Documente Academic
Documente Profesional
Documente Cultură
24. The concrete has been tested for consistency by the use of a slump cone with base and
tamping rod. After the test, the highest concrete measured is 178 mm. What is the slump of
the concrete?
127mm (height of slump cone = 305mm)-(height of fresh conc after subsidence = 178)
25. What is the rate of revolution per time of an abrasion machine used for testing the mass
percent of wear?
30 – 33 rpm
26. If the design of concrete mix has the following corrected batch weights: current = 40 kgs, fine
aggregates = 65 kgs, coarse aggregate = 115 kgs, and water = 15 liters. What is your actual
batch weight for 1 cu.m Class “A” concrete?
360 bags of cement; 585 kgs of the aggregations; 1035 kgs of coarse
aggregates; 130 liters of water (provide computation)multiply the given weight by 9
27. Why is it that 6 samples are needed for quality test of concrete masonry?
3 samples for compressive strength and 3 samples for absorption
28. The ME should always be alert of his schedule with regards to the number of days of a quality
test that takes place. Since not all construction materials can be tested just for a day or even
a week so, what is the lead time should he consider for a quality test of a cement sample?
One (1) month
29. Properties of concrete are, except
workability, strength, durability, cracking
30. Minimum time for removal of forms and false works for centring under girders, beams, frames,
and arches
14 days (minimum % of design strength – 80%)
31. Minimum time for removal of forms and false works for floor slabs.
14 days (minimum % of design strength – 70%)
32. Minimum time for removal of forms and false works for walls.
1 day (minimum % of design strength – 70%)
33. Minimum time for removal of forms and false works for columns.
2 days (minimum % of design strength – 70%)
34. Minimum time for removal of forms and false works for side of beams and all other vertical
surfaces.
1 day (minimum % of design strength – 70%)
35. A mass of solid reinforced concrete cast around the head of a group of piles to ensure that act
as a unit to support the imposed load.
Pile Cap
36. Class of concrete deposited in water.
Class Seal 9.5 bags 20.7MPa(3,000psi)25mm(1” Aggregates)
37. Class of concrete used in all superstructures and heavily reinforced substructures. The
important parts of the structure included are slabs, beams, girders, columns, arch ribs, box
culverts, reinforced abutments, retaining walls and reinforced footings.
Class A 9 bags 20.7MPa(3,000psi)37.5mm(1½” Aggregates)
38. Class of concrete used in footings, pedestal, massive pier shafts, pipe bedding and gravity
walls, unreinforced or with only a small amount of reinforcement.
Class B 8 bags 16.5 MPa(2,400psi)50 mm(2” Aggregates)
39. Class of concrete used in thin reinforced sections, railings, pre-cast piles, cribbing, and for
filler in steel grid floors.
Class C 9.5 bags 20.7MPa(3,000psi)12.5mm(½” Aggregates)
40. Class of concrete used in pre-stressed concrete structural members
Class P 11 bags 37.7 MPa(5,000psi)19 mm(¾” Aggregates)
41. Height of dropping concrete to the point of deposit
1.50m
42. Concrete beam sample when tested by Third – Point Method shall have a flexural strength of
______ when tested in 14 days.
3.80 MPa (550 psi)
43. The required flexural strength of concrete beam sample of item 311 when tested by the
midpoint method.
4.50 MPa (650 psi) for third point (550 psi-3.8 MPa)
44. If slag is used as coarse aggregate for item 311, the minimum density is _______
1,120 kg/m3
45. Minimum price allowed of contract for deficiency in strength of concrete specimens for PCCP
which 10% to less than 15%.
70%
46. This joint is also called cold joint. It is constructed when there is an interruption of more than
30 minutes in the concreting operation.
Transverse Construction Joint
47. If the paving of concrete pavement will be done at the rate of 200 l.m, half width per paving
day, how many sets of concrete beam samples shall be required.
Given: A = 115,000 sq.m, width = 6.50m, thickness = 230mm
353 sets = (115,000 x .23)/75=352.67 say 353 sets
48. It is used for the rapid in – situ measurement of the structural properties of existing pavement
with unbound and granular properties.
