Documente Academic
Documente Profesional
Documente Cultură
Preparation Training
Your key in Successful Project
Management
Who am I?
My name is Akram M. Alnajjar
Certified Project Management Professional (PMP) by PMI / USA
Planning and Schedule Professional PSP by AACE (The Association
for the Advance Cost Engineer international) /USA
Postgraduate Diploma for Construction Management by Ain Shams
BSC , Civil Engineering 1984
PM consultant and Shareholder for ITI and owner of Pmi House
Currently working as lecturer for Arab Academy , ITI, PMI Gulf
Chapters , Projacs international Company,
Previously worked as :
Project Control Manager for Eni Group /AGIP (Italian Oil and Gas
company) Port-Harcourt / Nigeria to July 2005
Senior Project Control Planner for Eni Group/AGIP Assaluyeh / Iran
Planning and Training Manager for Promastar Co. (Primavera
Authorized representative / Egypt and Saudi Arabia ) Responsible
for Primavera professional training courses and Primavera
consultation services.
Planning and Cost Control Manager for Bin-Jarallah Group / Riyadh
Planning and Cost Control Manager for Saudi Lada Group Riyadh
2
Question # 1: In a kick-off meeting for your project, you provided information to your team
members about the different process groups which will be followed during project
implementation. According to PMI, what are the project management process groups?
Question # 2: A project manager wants to create a project plan. You tell him that the project
plan should include:
Question # 3: You are explaining the importance of Work Breakdown Structure (WBS) to
your project team members. In this context, all the following statements about Work
Breakdown Structure (WBS) are correct EXCEPT:
Question # 4 : Please refer to the diagram given below: (all units are in days)
What is the project float if management wants to do this project within ten days?
A. 0 days
B. - 4 days
C. 2 days
D. Cannot be determined because information in the question is inconsistent
3
Question # 5: In your project, you have reason to believe that the current variances
occurred because of extraneous factors, and you do not expect similar variances to
happen in the future. What should be the Estimate at Complete for your project?
* BAC = $ 300,000
* AC = $ 100,000
* EV = $ 150,000
* CPI = $ 1.5
A. $ 250,000
B. $ 220,000
C. $ 280,000
D. $ 200,000
Question # 6 : According to the 80/20 rule, 80 percent of the problems are because of
20 percent of the causes. To facilitate finding out which are the most probable
defects, and to evaluate nonconformities, you do a rank ordering of the defects
using:
A. Statistical Sampling
B. Control Chart
C. Pareto Diagrams
D. Inspection
Question # 7 : To get the work done, the supervisor threatens punishment and
carefully supervises the work. The supervisor believes in:
A. Performance Reviews
B. Variance Analysis
C. Trend Analysis
D. Earned Value Analysis
Question # 10: Since the buyer could not meet the requirements of the contract, you
(the seller) want to terminate the contract early. This should be done as part of:
A. Procurement Planning
B. Contract Administration
C. Contract Closure
D. Administrative Closure
4
Who are you? Please introduce
yourself!
Your name
Your company name and your job
title
Why do you attend this course?
Tell us your expectations
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
5
Category 1 eligibility criteria &
requirements:
EDUCATIONAL:
at the time of application, the candidate holds a
baccalaureate or global equivalent university degree
minimum 35 contact hours of project management
education (no time frame associated with this requirement)
EXPERIENTIAL:
Minimum 4,500 hours of Project Management experience,
covering the five project management process groups
At least 3 years (36 non-overlapping, unique months) of
project management experience, within the 6-year period
prior to the application
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
EXPERIENTIAL:
Minimum 7,500 hours of Project Management experience,
covering the five project management process groups
At least 5 years (60 non-overlapping, unique months) of
project management experience, within the 8-year period
prior to the application
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
6
Required supporting
documentation!
Educational Background: Diploma
Certificate of Attendance
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Exam Fees
For members of PMI:
Initial fee: $405.00
Re-examination fee: $275.00
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
7
PMP® Exam Overview
Computer-based
Language: English
Duration: 240 minutes. The exam will be scored when you are
ready or the time is up
Exam structure
PM Process Number of Percentage
questions
Initiation 20 11.42
Planning 40 22.85
Executing 48 27.42
Monitoring & 37 21.14
Controlling
Closing 15 8.57
Professional and 15 8.57
Social
Responsibility
Total 175 100%
8
The Project Management Framework
Chapter 1
Introduction
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Introduction
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
9
Purpose of this PMBOK® Guide
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
10
What is a Project
A project is a temporary endeavor
undertaken to create a unique
product or service, or result.
Progressively Elaborated
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
11
What is a Project
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
12
Samples of IT Projects
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
13
Projects and Strategic Planning
Projects are typically authorized as a result of one or
more of the following strategic considerations:
A market demand (e.g., an oil company authorizes a
project to build a new refinery in response to chronic
gasoline shortages)
An organizational need (e.g., a training company
authorizes a project to create a new course in order to
increase its revenues)
A customer request (e.g., an electric utility authorizes a
project to build a new substation to serve a new industrial
park)
A technological advance (e.g., a software firm authorizes a
new project to develop a new generation of video games
after the introduction of new game-playing equipment by
electronics firms)
A legal requirement (e.g., a paint manufacturer authorizes
a project to establish guidelines for the handling of a new
toxic material).
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Project Managem
ent
14
What is Project Management
Managing a project includes:
• Identifying requirements
• Establishing clear and achievable objectives
• Balancing the competing demands for quality,
scope, time and cost “triple constraint”
• Adapting the specifications, plans, and
approach to the different concerns and
expectations of the various stakeholders.
•Management by projects.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Project Dynamics:
The Triple Constraints
Scope Time
Quality
Cost
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
15
The PMBOK® Guide
PMBOK® Document has three sections:
Project Management Framework
Chapters 1Introduction, Chapters 2 Project Life
Cycle and Organization,
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Approach to
executing project
Commitment to
executing project
Formal product
Coordinating acceptance and
people and end of project
other resources
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
16
Project Management Knowledge Areas
Scope Management
Time Management
Cost Management
Quality Management
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Communications Management
Risk Management
Procurement Management
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
17
Project Management Framework
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Areas of Expertise
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
18
Areas of Expertise
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
19
Understanding the Project
Environment
Virtually all projects are planned and implemented in a
social, economic, and environmental context, and have
intended and unintended positive and/or negative impacts.
The project team should consider the project in its cultural,
social, international, political, and physical environmental
contexts.
Cultural and social environment.
Physical environment.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
20
Interpersonal Skills
Effective communication. The exchange of information
21
1.6 Project Management Context
Subprojects – Components of a
project that are often contracted out
Portfolios - A portfolio is a collection
of projects or programs and other work
that are grouped together to facilitate
effective management of that work to
meet strategic business objectives.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
22
Any questions?
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
23
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
24
Project Life Cycle and Organization
Chapter 2
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
AGENDA
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
25
Life Cycle
Project Lifecycle: Describes what you need
to do, to do the work of the project.
Approach to
executing project
Commitment to
executing project
Formal product
Coordinating acceptance and
people and end of project
other resources
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
26
Project Life Cycle
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
27
Phases and Resources Usage
Implement
Concept
Time -Æ
Concept 5%
Development 20%
Implement 60%
Close Out 15%
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
28
Project Life Cycle and Product Life
Cycle Relationships
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Project Stakeholders
29
Project Sponsor
Executive
Senior Manager
External client
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Project Sponsor
Role
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
30
Roles and Responsibilities
Project Sponsor Project Manager
Represents the owner on Establishes WHAT, WHO,
the project WHEN, WHERE, HOW
Provides the requirements Defines scope of work
Provides high level project based on project
goals requirements
Exercise #2
In each group, discuss and record
who are project sponsors in your work
environment.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
31
Who are the Project Stakeholders
Exercise #3
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
32
Organizational Cultures & Styles
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Organizational Structure
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
33
Organizational Planning
Functional Organization
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Projectized Organization
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
34
Matrix Organization
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Matrix Organization
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
35
Matrix Organization
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
36
Who is the Project Sponsor ?
Exercise #4
In each group, discuss and record
Which type of organization structure
you have in your work environment.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Any questions?
