COMPUTOS METRICOS

Proyecto: Construccion Sistema de riego cajas Baja pucara y collpa ckasa


Modulo: Red de Aduccion principal Comunidad: Hujachi Bajo, Mole Puncu, vila Loma y Sunchu pampa

DIMENCIONES
ITEM DESCRIPCIÓN UNID. CANT. TOTAL
ANCHO ALTO LARGO PARCIAL
1 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML.

ADUCCION
ADUCCION OBRA TOMA A HUJACHI BAJO TUBERIA HDPE D=8¨ 0+000.00 - 4+160.00 1 4160.00 4160.00 4160.00
ADUCCION HUJACHI BAJO A EMPALME MOLLE PUNKU HDPE D=6¨ 4+160.00 - 9+640.00 1 5480.00 5480.00 5480.00
ADUCCION MOLLE PUNKU A ESQ CKASA TUBERIA HDPE D=4¨ 9+640.00 - 9+750.00 1 110.00 110.00 110.00
ADUCCION ESQ CKASA A VILA LOMA TUBERIA HDPE D=3¨ 9+750.00 - 10+791.00 1 1041.00 1041.00 1041.00
ADUCCION ESQ CKASA A MOLLE PUNCU TANQ 1 TUBERIA HDPE D=3¨ 0+000.00 - 0+750.00 1 750.00 750.00 750.00
ADUCCION MOLLE PUNCU TANQ 1 A MOLLE P TANQ 2 TUBERIA HDPE D=2¨ 0+750.00 - 1+158.00 1 408.00 408.00 408.00
ADUC ESQ CKASA A SUNCHU PAMPA TANQ 1 TUBERIA HDPE D=3¨ 0+000.00 - 1+270.00 1 1270.00 1270.00 1270.00
ADUC SUNCHU PAMPA TANQ 1 A SUNCHU PAMPA TANQ 2 TUBERIA HDPE D=2¨ 1+270.00 - 2+005.00 1 735.00 735.00 735.00
ADUCC HUAJCHI HACIA TANQUE 1 TUBERIA HDPE D=2¨ 0+000.00 - 0+020.00 1 20.00 20.00 20.00
ADUCC HUAJCHI HACIA TANQ 2 TUBERIA HDPE D=2¨ 0+000.00 - 0+200.00 1 200.00 200.00 200.00
ADUCC HUAJCHI HACIA TERRENOS 3 TUBERIA HDPE D=3¨ 0+000.00 - 0+135.00 1 135.00 135.00 135.00
ADUCC HUAJCHI HACIA TERRENOS 1 TUBERIA HDPE D=3¨ 0+000.00 - 0+483.00 1 483.00 483.00 483.00
TOTAL 14792.00
2 EXCAVACION EN ROCA (MANUAL) M3
ADUCCION OBRA TOMA A HUJACHI BAJO TUBERIA HDPE D=8¨ 0+000.00 - 1+150.00 1 0.40 0.60 1150.00 276.00 276.00

ADUCCION OBRA TOMA A HUJACHI BAJO TUBERIA HDPE D=8¨ 1+150.00 - 4+160.00 1 0.40 0.60 3010.00 722.40 722.40
ADUCCION HUJACHI BAJO A EMPALME MOLLE PUNKU HDPE D=6¨ 4+160.00 - 9+640.00 1 0.40 0.60 5480.00 1315.20 1315.20
ADUCCION MOLLE PUNKU A ESQ CKASA TUBERIA HDPE D=4¨ 9+640.00 - 9+750.00 1 0.40 0.60 110.00 26.40 26.40
ADUCCION ESQ CKASA A VILA LOMA TUBERIA HDPE D=3¨ 9+750.00 - 10+791.00 1 0.40 0.60 1041.00 249.84 249.84
ADUCCION ESQ CKASA A MOLLE PUNCU TANQ 1 TUBERIA HDPE D=3¨ 0+000.00 - 0+750.00 1 0.40 0.60 750.00 180.00 180.00
ADUCCION MOLLE PUNCU TANQ 1 A MOLLE P TANQ 2 TUBERIA HDPE D=2¨ 0+750.00 - 1+158.00 1 0.40 0.60 408.00 97.92 97.92
ADUC ESQ CKASA A SUNCHU PAMPA TANQ 1 TUBERIA HDPE D=3¨ 0+000.00 - 1+270.00 1 0.40 0.60 1270.00 304.80 304.80
ADUC SUNCHU PAMPA TANQ 1 A SUNCHU PAMPA TANQ 2 TUBERIA HDPE D=2¨ 1+270.00 - 2+005.00 1 0.40 0.60 735.00 176.40 176.40
ADUCC HUAJCHI HACIA TANQUE 1 TUBERIA HDPE D=2¨ 0+000.00 - 0+020.00 1 0.40 0.60 20.00 4.80 4.80
ADUCC HUAJCHI HACIA TANQ 2 TUBERIA HDPE D=2¨ 0+000.00 - 0+200.00 1 0.40 0.60 200.00 48.00 48.00
ADUCC HUAJCHI HACIA TERRENOS 3 TUBERIA HDPE D=3¨ 0+000.00 - 0+135.00 1 0.40 0.60 135.00 32.40 32.40
ADUCC HUAJCHI HACIA TERRENOS 1 TUBERIA HDPE D=3¨ 0+002.00 - 0+483.00 1 0.40 0.60 481.00 115.44 115.44