Dynamic Cone Penetrometer
49. What is the equipment used to pinpoint rebar’s, conduits, pipes, nails, and other metals
embedded in concrete before cutting or drilling
Rebar Locator
50. It is an instrument used to measure pavement deflection resulting from vehicle wheel
loadings. The results of the elastic deformation test are used to evaluate the structural
condition of roads, and to help in the design of road strengthening measures and road
capacity improvement
Benkelman Beam and Deflection Logger
51. What is the instrument that is used for examining the quality of rigid materials such as rocks
and concrete? This instrument is a non-destructive portable instrument with dimensions of
110mm x 180mm x 160 mm and its main uses includes the determination of concrete strength
(either in – situ or pre - cast), also to determine the presence of voids, cracks and other
imperfections.
Pundit Ultrasonic Concrete Tester
52. The concrete pavement surface shows high spots of 15mm in a 3 – m straight edge. The
concrete in the area represented by these high spots______
shall be removed and replaced (but if high spots being noted exceeds 3 mm
but not exceeding 12 mm, it shall be ground down only)
53. In case of scarcity or non-availability of Type I Portland cement, what type of pozzolan shall
be used?
Portland Pozzolan Cement Type 1P
54. The required forms to be used in concrete pavement are______
Steel forms of an approved section
55. Sawing of the weakened plane joints shall be done usually at _______
within 24 hours
56. Removal of forms of concrete pavement
24 hours
57. The required slump of concrete using slip – form method of paving is ___________
1½ inches (40mm)
58. Deficiency is strength of concrete specimen wherein payment of contract price allowed is
25% or more
59. What is the length of a lot pavement when a single traffic lane is poured?
1,000 ln.m
60. What is the length of a lot pavement when two single traffic lanes is poured?
500 ln.m
61. What is the required size of concrete beam sample?
150mm x 150mm x 525mm (6”x6”x21”)
62. What is the required number of set of concrete beam specimens to be taken from each 330
sq.m of pavement and fraction thereof placed each day? ( 330m x 0.23m = 75 m3)
1 set
63. What is the required compressive strength that concrete piles be moved?
80% of designed 28-day compressive strength
64. The required circular pin diameter used to bend 10 – 20 mm Ø reinforcing steel.
6d (20mm – 25mm Ø =8d), (28mm Ø and above = 10d)
65. What is the slump of concrete Class A deposited in water?
10 to 20cm
110. The surface of a newly put concrete when has sufficiently set shall be cured for a period
of_____.
72 hours
111. The curing of the pavement is done by means of the following:
By covering the concrete with mats saturated with water
By thoroughly wetting the pavement
By ponding
By applying curing compound immediately after finishing of the surface
112. When is the right time to seal the joints?
After the curing period or before it is opened to traffic
113. What is the difference between Item 504 and Item 505 (bluebook ’95)?
The placement of stone or boulders and the ratio of cement and fine sand
114. The maximum absorption content of CHB
240 kg/m2
115. The maximum moisture content of CHB
45%
116. The allowable % variation in mass of deformed reinforcing steel is
6% maximum under nominal stress
117. The maximum allowable % phosphorus content of a deformed and plain ballet steel bar is
0.06%
118. Tensile and yield strengths of steel bars?
Tensile Strength Yield Point
Grade 40 483 MPa 276 MPa
Grade 60 621 MPa 414 MPa
Grade 75 689 MPa 517MPa
119. In truck mixing, the minimum number of revolution after all ingredients including water is in the
drum is
100 rpm
120. Mortar shall be used within in ___ after its preparation.
90 minutes
121. In placing concrete for slabs, using buggies, the correct method that should be followed is
Concrete should be dumped into the face of the previously placed concrete
122. There is a failure of flexural strength in the pavement, if you are the ME of your firm, what will
you recommend?
Conduct recoring
123. It is an impervious membrane applied to concrete pavement before its initial setting that
prevents rapid evaporation of water from the mix.
Curing compound
124. The test that determines the resistance of aggregates to disintegration by saturated solution
sulfate or magnesium sulfate.
Soundness test
125. The design of concrete mix specified in the bluebook is based on
Absolute Design Method
126. The initial setting time of Portland cement is not less than
45 minutes
127. The final setting time of Portland cement
10 hours
128. The standard sand used in testing the mortar strength of Portland cement
Ottawa sand
129. The apparatus used to determine the fineness of Portland cement by air permeability.
Blaine Air Permeability Apparatus
130. A mixture of cement and water is
Cement paste
131. The apparatus used to determine the initial and final setting of Portland cement in the
laboratory
Gillmore Needle
132. Le Chattelier Flask is an apparatus used in determination of specific gravity of Hydraulic
Cement.