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
37
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
38
Project Management Process Groups
Knowledge Area Processes Initiating Planning Executing Monitoring & Controlling Closing
Develop project Direct and manage Monitor and control project Close
Develop project charter
management plan project execution work project
Project Integration Mangement Develop preliminary project
Integrated change control
scope statement
Scope planning Scope verification
Project Scope Management Scope definition Scope control
Create WBS
Activity definition Schedule control
Activity sequencing
Acitivity resource
estimating
Project Time Management
Activity duration
estimating
Schedule
development
Cost estimating Cost control
Project Cost Management
Cost budgeting
Perform quality
Project Quality Management Quality planning assurance Perform quality control
Human resource
Project Human Resource Management planning Acquire project team Manage project team
Develop project team
Communications
Project Communications Management planning Information distribution Performance reporting
Stakeholders
Risk management
planning Risk monitoring and control
Risk identification
Qualitative risk
Project Risk Management factors
Quantitative risk
analysis
Risk response
planning
Plan purchase and Request seller Contract
Project Procurement Management acquisitions response Contract administration closure
Plan contracting Select sellers
39
40 anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
41 anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Initiation Process
Develop
Project
Charter
Develop
Preliminary
Project
Scope
Statement MONITORING & CONTROLLING
PROCESS GROUP
42 anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Planning Process
MONITORING
& CONTROLLING
PROCESS
GROUP
Risk
Identification H R Planning Schedule Development
EXECUTING
PROCESS
Qualitative Quality Planning GROUP
Risk
Analysis
Communication
Planning
Plan
Quantitative
Purchases
Risk
And
Analysis Plan Contracting CLOSING
Acquisitions PROCESS
GROUP
Risk Response Planning
43 anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Execution process
MONITORING
INITIATION Perform & CONTROLLING
PROCESS Quality Assurance PROCESS
GROUP GROUP
Acquire
Project Team
Direct and
Manage
Project
Execution
Develop Information
Project Team Distribution
CLOSING
PLANNING PROCESS
PROCESS Request Select
GROUP
GROUP Sellers Responses Sellers
44 anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Control Process
Scope Verification
INITIATION
PROCESS
GROUP Scope Control
Monitor
Schedule Control
And Control
Project
Work Cost Control
Integrated
Perform Reporting
Change
Control
Manage Stakeholders
EXECUTING
PROCESS
Risk Monitoring and Control
GROUP
Contract Administration
45 anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Close Process
PLANNING
PROCESS
GROUP
Close
Project
EXECUTING
PROCESS
GROUP
Contract
Closure
46 anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Project Management Process Groups
Knowledge Area Processes Initiating Planning Executing Monitoring & Controlling Closing
Develop project Direct and manage Monitor and control project Close
Develop project charter
management plan project execution work project
Project Integration Mangement Develop preliminary project
Integrated change control
scope statement
Scope planning Scope verification
Project Scope Management Scope definition Scope control
Create WBS
Activity definition Schedule control
Activity sequencing
Acitivity resource
estimating
Project Time Management
Activity duration
estimating
Schedule
development
Cost estimating Cost control
Project Cost Management
Cost budgeting
Perform quality
Project Quality Management Quality planning assurance Perform quality control
Human resource
Project Human Resource Management planning Acquire project team Manage project team
Develop project team
Communications
Project Communications Management planning Information distribution Performance reporting
Stakeholders
Risk management
planning Risk monitoring and control
Risk identification
Qualitative risk
Project Risk Management factors
Quantitative risk
analysis
Risk response
planning
Plan purchase and Request seller Contract
Project Procurement Management acquisitions response Contract administration closure
Plan contracting Select sellers
47
48 anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
49 anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
50
PMP
Preparation Training
Your key in Successful Project
Management
AGENDA
Initiating Process Group
Develop Project Charter
Develop Preliminary Scope Statement
Scope Management Processes
What is Scope Management?
How does the PMBoK® Guide describe Scope
Management?
Discussion
anajjar@pmihouse.org
+20105394312
51
Project Management Processes
Monitoring, measuring, and
taking corrective action
Approach to
executing project
Commitment to
executing project
Formal product
Coordinating acceptance and
people and end of project
other resources anajjar@pmihouse.org
+20105394312
anajjar@pmihouse.org
+20105394312
52
Initiating Process Group
Develop
Project
Charter
Develop
Preliminary
Project
Scope
Statement MONITORING & CONTROLLING
PROCESS GROUP
anajjar@pmihouse.org
+20105394312
53
Develop Project Charter
A business need.
A customer request.
A technological advance.
A legal requirement.
A social need.
anajjar@pmihouse.org
+20105394312
Scope Planning
Inputs
Project Charter
The document that formally authorized a project, and
address the following information:
anajjar@pmihouse.org
+20105394312
54
Scope Planning
Inputs
Assigned project manager and authority level.
Summary milestone schedule.
Stakeholders influence.
Organizational, environmental & external assumptions.
Organizational, environmental & external constraints.
Business case justification the project, including return
on investment.
Summary budget.
anajjar@pmihouse.org
+20105394312
anajjar@pmihouse.org
+20105394312
55
Develop Project Charter Inputs
56
Develop Project Charter Tools &
Techniques
anajjar@pmihouse.org
+20105394312
Present Value
57
Present Value
Year FV PV
0 $50,000 $50,000
1 $35,000 $31,819
2 $15,000 $12,397
Assume a 10% interest (or discount) rate
PV (Year 1) = FV / (1 + r)t
=$35,000/(1 + 0.1)1
= $31,819
anajjar@pmihouse.org
+20105394312
0 0 0 200 200
1 50 45 100 91
2 100 83 0 0
3 300 225 0 0
Total 353 291
58
Net Present Value (NPV).
A method of
ranking
investment
proposals using
the NPV, which
is equal to the
present value
of future net
cash flows,
discounted at
the marginal
cost of capital.
anajjar@pmihouse.org
+20105394312
Payback Period
The exact length of time needed to recover an initial
investment as calculated from cash inflows.
Month Costs Total Cost Benefits Total Benefits
1 $5000 $5000 $0 $0
2 $5000 $10000 $0 $0
3 $8000 $18000 $0 $0
4 $5000 $23000 $5000 $5000
5 $2000 $25000 $10000 $15000
6 $0 $25000 $10000 $25000
7 $0 $25000 $10000 $35000
PAYBACK PERIOD is 6 MONTHS anajjar@pmihouse.org
+20105394312
59
Internal Rate Of Return (IRR)
anajjar@pmihouse.org
+20105394312
60
Benefit Cost Ratio (BCR)
¾Compares the cost to the benefits of different projects. A
BCR of > 1 means the benefits are grater than the costs. A BCR
of < 1 means the costs are grater than the benefits. A BCR =1
means the costs and benefits are the same.
¾If the BCR of project A is 2.3 and BCR of project B is 1.7
which project would you select?
anajjar@pmihouse.org
+20105394312
anajjar@pmihouse.org
+20105394312
61
Project Charter
Exercise #1
anajjar@pmihouse.org
+20105394312
Scope Planning
Inputs
Assigned project manager and authority level.
Summary milestone schedule.
Stakeholders influence.
Organizational, environmental & external assumptions.
Organizational, environmental & external constraints.
Business case justification the project, including return
on investment.
Summary budget.
anajjar@pmihouse.org
+20105394312
62
Sample Project Charter
Project Title: Information Technology (IT) Upgrade Project
Project Start Date: March 4, 2002 Projected Finish Date: December 4, 2002
Project Manager: Kim Nguyen, 691-2784, knguyen@abc.com
Project Justification: Upgrade hardware and software for all employees (approximately 2,000)
within 9 months based on new corporate standards. See attached sheet describing the new
standards. Upgrades may affect servers and midrange computers as well as network hardware and
software.
Budgeted $1,000,000 for hardware and software costs and $500,000 for labor costs.
Approach:
• Update the IT inventory database to determine upgrade needs
• Develop detailed cost estimate for project and report to CIO
• Issue a request for quotes to obtain hardware and software
• Use internal staff as much as possible to do the planning, analysis, and installation
Microsoft Word
anajjar@pmihouse.org
Document
+20105394312
Microsoft Word
Document
anajjar@pmihouse.org
+20105394312
63
Develop Preliminary Project Scope
Statement
Outputs
1. Preliminary Project Scope Statement
anajjar@pmihouse.org
+20105394312
anajjar@pmihouse.org
+20105394312
64
Develop Preliminary Project Scope
Statement
• Product acceptance criteria.
• Project boundaries.
• Project requirements and deliverables.
• Project constraints.
• Project assumptions.
• Initial project organization.
• Initial defined risk.
• Schedule milestones.
• Initial WBS.
• Order of magnitude cost budget.
• Project configuration management requirements.
• Approval requirements.
anajjar@pmihouse.org
+20105394312
Develop
Project
Charter
Develop
Preliminary
Project
Scope
Statement MONITORING & CONTROLLING
PROCESS GROUP
anajjar@pmihouse.org
+20105394312
65
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
66
Chapter 5
Project
Scope Management
anajjar@pmihouse.org
+20105394312
67
anajjar@pmihouse.org
+20105394312
Scope Planning
Scope Definition
Create WBS
Scope Verification
Scope Control anajjar@pmihouse.org
+20105394312
anajjar@pmihouse.org
+20105394312
69
Scope Planning
The project management team documents
decisions in the scope management plan.
Inputs
1. Enterprise Environmental Outputs
Factors 1. Scope
2. Organizational Process Assets Management
3. Project Charter Plan
4. Preliminary Project Scope
Statement
anajjar@pmihouse.org
5. Project Management Plan +20105394312
70
Scope Planning
Inputs
anajjar@pmihouse.org
+20105394312
Scope Planning
Inputs
anajjar@pmihouse.org
+20105394312
71
Scope Planning
Inputs
anajjar@pmihouse.org
+20105394312
Scope Planning
Inputs
• Product acceptance criteria.
• Project boundaries.
• Project requirements and deliverables.
• Project constraints.
• Project assumptions.
• Initial project organization.
• Initial defined risk.
• Schedule milestones.
• Initial WBS.
• Order of magnitude cost budget.
• Project configuration management requirements.
