation of risks to relevant committees based on the risk score
There are about 112 bridges built pre-1930 with 47 bridges constructed before 1912.
This is a significant number of bridges that were constructed between 1912 and 1930
around the time when the rail network was electrified and expanded. The 47 bridges
with an age in excess of 100 years will remain in operation into the foreseeable
future, which is acceptable given MTM continues to monitor the asset condition and
there is no foreseeable risks. Continuing asset condition monitoring will identify any
bridge requiring renewal or rehabilitation in the future.
The risks associated with Bridge Assets are mitigated through the specification of
tolerances which are captured in the MTM Structures Maintenance Instructions. In
principle the inspection and maintenance regimes mean that Bridge Assets are
maintained within tolerances that mitigate risks in advance of any safety and
performance related incidents occurring.
The key longer-term risks associated with Bridge Assets therefore relate to the overall
degradation of the asset to the point at which the specified maintenance and
inspection regimes cannot be applied cost effectively and the asset needs to be
replaced.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 65 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 67 of 91
BRIDGES STRATEGY
Increased
Changes to frequencies
maintenance
to ensure critical bridges
cost (or Frequency based inspection
are inspected with
replacement regimes used to ensure all
greater frequency
cost) due to bridges are inspected within a
Load capacity
insufficient minimum period of time
assessments to be
inspections Detailed bridge condition reports
and/or failure conducted to greater
completed for critical bridges
understand bridge
to identify
defects condition
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 68 of 91
BRIDGES STRATEGY
Using the assumptions outlined above and following an assessment of the capital and
operating expenditure requirements based on engineering inputs (i.e., reports,
inspections etc.) as well as the assessment of the risk profile costs can be allocated
to each option accordingly.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 69 of 91
BRIDGES STRATEGY
The result enables each option to be objectively assessed against each other as
providing the best value to the network.
For the scenarios provided below, a general assessment is provided as a summary
for the nineteen most critical bridges (detailed in Section 5c), as well as a specific
example from Elizabeth St Collingwood, one of the critical bridges. For detail on the
recommended strategy for each of the critical bridges, see Section 11.
i. Description
Do Nothing (Reactive Maintenance Approach) – This concept is generally
associated with the least direct cost and comprises of applying a reactive
maintenance approach over the remaining structure life (50 years).
ii. Outcomes
The continuation of frequent inspections and reactive maintenance type
interventions on bridges, in order to keep costs low and to limit risk from rising to
unacceptable levels.
Example: Reactive Maintenance Actions for Elizabeth St Bridge, Collingwood:
Reactive replacement of deck timbers year on year
Ad-hoc replenishment of ballast depth due to loss through the deteriorating
deck
Budgeted maintenance costs of $10,000 per annum
iii. Benefits
Reduced costs and the ability to redirect budget towards other renewals is the
greatest benefit of this approach. Through the Life Cycle Cost analysis, the
average cost of implementing this scenario over a fifty year period, is calculated
at just 3% (NPV) of the cost of a renewal approach and 20% of a refurbishment
approach over the same period.
Example: Benefits of Reactive Approach for Elizabeth St Bridge, Collingwood:
Estimated costs of just $98,000 (Net Present Value) over fifty years, compared
to costs of over $2 million for renewal of the bridge. This equates to
approximately 5% of the potential spend on the bridge.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 70 of 91
BRIDGES STRATEGY
The low NPV spend over fifty years on Elizabeth St allows for a strategy that
promotes minimal spend on many bridges, rather than a large spend on a
select few bridges.
iv. Consequences
The ‘Do Nothing’ scenario results in no decrease in discarded risk over the fifty
year period. Instead, the approach aims to limit the increase of risk to
unacceptable levels. On bridges where risk is already at a level of concern, this
may not be an appropriate scenario.
An example of the resulting comparison risk profile of each scenario is provided
in Figure 36 below:
As is shown, from the point of view of risk, the ‘Do Nothing’ option is the least
attractive of the three scenarios.
i. Description
Refurbish (Life Extend) – The work involved in applying this option varies for
each structure dependent on the defect(s) that are causing the poor performance
and the type of structure being refurbished. This option includes strengthening
over stressed or significantly deteriorated members, deep soil injection to arrest
settlement problems, or replacing a timber deck like for like. The refurbish option
generally achieves 25 - 50 years extra life for the structure, but requires less
capital expense to implement than renewal.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 71 of 91
BRIDGES STRATEGY
ii. Outcomes
This scenario consists of medium level investment for renewal of bridge
components that are in poor condition, rather than renewal of the full structure.
The balance between refurbishment and maintenance will vary from asset to
asset.
