Documente Academic
Documente Profesional
Documente Cultură
317
CHAPTER XXXVII
https://archive.hnsa.org/doc/dc/part10.htm 1/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
318
Figure 37-2. Sketch illustrating the use of bagged concrete to stop leaks in ruptured deck D.
Note the use of steel plate P to support the bags, and how the bags are laid crisscross.
The basic materials should be mixed in it may be advisable to have two mixing
approximately the following proportions (by boxes, staggering the batches so as to have a
volume): steady flow of fresh concrete.
1 part High early strength Portland In depositing concrete above water it usually
cement. is necessary to build a form to retain the
1 1/2 parts Sand. concrete while it is setting. Frames, bulkheads
and other parts of the ship's structure may be
2 parts Aggregate. used as part of the form. Place the concrete in
the form with a shovel or a bucket. Do not
Various authorities recommend different drop or throw the material in loosely, for this
formulas, with slightly higher proportions of will tend to entrap air pockets. Press or tamp
sand and aggregate. If more bulk is required the concrete tightly into the form. If the
less cement may be used. Four cubic feet of concrete settles rapidly without air pockets it
the separate materials will make about three is a sign that it contains too much water. If
cubic feet of concrete when mixed, although time and conditions permit, it is advisable to
the concrete will tend to swell when scrape and clean metal surfaces against which
deposited under water. concrete is to be deposited.
The materials may be mixed in gun tubs, in a Concrete can best be deposited under water
wooden box, or on the deck of a washroom. by use of a chute made of watertight pipe or
In the latter case, cover drains to keep from waterproofed canvas. It may also be made of
fouling them. The best procedure is to lay the 1/2-inch lumber. The chute or tube should be
sand first, and to pour the cement over it. The large enough to permit free flow of the
two are mixed dry by turning them over with concrete. An inside diameter of four to six
a shovel or a garden hoe until the mass has a inches should suffice. The upper end,
uniform color. The aggregate is then added however, may be made much larger, to serve
and the mixture again turned over. as a sort of hopper. The tube is used to avoid
dropping the concrete loosely through the
Calcium chloride generates heat upon contact
water and thereby wasting much of it. The
with water, and thereby facilitates the setting lower end of the tube should be right down in
of concrete (under water). Use two pounds of the mass of deposited concrete. If possible,
calcium chloride for each 51/2 gallons of keep the tube full of concrete to exclude
water, dissolving the calcium chloride in the
https://archive.hnsa.org/doc/dc/part10.htm 2/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
water before the latter is poured into the dry water, and lay the mixture like toothpaste
ingredients. The use of calcium chloride is flowing from a tube.
desirable but not mandatory. It tends to
impart high early strength characteristics. At best, it is difficult to use concrete for
However, it is more desirable to have a rather underwater leak stopping. The heavier
stiff mixture made with water above 70° F. materials will sink to the bottom, hut the finer
particles tend to wash away-especially the
37-3. Application of concrete. Concrete cement. Therefore, every effort must be
should be deposited promptly after it is
mixed. For a large job
319
made to prevent the flow of water through or temporary drain pipe running from a point
across the mixture while it is being poured near the leaky seam or hole to a point outside
and after it is in place. As a preliminary the form. The pipe carries away water while
measure, try to stop or restrict the flow of the concrete is setting, after which the pipe
water through cracks or holes that are to be can be plugged.
patched. Mattresses, pillows, oakum, wedges,
plugs and similar materials may be used for Concrete may also be deposited under water
this purpose. by utilizing bags of about one cubic foot
capacity (see fig. 37-2). The bags may be
made of a coarse cloth such as burlap-the
common gunny sack. After filling a bag about
two-thirds full, tie it securely. The bags of
concrete are laid in a criss-cross manner, so
that the whole structure is interlocked.
Cement leaking through the pores in the
sacking will bind the bags together.
to reduce the washing effect of water. The 45 minutes. However, the concrete will not
form is necessarily left open at the top for have any appreciable strength until it has set
deposition of the concrete. for at least a day, maximum strength being
attained when it is about four weeks old.
Put the chute well down into the form, with
the lower end practically buried in concrete. As previously noted, sea water may be used
Fill the chute to a height above the water in mixing concrete when fresh water is not
level, and move the chute along the bottom, available. It speeds the initial set. In this
gradually depositing concrete as you go. connection it is important to remember that if
Continue to shovel concrete into the tube. Do a smaller amount of water is used the time of
not let the concrete pile up at any one point setting will be reduced. This practice,
and then try to relocate it with a shovel or a however, results in a stiffer mix which is
hoe. more difficult to handle
Often it has been found advisable to install a 37-5. Reinforcing concrete. Dry concrete has
a had tendency to crack and fracture under
stress, especially if the mixture does not
contain enough cement.
320
Figure 37-6. Leaks and ruptures in damaged door and bulkhead plugged with wood wedges
and rags to stop flow prior to pumping. Two cofferdams (A) are being used to hold back
water remaining in the compartment. The space between one cofferdam and the outboard
bulkhead has been filled with concrete. To check flow of water prior to pumping, bags of
concrete were laid over deck rupture R.
https://archive.hnsa.org/doc/dc/part10.htm 4/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
Unsupported, it may break away from the or wires are useless for this purpose. In
place where laid. It is therefore desirable to addition, it is advisable to weld bolts, hooks
bury jagged metal rods or heavy wire mesh in or nails to the hull structure, and to have them
the concrete as it is poured (see fig. 37-5). protruding into the poured concrete in order
These reinforcing materials will hold the to provide a positive mechanical bond
blocks of dry concrete together mechanically between the ship and the patch. Ship's frames
no matter where the fractures occur. Smooth may also be utilized for this purpose.
rods
321
CHAPTER XXXVIII
38-1. Foreword. The engineer department is may prevent the engineering plant from
an essential and integral part of the damage- meeting all speed demands.
control organization. The general functions of
the engineer department in the control of 7. To provide an adequate supply of
damage are set forth in FTP-170B. They are compressed air for the gas-ejection system.
as follows:
8. To supervise the engineering casualty
1. To operate and maintain the machinery and control organization and make decisions
power facilities necessary to insure the relative to this vital phase of engineering in
maximum mobility and maneuverability of case of battle damage to any part of the plant.
the ship.
9. To cooperate with the damage control
2. To establish and maintain an uninterrupted officer:
supply of electrical power and compressed air
to the offensive weapons and their auxiliaries. a. In maintaining the stability of the ship
by shifting fuel oil, pumping ballast,
3. By means of drainage pumps and and flooding tanks.
connected piping, to pump out flooded
compartments as directed by the damage b. By maintaining adequate pressure in
control officer. the fire-main systems.
4. By transfer within the ship of fuel oil and c. In the operation of a considerable
fresh water, as directed by the damage control portion of the drainage systems.
officer, to maintain the ship in stable
condition. 10. As a line head of department in the chain
of command, to succeed to the command of
5. To repair damage with a minimum of the ship in case his seniors become casualties.
interference to 1 and 2 above.
11. In accordance with recent alterations
38-2. Main responsibilities of engineer removing the ship-control apparatus from
officer in battle. The main responsibilities of central station and making the main engine
the engineer officer in battle may be outlined control station a ship-control station, the
as follows: engineer officer must be prepared to take over
steering control in case the other ship-control
1. To meet all the speed demands of the stations are disabled.
Commanding Officer.