• Approval requirements.
anajjar@pmihouse.org
+20105394312
72
Scope Planning
Inputs
anajjar@pmihouse.org
+20105394312
Scope Planning
anajjar@pmihouse.org
+20105394312
73
Scope Planning
Outputs
Scope Management Plan: It provides guidance on how project
scope will be defined, documented, verified, managed by the
project management team. The components of a scope
management plan include:
A process to describe the preparation of a detailed scope
statement based upon the preliminary project scope statement
A process that enables the creation of the WBS from the detailed
project scope statement
A process that specifies how formal verification or acceptance of
the completed project deliverables and its companion WBS will be
obtained.
A process to control how requests for changes to the detailed
project scope statement will be processed. This process is directly
linked to integrated change control.
The scope management plan can be informal and broadly framed,
or formal and highly detailed, based on the needs of the project
anajjar@pmihouse.org
+20105394312
Scope Definition
anajjar@pmihouse.org
+20105394312
74
Scope Definition “continue”
Outputs
Inputs 1. Project Scope
1. Project charter Statement (detailed)
2. Project Scope management Plan 2. Requested change
3. Preliminary Project Scope Statement 3. Scope Management
4. Organizational process Assets Plan (updates)
5. Approved Change Requests anajjar@pmihouse.org
+20105394312
Inputs
1. Project Charter: If charters or preliminary scope
statements are not used in a performing organization,
comparable information needs to be acquired or
developed and then used to develop the detailed project
scope statement
75
Tools & Techniques
1. Product analysis: Techniques to develop a better
understanding of the product (e.g., systems engineering, value
engineering, function analysis, quality function deployment)
2. Alternative Identification: It is a technique used to
generate different approaches to the work of the project. A
variety of general management techniques are often used here,
the most common of which is brainstorming.
3. Expert judgment
4. Stakeholders Analysis
• Identification the influence and interest of the various
stakeholders and document their needs, wants, and
expectations
anajjar@pmihouse.org
+20105394312
Output
Project Scope Statement (Detailed): It
describes, in detail,
The project’s deliverables and the work required to
create those deliverables.
Provides a common understanding among all
stakeholders,
Describes the project’s major objectives, enables the
team to perform more detailed planning,
Guides the team’s work during execution, and
provides the baseline for evaluating whether client
requests for changes or additional work fall within or
outside the project’s boundaries.
anajjar@pmihouse.org
+20105394312
76
Output
The detailed scope statement includes, either
directly or by reference to other documents:
Project and Scope objectives
Project Scope Description
Project Boundaries
Project Deliverables
Product acceptance criteria
Project Constraints
Project assumptions
Initial Project Organization
Initial Defined risks
Schedule milestones
Order of Magnitude Cost Estimate
Project Configuration management requirements
Approval Requirements
anajjar@pmihouse.org
+20105394312
Output
Scope Management Plan (Updates): The Scope
management plan should be updated to include
Changes to the scope management plan that result
from changes to the scope definition process.
Requested changes (additions, modification,
revisions) to the project management plan and its
subsidiary plans are processed through integrated
change control
• Requested changes
anajjar@pmihouse.org
+20105394312
77
Create The Work Breakdown
Structure
A work breakdown structure (WBS) is an
outcome-oriented analysis of the work involved in
a project that defines the total scope of the project
It is a foundation document in project management
because it provides the basis for planning and
managing project schedules, costs, and changes
You need a WBS to create a Gantt chart, do critical
path analysis, and to use earned value analysis
anajjar@pmihouse.org
+20105394312
Tools
1. WBS templates
2. Decomposition
Outputs
1. Project Scope
Inputs Statement (updated)
1. Organizational Process Assets 2. Work breakdown
2. Project Scope statement “detailed” structure
3. Scope Management Plan 3. WBS dictionaries
4. Approved change requests 4. Scope Baseline
5. Project Scope
Management Plan
“updates”
anajjar@pmihouse.org
+20105394312
78
Create WBS
Inputs
1. Project Scope Statement (Detailed)
anajjar@pmihouse.org
+20105394312
Create WBS
anajjar@pmihouse.org
+20105394312
79
Create WBS
Outputs
Work Breakdown Structure and Dictionary: For
each WBS element, the WBS dictionary includes a statement of
work, a list of associated activities, and a list of milestones.
Other information can include the responsible organization, start
and end dates, resources required, an estimate of cost, charge
number, contract information, quality requirements, and
technical references to facilitate performance of work. Each WBS
element should be cross-referenced, as appropriate, to other
WBS elements in the WBS dictionary.
WBS Definition
Deliverable oriented grouping of
project elements that
organizes and defines the total
scope of the project
anajjar@pmihouse.org
+20105394312
80
Create WBS
anajjar@pmihouse.org
+20105394312
2.1
2.1.3.1
2.1.3.1 2.1.3.2
2.1.3.1.1
2.1.3.1.2
anajjar@pmihouse.org
+20105394312
81
Sample of WBS in IT Projects
Table 4-3. Intranet WBS in Tabular Form
1.0 Concept
1.1 Evaluate current systems
1.2 Define Requirements
1.2.1 Define user requirements
1.2.2 Define content requirements
1.2.3 Define system requirements
1.2.4 Define server owner requirements
1.3 Define specific functionality
1.4 Define risks and risk management approach
1.5 Develop project plan
1.6 Brief web development team
2.0 Web Site Design
3.0 Web Site Development
4.0 Roll Out
5.0 Support
anajjar@pmihouse.org
+20105394312
anajjar@pmihouse.org
+20105394312
82
Sample of WBS in IT Projects
Figure 4-6b. Sample Intranet WBS
Organized by Phase
anajjar@pmihouse.org
+20105394312
anajjar@pmihouse.org
+20105394312
83
Sample of WBS in IT Projects
Figure 4-8. Intranet WBS and Gantt Chart Organized by PM Process Groups
anajjar@pmihouse.org
+20105394312
Typical WBS
Information
System
1.
anajjar@pmihouse.org
+20105394312
84
Work Breakdown Structure
Exercise #2
anajjar@pmihouse.org
+20105394312
Scope Verification
anajjar@pmihouse.org
+20105394312
85
Scope Verification
Scope Verification
Tools
1. Inspections
Inputs Outputs
1. Project scope 1. Acceptance
statement deliverables
2. WBS dictionary 2. Requested changes
3. Project scope 3. Recommended
management plan corrective actions
4. Deliverables anajjar@pmihouse.org
+20105394312
Scope Verification
Inputs
1. Project scope statement
2. WBS dictionary
4. Deliverables
The deliverables are those that have been fully or
partially completed, and are an outputs of the direct and
manage project execution process.
anajjar@pmihouse.org
+20105394312
86
Scope Verification
anajjar@pmihouse.org
+20105394312
Scope Verification
Outputs
1. Acceptance deliverables
• Documents the deliverables that have been completed
and accepted and the ones that have not been accepted
and the reasons for non-acceptance.
2. Requested changes
87
Scope Change Control
• A process for controlling changes to project scope
by:
Influencing the factors that create project scope changes, in
order to ensure the changes are agreed upon
Assuring that all requested changes are processed according
to the project integrated change control
Managing the actual changes when they occur
anajjar@pmihouse.org
+20105394312
88
Scope Control
Outputs
1. Project scope statement (updates)
2. WBS (updates)
Inputs 3. WBS dictionary (updates)
1. Project scope statement
4. Scope baseline (updates)
2. WBS
5. Requested changes
3. WBS dictionary
4. Project Scope management plan 6. Recommended corrective actions
5. Performance reports 7. Org. process Assets (updates)
6. Approved change requests 8. Project management plan
anajjar@pmihouse.org
+20105394312
7. pmbok
Source: Work performance information
guide 2004
(updates)
Scope control
Inputs
1. Project scope statement
2. WBS
3. WBS dictionary
4. Project Scope management plan
5. Performance reports
Provide information on project work Performance, such
as interim deliverables that have been completed.
6. Approved change requests
Any modification to the agreed-upon project scope
baseline.
anajjar@pmihouse.org
+20105394312
89
Scope control
Inputs
7. Work performance information
Schedule progress showing status information.
Deliverables that have been completed and those not
completed.
Schedule activities.
Extent to which quality standard are met.
Costs authorized and incurred.
ETC the schedule.
% physically completed
Lessons learned.
Resource utilization detail.
anajjar@pmihouse.org
+20105394312
2. Variance analysis
• Determining the cause of variance relative to the scope
baseline and deciding whether corrective action is
required.
anajjar@pmihouse.org
+20105394312
90
Tools & Techniques
3. Re-planning
anajjar@pmihouse.org
+20105394312
91
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
92
PMP
Preparation Training
Your key in Successful Project
Management
Chapter 6
Time Management
93
AGENDA
Time Management
Processes required to accomplish
timely completion of the project
Activity Definition
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
94
Key Elements Of Time Management
Estimating
Network Analysis Techniques
Estimating
95
Estimating
Activity Duration Estimating
Estimating
Parametric / Quantitatively Based Durations
96
Estimating
Parametric / Quantitatively Based Durations
Estimating
PERT Duration Calculation
Higher
Most Likely
Probability (Used in original CPM Calculations)
Of PERT Weighted Average =
Optimistic + 4 X Most Likely + Pessimistic
Occurrence ( 6 )
Beta Distribution
97
Calculation of PERT
PROBABILITIES
TIME ESTIMATE
Te= a + 4b + c
6
a = OPTIMISTIC
b= MOST LIKELY
c = PESSIMISTIC
TIME VARIANCE
σ=c–a
V = σ2
6
a = OPTIMISTIC
c = PESSIMISTIC
98
Normal Distribution
-1σ +1 σ
-2 σ +2 σ
68.26%
95.46%
99.73%
LCL UCL
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Critical Path
Early/Late Start and Finish
Float
99
Network Diagram Analysis
2 Days 12 Days 5 Days
A B C
Start Finish
6 Days 7 Days 3 Days
D E F
A B
Start-to-Start – Activity A must start before
Activity B can start , the initiation of the work of
the successor depends upon the initiation of the
work of the predecessor.