30 %
TOTAL 1258.08
DIMENCIONES
ITEM DESCRIPCIÓN UNID. CANT. TOTAL
ANCHO ALTO LARGO PARCIAL
3 EXCAVACION (0-1 M.) S. DURO M3
ADUCCION OBRA TOMA A HUJACHI BAJO TUBERIA HDPE D=8¨ 0+000.00 - 1+150.00 0 0.00 0.00 0.00 0.00 0.00

ADUCCION OBRA TOMA A HUJACHI BAJO TUBERIA HDPE D=8¨ 1+150.00 - 4+160.00 1 0.40 0.60 3010.00 722.40 722.40
ADUCCION HUJACHI BAJO A EMPALME MOLLE PUNKU HDPE D=6¨ 4+160.00 - 9+640.00 1 0.40 0.60 5480.00 1315.20 1315.20
ADUCCION MOLLE PUNKU A ESQ CKASA TUBERIA HDPE D=4¨ 9+640.00 - 9+750.00 1 0.40 0.60 110.00 26.40 26.40
ADUCCION ESQ CKASA A VILA LOMA TUBERIA HDPE D=3¨ 9+750.00 - 10+791.00 1 0.40 0.60 1041.00 249.84 249.84
ADUCCION ESQ CKASA A MOLLE PUNCU TANQ 1 TUBERIA HDPE D=3¨ 0+000.00 - 0+750.00 1 0.40 0.60 750.00 180.00 180.00
ADUCCION MOLLE PUNCU TANQ 1 A MOLLE P TANQ 2 TUBERIA HDPE D=2¨ 0+750.00 - 1+158.00 1 0.40 0.60 408.00 97.92 97.92
ADUC ESQ CKASA A SUNCHU PAMPA TANQ 1 TUBERIA HDPE D=3¨ 0+000.00 - 1+270.00 1 0.40 0.60 1270.00 304.80 304.80
ADUC SUNCHU PAMPA TANQ 1 A SUNCHU PAMPA TANQ 2 TUBERIA HDPE D=2¨ 1+270.00 - 2+005.00 1 0.40 0.60 735.00 176.40 176.40
ADUCC HUAJCHI HACIA TANQUE 1 TUBERIA HDPE D=2¨ 0+000.00 - 0+020.00 1 0.40 0.60 20.00 4.80 4.80
ADUCC HUAJCHI HACIA TANQ 2 TUBERIA HDPE D=2¨ 0+000.00 - 0+200.00 1 0.40 0.60 200.00 48.00 48.00
ADUCC HUAJCHI HACIA TERRENOS 3 TUBERIA HDPE D=3¨ 0+000.00 - 0+135.00 1 0.40 0.60 135.00 32.40 32.40
ADUCC HUAJCHI HACIA TERRENOS 1 TUBERIA HDPE D=3¨ 0+002.00 - 0+483.00 1 0.40 0.60 481.00 115.44 115.44

70 %
TOTAL 2291.52
4 PROV. Y TEND. TUBERIA HDPE. D= 8" PN6 SDR 26 H= Ml

ADUCCION OBRA TOMA A HUJACHI BAJO TUBERIA HDPE D=8¨ 0+000.00 - 2+080.00 1 2080.00 2080.00 2080.00
TOTAL 2080.00
5 PROV. Y TEND. TUBERIA HDPE. D= 8" PN12 SDR 13,6 H= Ml

ADUCCION OBRA TOMA A HUJACHI BAJO TUBERIA HDPE D=8¨ 0+000.00 - 2+080.00 1 2080.00 2080.00 2080.00
TOTAL 2080.00
6 PROV. Y TEND. TUBERIA HDPE. D= 6" PN6 SDR 26 H= Ml

ADUCCION HUJACHI BAJO A ESQ CKASA TUBERIA HDPE D=6¨ 4+160.00 - 9+640.00 1 5480.00 5480.00 5480.00
TOTAL 5480.00
7 PROV. Y TEND. TUBERIA HDPE. D= 6" PN12,5 SDR 13,6 H= Ml

ADUCCION HUJACHI BAJO A ESQ CKASA TUBERIA HDPE D=6¨ 0+000.00 - 1+000.00 1 1000.00 1000.00 1000.00
TOTAL 1000.00
8 PROV. Y TEND. TUBERIA HDPE. D= 4" PN8 SDR 21 H= Ml