12. If the damage control officer and his
2. To route live steam in the main and principal assistant become casualties, the
auxiliary steam lines to the main engines and engineer officer must be prepared to take over
all of their auxiliaries, and the auxiliary control of damage. The necessity for this has
exhaust. already been amply demonstrated in the case
of at least one of our heavy cruisers, where
https://archive.hnsa.org/doc/dc/part10.htm 5/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
3. To route feed water and condensate in all after a serious battle casualty had occurred
systems. the engineer officer took over control of
damage and performed outstanding work in
4. To provide an adequate supply of fuel oil helping to save the ship.
to all boilers (or main and auxiliary engines,
in the case of Diesel-driven vessels) through 38-3. Publications recommended for study.
the fuel-oil transfer and service systems. In order to perform his damage-control duties
efficiently, the engineer officer must be
5. To provide electrical power for the ship, thoroughly familiar with the following
especially for ship control and the gunnery publications in addition to U. S. Navy
department, through main- and emergency- Regulations and the Bureau of Ships Manual.
power systems, with alternate supply feeders Many of them contain mandatory directives
and the casualty power system. relative to engineering damage control:
6. To see that proper action is taken in the
case of any minor casualties, such as hot
bearings, low vacuum, and other
derangements which
322
1. Ship's Damage Control Book. school. The engineer officer should cooperate
2. Ship's Engineering Casualty Control Book. with the damage control officer to see that all
3. FTP-170B. hands are trained in the proper method of
4. USF-10A. extinguishing electrical fires.
5. Type Commander's letters on damage
control. Electrical equipment and wiring are to be
6. Bureau of Ships letters relative to damage found in nearly every compartment on the
control, engineering casualty control, etc. ship, and electrician's mates cannot always be
7. Bureau of Ships bulletins of information. present wherever an electrical fire starts. Too
often valuable electrical apparatus has been
A careful study of the action and war damage ruined beyond economical repair by ignorant
reports is also recommended, for they contain or careless fire fighting. All hands must be
many valuable lessons in engineering damage impressed with the simple fact that the only
control. proper way to extinguish a purely electrical
fire is through the use of carbon dioxide.
38-4. Factors in engineering damage Abundant past experience has indicated the
control. Engineering Damage Control can be necessity for this.
considered logically in two sections, as
follows: 38-7. Split-plant operation. Limitation of
damage is accomplished in the engineer
1. Limitation of damage. department chiefly by proper segregation of
2. Repair of damage. the plant in split-plant operation. Split-plant
operation may be defined as the subdivision
LIMITATION OF DAMAGE of the entire machinery and electrical plant of
the engineer department into two or more
38-5. Relationship of design to damage independent plants (depending on layout and
control. Prevention of damage to engineering design) by closing the proper valves and
installations is largely a function of ship switches.
design and construction. The general
arrangement of the machinery and electric Taking a relatively new DD as an example
plants, including piping and wiring systems, and referring to figure 38-1, boilers 1 and 2 in
must provide for their location underneath the forward fireroom are supplying main
and behind armor and the torpedo protection steam to the starboard turbines, located in the
in large vessels. In small vessels where armor forward engine room, and power to the
and torpedo protection are impracticable of starboard shaft. Boilers 3 and 4, located in the
installation, the design provides maximum after fireroom, are supplying main steam to
https://archive.hnsa.org/doc/dc/part10.htm 6/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
dispersal of the engineering plant in as many the port turbines, located in the after engine
watertight compartments as possible, with room, and power to the port shaft. The two
duplicate units and provision for split-plant main plants are isolated by closing two main
operation wherever this may be done. stop valves in the forward engine room cross-
over line, one located on the port side forward
38-6. Personnel and organization. Matters in the forward engine room, and the other on
pertaining to organization, training and the starboard side near the forward bulkhead
education of personnel for damage control of the after fireroom. The by-pass valve is
are discussed in other Chapters. As far as the open around the forward engine room cross-
engineer department is concerned, every over valve, and the drains are open in the
officer and man of the organization should be cross-over line to the after fire-room, since
so well trained and educated in the principles 600 p.s.i steam lines cannot be warmed up
of damage control that, if the complement of rapidly without danger of rupture from water
the engineer's force is 456 officers and men, hammer. The cross-over line is thus warmed
the engineer's repair party numbers 456 and ready, in case the plant must be "unsplit."
officers and men. The forward engine room is the control
engine room and the engineer officer's battle
Since preventive damage control consists station. All the other essential systems are
largely of correct utilization of the damage- split, so that the plants are independent, for
control features built into the ship, the example:
training of personnel must place emphasis on
proper operation of the systems and 1. Auxiliary steam. Steam to the auxiliaries in
equipment furnished, and their upkeep and the forward fireroom and engine room is
maintenance. supplied by boilers 1 and 2, and to the
auxiliaries in the after fireroom and engine
The subject of fire fighting is dealt with in room by boilers 3 and 4. Cut-out valves are
Chapter XXXII. All officers and men of the closed isolating the two plants.
engineer force should be thoroughly familiar
with the use of firefighting apparatus in the
engineering spaces. In addition, it is desirable
that all attend the fire-fighting
323
https://archive.hnsa.org/doc/dc/part10.htm 7/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
324
2. Auxiliary exhaust. Exhaust from the Unless reserve feed becomes dangerously low
forward auxiliaries is utilized in the forward they should be kept secured in action, due to
engine room in the main distilling plant, danger of priming and salting up. The reserve
turbine gland seal and de-aerating feed tank; feed supply should be kept up in wartime
excess goes to the turbines and the main cruising so that these plants can be kept
condenser. Cut-out valves are closed so that secured in action.
the exhaust from the after auxiliaries is
https://archive.hnsa.org/doc/dc/part10.htm 8/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
similarly disposed of in the after engine In the newest destroyers, one 400 K.W. A.C.
room. The latest DD's have an auxiliary turbogenerator with a 50 K.W. D.C. exciter
distilling plant in the after engine room. (also supplying D.C. power to searchlights,
etc.) on the same shaft, is located in each
3. Main feed and condensate. Cut-out valves engine room. Electric power is distributed
are closed so that the two plants are isolated. from main distribution switchboards, one in
Condensate from the forward main condenser each engine room. The A.C. and D.C.
goes to the forward de-aerating and feed tank generators, although capable of parallel
in the forward engine room, then via two operation if desired, are not paralleled in
main feed pumps, located in the forward split-plant operation. In general, the
engine room, to boilers 1 and 2. Make-up distribution of power is as follows: Units
feed is taken from two tanks, one on each located above and forward of the forward
side of the forward fire-room. Emergency engine room receive their power through
feed is taken by a reciprocating feed pump "normal" feeders from the forward
located in the forward fireroom via a direct distribution board, and have "alternate"
cold suction line from the two reserve feed feeders from the after distribution board.
tanks, one on each side of the fireroom, and Similarly, units aft receive "normal" power
discharged directly to boilers 1 and 2. This from the after distribution board, with
pump should be kept warmed up and turning "alternate" feeders from the forward
over slowly in split-plant operation. A distribution board. Main power cables are
duplicate of this installation is located in the well distributed in runs on both sides of the
after engine room and fireroom. ship, in oil-tight trunks where they pass
through oil tanks, and the main lire-control
4. H.P. and L.P. drains. The steam drain wiring is led through a vertical wiring trunk
mains are isolated forward and aft by cut-out centrally located 'all the way up to the main-
valves. battery director. Suitable connections are
provided with "bus-tie" switches, so that the
5. Fuel-oil system. Two fuel-oil service main distribution boards can be tied together
pumps in the forward fireroom take direct for parallel operation, or one generator can
suction from service tanks located on the supply both boards by closing the "bus-tie"
centerline forward of the forward fireroom switches. If the "bus-tie" switches are opened
with the cofferdam (A4VF or A5VF) in at either or both boards, each board is
between, and discharge through a fuel-oil independent for split-plant operation. Normal
heater to the manifolds located on the fronts practice in DD's is to close the "bus-tie"
of boilers 1 and 2. This installation is switch at the after board, and open the "bus-
duplicated in the after fireroom for boilers 3 tie" switch at the forward board for split-plant
and 4, and the after service tanks are located operation. Since the forward engine room is
on the centerline just abaft the after engine the control engine room, the operator at the
room. Cut-out valves are closed in the fuel- forward distribution board has control over
oil transfer system, and the manifold, suction splitting or unsplitting the electric plant. In
and sluice valves to the fuel-oil storage tanks addition to the main generators, one 100 K.W.