390 grams
230. Wt. of steel spheres.
455 grams
231. No. of spheres needed & weight of sample/grading.
Grading A – 12 spheres – 5000 ± 25 grams
Grading B – 11 spheres – 4584 ± 25 grams
Grading C – 8 spheres – 3330 ± 20 grams
Grading D – 6 spheres – 2500 ± 15 grams
232. Defined as the product obtained by burning to incipient fusion a properly proportioned mixture
of argillaceous and calcareous materials.
Portland Cement
233. This is burnt product which is used by Gypsum and pulverized to form Portland cement.
Clinker
234. This reacts or combined with H2O, one that will harden underwater.
Hydraulic Cement
235. This is the heat produced by the chemical reaction between cement and H 2O.
Heat of Hydration
236. This is the process in which the cement reacts or combined chemically with H 2O.
Hydration
237. Those materials that contribute Silica (SiO2), Alumina (Al2O3) and Iron Oxide (Fe2O3) to the
clinker, its include clay, shale, iron ore and sand, etc.
Argillaceous Raw Materials
238. Those material which contribute Lime (CaO) and Magnesia (MgO) to the clinker, its include
limestone, chalk, marls, marine oyster shells, etc.
Calcareous Raw Materials
239. This type of cement is used for General Construction.
Normal Cement or Type I
240. These are used where sulfate concentration in ground waters are higher than normal but not
sever, generate heat at a slower rate than normal.
Moderate Sulfate Resistant or Type II
241. This type develops approximately 190% of the strength of Type 1 at 3 days & 90 to 130% at
28 days.
High Early Strength or Type III
242. This is special cement for use where the amount and rate of heat generated must be
minimized.
Low Heat of Hydration or Type IV
243. Special cement intended to be used in structure to prevent damaged from severe sulfate
action of soils or high alkali content of H 2O.
Sulfate Resistant or Type V
244. The consistency of the concrete mixture should be checked frequently by this test.
Slump Test
245. Slump of concrete deposited in water.
between 10 – 20 cm
246. The minimum cement content of concrete deposited in water.
400kg/cu.m. of concrete
247. The maximum distance of the discharge point from the point of deposit by pneumatic means.
3.0 meters
248. The maximum time for consolidation/compaction of structural/concrete.
15 seconds
249. The space interval of inserting vibrator that should be withdrawn vertically to penetrate
underlying lift for homogeneity between lifts.
50 – 60 cm
250. Min. bar lapping for tension.
24 bar Ǿ for G40
36 bar Ǿ for G60
251. Min. bar lapping distance for compression.
20 bar Ǿ for G40
24 bar Ǿ for G60
252. Min. separation of splices when staggered.
40 bar Ǿ
253. Consist of furnishing, placing and finishing concrete in all structures except pavement
conforming to the lines, grade and dimensions.
Structural Concrete
254. Min. grouting pressure for bonding tendons.
0.6894 MPa (100 psi)
255. When concrete pile cast in place formed by first removing the soil by drilling and filling the
void by concrete.
Bored Pile
256. The instrument used in placing concrete in water in a compact mass in its final position.
Tremie with 250 mm Ø
257. Max. Length of tremie pile and its diameter.
2.5 meters and 20cm Ø
258. Length of tremie pipe that must be submerged into concrete.
2 – 6 m w/ Bentonite
3.5 m without Bentonite
259. What is density of Bentonite to 1cu.m of H2O.
30 -100 kilos/cu.m
260. Reinforcement that consists of spiral bars coiled outside the main longitudinal reinforcement.
Transverse Reinforcement
261. The usual size of the stiffening rings.
2.5mm Ø
262. The minimum spacing of steel bars on bored piles to ensure that concrete would still flow
outwards to the walls of the bored piles.
100 mm
263. Must be within the limit of water cement ratio for concrete.
0.50 – 0.60
264. Required revolution of concrete mixer.
4 – 6 RPM
265. The minimum revolution for each concrete mix.
100 Revolutions
266. The minimum interval of concrete pouring to avoid cold joint.
30 minutes
267. The main objective of this design is to determine the main proportion of the ingredients that
will produce concrete of the proper workability when fresh and the desired durability and
strength after it has hardened.