ADUCCION ESQ CKASA A VILA LOMA TUBERIA HDPE D=4 9+750.00 - 10+791.00 1 1041.00 1041.00 1041.00

TOTAL 1041.00
DIMENCIONES
ITEM DESCRIPCIÓN UNID. CANT. TOTAL
ANCHO ALTO LARGO PARCIAL
9 PROV. Y TEND. TUBERIA HDPE. D= 3" PN8 SDR 21 H= 128.61 Ml
ADUCCION ESQ CKASA A VILA LOMA TUBERIA HDPE D=3¨ 9+750.00 - 10+791.00 1 0.40 0.60 1041.00 249.84 249.84
ADUCCION ESQ CKASA A MOLLE PUNCU TANQ 1 TUBERIA HDPE D=3¨ 0+000.00 - 0+750.00 1 0.40 0.60 750.00 180.00 180.00
ADUC ESQ CKASA A SUNCHU PAMPA TANQ 1 TUBERIA HDPE D=3¨ 0+000.00 - 1+270.00 1 1270.00 1270.00 1270.00
ADUCC HUAJCHI HACIA TERRENOS 3 TUBERIA HDPE D=3¨ 0+000.00 - 0+135.00 1 0.40 0.60 135.00 32.40 32.40
ADUCC HUAJCHI HACIA TERRENOS 1 TUBERIA HDPE D=3¨ 0+002.00 - 0+483.00 1 0.40 0.60 481.00 115.44 115.44

TOTAL 1597.84
10 PROV. Y TEND. TUBERIA HDPE. D= 2" PN8 SDR 21 Ml
ADUCCION MOLLE PUNCU TANQ 1 A MOLLE P TANQ 2 TUBERIA HDPE D=2¨ 0+750.00 - 1+158.00 1 0.40 0.60 408.00 97.92 97.92
ADUC SUNCHU PAMPA TANQ 1 A SUNCHU PAMPA TANQ 2 TUBERIA HDPE D=2¨ 1+270.00 - 2+005.00 1 0.40 0.60 735.00 176.40 176.40
ADUCC HUAJCHI HACIA TANQUE 1 TUBERIA HDPE D=2¨ 0+000.00 - 0+020.00 1 0.40 0.60 20.00 4.80 4.80
ADUCC HUAJCHI HACIA TANQ 2 TUBERIA HDPE D=2¨ 0+000.00 - 0+200.00 1 0.40 0.60 200.00 48.00 48.00

TOTAL 0.00
11 RELLENO Y COMPACTADO MANUAL C/TIERRA SELECCIONADA M3
1 0.40 0.30 14792.00 1775.04 1775.04

TOTAL 1775.04
12 RELLENO Y COMPACTADO MANUAL C/TIERRA COMUN M3
1 0.40 0.30 14792.00 1775.04 1775.04

TOTAL 1775.04
13 PRUEBA HIDRAULICA (HASTA D=12") ML.
1.00 14792.00 14792.0 14792.00

TOTAL 14792.00
14 PUENTE COLGANTE ACUEDUCTO (L=50m +/- 5 M) Pza 1.00 1.00 1.00

TOTAL 1.00
15 PUENTE COLGANTE ACUEDUCTO (L=40m +/- 4 M) Pza 1.00 1.00 1.00

TOTAL 1.00
16 PUENTE COLGANTE ACUEDUCTO (L=30m +/- 3 M) Pza 1.00 1.00 1.00

TOTAL 1.00
17 PUENTE COLGANTE ACUEDUCTO (L=20m +/- 2 M) Pza 20.00 1.00 20.00

TOTAL 20.00
18 PUENTE COLGANTE ACUEDUCTO (L=15m +/- 2 M) Pza 13.00 1.00 13.00

TOTAL 13.00
DIMENCIONES
ITEM DESCRIPCIÓN UNID. CANT. TOTAL
ANCHO ALTO LARGO PARCIAL
19 PUENTE COLGANTE ACUEDUCTO (L=10m +/- 1 M) Pza 13.00 1.00 13.00

TOTAL 13.00
20 PUENTE PASO QUEBRADA (L=6m +/- 1 M) Pza 23.00 1.00 23.00

TOTAL 23.00
21 CAMARA DE REPARTICION (0,8X0,80) Pza 7.00 1.00 7.00

TOTAL 7.00
22 ACCESORIOS DE CAMARA DE REPARTICION Glb 7.00 1.00 7.00

TOTAL 7.00
23 CAMARA DE PURGAS (0,6X0,60) Pza 10.00 1.00 10.00

TOTAL 10.00
24 ACCESORIOS DE CAMARA DE PURGAS Glb 10.00 1.00 10.00

TOTAL 10.00
25 CAMARA DE AIRE (0,4X0,40) Pza 10.00 1.00 10.00

TOTAL 10.00
26 ACCESORIOS DE CAMARA DE AIRE Glb 10.00 1.00 10.00

TOTAL 10.00