are kept closed. No transfer of fuel oiI should emergency Diesel-driven generator is located
be attempted in action unless directed by the in a separate compartment forward and
damage control officer to correct list or trim. another aft of the engineering spaces. Each
Diesel generator has its own switchboard
6. Distilling plants. Latest DD's have a main located in the same compartment, with
distilling plant (12,000 G.P.D.) located in the suitable cable connections and "bus-tie"
forward engine room and an auxiliary switches for tying the two Diesel
distilling plant (4,000 G.P.D.) located in the
switchboards together so that either
after engine room. These plants are isolated emergency generator can energize both
from each other in split-plant operation, and emergency boards (but they cannot be
are available for distillation of boiler feed in paralleled) , or separating them for split-plant
an emergency.
operation. Also, either Diesel switchboard
can supply the main distribution boards
through suitable cable connections and "bus-
tie" switches. Normally, in split-plant
operation, all the "bus-ties" are open at
https://archive.hnsa.org/doc/dc/part10.htm 9/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
325
both Diesel boards, so that the forward Diesel The destroyer has been used as the example
can supply forward emergency power and the of split-plant operation in the foregoing
after Diesel after emergency power. The paragraphs because the DD installation is
Diesel-driven generators are supplied with relatively simple. In the case of larger ships
automatic electric starting (from storage which have multiplex engineering plants and
battery supply) , and are designed to start intricate watertight compartmentation split-
automatically through a voltage relay when plant operation is not so simple. The electric
the main A.C. voltage falls to a certain plants especially are more complicated, large
specified value lower than the normal 450 ships having as many as four independent
volts, and to be up to speed and take over the plants. In some of the later ships, Diesel-
emergency load in less than 10 seconds. Most driven generators supply up to 40 per cent of
emergency Diesel-driven generators will pass the normal power supply and no emergency
this test satisfactorily; however, it is Diesels are installed. The same general
recommended that automatic starting not be principles apply, however, therefore no
relied upon in action in cold weather, when attempt will be made to give a detailed
the Diesels are slow in starting. When action example here.
is imminent in cold weather it is
recommended that the Diesels be started and 38-8. The Engineering Casualty Control
warmed up and preferably kept running Book. FTP-170B requires the engineer
during action, so that no delay will be department of each ship to prepare an
encountered in obtaining emergency power. Engineering Casualty Control Book. Its
Also, when not in action, when entering or purpose is to establish methods of operating
leaving port, or navigating in restricted the engineering plant under all conditions. In
waters, it will be found desirable to start the other words, this book should represent
after Diesel generator and keep it running so standard engineer department doctrine for
that a reliable immediate supply of operational casualties, battle casualties, and
emergency steering power is available. In all conditions that have to be met in running
wartime cruising, a regular routine of starting the engineering plant.
and testing emergency Diesel generators
should be established, and a thorough check The detailed instructions for preparing the
made to insure that the starting batteries are Engineering Casualty Control Book are
kept properly charged. The necessity for contained in FTP170B, Chapter 9. In general,
these precautions is abundantly borne out by this book must contain the following
operating experience. The experienced information:
practical engineer officer must always "have
an ace up his sleeve" where automatic 1. Diagrams of all piping and wiring systems.
devices are concerned.
2. Instructions for setting valves and fittings
The vital services on the DD's have three of the main propelling machinery and
sources of power, i.e., normal, alternate and auxiliaries under the several material
emergency. Normal and alternate supplies conditions.
come from the main generators, and
3. Instructions dealing with the division,
emergency from the Diesel-driven generators.
Transfer of power is accomplished by means segregation, and readiness of main and
of automatic or manual-type transfer switches auxiliary sources of electrical light and
located near the units involved throughout the power, the distribution thereof, and the setting
of distribution controls (switches, etc.) under
ship. The vital services so supplied are:
the several conditions of readiness.
1. All 5"/38 cal. and 40 mm. gun mounts.
4. Instructions regarding the securing and
2. Steering gear.
3. Radio control and emergency radio. isolation of auxiliary machinery units which
4. I.C. and F.C. switchboard. are not required to be in service under certain
5. Battle lighting. conditions of readiness.
6. Electrically driven fire pumps. 5. Instructions concerning the stowage of fuel
oil, indicating the full bunker condition, the
https://archive.hnsa.org/doc/dc/part10.htm 10/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
Note that electric auxiliaries in the engineer order in which tanks shall be emptied, the
department are not vital, and are not supplied order in which tanks shall be refilled and
with emergency power. No direct current is instructions for ballasting by filling specified
available from either Diesel generator. A tanks with sea water to compensate for oil
casualty power system, consisting of certain consumed.
permanent and portable runs of cable is
supplied for use in the event of damage to 6. Instructions similar to the above but
main power cables. concerned with fresh-water systems.
326
2. Casualty power system with data and The above plates are isometric plans, showing
details on auxiliary sources of power, the piping and wiring diagrams by decks, and
connections, and methods of distributing the connections between decks. Larger
power. vessels will require more E.C. Plates than
DD's, particularly of the electrical systems,
3. Fire and flushing systems. but the example given above indicates the
important systems for the benefit of ships
https://archive.hnsa.org/doc/dc/part10.htm 11/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
327
Book of a large vessel will serve as an 3. The shifts referred to above will be made at
example of the material content of a well- such time as best fits the tactical situation,
written casualty control book, and may be and will fit the meal schedule if meals are not
described as follows: served on station. These reliefs will be made
only on orders from main control.
Part A-Organization for engineering casualty
control. 4. The shift will be made in an orderly
manner and reserve personnel from Repair V
This part contains a brief description of the will be utilized to avoid leaving vital stations
general organization of the engineering unmanned during the shift."
department for casualty control, with a
description of the plan for relieving the Part B-Engineering battle (and Repair V
watch, and going to general quarters from a station) bill.
war cruising condition. This plan is not
mandatory, but is comprehensive and well
https://archive.hnsa.org/doc/dc/part10.htm 12/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
organized; therefore, it is quoted below for Detailed bill by stations, showing men by
information and guidance. It can be adapted number and rate, and detailing general
to small vessels as well as large ones: quarters and war cruising stations.
"To eliminate confusion and to expedite the Part C-Repair V organization and remote
manning of battle stations at general quarters, valve control bill.
the engineering section on watch shall remain
on watch and be augmented from the relief This contains the organization of Repair V,
sections to provide the necessary additional and the detailed list of valves, assignment to
personnel to man stations not manned in groups of personnel, etc., for remote-
cruising condition. The remaining men of the controlled valves in the engineer department.
relief sections are assigned to Repair V,
engineering reserve, and gunnery department Part D-Engineering casualty control
battle stations. The cruising watch is based on conditions (plant isolation).
a full three-section watch with sufficient
stations manned to supply full power Detailed instructions for split-plant operation
continuously. This system requires that each for engineering conditions corresponding to
man have three distinct battle stations, the conditions of readiness for action I, I-E, II,
particular station manned being dependent on and III.
the watch section on watch at the time
general quarters sounds. If general quarters or Part E-Communications bill and voice
condition I-Easy lasts for an extended period, procedure.
personnel will be shifted to relieve those men
Description of telephone systems used by the
on the hottest stations and those stations engineer department in battle, how they are
requiring the greatest degree of alertness. In manned, and vocabulary and instructions for
general, this shift will be made as follows: talkers.