Design of the Concrete Mixture
268. This should be done during the first seven days in order that the expected development of
strength will be obtained and the occurrence of plastic cracks will be prevented or minimized.
Curing of Concrete
269. For item 505 (Stone Masonry) qty of Cement & Fine Aggregate.
Cement – 2 bags/cu.m
F.A. – 0.17 cu.m/cu.m of concrete
270. Placing of Riprap must be
Perpendicular to the slope
271. Placing of stone masonry must be
Parallel to the slope
272. Min. required of weep-holes & their diameter Ø
2 meters o. c. & 2” Ø
273. Strength requirement for PCCP
Flexural = 500 psi
Compressive = 3,550 psi
274. If concrete is continuously moist, cured, it will gain strength beyond 180 days
True
275. The quality of paving concrete is usually measured by its
Flexural Strength
276. Generally speaking, batching of aggregate by volume is preferable than weight
False
277. If angular coarse aggregate is used in concrete mix, it will require more
300. The completed pavement shall be accepted on a lot basis. A lot shall be considered as 500
linear meter double lane.
301. E a c h l o t s h a l l b e d i v i d e d i n t o 5 e q u a l s e g m e n t s a n d o n e c o r e will be
obtained from each segment in accordance with AASHTO T24.
paste and fines at the surface. This overly rich surface is then a prime candidate
for cracking.
c) Finishing or bull floating concrete with bleed H 2O on the surface, over-trowelling
or premature trowelling increases the water / cement ratio, creating a weak
surface layer and adding to the susceptibility of cracking and later dusting.
d) Additional Dry Cement sprinkled on the surface to dry up on overly wet surface
can cause alligator cracking.
e) Additional H2O added to the surface of dry shake and toppings as finishing aid is
another prime cause for alligator cracks.
Alligator cracks are usually 3mm deep.
Plastic Shrinkage cracks area generally 1 meter apart and 12mm deep.
345. In placing concrete for slab using buggies, the correct method will be.
a) Concrete should be dumped into face of previously placed concrete.
b) Dump concrete away from previously placed concrete
c) Any of a) & b)
346. The strength of # 5 steel bar that was tested for;
Yield Load = 13,000 lbs.
Ultimate Load = 30,000 1bs Yield Load, lbs
Determine the grade of steel? Yield Stress, psi =------------------------
a) Grade 30 Area of bar, in2
b) Grade 40 = 13,000 lbs
c) Grade 60 0.31 in2
= 41,935 lbs/in2 say 40,000 = Grade 40
347. Scales for weighing aggregates and cement shall be accurate within ____ %
throughout the range of use. Scales shall be inspected and sealed as often as the Engineer
may deem necessary to assure their continued accuracy.
a) 1.0 %,
b) 1.5 %
c) 0.5 %
348. Concrete admixtures used when the normal setting time is shortened by higher temperature,
preventing the formation of cold joint, reduce the incidence of thermal cracking and to
maintain concrete workability during large pours or long ready-mix hauls;
a) Accelerator
b) Retarders
c) Superplasticizers
349. An angular coarse aggregate use for concrete mix will provide more;
a) Water content
b) Cement and water
c) Cement and fine aggregates
350. Thickness determination of concrete cores shall be done at;
a) 4 measurements
b) 6 measurements
c) 9 measurements
351. No. of sets of concrete cylinder sample taken for every 75 cu.m. of concrete;
a) 1 set (3 cylinder)
b) 2 sets (6 cylinder)
c) 3 sets (9 cylinder)
352. There is a failure of flexural strength in the pavement, if you are the ME of your firm, what will
you recommend?
a) Reject
b) Recoring
c) Remove and replace
353. Most effective factor for strength of concrete;
a) Water-cement ratio
b) Water , cement and fine aggregates
c) Cement plus water
354. Number of hours that concrete cylinder sample to be submitted to the laboratory before
testing;
a) 24 hours
b) 48 hours
Concrete & Concrete Products Page 16/25
MATERIALS ENGINEERS (DPWH) ACCREDITATION EXAM REVIEWER II
c) 12 hours
355. Required weight of sample for testing for coarse aggregates use for concreting;
a) 40 kgs
b) 50 kgs
c) 70 kgs
356. Required weight of sample for testing for fine aggregates use for concreting;
a) 40 kgs
b) 50 kgs
c) 70 kgs
357. Most specifications for concrete exposed to weathering require that water-cement ratio;
a) 0.46
b) 0.53
c) 0.55
358. What test of cement determines the amount of water required to prepare hydraulic cement
testing?