A B
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
100
Activity Sequencing Process
Finish-to-Finish – Activity A must finish before Activity
B can finish , the completion of the work of the
successor depends upon the completion of the work of
the predecessor.
A B
Start-to-Finish – Activity A must start before
Activity B can finish , the completion of the
successor is dependent upon the initiation of the
predecessor.
A B
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Start 0 -------------
A 2 Start
B 12 A
C 5 B&D
D 6 Start
E 7 D
F 3 E
Finish 0 C&F
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
101
Network Diagram Analysis
2 Days 12 Days 5 Days
A B C
Start Finish
6 Days 7 Days 3 Days
D E F
102
Critical Path Method
The Forward Pass …
Early Start = Highest of predecessor’s
Early Finish Times
Start Finish
6 Days 7 Days 3 Days
0 6 6 13 13 16
D E F
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
103
Critical Path Method
The Backward Pass …
Late Finish = Lowest of successor’s
Late Start Times
2 Days 12 Days 5 Days
0 2 2 14 14 19
A B C
0 2 2 14 14 19
0 0 19 19
Finish
Start
6 Days 7 Days 3 Days 19 19
0 0
0 6 6 13 13 16
D E F
3 9 9 16 16 19
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
104
Critical Path Method
Critical Path = The longest path through the network
= The path through the network with all tasks at 0 Float
= Start-A-B-C-Finish
2 Days 12 Days 5 Days
0 2 2 14 14 19
A B C
0 2 2 14 14 19
0 0 19 19
(0) (0) (0) Finish
Start
6 Days 7 Days 3 Days 19 19
0 0
0 6 6 13 13 16 (0)
Float = (0) D E F
3 9 9 16 16 19
(3) (3) (3) Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
105
10 1 4
Figure H
C D E
6 7 9 8 4 6 3
A B F G H J K
11
10 1 4
Figure H
C D E
6 7 9 8 4 6 3
A B F G H J K
11
106
10 1 4
Figure H
C D E
6 7 9 8 4 6 3
A B F G H J K
11
A. 2
B. 3
C. 5
D. 0
Preceding Estimate
Activity activity weeks
Start 0
C Start 3
D C 6
A C 8
E D 4
B A,E 5
F E 3
End B,F 0
107
- You have a project with the following tasks: Task 1 can
start immediately and has an estimated duration of
four. Task 2 can start after Task 1 is completed and
has an estimated duration of eight. Task 3 can start
after Task 2 is completed and has an estimated
duration of five. Task 4 can start after Task 1 is
completed and has an estimated duration of eight.
Task 5 has an estimated duration of three and must
take place concurrently with Task 3. It can start after
Tasks 4 and 2. What is the duration of the critical
path of this project?
A. 15.
B. 18.
C. 17.
D. 12.
TIME VARIANCE
σ=c–a
V = σ2
6
a = OPTIMISTIC
Te= a + 4b + c
c = PESSIMISTIC 6
b = MOST LIKELY
108
Normal Distribution
-1σ +1 σ
-2 σ +2 σ
68.26%
95.46%
99.73%
LCL UCL
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
PERT Example
1- Expected Project Duration: 12.17 days
2-VARIANCE
A B =0.67x0.67+0.5x0.5+0.33x0.33=0.8078
3- Standard Deviation of Critical Path: .898
C D Task
Time, Days PERT standard
Activity OptimisticMost Likely Pessimistic Expected deviation
A 2 4 6 4 .67
B 2 3 5 3.17 .5
C 4 7 10 7 1
D 4 5 6 5 .33
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
109
PMBOK® Chapter 6
There are 6 major Processes:
1. Activity Definition
2. Activity Sequencing
3. Activity Resource Estimating
4. Activity Duration Estimating
5. Schedule Development
6. Schedule Control
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Time Management
Planning Controlling
110
111
Activity Definition
Activity Definition
Tools & Techniques
• Decomposition
• Templates
• Rolling Wave Planning
• Expert Judgment
• Planning Component
Inputs
• Enterprise Environmental
Factors Outputs
• Organizational Process • Activity list
Assets • Activity Attributes
• Project Scope Statement • Milestone List
• WBS • Requested Changes
• WBS Dictionary
Akram Al-Najjar, PMP,PSP
• Project Management Plan anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
112
Activity Definition Tools &
Techniques
Rolling Wave Planning
:Form of progressive elaboration
planning where the work to be
accomplish in the near future is planned
in detail while the work in the far future
is at higher level of WBS, it is indicating
that planning is an iterative and
ongoing process.
Activity Sequencing
113
Activity Sequencing
Tools & Techniques
• Precedence diagramming
method (PDM)
• Arrow diagramming
method (ADM)
• Schedule network templates
• Dependency determination
• Applying leads and lags
Inputs Outputs
• Project Scope Statement • Project Schedule network
• Activity list diagram
• Activity Attributes • Activity list (updates)
• Milestone List • Activity Attributes (updates)
• Approved Requested • Requested Change
Akram Al-Najjar, PMP,PSP
Changes anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
A B
Start E Finish
C D
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
114
Activity Sequencing Process
Finish-to-Start – Activity A must finish before Activity B
can start , the initiation of the work of the successor
depends upon the completion of the work of the
predecessor.
A B
Start-to-Start – Activity A must start before
Activity B can start , the initiation of the work of
the successor depends upon the initiation of the
work of the predecessor.
A B
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
A B
Start-to-Finish – Activity A must start before
Activity B can finish , the completion of the
successor is dependent upon the initiation of the
predecessor.
A B
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
115
Tools and Techniques (cont.)
Arrow diagramming method (ADM) or
(AOA) – Uses arrows to represent activities
and connecting nodes to show dependencies
Start
A =10d
B=5d
C=20d
D=4d E=2d
Finish
116
Activity Resource Estimating
117
Activity Duration Estimating
The process of estimating schedule activity
durations uses information on schedule
activity scope of work, required resource
types, estimated resource quantities, and
resource calendars with resource availabilities.
118
Tools & Techniques
Reserve Analysis: An additional
time frame, called time reserve,
contingency, or buffer, that can be
added to the activity duration or
elsewhere in the schedule as
recognition of schedule risk
Schedule Development
119
Schedule Development
Tools & Techniques
• Schedule Network Analysis
• Critical Path Method
• Schedule Compression
• What-If Scenario Analysis
• Resource Leveling
Inputs •
•
Critical Chain Method
Project Management Software
• Organizational Process Assets • Applying Calendars
• Project Scope Statement • Adjusting Leads and Lags
• Activity List • Schedule Model
• Activity Attributes Outputs
• Project Schedule Network Diagrams • Project schedule
• Activity Resource Requirements • Schedule Model Data
• Resource Calendars • Schedule Baseline
• Activity Duration Estimates • Resource-requirement updates
• Project Management Plan • Activity Attributes (Updates)
Risk Register. • Project Calendar (Updates)
• Requested Changes
• Project Management Plan (Updates)
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
120
Tools & Techniques
What-if analysis: such as delaying a major component delivery,
extending specific engineering durations, or introducing external
factors, such as a strike or a change in the permitting process.
Outputs
Project schedule : includes at least a planned start
date and planned finish date for each schedule activity.
Project schedule network diagrams.
Bar charts.
Milestone charts.
Schedule Model Data
Schedule Baseline : baseline is a specific version of
the project schedule developed
Resource Requirements (Updates)
Activity Attributes (Updates)
Project Calendar (Updates)
Requested Changes
Project Management Plan (Updates)
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
121
Basic Terminology
Gantt Charts
122
Typical Gantt Chart
Activity
Task A
Task B
Task C
Task D
June July Aug Sep Oct Nov
123
Schedule Control
Schedule Control
Tools & Techniques
• Progress Reporting
• Schedule Change Control System
• Performance Measurement
• Project Management Software
• Variance Analysis
• Schedule Comparison Bar Charts
Outputs
• Schedule Model Data (Updates)
Inputs • Schedule Baseline (Updates)
• Schedule Management Plan • Performance Measurements
• Schedule Baseline • Recommended Corrective Actions
• Performance Reports • Organizational Process Assets (Updates)
• Approved Change Requests • Activity List (Updates)
• Activity Attributes (Updates)
• Project Management PMP,PSP)
Plan (Updates
Akram Al-Najjar,
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
124
Tools & Techniques
Outputs
Schedule Model Data (Updates)
Schedule Baseline (Updates)
Performance Measurements
Requested Changes
Recommended Corrective Actions
Organizational Process Assets (Updates)
Activity List (Updates)
Activity Attributes (Updates)
Project Management Plan (Updates)
125
Short Break
Any questions?
