Documente Academic
Documente Profesional
Documente Cultură
Overview
Once a project is approved to proceed, it is the responsibility of the project
manager, reporting to the sponsor(s) and steering committee to ensure that it
is progressed successfully and that the expected benefits are delivered.
The reason that the benefits realisation process must be managed is that
many project benefits are the result of changes in business processes that are
enabled by the project or technology, rather than being directly attributable to
a successful implementation of the project itself.
• benefit planning
• benefit identification,
• benefit definition,
• benefit monitoring.
Benefits Planning
The first stage is to document and plan for the management of the benefits
that are expected to be delivered by the project. These are the benefits that
will be monitored throughout the life of the project, and achievement of these
benefits will be measured and reported at the end of the project.
As stated in the introduction there are specific elements within this planning
cycle which warrant further explanation and guidance. These are detailed in
the following sections:
Many approaches dictate that benefits should be split into tangible (those that
can be quantified and measured in isolation) and intangible (those that are
delivered either as purely qualitative improvements or are so aggregated into
a combination of changes they cannot be easily separated). It must be
recognised that this guidance with respect to realisation applies equally to
both tangible and intangible benefits. If the project is delivering benefits that
warrant usage of a disciplined realisation approach this will usually centre on
delivered tangible benefits, however, the intangible benefits should be
included – too often some hazy notion or quantification of intangible benefits
is used to support a business case and because of this, actual benefit
realisation is compromised.
Cost Reduction
A reduction in operating budget (or a need to make reduction) may drive
the need to undertake a change project. The benefits from this are direct
and realised through the business area’s success in reducing actual
costs whilst maintaining an acceptable service level. The current
operating costs need to be well documented, as do the proposed
reductions and how they will actually be achieved. Failure to reduce
budgets soon after a change will encourage benefits erosion.
Improved Effectiveness
It may be possible to quantify benefits in terms of time saved by the
business. If so, quantitative measures must be defined that will be used
to demonstrate that the benefits have been achieved. It may be
necessary to define qualitative indicators that can be quantitatively
assessed, such as customer satisfaction results and or complaints.
Improved Services
A business area providing a direct service (internally or to customers)
may wish to make an investment to enable it to provide a better,
customer focused service through change to its service delivery. Benefits
from such an initiative may include cost avoidance type savings to the
initiating business areas or its internal customers.
Business Imperative
The need for change is driven by a clear business imperative; which can
be either internal (e.g. new product range launched) or external (e.g.
Technology Changes
In order to identify the benefits of replacing or upgrading both hardware
and software, it will be necessary to document all costs of the current
environment, all the costs of the proposed change(s) and the savings to
be derived. Then it will be necessary to demonstrate how these savings
will be realised. For example, will the savings be realised as a reduction
in ongoing costs or by increasing capacity to support extra services
within the existing cost / budget. In reality Technology Change benefits
usually are at least strongly associated with one of the other benefit
categories.
These categories are for guidance and are not intended to be exhaustive.
Benefit Definition
Benefits are broadly defined as either a reduction in or avoidance of cost of
performing business (cost related benefits), or as an enhancement to the
provision of services (service related benefits). The following is intended to
be a guide for defining possible benefits:
Benefits Realisation
It is the responsibility of the Sponsor (through the Project / Programme
Manager) to ensure:
• all activities identified in the local level Benefit Realisation Plans are
implemented, and
• the appropriate control structures necessary for benefits realisation are
put in place and handed to the business for implementation after
project closure.
Each of the key benefit areas should have a number of milestones developed
against which progress can be measured during project implementation, as
represented on the Benefits Statement.
Benefits Monitoring
As the achievement of some benefit targets will rely on activities occurring
after project closure it will be necessary to ensure that post implementation
reviews (PIRs) check that benefits are being realised. These should include:
Where remedial action can be put in place to manage benefit realisation after
formal project closure the Benefits Statement should be updated subject to
approval by the Sponsor(s) to reflect the newly agreed benefits targets. The
update should be supported by an analysis of the business benefits, which
were expected, and the reasons for the shortfall to ensure that the Sponsor(s)
is aware of any business impact arising from their non-attainment.