a) Specific Gravity
b) Normal Consistency
c) Time of Setting
359. A concrete road section was not accepted for payment because beam samples representing
said section failed to meet specified strength requirements. As Materials Engineer of the
project, what would you recommend?
a) Conduct T-core test for strength determination
b) Conduct Field Density Test
c) Remove and replace said section
360. ____________ are materials added to the concrete mix immediate before or during mixing to
modify one or more properties of concrete in the fresh or hardened state.
a) Curing Compound
b) Admixtures
c) Sulfate
361. _____________ is the heat produced by the chemical reaction of cement and water.
a) Heat of hydration
b) Hydrolysis
c) Incipient fusion
362. In breaking cylinder samples, the load should be applied at a uniform rate within the range of
_________ per minute.
a) 20 – 50 psi
b) 120 – 130 psi
c) 125 – 175 psi
363. Ends of cylinder samples which are not plane within ____ shall be capped.
a) 0.050 mm
b) 0.050 in
c) 0.050 cm
364. Concrete specimen molded in a 6” x 6” x 21” beam mold should be rodded
a) 60
b) 61
c) 62
d) 63 times (1 blows per 2 inch2)
365. Quality determination of concrete coarse aggregate sample requires
a) abrasion test
b) sieve analysis
c) stability
d) both a and b
366. Concrete fine aggregate should be tested for
a) compaction
b) stripping
c) stability
d) none of the preceding
367. Admixtures are used to
a) improve workability
b) increase strength
Concrete & Concrete Products Page 17/25
MATERIALS ENGINEERS (DPWH) ACCREDITATION EXAM REVIEWER II
369. Angular coarse aggregate will require more___ per unit volume of concrete
a) sand
b) water
c) both a and b
370. Slump test could be used to detect
a) increase in cement content
b) increase in water
c) increase in volume
d) increase in aggregate
371. Greatest net water is required in a concrete mix with
a) very coarse
b) coarse
c) fine
d) very fine, fine aggregate
372. If the concrete beam specimen is raptures during test outside the middle third, but within 5%
of the span length, the formula to be used in computing the stress is
a) R = PL/bd2
b) R = 3Pa/bd2
c) R = PLa/bd2
373. In molding concrete cylinder specimen, each layer should be rodded ___ times.
a) 25
b) 56
c) 60
d) 100 times
374. Concrete cylinder sample should be molded in ____ equal layers
a) 1
b) 2
c) 3
d) 4
375. Maintaining the water-cement ratio, the concrete containing____ maximum size of aggregates
will develop the highest strength.
a) 50.0 mm
b) 37.5 mm?? ? ?
c) 19.0 mm
d) 12.5 mm,
376. Paving concrete will need less____ than structural concrete
a) sand
b) water
c) coarse aggregates
d) both a & b
377. Tests for coarse aggregate include
a) abrasion
b) mortar strength
c) absorption
d) all of the preceding
378. Tests for fine aggregate for concrete include
a) gradation
b) mortar strength
c) abrasion
d) all of the preceding
379. Unless otherwise specified in the special provision, the type of Portland cement used in
paving concrete shall be
a) Type I
b) Type II
c) Type III
Concrete & Concrete Products Page 18/25
MATERIALS ENGINEERS (DPWH) ACCREDITATION EXAM REVIEWER II
d) Type IV
388. The more the concrete is exposed, the greater the range of movement is.
a) true
b) false
c) it depends upon the type of cement
389. The samples of RSB to be submitted for test should be at least
a) 20 cm
b) 40 cm
c) 100 cm
390. For ITEM 311 PCCP, coarse aggregate shall have a mass percent of wear not
exceeding___ when tested by AASTHO T-96
a) 50%
b) 40%
c) 45%
d) 60%
391. At least one (1) set of 3 cylinder samples shall be taken from____ cu.m. of each
class of concrete or fraction thereof, placed each day
a) 50
b) 75
c) 100
Concrete & Concrete Products Page 19/25
MATERIALS ENGINEERS (DPWH) ACCREDITATION EXAM REVIEWER II
d) 150
392. Fine aggregates used in concrete pavement shall contain no more than ____ of
material passing the 0.075mm sieve by washing
a) 1.5%
b) 3%
c) 4%
d) 1%
393. Requirement of PCCP construction
a) opening to traffic after 14 days the concrete was placed
b) opening to traffic after 28days the concrete was placed
c) a compressive strength of 25.08 Mpa or more
394. In manufacture of culvert pipes, the class of concrete used is
a) Class “C”
b) Class “B”
c) Class “A”
395. A Portland cement concrete pavement, 6.5m wide and 23 cm. thick will be
constructed for a total paved area of 165,000 m2. Angular coarse aggregate will be
used. If pavement will be opened to traffic 14 days
a) How many bags of cement will be required for Class “A”
concrete?