126
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
127
PMP
Preparation Training
Your key in Successful Project
Management
Chapter 7
Project Cost
Management
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
128
AGENDA
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
129
Project Cost Management
Cost Estimating
Cost Budgeting
Cost Control
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Gantt Chart
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
130
Planned Value (PV)
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
131
Work Plan Status
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
PV and EV
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
132
Earned Value (EV)
¾ Previously (and still in many places) called
Budgeted Costs for Work Performed (BCWP).
¾ A monetary representation of how much work
has been completed, using the baseline cost for
that work, at a point in time.
Example: After 4 months, we have completed
Activity 1 and 50% of activity 2 . The budgeted
cost for this work completed was $24,000. The
total project budget is $100,000. The Earned
Value at 4 months is $24,000.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
PV , EV and AC
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
133
PV , EV and AC
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
134
Schedule Variance (SV)
The project has
New: delivered $8,000
less work at this
SV = EV – PV point in time than
was planned. This
= $24,000 - $32,000 project is behind
schedule. This is a
= ($8,000) great way to depict
ahead or behind on
Old: schedule, even
though it is in
SV = BCWP - BCWS monetary terms!!!
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Old:
CV = BCWP - ACWP
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
135
Schedule Performance Index (SPI)
New: The project is
delivering work
slower than
SPI = EV / PV planned. The work
is being done at
= $24,000 / $32,000 75% of the
expected rate.
= 0.75
Old:
SPI = BCWP / BCWS
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Old:
CPI = BCWP / ACWP
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
136
Case 1
PV = $ 1,860 This is the ideal
situation, where
EV = $ 1,860 everything goes
according to plan.
AC = $ 1,860
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
137
Estimate At Completion (EAC)
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
138
Estimate At Completion (EAC)
(2nd of 3 methods)
¾If the original estimates were flawed,
we should build new estimates for all
the remaining work … Assume this
¾ETC is the Estimate to Complete the was the
total ETC
remaining work. from a
¾EAC = AC + ETC completely
rebuilt
= $29,000 + $120,000 estimate
= $1,49,000
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
139
EVM Performance Measures
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
140
Types Of Costs
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
DEPRECIATION
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
141
LIFE CYCLE COSTING
costs costs
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
142
Questions & Answers EV
A. Over budget
B. On budget
C. Under budget
D. Not having enough information provided
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
143
Questions & Answers EV
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Cost Estimating
Cost Budgeting
Cost Control
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
144
145
Cost Management
Planning Controlling
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Cost Estimating
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
146
Cost Estimating
Tools & Techniques
• Analogous estimating
• Determine Resource Cost Rates
• Bottom-up estimating
• Parametric estimating
• Project Management Software
Inputs • Vendor Bid Analysis
• Enterprise Environmental Factors • Reserve Analysis
• Organizational Process Assets • Cost of Quality
• Project Scope Statement
• Work Breakdown Structure
• WBS Dictionary Outputs
• Project Management Plan • Activity Cost estimates
Schedule management plan. • Supporting detail
Staffing management plan. • Requested Changes
Risk register. • Cost management plan
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Inputs
Enterprise Environmental Factors , considers:
Marketplace conditions.
Commercial databases.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
147
Inputs (cont.)
Project Scope Statement
describes the business need, justification,
requirements, and current boundaries for the
project.
Work Breakdown Structure
Inputs (cont.)
Project Management Plan
Schedule management plan: The type and quantity of
resources and the amount of time those resources
are applied to complete the work of the project is a
major part of determining the project cost.
Staffing management plan.
Project staffing attributes and personnel rates
(Section 9.1.3.3) are necessary components for
developing the schedule cost estimates.
Risk register.
The cost estimator considers information on risk
responses (Section 11.2.3.1) when producing cost
estimates.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
148
Tools & Techniques
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
149
Outputs
Types of estimates
Order of magnitude
Budget estimate
Definitive estimate
Supporting detail
Description of estimated scope of work
Documentation of the basis for the estimate
Documentation of any assumptions made
Range of possible results
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Cost Estimating
Outputs (cont.)
Requested Changes
The Cost Estimating process may generate
requested changes that may affect the cost
management plan, activity resource requirements
and other components of the project management
plan. Requested changes are processed for review
and disposition through the Integrated Change
Cost management plan
Describes how cost variances will be
managed
Part of the overall project plan
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
150
Cost Budgeting
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Cost Budgeting
151
Inputs
Project Scope Statement :
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Inputs
Contract
(Section 12.4.3.2) information related to what
products, services, or results have been
purchased — and their costs — are used in
developing the budget.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
152
Tools & Techniques
Cost Aggregation
Reserve Analysis :
Management contingency reserves are budgets
reserved for unplanned, but potentially
required, changes to project scope and cost.
Parametric Estimating
Funding Limit Reconciliation
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Outputs
80
60
40
20
0
Jan Feb Mar Apr May Jun
Reporting Period
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
153
Outputs
Requested Changes
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Cost Control
• Influencing the factors that create changes
to the cost baseline to ensure that changes are agreed upon
• Determining that the cost baseline has changed
• Managing the actual changes when and as they occur
Includes:
Monitoring cost performance to detect variances from the
plan
Ensuring that all appropriate changes are recorded
Preventing incorrect, inappropriate, or unauthorized
changes
Informing the appropriate stakeholders of authorized
changes
Analyzing positive and negative variances and how they
affect the other control processes
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
154
Cost Control
Cost Control
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
155
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
156
1: You are managing the release of a new drug in the market. Your Role is that of a:
A. Functional Manager, because you have good understanding functional knowledge of the
Pharmaceutical industry
B. Project Manager, because you are creating a unique product within specific time
schedules
C. Operations Manager, because you have to do several repetitive tasks
D. Program Manager, because you have to manage several subprojects to effectively do
your job
2: Which of the following statement related to Standards and Regulations is not correct?
A. Functional Organization
B. Weak Matrix
C. Strong Matrix
D. Projectized Organization
5: Collectively, project phases are also referred to as "Project Life Cycle". All the
following statements about project life cycles are correct EXCEPT:
157
6: As a project manager, you realize that handling Project Stakeholder expectations is an
important priority. Which statement regarding project stakeholders is not correct?
7: You have been managing a project to complete a flyover over Interstate 10. You have
divided the project into phases to provide better management control. Which of the
following is a characteristic of a project phase?
8: Which of the following is an output from the Monitoring and Controlling Process?
A. Scope
B. Time
C. Integration
D. Cost
158
10: All the following statements related to Progressive Elaboration of projects are true
except:
A. Scope of the project can change when product characteristics are progressively
elaborated, and project manager must plan for such scope changes.
B. Because the product of each project is unique, characteristics that distinguish the
product or service must be progressively elaborated.
C. Requirements are made more explicit as the project team develops a better and
more complete understanding of the project
D. Progressive Elaboration is a characteristic of projects that integrates the concept of
temporary and unique.
11: As a project manager, you must formalize acceptance of the project scope and keep
The project focused on the business need that it was undertaken to address. This
Should be done:
12: All the following statements about Work Breakdown Structure (WBS) is correct
EXCEPT:
13: There has been a change to the scope of your project, which may adversely impact the
project schedules and cost. You have updated the technical and planning documents - all
the requested changes and recommended corrective action will now be processed through:
159
14: One of your tasks as a project manager is to prepare a Scope Statement for your
project. The scope statement provides:
15 :Projects are usually chartered and authorized external to the project organization by
an enterprise, a government agency, a company, a program organization, or a portfolio
organization as a result of any of the following EXCEPT:
16: Creating Work Breakdown Structures (WBS) is very helpful in managing the project.
The first step in creating a WBS is:
17: All the following are inputs for Scope Planning EXCEPT:
A. Scope Planning
B. WBS creation
C. Scope Elaboration
D. Scope Definition
160
19: Scope Verification is essential for:
A. Project Selection
B. Creating Work Breakdown Structures
C. Providing acceptance of project scope
D. Mitigating project risks
20: In Project Initiation, Expert Judgment will often be required to assess the inputs to
the process. This can be provided by all the following except:
21: Please refer to the diagram given below: (all units are in days)
What is the project float if management wants to do this project within 10 days?
A. 0 days
B. - 4 days
C. 2 days
D. Cannot be determined because information in the question is inconsistent
22: Your project will most likely be completed in 10 weeks. Worst case scenario, the
project will require 19 weeks, and if everything goes well the project will be completed in
7 weeks. What is the PERT estimate for the task?
A. 10 weeks
B. Cannot be determined with the information provided
C. 9 weeks
D. 11 weeks
161
23: You are the project manager of a construction company. You know that after pouring
the cement, you will have to wait for 3 days before you can start painting. This waiting
time can also be referred to as:
A. Lag
B. Lead time
C. Project Float
D. Constraint
24: As a project manager, you are responsible for meeting the project schedule deadlines.
If there is some delay in the project schedule, you should:
26: While creating a project schedule, what is the duration you will provide to a
milestone?