Example: Refurbishment Actions for Elizabeth St Bridge:
Budgeted refurbishment costs of $800,000 for year one
Replace timber deck like-for-like
Strengthen/refurbish girders (repaint, replace stiffeners/rivets, flange
strengthening plates)
Ancillary rail works (track and overhead)
Permits and general overhead (5% of bridge works)
iii. Benefits
On average, the refurbishment or life extension approach reduces the risk of
doing nothing by 25%. While the scenario does not reduce risk to the same
extent as a full renewal approach, costs are much lower, with estimated NPV
costs being around just 15% of the cost of completing a full renewal.
Example: Benefits of Refurbishment for Elizabeth St Bridge, Collingwood:
Estimated costs of just $697,000 (Net Present Value) over fifty years,
compared to costs of over $2 million for renewal of the bridge. This equates to
approximately 30% of the potential spend on the bridge.
The life extension works estimated to provide a 30% reduction in risk related
to the bridge
iv. Consequences
The average cost of the life extension approach is expected to be around five
times more expensive than managing bridge assets through reactive
maintenance. This additional costs represents reduced risk, however the
reduction in risk is not as large as can be achieved through full renewal.
Example: Consequences of Refurbishment for Elizabeth St Bridge, Collingwood:
The costs to refurbish the Elizabeth St Bridge is expected to be around 14
times that of the estimated reactive maintenance
The reduction in risk for completing life extension is approximated at 30%,
while full renewal is expected to achieve a reduction of 37%
i. Description
Renewal – This option considers the complete replacement of the asset or
significant component with another providing the same or equivalent level of
service. This includes replacing an entire superstructure of a given bridge but
maintaining existing substructure, or the replacement or an entire structure.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 72 of 91
BRIDGES STRATEGY
ii. Outcomes
This option should always achieve the minimum new design life of 100 years but
generally requires significantly more capital than “do nothing” or refurbish
options.
Example: Renewal Actions for Elizabeth St Bridge, Collingwood:
Estimated renewal costs of $2.5 million in year one
Replace superstructure, including deck (new structure compliant to AS5100)
Replace bluestone imposts
Ancillary rail works (Track & Overhead)
Permits and general
iii. Benefits
Purely considering risk reduction, the best performing approach is renewal. On
average, renewing one of the critical bridges will reduce risk to a level from which
it will take more than 40 years of service for the asset return to a similar level of
risk as is carried by the structure today.
Example: Benefits of Renewal for Elizabeth St Bridge, Collingwood:
Renewal of this bridge is expected to reduce risk by 37% over a fifty year
period
By renewing the asset in the short term, frequencies of inspection can be
reduced allowing for more frequent assessments of other critical bridges
iv. Consequences
The short term capital costs required to implement this scenario are very high in
comparison to the other scenarios analysed. On average, a full renewal approach
is approximately six times as expensive as refurbishment and over thirty times as
expensive as the ‘Do Nothing’ reactive maintenance approach.
Example: Consequences of Renewal for Elizabeth St Bridge, Collingwood:
The cost of full renewal of the Elizabeth St Bridge is estimated at $2.5 million,
representing a Net Present Value of $2.3 million over fifty years. Approximate
NPV for refurbishment over the same period is $697,000, while reactive
maintenance NPV is just $98,400.
The practicality of implementing such an approach is also a concern. Only a
certain number of bridge renewals can be completed per annum, due to
constraints such as occupation availability, program management time, cash
flow and material availability.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 73 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 74 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 75 of 91
BRIDGES STRATEGY
a. Approach
In order to provide a robust approach to the track system asset class, a number of
variables (outlined throughout the earlier sections of this report) need to be
considered:
Asset management objectives
Group requirements including network criticality, as stipulated by Network
Development
Age of the assets
Condition of the assets
Expenditure analysis
Utilisation and failure history
Asset deterioration and Consequences
Risks and proposed controls
The approach to this strategy has been to recommend actions (both specific and
general) over the short, medium and long term. As a rule of thumb: short term is
considered to be the next two years; medium term is between two and five years; and
long term is beyond the next five years.
There are a number of constraints that are envisaged to prevent bridge assets being
maintained at an optimum capacity. These constraints are detailed in Table 24:
Limited track access Due to increased services across the network, track time
for inspections during days is limited between trains.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 76 of 91
BRIDGES STRATEGY
Constraint Impact
Limited funding for The budget for maintenance is likely to limit the ability to
maintenance implement all strategic recommendations.
Strategy
Assess all bridges individually by applying life cycle cost modelling, choosing a
renewals approach that constitutes the best value for money
Complete life cycle cost modelling for all bridge assets on the network
Where superstructure renewal is recommended, consideration is to be given to
improvements in clearances and track quality (eg. increased ballast depth, road
clearance and overhead heights)
Gradual and continued installation of secondary fall protection on crash beams
lacking such a prevention system
In the medium term, improvements in bridge condition data are to be sought
through the use of load capacity assessments on critical bridges
Napier St Bridge, Footscray to be fitted with a Bridge Impact Detection and
Remote Investigation Capability system
Aitken Creek Bridge, Life Extension Replace deck, strengthen girders, track
Craigieburn Works and overhead renewals
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 77 of 91
BRIDGES STRATEGY
Short Term
Bridge Description
Strategy
Westgarth Station Life Extension Replace timber deck and strengthen
Footbridge Works girders
As can be seen from the nominated short-term works, life extension or bridge
refurbishment is generally the most cost effective and best value approach. Further
detail on each of these nominated works locations is provided in Section 11c, Critical
Bridges Strategy & Tactics. These bridges are to be nominated to the annual works
plan through the RPT process.