b) How many quality tests are required for the cement?
c) How many quality and grading tests each are required for the
coarse and fine aggregates?
d) How many sets of concrete beam samples will be required?
V concrete = 165,000 x 0.23 = 37,950 m3
a) cement= 37,950 x 9 = 341,550 bags
b) QT of cement = 341,550/2000 = 171
c) V F A = 37,950 x 0.54= 20493 ; Q F A = 20,493/1500= 14
: G F A = 20,493/75 = 274
; G C A = 25,806/75 = 345
d) 37,950/75 = 506 sets
396. The localized upward displacement of a pavement due to swelling of the subgrade or some
portion of the pavement structure.
a) Upheaval
b) ravelling
c) edge cracking
397. Scales for weighing aggregates and cement shall be accurate within ____ %
throughout the range of use. Scales shall be inspected and sealed as often as the Engineer
may deem necessary to assure their continued accuracy.
d) 1.0 %,
e) 1.5 %
f) 0.5 %
398. When cement is placed in contact with the aggregate, batches may be rejected unless mixed
within _____ hours of such contact.
a. 1.5 hours (90 minutes)
b. 2.0 hours,
c. 0.5 hours,
399. When mixed at the site or in a central mixing plant, the mixing time shall not be less than
______ nor more than ____ unless mixer performance test prove adequate mixing of
concrete in a shorter time period.
a. 30 seconds nor more than 90 seconds
b. 50 seconds nor more than 90 seconds
c. 60 seconds nor more than 120 seconds
400. The flow of water shall be uniform and all water should be in the drum by the end of the first
____ seconds of the mixing period.
a) 45 seconds c) 15 seconds
b) 30 seconds d) 20 seconds
Concrete & Concrete Products Page 20/25
MATERIALS ENGINEERS (DPWH) ACCREDITATION EXAM REVIEWER II
401. When concrete is delivered in truck mixers, additional water may be added to the batch and
additional mixing performed to increase the slump to meet the specified requirement if
permitted by the Engineer, provided all these operation are performed within ____ after the
initial mixing operation and the water and cement ratio is not exceeded.
a) 30 minutes c) 45 minutes
b) 15 minutes d) 60 minutes
402. The concrete samples should be stored in a moist conditioned temperature within the range
of ________ until the time of test. (for best results = 15.5⁰ C to 37.5⁰ C)
a. 18* C to 24* C c) 14* C to 24* C
b. 15* C to 18* C d) 18* C to 28* C
403. Cast in place concrete shall not be post – tensioned until at least ____ and until the
compressive strength has reached the strength specified.
a) 7 days b) 10 days c) 14 days d) 20 days
404. Vibration shall operate a frequency of 8,300 to 9,600 impulses per minute under load at
a maximum spacing of ____ cm.
a) 30 cm c) 60 cm
b) 50 cm d) 40 cm
405. Before the cement is to be used, sampling must be done at least _____ before use.
a) one week c) two weeks
b) 14 days d) 12 days
406. Batching tolerance for Sand and Aggregate is ________.
a) 1 % b) 3 % c) 2 %
407. Between stages of curing, concrete shall not be exposed for more than how many hours?
a) 24 hours c) ½ hour
b) 3 hours d) 72 hours
408. As a Materials Engineer, what will you do with major honeycombed area that is considered as
defective work?
a) Plaster
b) Payment of the concrete will be made an adjustment
c) Removed and replaced at the expensed of the contractor
409. If the strength of control specimen does not meet the requirement and not feasible to obtain
cores due to structural consideration, as a Materials Engineer what will be your decision?