1. For fireroom and engine room and Part F-De-energization of circuits in vicinity
generator crews, the general quarters crews of gasoline system in case of damage.
comprise about one and one-half steaming
sections, the remaining one and one half Detailed instructions for pulling circuits,
sections manning Repair V and other investigation of damage, etc., in the vicinity
relatively cool or inactive stations. This of gasoline tanks and adjacent spaces.
permits a natural watch and watch to be set
up for firerooms and engine rooms, the off Part G-Fuel-oil bill, sequence of emptying
time being spent at an easier station. These fuel-oil tanks, and water ballasting.
two groups will alternate with each other. It
should be noted that this will normally result Detailed instructions for operating the fuel-oil
in the first relief section being split in two to transfer, filling and water ballasting systems.
augment the on watch and the second relief
sections respectively. Part H-Operational instructions and data.
2. For other divisions and stations where the Detailed routine operating instructions and
ratio of additional personnel is much higher data concerning the engineering plant.
and conditions less onerous, the relief of men
on alert watches will be accomplished by an Part I-Sample casualties and corrective
organized shift of personnel to the stations measures.
they would have had if general quarters had
been initiated during the new watch. Includes both operational and battle
casualties.
https://archive.hnsa.org/doc/dc/part10.htm 13/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
328
and frigates, excellent Type Organization the lines. The Engineering Casualty Control
Books and Engineering Casualty Control Book should contain instructions covering the
Books are available, and are obtainable from securing of the following items unless
the Fleet Operational Training Commands or existing conditions require their use:
Type Commanders. These are of great aid
(particularly in the case of a new 1. Steam and exhaust lines to galley, heating
construction) in preparing the organization of system, showers, washrooms, laundry,
the engineer department and the Engineering pantries, fuel-oil heating coils, lubricating oil
Casualty Control Book. The Type Casualty settling tanks, soot blowers, sea chests, and
Control Books are outlines designed to serve evaporators. In this connection, consideration
as guides, and the details should be filled in should be given to the securing of the
by engineer officers for individual ships as exposed piping and drains to the whistle and
prescribed by FTP-170B and described in the siren in battle. A type, task force and
preceding paragraphs. Chips of other types Commanding Officer's policy should be
(new construction) are advised to obtain ascertained by engineer officers of individual
organization books and casualty control vessels. As an example of the desirability of
books for guidance from vessels of their securing this piping in action, some personnel
types already in commission. on one ship were severely burned and scalded
by steam escaping from a ruptured whistle
38-10. Readiness of auxiliary machinery. line in the superstructure following a shell hit.
All auxiliary machinery likely to be required
in battle, or used to overcome the effects of 2. Air supply to workshops and compartment
damage must be ready for immediate use. air-testing connections.
Steam-driven machinery, such as drainage
pumps and fuel-oil transfer pumps should be 3. Electrical circuits to boat-handling
kept warmed up and drained, and periodically equipment, trash burners, laundry, galley,
operated to insure readiness. Mention has bakery, battery-charging panels, and anchor
been made in a previous paragraph of the windlass.
necessity for testing emergency Diesel-driven
generators. Similarly, other Diesel-driven 4. Tanks and lines supplying fuel to galleys,
equipment, such as emergency fire pumps, - workshops and trash burners should be
divorced" generators, etc., should be tested drained and the valves secured.
periodically. Electrical units should be
energized up to the starting panel. 5. Close valves and isolate as much of the
Instructions dealing with these items should freshwater system as possible, especially to
be in the Engineering Casualty Control Book. baths not required for decontamination
stations, and to workshops, pantries, galleys,
38-11. Isolation of open funnel drains. A laundry, barber shop, and scuttlebutts located
recent action report emphasizes the necessity in spaces which are isolated in battle.
for proper isolation of open funnel drain
systems. The principal flooding came from 38-13. Split-plant operation in port. FTP-
the open funnel drains. The pump drains in 170B prescribes material condition zebra (or
the after engine room of this installation were able) and split-plant operation for entering
collected in a funnel drain tank which and leaving port, and material condition yoke
(or baker) and normal split-plant operation in
emptied through connecting piping into a
collecting tank in the after fireroom. There port. This will be ordered by the O.T.C.
was no bulkhead cut-out valve that could be according to the circumstances. When in a
operated from the fireroom. The foregoing port or base Within bombing range of the
account shows the importance of providing enemy, unless the engineering plant is
https://archive.hnsa.org/doc/dc/part10.htm 14/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
and utilizing properly the means for splitting completely or partially disabled for repairs of
and securing this system, as well as the more the most urgent nature, split-plant operation
vital systems. The Engineering Casualty for auxiliary steaming is necessary to
Control Book should contain the necessary minimize damage in case of hits or near
instructions and precautions. misses, and to facilitate getting underway in
case of emergency. For example, in the case
38-12. Securing unnecessary machinery of a new destroyer having two duplicate
and piping systems. Some machinery and plants, one boiler in each fireroom should be
equipment are unnecessary in battle, and kept steaming, and both main generators
should be secured to prevent leakage, should be in operation, with the auxiliary
flooding, or short circuits in the event of steam lines, feed and fuel-oil systems, drains,
damage. (Refer to FTP-170B, Art. 9-13). etc., and the electric power distribution
Interruption of the services should be close to system properly set for split-plant operation
the sources of power or service in order to as if
isolate the maximum lengths of
329
the ship were underway. Similarly, in the case number of cases of boiler superheaters being
of large vessels, more than one auxiliary plant burned up and turbine and gear bearings
and boilers from more than one bank should being wiped have occurred in new
be in use, with the plants segregated properly. construction, largely due to lack of operating
A proper material condition (yoke or baker) experience and ignorance on the part of
should also be maintained. engineering personnel. Training in
operational casualties serves the cause of
38-14. Dispersal of personnel. The damage control well, since derangements of
organization for berthing and messing of the nature described above disable machinery
engineering personnel should provide for almost as effectively as enemy shell and
dispersal forward and aft in the living spaces bomb hits.
so that all key ratings will not be wiped out
by a hit in one compartment or vicinity. -The 2. Personnel of engineering battle stations and
2,200-ton destroyers are admirably designed repair parties must be trained to investigate
and arranged for such dispersal of key damage thoroughly before recombining split
officers as well as enlisted personnel. systems. They must be trained to limit the
spread of damage to undamaged
38-15. Training. The subject of training is compartments and machinery. Indoctrination
dealt with in other Chapters; therefore, only a should be thorough in such fundamentals as
few suggestions will be made here: pulling electrical circuits to damaged areas
and in vicinity of gasoline systems,
1. Training of personnel in handling routine establishing boundaries around fires and
operation of the plant, splitting and flooded areas, testing fuel and feed tanks for
recombining the various systems, and dealing salt water contamination due to damage, etc.
with operational casualties is equal in
importance to training in handling battle 3. During long periods of wartime cruising
casualties, especially since most personnel and operations in combat areas, instruction
are relatively inexperienced due to the rapid should take place on station so that men off
expansion of the service. One of our new watch will get their needed rest. Casualty
destroyers recently was dead in the water in a drills are suggested for the duration of routine
combat area for forty-five minutes due to dawn and dusk general quarters, and other
confusion in splitting and recombining the instruction should take place on station for
plant. A the men on watch.