27: Dummy activities have zero duration and are used to show a
logical relationship between tasks. They can be used in all these diagrams except:
A. CPM
B. PERT
C. ADM (Arrow Diagramming Method)
D. PDM (Precedence Diagrammatic Method)
162
28: In your project, you prefer Milestone charts over project network diagrams for the
purpose of:
A. 99.99 %
B. 99.73 %
C. 95.46 %
D. 68.26%
A. 3
B. 2
C. 4
D. -4
163
31: In your company, Payback period is primarily used as the decision criteria for project
selection. Payback period is the:
32: You were talking with your finance manager who mentioned that for accounting
purposes, your property depreciates by the same amount every year. This is also called:
33: All the following statements about Cost Baseline are correct EXCEPT:
34: In your project, there have been several changes in the cost and schedule estimates
and the original estimating assumptions are no longer valid. What is the Estimate at
Complete for your project?
* BAC = $ 300,000
* AC = $ 100,000
* EV = $ 150,000
* CPI = $ 1.2
* ETC = $ 120,000
A. $ 250,000
B. $ 220,000
C. $ 280,000
D. $ 300,000
164
35: If cost variance is negative, but schedule variance is positive, then this indicates:
A. Project A
B. Project B
C. Project C
D. Project A, B or C can be selected because all of them have equal value
37: Activity Cost Estimate Supporting Detail includes: (please select the best answer)
39: A project was expected to cost $ 6 million for 3 months. At the end of 1 month, you use
Earned Value as a performance management tool and get the following information:
* BCWP = $ 1.5 million
* BCWS = $ 2.5 million
* ACWP = $ 2.2 million
What is the Schedule Variance?
A. 0.3 Million
B. -1 Million
C. 1 Million
D. 0.7 Million
165
40:Earned Value Technique(EVT) is a tool and technique to measure project
performance. In EVT, BCWP refers to:
A. Physical work actually accomplished, including the estimated value of this work
B. Physical work scheduled to be performed, including the estimated value of this
work
C. Actual cost incurred to accomplish the earned value
D. None of the above
166
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
167
PMP
Preparation Training
Your key in Successful Project
Management
Chapter 8
Project Quality
Management
168
AGENDA
What is Quality ?
VW
or
Rolls Royce
169
Project Quality Management
Quality:
The Quality is the degree to which a set of inherent characteristics
fulfill requirements. (American Society for Quality, 2000.)
Grade:
Grade is a category assigned to products or services having the same
functional use but different technical characteristics.
a software product can be of high quality (no obvious defects,
readable manual) and low grade (a limited number of features),
or of low quality (many defects, poorly organized user
documentation) and high grade (numerous features).
Final inspection
170
Project Quality Management
Management responsibility
Success requires participation of all members of the team, but it
is the responsibility of management to provide resources needed
Continuous improvement.
Plan/Do/Check/Act cycle
171
Project Quality Management
1. ISO 9000
172
Project Quality Management
3. Quality Gurus
A - Deming
Continuous improvement ( PDCA ) (Plan – Do – Check – Act)
Top down support ( top management support )
B – Crosby
Performance standard is “Zero defect “
Cost of quality is measured by cost of non-conformance
Conformance to requirements
Quality comes from Prevention
C – Juran
Fitness for use
Technical / Statistical focus
Juran’s Trilogy :
Quality improvement, Quality planning and Quality Control
173
Project Quality Management
Senior
Management
Customer Regulatory
Authorities
Project
Manager
Quality Management
174
Project Quality Management
Process Orientation
Planning
8.1 Quality Planning
Execution
8.2 Perform Quality Assurance
175
176
Project Quality Management
Quality Planning
177
Project Quality Management
2. Benchmarking:
3. Design of experiments:
Is a statistical method that helps identify which factors
might influence specific variables. example is where an
organization can use DOE to reduce the sensitivity of
product performance to sources of variations caused by
environmental or manufacturing differences.
For example, automotive designers use this technique to
determine which combination of suspension and tires
will produce the most desirable ride characteristics at
a reasonable cost
The technique is applied to the product of the project and the
project management issues.
178
Project Quality Management
5. Cost of Quality:
Cost of quality refers to the total cost of all
efforts to achieve product/service quality, and
includes all the work to ensure conformance to
requirements, as well as all work resulting from
non-conformance to requirements.
Cost of Quality
Cost of conformance:
Prevention
Appraisal
Cost of Nonconformance:
Internal failures (in house) ( under control)
External failures (customer / field)
179
Project Quality Management
Cost of Quality
Cost of Conformance
1. Prevention cost:
Quality training
Quality auditing
Survey of vendors / suppliers
Survey of subcontractors
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Cost of Quality
Cost of Conformance
2. Appraisal Cost:
Inspection and testing of the products
Maintenance of inspection and test equipment
Cost to process and report inspection data
Laboratory testing
Internal design review and walk through
180
Project Quality Management
Cost of Quality
Cost of Nonconformance
1. Internal Failure Cost:
Scrap and rework
Charges related to late payment of bills
Inventory costs
Engineering change cost related to correcting a
design error
Correcting documentation
Cost of Quality
Cost of Nonconformance
2. External Failure Cost:
Complaints
Warranty cost: cost of repair or replacement.
Product rejected and returned.
Concessions ﺗﺮﺧﻴﺺ
Future business losses.
Product recall costs
Product liability
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
181
Project Quality Management
Saving 50%
of the total
in 3 years
Failure Cost
%75
Failure Cost
23% 10 – 15%
182
8.2 Perform Quality Assurance
INPUTS PROCESS OUTPUTS
Quality management plan “application of planned, Requested changes
Quality metrics systematic quality activities to Recommended corrective
Process improvement plan ensure that the project will actions
Work performance employ all processes needed to Organizational process
information meet requirements” assets (updates)
Approved change requests Project management plan
Quality control measure- (updates)
ments TOOLS & TECHNIQUES
Implemented change Quality planning tools and tech-
requests nique
Implemented corrective Quality audits
actions Process analysis
Implemented defect repair Quality control tools and techni-
Implemented preventive ques
actions
2. Quality Audit:
A quality audit is a structured review of the
management activities. It is used to:
Determine whether quality activities and related results comply
with the planned arrangements.
Determine whether the arrangements are implements effectively
and are suitable to achieve objectives
Identify lessons learned that can improve performance
May be scheduled or random
Carried out by trained in-house auditors or by third parties such
as registration agencies
183
Quality Process Difference
184
Project Quality Management
Prevention:
Keeping errors out of the process
Inspection:
Keeping the errors out of the hands of the customer
Attribute sampling:
The result conforms or it does not
Variables sampling:
The result is rated on a continuous scale that measures
the degree of conformity
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Tolerances:
The result is acceptable if it falls with the range
specified by the tolerance
Control Limits:
The process is in control if the result falls within the
control limits (upper limit & lower limit).
185
Project Quality Management
186
8.3 Perform Quality Control
INPUTS PROCESS OUTPUTS
“monitoring specific project
Quality management plan Quality control measurements
results to determine if they
Quality metrics Validated defect repair
comply with relevant quality
Quality checklists Quality baseline (updates)
standards and identifying ways to
Organizational process Recommended corrective
eliminate causes of unsatisfactory
assets actions
results”
Work performance informa- Recommended preventive
tion actions
Approved change requests TOOLS & TECHNIQUES Requested changes
Deliverables Cause and effect diagram Recommended defect repair
Control charts Organization process assets
Flowcharting (updates)
Histogram Validated deliverables
Pareto chart Project management plan
Run chart (updates)
Scatter diagram
Statistical sampling
Inspection
Defect repair review
Major
Defect
Causes Effect
187
Project Quality Management
Control Charts
Graphic displays of the results, over time, of a process;
used to assess whether the process is in control
Control Charts
1. Upper & lower control limit
2. Assignable cause
3. The process is out of control
4. Rule of seven
5. Specification limits
3 2
5
1
4
1
5
188
Quality Control
Normal Distribution
-1σ +1 σ
-2 σ +2 σ
-3σ μ +3 σ
68.26%
95.46%
99.73%
LCL UCL
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
189
Quality Control
•
• Standard deviation – Square root of the variance;
thus 0.0625 = 0.25 Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Quality Control
190
Flowcharting
Pareto Diagram
Histogram, ordered by frequency of occurrence, that
shows how many results were generated by type or
category of identified cause
Pareto's Law
A relatively small number of causes will typically
produce a large majority of the problems or defects
(80/20) principle, where 80 % of the problems are
due to 20 % of the causes.
191
Project Quality Management
20 50
Frequency by
10 cause 25
0 A B C D E F 0
192
Project Quality Management
Statistical sampling
Choosing part of a population of interest for
inspection.
Inspection
Measuring, examining, and testing to
determine whether results conform with
requirements
193
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
194
PMP
Preparation Training
Your key in Successful Project
Management
Chapter 9
Project
Human Resource
Management
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
195
AGENDA
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
196
Some term to be familiar with !
includes general HR topics such as:
Leadership
Delegation
Motivation
Organizational Behavior
197
Some term to be familiar with !
Motivation
Abraham Maslow developed a hierarchy
of needs to illustrate his theory that
people’s behaviors are guided by a
sequence of needs
Maslow argued that humans possess
unique qualities that enable them to
make independent choices, thus giving
them control of their destiny
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Team Development
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
198
Team Development
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Team Development
McGregor’s Theory
Douglas McGregor popularized the human relations
approach to management in the 1960s
Theory X: assumes workers dislike and avoid work, so
managers must use threats and various control
schemes to get workers to meet objectives
199
Team Development
Hygiene
Pay; working conditions; boss’s attitude
Poor hygiene factors negatively impact
motivation
Good hygiene factors increase motivation
Motivators
Positive motivation leads to achievement and
self-actualization
Workers have a sense of personal growth and
responsibility
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
200
Some term to be familiar with !