a) Removed and replaced
b) Area will not be paid
c) Payment will be made at an adjusted price
410. After concrete has been placed, it is advisable to maintain fully wetted and in position for how
many hours?
a) 14 hours c) 72 hours (3 days)
b) 24 hours d) 15 – 18 hours
411. Minimum penetration of all piles shall be ____.
a) 3 meter c) 7 meter
b) 6 meter d) 4.5 meter
412. Piles shall not be driven within 7 meters of concrete less than _____ old.
a) 7 days b) 14 day c) 21 days
413. The depth of the weakened joints must not be less than ____ and a width of ___.
a) 40 mm & 6 mm c) 40 mm & 5 mm
b) 50 mm & 5 mm d) 50 mm & 6 mm
414. Submission of sample for testing for cement is _____.
a) 10 kg c) 15 kg
b) 20 kg d) 40 kg
415. For small project where quantity of steel bars is 10,000 kg or less, what is the basis for
acceptance of material?
a) No testing b) Mill certificate c) P.E, certificate
416. What is the relative strength of mortar at 7 & 28 days of fine aggregates, when tested for the
effect of organic impurities, which is higher than the standard?
a) not less than 90 % c) not less than 95 %
b) not less than 80 % d) not less than 98 %
417. What is the rate of loading for concrete beam tested for flexural stress?
a) 110 – 150 psi/sec c) 125 – 175 psi/sec
b) 115 – 150 psi/sec d) 130 - 175 psi/sec
418. In concrete sampling paste shall be of normal consistency of _____ when the rod settles to a
point below the original surface in 30 secs.
a) 10 +/- 1 mm c) 15 +/- 1mm
b) 11 +/- 1 mm d) 20 +/- 1 mm
419. Retarder can delay the setting time of concrete up to how many hours?
a) 1 hour c) 4 hours
b) 2 hours d) 8 hours
420. Super plasticizer can increase the strength of concrete up to how many percent?
a) 40 –60 % c) 50 – 70 %
b) 50 – 60 % d) 60 – 70 %
421. In the absence of beam mold in site, cylinder mold is allowed by specification. What is the
required strength?
a) 2,500 psi c) 3,500 psi @ 14th days
b) 3,000 psi d) 4,000 psi
422. ________ burnt product which is used by Gypsum and pulverized to form Portland Cement.
a) Hydraulic cement c) Fly Ash
b) Clinker d) Volcanic
423. ______ is a type of cement which shall be transferred to an elevated, air tight and weather
proof bins storage.
a) Portland Cement c) Bulk Cement
b) Pozzolan Cement d) None of the above
424. The minimum thickness of conventional concrete as the surface course in monolithic
pavement.
a) 50 mm c) 100 mm
b) 75 mm d) 150 mm
425. The number of specimen samples in testing concrete hollow block.
a) 6pcs./10,000 units (3 for absorption test and 3 for strength test )
b) 8 pcs./10,000 units
c) 4pcs/10,000 units
426. T h e k i n d o f t e s t t h a t d e t e r m i n e s t h e c o n s i s t e n c y o f c o n c r e t e i s _____.
a) Slump test c) Abrasion test
b) Specific Gravity
427. What is the dimension of concrete cylindrical sample?
a) 6” dia. and 12” high c) 8” dia. and 14 high
b) 4” dia and 8” high
428. The minimum compressive strength for class A concrete is
a) 3,000 psi (20.7 NM/m2)
b) 2,400 psi (16.5 NM/m2)
c) 5,000 psi (37.7 NM/m2)
429. A tie bar shall be ______.
a) Deformed bar b) round bar c) flat bar
430. A dowel bar shall be_____.
a) Deformed bar b) round bar c) flat bar
431. The mortar for masonry units shall consist of _________.
a) One (1) part Portland cement & two (2) parts of sand
b) One(1) part Portland cement & three (3) parts of sand
c) one (1)part Portland cement & four (4) parts of sand
432. _______is the type of cement to be used in the DPWH
infrastructure project as indicated in the Blue Book.
a) Portland Cement Type I
b) Pozzolan Cement
c) Portland Cement Type II
433. The design of concrete mix specified by the blue book is based on ____..
a) Absolute Volume Method
b) Area Method
c) American Method
434. The minimum flexural strength requirement of beam sample when tested by third point
loading method is ____________.
a) 3.5 Mpa b) 3.8 Mpa (550 psi) c) 4.0 Mpa