330
CHAPTER XXXIX
https://archive.hnsa.org/doc/dc/part10.htm 15/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
39-3. Battle stations: engineer department. In new destroyers the engineer officer is
The split-plant principle of dispersing key stationed in the control (forward) engine
officer personnel should be applied in room, and if there is only one assistant
assigning battle stations of engineer officers. engineer officer, he is in charge of Repair II
To some extent, this policy is limited by (main deck amidships). If there is a second
Navy regulations and type organizations. The assistant engineer officer, he is stationed in
engineer officer himself is required by Navy the after engine room. A recent action report
regulations to be at the main engine control from a new destroyer illustrates the value of
station. The assistant engineer officer in large having the assistant engineer officer stationed
vessels normally is stationed in an engine outside of the engineering spaces. This
room other than the control engine room. or destroyer sustained a shell hit in the forward
in charge of Repair V on the engineer's engine room which disabled that space and
damage-control deck (usually third deck in killed all personnel, including the engineer
large vessels). In an electric-drive vessel officer. The assistant engineer officer
(where the main control room is the only stationed at Repair II was available for taking
station equipped for complete control of the damage-control action and assuming control
plant) policy on some ships has been to of the engineering plant.
station the assistant engineer officer in the
main control room with the engineer officer. 39-4. Engineering force and repair parties.
This is not in line with proper dispersal In both large and small vessels the engineer
principles, and is not recommended. A better department supplies key personnel for all
station for the assistant engineer officer in the repair parties, and particularly oil kings and
case of these vessels would be in charge of electrician's mates. Repair V on large vessels
Repair V at the Repair V headquarters on the and the engineer repair party on small vessels
third deck. At this must be equipped for the following tasks:
331
1. Repair or shoring of structural damage. the noise will interfere with the orders being
https://archive.hnsa.org/doc/dc/part10.htm 16/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
boilers exploding due to rapid flooding are on given speed. Therefore, if it is possible,
record, and there is no necessity for lifting propellers should be removed from locked
safety valves when abandoning ship; shafts. Some of our vessels which have
suffered battle damage or serious
332
operational derangements have had to resort rust off metal parts. The use of tectyl (thin
to emergency methods for locking shafts and film, polar type, rust-preventive compound) is
removing propellers. recommended for removing salt and rust from
flooded equipment. It has proved to be
39-9. Fuel-oil systems in action. When in invaluable in the salvage of machinery and
action cut-out and sluice valves must be equipment located in flooded compartments.
closed in the fuel-oil system and no transfer
of oil undertaken unless ordered by the To reduce the damage to electric equipment
damage control officer for stability reasons. and the probability of electrical fires, prompt
The oil level in the service tanks must not be action should be taken at the control main
permitted to become dangerously low. distribution switchboard to pull circuits
Prompt investigation should be made as soon immediately and remove power from
as a hit is received to ascertain if any tanks damaged areas, especially in the vicinity of
are holed or contaminated with salt water gasoline stowage.
from sprung rivets and seams. All tanks must
be carefully tested by the tank drain system Latest instructions provide that circuit
for the presence of water before being used. breakers at distribution boards shall not be
locked to prevent interruption of power to
In the case of large ships, a stability control important equipment. Instead, if breakers
officer is stationed in the damage-control open due to shock or other causes, they shall
headquarters during action. He issues the immediately be closed again by men stationed
orders for transfer of fuel oil and other liquids at the board for that purpose. If they again
to correct list and trim after damage has open short circuits and damage have occurred
occurred, under the direction of the damage in the circuits and the breakers shall be left
control officer. An oil king (the principal oil open until the trouble is investigated and
king or an assistant) who is thoroughly repaired. Locking the breakers inevitably will
familiar with the fuel-oil system should be result in serious damage to the switchboard
assigned as an assistant and advisor to the and other circuits. Breakers at the local power
stability control officer to facilitate the panels near electrical units may be locked if
transfer of fuel oil and Diesel oil. Close desired, however, providing discretion is
liaison must exist with the engineer exercised.
department in the control of liquid loading.
39-12. Casualty power supply systems. In
39-10. Feed and condensate systems. Main repairing damage to electrical circuits it may
condenser tubes may become leaky due to be necessary to run portable cables through
shock and reserve feed tanks may be flooded flooded or around damaged areas. For this
and contaminated by salt water from hull purpose casualty power supply systems are
damage. The distilling plants should not be now provided in most vessels for ship's power
operated in action to distill feed water, circuits, and in electric-drive vessels for the
because priming due to shock may result in main A.C. propulsion system as well as D.C.
salting up. Extreme vigilance must be power circuits. Frequent drills should be held
exercised after damage to prevent complete in hooking up casualty power cable. They
salting up of the entire feed and condensate should be as realistic as possible and
systems. In case of extreme emergency, and electrical equipment should be operated by
only as a last resort, boilers can be steamed at casualty power when practicable.
a low firing rate using salt water for feed. The
density of the water in the boiler will As an example of a typical casualty power
gradually increase, and as time goes on, system, the installation of a 2,100 ton DD will
serious priming and damage will occur. be described briefly. Power from both main
Prolonged operation of boilers on salt water switchboards and the emergency Diesel
https://archive.hnsa.org/doc/dc/part10.htm 18/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
333
On D.C. circuits casualty power bulkhead equipment furnished for fighting fires in
terminals are in pairs, one marked red for engineering spaces is excellent on most
positive leads and the other green for vessels, and personnel in the space (unless all
negative leads. Do not make the mistake of are killed or wounded) and the engineer
connecting the two main cables to one repair party should have no trouble in
terminal even though it does have two bringing fires under control. In damaged
binding posts, because they are both either spaces, ruptured steam lines will assist in
positive or negative, and the result will be a smothering a fire. In extreme cases when a
short circuit. The upper binding posts are for fire gets out of control, the space should be
passing current from one compartment to abandoned, closed up tightly, and the remote-
another; the lower terminals for operating control valves of the steam smothering
lights and tools within the compartment. system opened. As previously mentioned, all
hands in the engineer's force should be
On A.C. circuits, there is only one terminal trained as expert fire fighters.
per bulkhead. Each terminal has sets of slots
marked A, B and C to allow for 3-phase 39-15. Securing and salvage parties. While
current. Take care to connect the phases the ship is still afloat every effort must be
properly or casualties will result. The face of made to save it. Nevertheless, the situation
the connector should be divided into three may require the Commanding Officer to order
sectors: A-sector red, B-sector white, and C- abandonment except for a small securing and
sector black. salvage detail, to prevent probable
unnecessary loss of life. In such case, the
Jumper cables should be marked as follows: organization of the ship should provide for
D.C. positive leads with red bands, negative the detail and equipment of a party, normally
with green; A.C. cables (the three individual under the direction of the engineer officer, for
conductors) with red, white and black bands securing and salvage in the engineering
for phases A, B and C. Thus the cables are spaces, and under the damage control officer
marked to correspond with the terminals, or one of his assistants for the remainder of
which facilitate hooking up properly and the ship. The engineer department should be
speedily. secured and preparations made for receiving
outside assistance such as electric power,
39-13. Smoke in firerooms and engine submersible pumps, towing, etc. Type
rooms. If there are fires near the intakes for instructions are available for the securing
the forced draft and ventilation blowers detail of destroyers.
supplying firerooms and engine rooms smoke
will be drawn into these spaces. Unless 39-16. Summary. In conclusion, the
equipment is provided for operating following points are emphasized:
personnel they eventually will be forced to
abandon the spaces. In ships having air- 1. The engineer department is a vital and
encased boilers, no smoke will be drawn into integral part of the ship's damage-control
https://archive.hnsa.org/doc/dc/part10.htm 19/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
Fires are likely to start wherever a hit occurs 5. The most important mission of the engineer
or where there are electrical short circuits. department is to maintain the mobility and
The maneuverability of the ship at all costs.