Sources of Authority and Control: (Power)
• The PM must deal with upper management,
subordinates, functional managers, interface
personnel, and people outside the firm.
201
Some term to be familiar with !
Reward and Recognition Systems
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Leadership Styles!
Managing can be described as “consistently
producing key results expected by
stakeholders” while leading involves:
Establishing direction
Aligning people
Motivating and inspiring
Leadership must be demonstrated at all
levels of the project (project leadership,
technical leadership, and team leadership).
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
202
Leadership Styles (Cont’d)!
Leadership styles can come in several forms.
The most common names for these are:
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
203
Some term to be familiar with !
Seven Sources Of Conflict
• Schedules
• Project Priorities
• Resources
• Technical opinions
• Administrative Procedures
• Cost
• Personality
The exam may ask for the top sources of conflict. So it would be useful to
know the top four. Since many project managers think that number 1 is
personality conflict. You can expect the exam to include questions with that
choice.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
204
Some term to be familiar with !
Conflict Management
Forcing:
• Pushing one viewpoint at the expense of another party.
• This method provides resolution but is considered to be a win-lose.
Problem Solving: (confrontation)
• Directly addresses disagreements.
• Conflict is treated as a problem. The problem is defined; information is
collected; alternatives are identified and analyzed, and the most
appropriate alternative is selected.
• Theoretically considered the best because both parties can be satisfied if
they work together to solve the problem.
• Both parties must want to solve the problem and be willing to work
together.
•This method is considered to be a win-win.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
205
206
anajjar@pmihouse.org
Source: pmbok guide 2004
Source: pmbok guide 2000 Slide 23 +20105394312
207
Human Resource Planning
1. Tools & Techniques
2. Organization Charts &
Position Descriptions
3. Networking
4. Organizational theory
Inputs 1. Outputs
1. Enterprise Environmental 2. Roles and responsibilities
Factors 3. Project Organization Charts
2. Organizational Process Assets 4. Staffing management plan
3. Project Management Plan
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Inputs
Enterprise Environmental Factors:
Project interfaces: Formal and informal relationships
among the various organizational units, technical
disciplines ,and individuals involved with the project work ,
Logistical & Political
constraints: Organizational structure, collective barging
agreements and competencies of expected staff that may
impact organizational planning
Organizational Process Assets:
Templates : Boilerplates or models that can be
modified or used as is, to document roles and
responsibilities and reporting relationships from
previous or similar.
Project Management Plan– The skills required to do
the project and when those skills are required
description of project management activities.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
208
Human Resource Planning
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Outputs
Roles and responsibilities –
Roles (who does what , Examples of project roles are civil
engineer) and responsibilities (who decides what , The work
that a project team member is expected to perform in order
to complete the project’s activities.) assigned to the
appropriate stakeholder
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
209
Human Resource Planning
Outputs
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Outputs (cont.)
Organization Chart – Graphic display of project reporting
relationships. (OBS) indicates which organizational unit is
responsible for which work items
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
210
Human Resource Planning
Resource Histogram
300
Senior Designers
275
250
225
Resource Usage
200
175
150
125
100
75
50
25
0
9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22
Jan Feb Mar Apr May
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
211
Acquire Project Team
Tools & Techniques
1. Pre-assignment
2. Negotiations
3. Acquisition
4. Virtual teams
Inputs
1. Enterprise environmental
factors Outputs
2. Organizational process 1. Project staff assignment
assets 2. Resource availability
3. Roles and responsibilities 3. Staffing management plan
4. Project organization charts (updates)
5. Staffing management plan
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Inputs
1. Enterprise environmental factors
Availability -
Experience
interests
Cost
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
212
Acquire Project Team
Negotiations
Acquisition
People outside the organization obtained to perform project
activities
Virtual teams
A group of People with a shared goal who fulfill their role
with little or no time spent meeting face to face.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Output
Project staff assignment
The assignment of people who will work on the
project, full-time, part time, or as needed
Resource availability
A schedule of time team members can spend
working on the project
Staffing management plan (update)
Due to promotions, retirements, illnesses,
performance issue, workloads, and expertise
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
213
Develop Project Team
Develop project team improve the
competencies and interaction of
team members to enhance project
performance.
Objectives:-
Improve skills of team members.
Improve feelings of trust and cohesiveness among
team members in order to raise productivity
through greater teamwork.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
214
Develop Project Team
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Inputs
1. Project Staff
Outputs
assignments
1. Team performance
2. Staffing management
assessment
plan
3. Resource availability
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
215
Develop Project Team
Ground rules
Rules describing clear expectation as to the expected code of conduct from team
members.
Co-Location – Establishment off a common physical location for a project team in War
room
Rewards and recognition system
A formal method used to reinforce behaviours or performance
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Output
Team performance assessment
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
216
Manage Project Team
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Inputs Outputs
1. Organization process 1. Requested changes
assets 2. Recommended corrective
2. Project staff assignments actions
3. Roles and responsibilities 3. Recommended preventive
4. Project organization chart actions
5. Staff management plan 4. Organization process assets
6. Team performance (updates)
assessment 5. Project management plan
7. Work performance (updates)
information
8. Performance reports anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
217
Manage Project Team
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Output
Organization process assets (updates)
Inputs to organizational performance appraisals
Lesson learned documentation
Project organization charts, position descriptions, and
staff management plan.
Ground rules, conflict management techniques.
Procedures for virtual teams, co-location, negotiation
and training
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
218
Project Human Resource Management
?
Source: pmbok guide 2004
219
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
220
PMP
Preparation Training
Your key in Successful Project
Management
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
221
Chapter 10
Project
Communication
Management
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
AGENDA
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
222
Transmission of information and meaning
from one person to another or to a group
Introduction of people
Information must be
properly interpreted
223
Why Communication is
Important
90% of Project Manager’s time is spent
communicating
Introduction
Basic Elements of
Communication
Sender Originator of an idea
Introduction
224
The Communication Model
Sender Receiver
Feedback
Barriers to Communication
Amount of information
¾ Follow KISS principle (keep it simple, short)
Introduction
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
225
Communication
Medium
Methods of communication
Introduction
Telephone calls
Voice mail
Email
Fax
Informal visits
Formal meetings
Formal presentations
Hand written notes
Formal correspondence
Formal reports anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Listening Model
Factors which impact listening
Message
Introduction
The Environment
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
226
Active Listening
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Meetings
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
227
Meetings
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Project Communications
Management
Processes required to ensure timely and
appropriate generation , collection, dissemination,
storage, and, ultimately disposition of project
information
Communications Planning
Information Distribution
Performance Reporting
Manage Stakeholders
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
228
229
Communication Management
Planning Executing Controlling
10.1
Communications 10.3
Planning Performance
Reporting
10.2
Information
Distribution 10.4
Manage
Stakeholders
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Communications Planning
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
230
Communications Planning
Tools & Techniques
• Communications
requirements Analysis
• Communication technology
Inputs
• Enterprise Environmental
Factors
• Organizational Process Outputs
Assets • Communication
• Project Scope Statement management plan
• Project Management Plan
Constrains & Assumption anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Communications Planning
Inputs
Enterprise Environmental Factors
All the factors described in Section 4.1.1.3 are used as inputs for
this process.
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
231
Communications Planning
Requirement
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Communications Planning
-Conversations
-documents Expected Project Staffing
Availability of -on-line schedules
Technology -databases
-etc..
232
Communications Planning
Outputs
Communication management plan – provides:
Collection and filing structure – Methods used to
gather, update, and store various types of information
Distribution structure – Specifies to whom
information will flow and what method will be used to
distribute various types of information.
Description of information to be distributed –
Includes format, content, level of detail, and
conventions and definitions to be used
Production schedules – Showing when each type of
communication will be produced
Methods for accessing information
Method of updating and refining the
communication management plan as the project
progresses
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Communications Planning
Outputs
Sample attributes of a communications management plan can
include:
Communications item. The information that will be distributed to
stakeholders.
Purpose. The reason for the distribution of that information.
Frequency. How often that information will be distributed.
Start/end dates. The time frame for the distribution of the
information.
Format/medium. The layout of the information and the method of
transmission.
Responsibility. The team member charged with the distribution of
information.