Where superstructure renewal is recommended, consideration is to be given to
improvements in clearances and track quality (eg. increased ballast depth, road
clearance and overhead heights).
Expansion of the life cycle cost modelling from a selection of the most critical bridges
on the network to all bridge on the network is a key short-term strategy. This will allow
for improved planning, greater visibility of required future interventions and an
understanding of when and where funding will be required.
MTM is responsible for the maintenance of 136 rail-over-road bridges (as defined in
Section 3d, Asset Base). Of these bridges, 58 are protected by crash beams,
resulting in a total of 115 individual crash beam assets across the network. The
potential consequence of a crash beam falling onto the roadway following a bridge
strike has driven the need for a crash beam strategy. The short-term recommendation
is to begin requires the gradual and continued installation of secondary fall protection
on the beams lacking such a prevention system (full list available in Appendix D).
In the short term, it is recommended that Napier St Bridge in Footscray be fitted with
a Bridge Impact Detection and Remote Investigation Capability system. The system
enables remote monitoring of the bridge and would represent a significant
improvement from the current process where bridge strikes are most commonly
reported though the public. This would also represent a trial of the system and if
successful, could be rolled out to other bridges that see high numbers of bridge
strikes.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 78 of 91
BRIDGES STRATEGY
General Motors
Removal Remove remaining steel structure
Station Footbridge
Glenferrie Station Life Extension Deep soil injection, brickwork repairs and
Subway Works drainage improvement works
Maribyrnong River
Life Extension
Bridge, South Cross girder strengthening
Works
Kensington
Further detail on each of these nominated works locations is provided in Section 11c,
Critical Bridges Strategy & Tactics.
In the medium term, improvements in bridge condition data are to be sought through
the use of load capacity assessments on critical bridges; including bridges of low
condition index and bridges in locations where tonnage changes are expected (high
capacity trains, increased freight, increased timetables). Load capacity information is
critical to understanding the bridge components requiring strengthening or
replacement and whether a bridge has capacity for all train configurations.
Progressive installation of secondary fall protection on crash beams lacking such a
prevention system is a medium term recommendation. For bridges regularly struck by
vehicles, such as Napier St in Footscray, consideration shall be given to the fitting of
seismic sensors that provide notification to structural engineers of bridge strikes and
also allow for remote inspection and assessment of the bridge’s stability.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 79 of 91
BRIDGES STRATEGY
Further detail on each of these nominated works locations is provided in Section 11c,
Critical Bridges Strategy & Tactics.
Knowledge of load capacity/structural integrity of all MTM managed bridge assets
would represent a key asset management improvement. Therefore MTM strategy
over the long term is to conduct engineering assessments on all bridges in order to
calculate a benchmark load capacity for all bridge assets.
Implementation of an Asset Health Index instigated load capacity assessment regime,
which ensures high criticality bridges are load tested at appropriate intervals.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 80 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 81 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 82 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 83 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 84 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 85 of 91
BRIDGES STRATEGY
12. References
1. J15-313_RPT_V0.1 Life Cycle Cost Analysis, Sterling Group Consultants, 2015
2. Bridge Life Extension Paper, Metro Trains Melbourne, 2013
3. Bridges, Footbridges, Subways & Overhead Structures – Valuation Analysis,
Sterling Group Consultants, 2015
4. Old Flinders Street Viaduct – Cost Benefit Analysis, Sterling Group Consultants,
2013
5. Metropolitan Railway Bridges Crash (Protection) Beam Compliance Investigation,
Sterling Group Consultants, 2010
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 86 of 91
BRIDGES STRATEGY
13. Appendices
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 87 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 88 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 89 of 91
BRIDGES STRATEGY
Fair Condition
Condition State 2 Component shows deterioration of a minor nature with
primary supporting material which is first signs of being
affected.
Poor Condition
Condition State 3 Component shows advancing deterioration and loss of
protection to the supporting material which is showing
deterioration and minor loss of section.
During asset inspection, the Field Inspector will record the observed condition state
for each structural component and the extent to which it exists according to the
general guidelines of the above table. The extent of each condition state affecting the
component shall be measured as a percentage of the whole component. That is, the
percentage of each condition state (1, 2, 3 and 4) must add up to 100% for each
structural component being assessed.
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 90 of 91
BRIDGES STRATEGY
Approving Manager: Chief Engineer Approval Date: 30/11/2015 Next Review Date: 30/11/2018
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 91 of 91