334
APPENDIX A
A-2. Mechanics of the experiment. The The following items are suggested for use as
actual mechanics of running this inclining weights:
experiment are as follows:
1. Pig iron or pig lead crated.
1. A large weight (about 1/2 per cent of the 2. Iron or lead billets.
displacement) is moved transversely across 3. Shaft sections.
the deck to produce a list. The heeling 4. Depth charges or projectiles.
moment caused by moving the weight is 5. Bags of sand.
calculated. Both the weight of the weight, and
the distance it is moved, must be carefully Weights can be moved by crane (if available),
determined. on pipe rollers, or by hand. The weight of the
https://archive.hnsa.org/doc/dc/part10.htm 20/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
2. The angle of rotation (change of list) items to be used for the inclining weight
produced by the weight movement is should be accurately determined before the
measured by means of a pendulum and a start of the experiment.
horizontal batten.
A-5. Pendulum. The pendulum used for
3. With the data obtained under 1 and 2 measuring the angle of heel consists of a
above, the metacentric height (GM) of the plumb bob suspended by a light flexible wire.
vessel is calculated from the formula: Any weight heavy enough to keep the wire or
string taut may be used for a plumb bob. The
GM = wd / (W tan θ) pendulum should not be less than 10 feet
long. In the case of large ships, the pendulum
Where: should be from 20 to 25 feet long.
w = inclining weight (long tons).
d distance weight (w) is moved athwartship. To obtain sufficient length, the pendulum
W = displacement of ship (including w) (long probably will have to pass down through a
tons). scuttle or hatch. The tangent of the angle of
θ = angle of list produced by moving the rotation (change of list) -tangent θ-is obtained
inclining weight. by measuring the distance the pendulum wire
moves along a horizontal batten board and
A-3. Equipment Required. The minimum dividing this distance by the length of the
equipment required for performing a check pendulum. To dampen secondary oscillations
inclining experiment is listed below. It may of the pendulum the plumb bob is immersed
be possible to substitute other material which in a bucket of heavy
will work as well as that indicated.
335
https://archive.hnsa.org/doc/dc/part10.htm 21/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
lubricating oil. For greater accuracy it is operation, it should be present when the ship
suggested that two or possibly three is inclined. Stores and ammunition that will
pendulums be set up at various locations in be aboard during the future operation should
the ship. See figure A-1 for assembly of a be brought aboard and stowed in proper
pendulum. location. Liquids in the machinery plant
should approximate operating levels.
A-6. Preparatory measures. Before
conducting the experiment, certain measures An approximate calculation of the existing
should be taken to prepare the ship for the GM should be made. If negative GM is
inclining. suspected, ballast should be added to correct
this condition before the inclining. Remember
Before inclining the ship should have little or that there is to be an inclining weight on the
no list. If the purpose of the check inclining deck during the experiment, and that there
experiment is to determine the stability may be considerable free surface in the ship's
characteristics of the ship for future tanks.
operations, the ship and its loading should be
brought as near to the prospective condition There should be a minimum number of crew
of operation as possible. This will require that and officers aboard during the inclining. Only
tanks be filled to approximate the operating those actually needed for the experiment
condition. If free surface is to exist in the should remain.
ship's tanks during
336
Although all of the crew must be aboard in sets of draft figures at the bow or stern, the
actual operation, the movement of the men on Arabic numbers (0, 1, 2, 3, and so on) are
the ship during the inclining will produce navigational marks; the Roman numerals (X,
greater errors than that introduced by their XI, XII) are the displacement marks; the latter
absence. should be used. When there is only one set of
draft marks they will be Arabic and are used
The inclining weight or weights should be as both navigational and displacement marks.
brought aboard while the ship is still
alongside the pier. Have the pendulum or The initial position of the weights should be
pendulums set up beforehand, and their marked on the deck with chalk or crayon.
lengths measured. With the inclining weights in position the
location of the pendulum is marked on the
A means of communication should be batten board as zero. (There may be slight
established between the location of the oscillations of the pendulum; the average
inclining weights, the pendulum, and the position should be marked.) Try to locate this
officer-in-charge of the experiment. He will zero position at least twice to obtain an
locate himself on the bridge unless a clear average position.
view of all mooring lines is obtainable from
the deck where the inclining weights are When the pendulum recorder signifies that he
located. In that case the officer-in-charge has marked his zero position, the condition of
should be stationed at the weights. Ship the lines should be noted and all future
service phones, sound-powered phones or readings by the pendulum recorder should be
messengers will serve as means of made when the lines are in the same condition
communications. of tautness.
A-7. Mooring conditions. If possible, the After preparations indicated above have been
ship should be inclined in calm water, with made, the inclining weights are moved
little or no wind blowing. However, when athwartship to starboard (or port). When the
such conditions do not prevail, try to locate weights are moved outboard as far as possible
the ship so as to take the wind bow on or and secured from further movement, the
dead astern. If this is not possible, then
https://archive.hnsa.org/doc/dc/part10.htm 22/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
attempt to have the ship on the lee side of a distance moved in feet is measured, recorded,
pier so that it will not be driven into the pier and reported to the calculator.
by the wind. If on the lee side, the wind will
push the ship away from the pier and there As the weights are being moved, the
will not be danger that the ship will bump the pendulum recorder will have to move the
pier during the inclining. With all conditions bucket of lubricating oil so that the pendulum
of wind mooring lines should be reduced to a will not touch the sides. After the weights
minimum and singled up. have been secured, all personnel move back
to the centerline and on word from the
A-8. Shore leads. Shore power leads, steam officer-in-charge of experiment, the
lines, and water hose should be secured and pendulum recorder marks the new location of
removed from ship. If necessary, however, the pendulum wire on the batten board. Then
they may be retained, provided that there is after two or three minutes the pendulum is
sufficient slack in them. These lines should read again to check the previous marking. An
never be taut. The power lead may have to be appreciable difference between these two
retained to supply power to winches for readings indicates a change in conditions, the
moving weights. cause of which must be ascertained and
eliminated. The distance in inches between
A-9. Conduct of the experiment. With the this average mark and the zero mark is
ship ready for inclining, inclining weights measured and reported to the calculator.
aboard and in position, (i.e., on centerline if
possible), pendulum set up, lines singled up The inclining weights are moved to the other
and extra crew put ashore, the actual side of the ship and the measurement of
experiment may begin. weight movement and pendulum deflection
are recorded. All distances are measured from
The gangway is removed and lines are eased the initial position.
until the ship is 5 to 10 feet away from the
pier. Keep as many lines slack as possible; A-10. Calculations. The experiment is now
those that are unavoidably taut should be taut concluded except for the calculations. After
during all readings. the drafts are read and reported, the calculator
must determine the displacement of the vessel
After the vessel has been moved away from from the ship's curves of form. (Where a
the pier, read drafts forward and aft, both port portion of the ship is missing, the
and starboard. Use a whaleboat or a punt for displacement must be estimated by the best
reading drafts. Reading from the pier will means at hand.) Then as each weight
give inaccurate data, especially if the ship has movement and pendulum
even a slight list. When there are two
337
should be moved out to either side again and 8. Cast off steam and water hose and shore
another set of readings made as a check. power cables.
Unless close agreement is obtained, the
results cannot be considered reliable. 9. Single up mooring lines.
A-11. Evaluation and use of results. The 10. Remove the gangway and ease up lines.
GM thus obtained is for the ship with the
inclining weights on board and with most of Execution of the experiment:
the crew ashore. For most ships the inclining
weights will be approximately equal to the 1. Read drafts.
weight of personnel and located at about the
2. Mark the location of inclining weights on
same height above the keel. Therefore the
the deck.
GM obtained from the check inclining
experiment can be used directly for future
3. All personnel on board take positions on
operations. centerline of vessel.
If The Inclining Experiment Booklet contains
4. Mark zero location of the pendulum.
a curve of static stability for the ship at
approximately the same displacement as 5. Move inclining weights athwartship to
when inclined; this curve may be corrected starboard. Secure weights after moving.
for the new position of G.
6. Measure distance moved from the initial
A-12. Summary. A chronological summary position. Report to the calculator.
or check list of the various steps taken in
preparing for and executing the experiment is 7. Personnel return to positions on centerline
as follows: of the ship.
Preparatory measures: 8. Measure deflection of the pendulum.
Report to the calculator.
338
APPENDIX B
SYMBOLS
339
INDEX
(Note: Items indexed by Article; e.g., 10-2 refers to Chapter X, Article 2.)
https://archive.hnsa.org/doc/dc/part10.htm 25/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
340
machinery and piping, 37-7; reports on, 39-2; Flooding, 1-2; additional factors in, 13-9;
resistance to, 1-1; structural, 33-6; survey of, boundaries, determination and establishment
33-2. of, 18-3; control of, 29-16; draft, changes of,
Damage control; bills, 22-11, 23-5, 28-10; 10-14; effect diagram, 9-8; how it takes place,
conditions of readiness for action and, 22-7; 13-5; loss by, 1-8; partial, 13-7; ship girder
drills, 26-17; education for, 22-4; and, 16-22; solid, 13-6.
fundamental elements of, 22-2; information Flotation; center of, 10-3; adding weight at,
sources on, 22-6; library, 22-14; literature, 10-11, 11-11.
26-9; lumber, 31-2; maintenance program, Fog and sprinkler heads, 32-5.
23-12; material and equipment, 22-14; Force, 2-5; at rest, 3-5; outboard, 3-7.
organization, necessity for, 22-3, 23-1; Fragment and flash suppression, 15-14,15-25.
purposes of, 22-1; pumping, 29-18; ships, Framing; bottom, 16-16; transverse, 16-7.
large, 23-2; ships, small, 23-3; ship design Freeboard, 3-4, 4-4; reduction of, 21-4.
and, 38-5; training, 22-5,23-11,34-32. Free communication; constriction of, 13-9;
Deck; covering, 31-2, 31-3; drains, 29-7; effect of, 8-12; evaluation of, 8-14;
stringers, 16-6. Density, 2-4. visualization of, 8-13.
Diagonal, 3-6; for KB and KM curves, 11-6; Free surface; breadth of, 8-8; bulkheads and,
weight shift, 6-6. 8-9; effect on stability, 8-2; evaluation of
Diesel-driven fire pumps, 29-4. effect, 8-4; location of, 8-7; pocketing and, 8-
Displacement, 3-3,4-4,7-2; change for trim by 10; ship's tanks and, 13-9; suppression of, 18-
https://archive.hnsa.org/doc/dc/part10.htm 26/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
stern, 10-4, 11-2; curves, 3-3, 3-6, 11-1, 11-4; 4; variables of, 8-10; visualization of, 8-3.
limiting of, 21-4; minimum, 21-4. Fresh water; for concrete, 39-2; system, 29-
Docking plan, 11-3. 20.
Draft, change of on flooding effect diagram, Fuel oil; hull piping system, 29-1; sequence
10-14; diagram, 11-3, 11-15, 11-16, 11-17; table, 9-8; transfer, 29-19.
displacement, 7-2; marks, 11-2; reading, 11- Furniture, upholstered, 31-2.
3; weight movement, effects on, 10-10.
Drag, 10-15. Garboard strakes, 16-6.
Drainage systems; gravity, 29-7; main, 29-10; Gas; incandescent, 15-4.
mechanical, 29-8; secondary, 29-11; separate, Gas masks, 32-13.
29-12. Gasketed covers, 30-4.
Drains, deck, 29-7; open funnel, isolation of, Gasoline, 31-4.
38-11. Drills, 26-17; repair party, 27-3. Gear; for hull piping systems, 29-2;
Dynamic stability, 4-9. miscellaneous, 36-8; rigging, 36-7; topside,
31-4.
Education; activities, examples of, 26-13; Generators; foam, 32-8.
presentation, methods of, 26-8; subjects, General quarters, 22-7; medical department
general, 26-6; starting program, 26-12; topics stations, 25-3. General Information Book, 29-
suggested, 26-7; visual aids, use of, 26-10. 3.
Eductors, portable, 29-15. General stability diagram; data needed for,
Emergency sound-powered telephones, 28-4. 12-4; description of, 12-2; purpose of, 12-1;
Engineer department; damage control and, results, dependability of, 12-5; uses of, 12-3.
38-1; dispersal of personnel, 38-14; personnel Girder, 16-6.
and organization, 38-6; publications for Glass; cloth of, 31-3; fiber and block
study, 38-3; split-plant operation, 38-7; in insulating material, 31-3.
port, 38-13; training, 38-15. GM; calculation of, 17-5; impaired and
Engineering; bills, 23-5, book, 29-5, 38-8, unimpaired, 14-4; on stability curve, 4-10,7-
38-9; department, battle stations for, 39-3; 3.
damage, 39-1; force and repair parties, 24-4, Gravity; center of, 2-4, 2-7; finding of in
39-4; plates and diagrams, 38-8. ships in design stage, 5-2.
Equipment; adequate, 21-9; fire-fighting, 32-
4; operation of, 30-21; protective, 32-13. Handy billy pump, 29-15,32-10.
Exponents, 2-2. Heel; angle of, 4-2,7-4.
High-explosive magazines; protection of, 15-
Files and records, 31-4. 25.
Fire, 39-14: bills, 32-18; control, 23-1; Hogging stresses, 16-5.
hazards, 31-1,31-2; hose and nozzle, 32-7; Holding bulkhead, 15-13.
marshal, 31-6; retardant material, 31-7,32-16; Holes in hull; above waterline, 34-6; flooding
severe, 1-2; spreading of, 33-7. effect of, 34-7; temporary repairs, 34-9;
Fire-protection officer, 31-6. types, 34-8; under waterline, 34-5; wooden
Fire fighting, 19-4; difficulties of, 32-19; plugs and, 34-10.
group action in, 32-17; organization for, 32- Hookbolts, 34-14.
14, 32-15; parties, 24-4, 32-15. Hull; allowance list, 22-14, 30-20; board, 30-
Fire main; elements of, 29-4; fouling of, 32- 11; flooding effects of holes in, 34-7; holes in
4; weekly inspection of, 32-5. under waterline, 34-5; holes in above
First-aid posts, 23-2; equipment for, 25-4. waterline, 34-6; piping systems, 29-1; repair
Fittings; classification of, 22-9; examples of, book, 29-3.
22-10; with watertight integrity, 30-4. Hull piping systems; compressed air, 29-33;
Flanges; blank, 34-26. construction of, 29-2; condenser-circulating,
Flexibility; of hull piping systems, 29-2. 29-8; damage-control, features of, 29-2;
drainage, 29-7, 29-8, 29-10; fire main, 29-3;
fresh water, 29-20; fuel-oil transfer, 29-1;
gasoline, 29-21; importance of, 30-12; salt
water, 29-1; sea-flooding, 29-17; secondary
drainage, 29-11;
https://archive.hnsa.org/doc/dc/part10.htm 27/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
341
sprinkling and flushing, 29-6; ventilation, 29- emergencies otber than action, 25-6;
22. equipment and material, 25-4; first aid, 25-12;
Hydrostatic pressures, 16-13. general quarters stations, 25-3; maintenance
of equipment, 25-11; stretcher bearers, 25-8;
Impaired stability, 13-1. training methods, 25-10.
Incandescent gases, 15-4. Metacenter, 3-8; transverse, 11-8.
Inclinations, longitudinal, 10-1. Metacentric height, 3-9; computation of
Inclining; arm, 6-5; experiment, 5-3; radius, 3-12; curve of transverse height above
moments, 2-6, 6-5. keel, 3-13; influence of, 3-10; negative, 14-
Inclining experiment; booklet, 21-3; 15; radius, 3-8, 11-9; relationships of, 3-11.
calculations, A-10; conduct of, A-9; Metal sbapes, 36-19.
equipment required, A-3; evaluation of, A-11; Minimum liquids, 21-3.
inclining weight, A-4; mechanics of, A-2; Missile attack, 1-4.
mooring conditions, A-7; necessity for, 5-3; Mobility and maneuverability, 17-10.
pendulum, A-5; performance of, 5-4; Mockups, use in training, 34-33.
preparatory measures, A-6; results of, 5-5,5- Moments, 2-6; of inertia, 2-9, 4-4; trimming,
6; usefulness of, 5-7. 10-8; to change trim, 10-7,11-10.
Inertia, moment of, 2-9. Movement; general effect of weight, 6-2.
Initial stability, 3-8.
Influences of metacentric height, 3-10. Negative metacentric height, 14-5.
Inspections; routine, 30-10. Non-contact explosions; at the side, 15-7;
Insulation, 34-30. under the bottom, 15-9.
Instructors; selection and training of, 26-4. Non-essential combustibles; elimination of,
Intact ship, 17-5. 31-2.
Non-inflammable items; replacement with,
Jumpers, use of, 34-28. 31-3.
Keel; flat, 16-6. Off-center weight, 14-2.
Kerosene, 31-4. Officer-in-charge, damage-control station, 21-
KG; alternative formula for, 7-7. 11.
Oil and water leaks; detection of, 30-6.
Knife edges and bearing surfaces, 30-4. Operation, test, and inspection, 30-15.
Organization and training, 21-10.
Ladder; portable, 35-3. Over-centralization; dangers of, 28-11.
Leaks; armored hatches, 34-17; cracks, 34-
16; rivets and, 34-17; torn seams and, 34-17; Paint; fire retardant, 31-3,31-4.
vacuum, 34-27. Painting, 16-18.
Lever arm, 3-7. Paper and office supplies, 31-4.
Liquid; density of in relation to free surfaces, Partial flooding, 13-7; in free communication
8-5; level in wing tanks, 15-25; loading with the sea, 13-8.
procedure, 21-3; optimum distribution of, 15- Parties; fire, 24-4, 32-15; repair, 23-2, 39-4;
15. securing and salvage, 39-15.
Lighting detail, 24-4. Patches; improvised, 34-13; Jubilee pipe, 34-
List; causes and effects of, 14-6; correcting 23; other types, 34-23; prefabricated plate,
of, 14-8, 17-10; danger of operating 34-12; soft, 34-22; special, 34-14; welded,
machinery with, 39-5; feel of, 14-4, 14-5; 34-15.
minimum, 21-7; minimizing of, 15-25; nature Patrol, 24-4.
of, 14-2; suppression of, 15-14; variations in Pendulum, A-5.
angle of, 14-3. Permeability; beneficial effects of, 8-10;
Literature, 26-9. surface, 13-9; volume, 13-9.
Local strength, 16-12. Personnel; damage-control station, 23-7;
Loading; conditions of, 9-2, 9-6; dynamic, engineering department, 38-11; repair party,
16-17; light 24-3; to be trained, 26-5. Pipe; lines,
condition, 9-5; standard condition, 9-4. blanking, 34-26; sections, renewing of, 34-24;
Longitudinal; inclinations, 10-1; stability, 1- shores and, 36-19; unions 34-24.
8,10-6. Loose water, 8-1, 18-5. Piping; fire main system, 29-4.
https://archive.hnsa.org/doc/dc/part10.htm 28/31
11/1/2020 HANDBOOK OF DAMAGE CONTROL - PART 10
342
curves of, 4-7,7-5; maximum, 4-8. Rotating Structures; basic shoring, 36-12.
shafts, 30-4. Stuffing tubes, 34-17. Submersible pumps,
32-12.
Sagging stresses, 16-4. Superstructure, 16-11. Supplies; cleaning, 31-
Salt-water systems, 29-1. 4. Supports; reinforcing, 30-21.
Salvage party, function of, 17-12; making Symbols, Appendix B.
decision concerning, 17-13. Systems, carbon dioxide, 32-9; compressed
Sand, 37-2. air, 29-23; condenser circulating, 29-8;
Schools, fire-fighting, 32-2. casualty power supply, 39-12; drainage, 29-7;
Screw flanges, 34-24. feed and condensate, 39-10; fire main, 29-3;
Seams; torn, 34-17. flooding, 29-17; fresh water, 29-20; gasoline,
Seamanship; to safeguard structural strength, 29-21; restoration of, 17-10; salt water, 29-1;
17-11. Seaworthiness; restoration of, 19-1, secondary drainage, 29-11; sprinkling and
19-3,21-4. Sectionalization, 29-2; of fire- flushing, 29-6; ventilation, 29-22.
main system, 29-5.
Securing and salvage parties, 39-15. Tactical situation, 17-10.
Segregated sections, 29-5. Tangent, 2-3.
Setting time; of concrete, 37-4. Telephone talkers; battle circuits, 28-2;
Sheathing, 34-6. message form and procedure, 28-9; rules for,
Ship; control, 23-1; design and damage 28-8.
control, 38-5; handling, 19-13; inclined, 3-7; Telescopic shore, 36-5.
in seaway, 16-3; service telephones, 28-6; Tests and inspections, 30-5; check tests, 30-
situation after damage, 19-8; without torpedo 19.
protection, 15-19. Tons per inch immersion curve, 11-5.
Sholes, 36-1,36-2,36-4. Tools, improvised, 35-3; markings, 35-2;
Shore, 36-1; strength of, 36-11; steel, 36-19; storage for small 35-4; storage for large, 35-5.
wooden, 36-2. Shoring; basic structures, 36- Topside weight; addition of, 13-2.
12; chest, 35-3, 36-1, 36-17; instructions, 36- Torpedo; depth, 15-17; at mid-depth, effect
20; material, metal, 36-5; obtaining and of, 15-22; shallow and deep, effect of, 15-23.
storing, 36-6; measuring, cutting, trimming, Torpedo-protection systems; classes of ships
36-13; miscellaneous suggestions, 36-16; designed with, 15-11; design features of, 15-
principles, 36-15; seaworthiness and, 19-12; 13; functions of, 15-14; purpose of, 15-12;
with steel shapes, 36-19; where and when to, situation after damage, 19-6.
36-10.
Silver soldering, 34-33.
Sine, 2-3; curve, 2-3.
Shock wave, 15-4. Sinking bodily, 1-8.
Slings, 35-3.
Sluicing, 8-16.
343
https://archive.hnsa.org/doc/dc/part10.htm 31/31