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
233
Communications Planning
Communications Planning
Exercise #1
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
234
Information Distribution
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
235
Information Distribution
Tools & Techniques
• Communications skills
• Information-retrieval
systems
• Information-distribution
methods
• Lesson Learned Process
Inputs
• Communication Outputs
management plan • Organizational Process
assets (updates)
• Requested changes
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Information Distribution
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
236
Information Distribution
Information Distribution
Outputs
Organizational Process Assets (Updates)
Project Records – Organized storage and
maintenance of correspondence, memos, reports, and
documents describing the project
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
237
Performance Reporting
Collecting and disseminating performance
information to provide stakeholders with
information about how resources are being
used to achieve project objectives
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Performance Reporting
Tools & Techniques
• Information Presentation Tools
• Performance Information
Gathering and Compilation
• Status Review Meetings
• Time Reporting Systems
• Cost Reporting Systems
Outputs
• Performance reports
Inputs • Forecasts
• Work Performance Information
• Requested Changes
• Performance Measurements
• Recommended Corrective Actions
• Forecasted Completion
• Quality Control Measurements • Organizational Process Assets (Updates))
• Project Management Plan
• Approved Change Requests
• Deliverables
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
238
Performance Reporting, Inputs
• Deliverables
Are any unique and verifiable or product, or
result to perform a services that must be
product to complete a process, phase or project
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
239
Performance Reporting
Outputs
Performance report – Organizes and
summarizes the information gathered and
presents the results of any analysis. Reports
should provide the kinds of information and
the level of detail required by various
stakeholders and documented in the
communications management plan
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Outputs
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
240
Performance Reporting
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
241
Case 2
But with EV measurements,
we see...$400 worth of work
PV = $ 1,900 is behind schedule in being
completed; i.e., we are 21
percent behind where we
EV = $ 1,500 planned to be.
AC = $ 1,700
SV = EV – PV =- $ 400
SV % = SV / PV x 100 =- 21 %
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Outputs
Performance report
8.E+07
7.E+07
Value .
6.E+07
5.E+07
4.E+07
3.E+07
2.E+07
1.E+07
0.E+00
2
2
2
02
02
l-0
-0
-0
-0
n-
planned value
p
ay
ar
ov
Ju
Se
Ja
Earned value
anajjar@pmihouse.org
Time +20105394312
Source: pmbok guide 2004
Actual Cost
242
Manage Stakeholders
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Manage Stakeholders
Tools & Techniques
• Communications Methods
• Issue Logs
Outputs
Inputs • Resolved Issues
• Communications • Approved Change Requests
Management Plan • Approved Corrective Actions
• Organizational • Organizational Process
Process Assets Assets (Updates)
• Project Management
Plan (Updates)
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
243
Manage Stakeholders
Issue Logs
Is a tool that can be used to document and monitor
the resolution of issues. Issues do not usually rise to
the importance of becoming a project or activity, but
are usually addressed in order to maintain good,
constructive
working relationships among various stakeholders,
including team members.
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
Manage Stakeholders
Output
Resolved Issues
As stakeholder requirements are identified and
resolved, the issues log will document concerns that
have been addressed and closed. examples include:
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
244
Any questions
anajjar@pmihouse.org
+20105394312
Source: pmbok guide 2004
245
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
246
Chapter 11
Project Risk
Management
Risk
Its primary components are a measure of probability that a risk occur and
the impact of the risk on a project.
247
Risks Tolerance
Risk tolerance address the level of risk a project manager or key stakeholder
is willing to take when money at stake is compared to the potential payoff.
It’s measured in terms of the amount of satisfaction or pleasure the
individual receives from payoff.
Risk averter : Not likely to take a risk that is considered a high risk
248
249
Risk Management
Planning
Inputs
9 Enterprise environmental factors
9 Organizations process assets Outputs
9 Project scope statement
¾ Risk Management Plan
9 Project management plan
250
Output: Risk Management Plan
251
Risk Management Planning Output
Templates for scoring and interpretation
252
Akram Al-Najjar, PMP,PSP
Source: pmbok guide 2004 Slide 11 anajjar@pmihouse.org +20105394312
253
Risk Identification
•Finally , you output the risk register. Initial risk identification may be
done at the macro level
Akram Al-Najjar, PMP,PSP
Source: pmbok guide 2004 Slide 13 anajjar@pmihouse.org +20105394312
Risk Identification
Tools & Techniques
• Documentation reviews
• Information-gathering
techniques
• Checklists analysis
• Assumptions analysis
• Diagramming technique
Inputs
9 Enterprise Environmental
Factors
9 Organizational Process Assets Outputs
9 Project Scope Statement ¾ Risk Register
9 Risk Management Plan
9 Project Management Plan
Akram Al-Najjar, PMP,PSP
Source: pmbok guide 2004 Slide 14 anajjar@pmihouse.org +20105394312
254
Information-Gathering Techniques
Information-Gathering Techniques
Delphi Technique
255
Project Risk Identification
Tools and Technique
Documentation review: Structured review of project plans and related
documents at both the total project and detailed scope level.
Risk Categories
Divisions into which project risks can be grouped to reflect
common sources of risk for a specific project, industry, or
application area.
Risk Categories
Technical, quality, or performance risks
Project management risks (time , resources , and cost
estimate )
Organizational risks (funding , conflicts and management
support )
External risks ( Union , security issues …etc)
256
Project Risk Identification
Output
Risk register
List of identified risk
List of potential responses
Root causes of risk
Update risk categories
257
Risk Identification
Exercise #1
258
Qualitative Risk Analysis
Tools & Techniques
Risk probability & impact assessment
Probability & impact matrix
Risk data quality assessment
Risk categorization
Risk urgency assessment
Inputs
9 Organizations process assets Outputs
¾ Risk Register
9 Project scope statement
update
9 Risk Management Plan
9 Risk register
Akram Al-Najjar, PMP,PSP
Source: pmbok guide 2004 Slide 23 anajjar@pmihouse.org +20105394312
259
Qualitative Risk Analysis
Output
260
Akram Al-Najjar, PMP,PSP
Source: pmbok guide 2004 Slide 27 anajjar@pmihouse.org +20105394312
261
Risk Analysis
Exercise #2
262
Quantitative Risk Analysis
Tools & Techniques
• Data gathering and
representation techniques
• Quantitative risk analysis and
modeling techniques
Inputs
9 Organizations process assets
9 Project scope statement
9 Risk Management Plan
9 Risk register Outputs
9 Project management plan ¾ Risk Register
-Project schedule management update
plan
-Project cost management plan
Akram Al-Najjar, PMP,PSP
Source: pmbok guide 2004 Slide 31 anajjar@pmihouse.org +20105394312
263
Quantitative Analysis Methods
Sensitivity Analysis
Expected Monetary Value
Decision Tree Analysis
Modeling and Simulation
264
Quantitative Risk Analysis,
Tools & Tech.
Expected Monetary Value (EMV) is a method of calculating the
average out come when the future is uncertain.
Probability
Status Payoff
%
Good Market – Good Quality 80,000 15
Good Market – Poor Quality 50,000 45
Poor Market – Good Quality 20,000 25
Poor Market – Poor Quality -20,000 15
Decision Tree
265
Quantitative Risk Analysis, Tools &
Tech.
266
Quantitative Risk Analysis, Tools & Tech.
Mean 46.67
Probability
.750
.500
.250
12%
.000
$ 41 $ 50
30.00 38.75 47.50 56.25 65.00
Cost $
267
Akram Al-Najjar, PMP,PSP
Source: pmbok guide 2004 Slide 41 anajjar@pmihouse.org +20105394312
268
Quantitative Risk Analysis,
Outputs
First , you review the risk management plan and risk register ,
which were updated with previous risk management planning
outputs.
Then , you employ an appropriate technique for each risk ,
either avoidance , transference , mitigation , acceptance or
exploitation .
Finally , you enter any alternation into the risk register , risk
response plan or the necessary project documentation.
269
Risk Response planning
Tools & Techniques 1-
Outputs
Inputs ¾ Risk register (updates)
9 Risk management plan ¾ Project management
9 Risk register plan (updates)
¾ Risk-related
Contractual agreements
Akram Al-Najjar, PMP,PSP
Source: pmbok guide 2004 Slide 45 anajjar@pmihouse.org +20105394312
Mitigation
(Corrective action)
Avoidance Acceptance
(Prevention) (Accept consequences)
Transference
(Shift Responsibility)
270
Risk Response planning
Tools and Technique
1. Strategies for negative risk or threats
2. Risk Avoidance : it is involves changing the project plan to
prevent a potentially detrimental risk condition or event from
happening. One way to eliminate a risk is to reduce or change
the scope of the project in an attempt to avoid high risk
activities. The scope change could involve the requirements or
specifications , or it can mean changing the approach to
meeting the requirements or specifications.
Example : The product description for an elementary social sciences
education multimedia program references stock video clips of children
riding bikes and roller skating without helmets or knee pads. During
risk identification , the project team reviewed the product description
and identified a potential risk of school administration not buying the
program because it appears to advocate unsafe activities. Viewing
this as a high risk , the team avoided this risk by changing the project
scope so that it did not include the videos.
Akram Al-Najjar, PMP,PSP
Source: pmbok guide 2004 Slide 47 anajjar@pmihouse.org +20105394312
271
Strategies for negative risk or threats
272
Strategies for both threats and
opportunities
Risk Acceptance : Is any decision not to change the project plan to
deal with a risk. It may be chosen for a risk that has an
extremely low possibility of occurrence or for which no suitable
risk response strategy is identified. Risk acceptance is
performed either passively by doing nothing or actively by
creating a contingency plan to deal with the risk.
Example:
You own a business on a hill in an area that floods relatively often.
Because of your location, you decide not to buy flood insurance.
Instead , you set aside money that is earmarked for the repair of
water damage in case of flooding.
In this case, you are employing a risk acceptance strategy by establishing
a contingency reserve for an emergency . Although you aren’t
ignoring the risk , you will spend money only if the risk event actually
occurs.
273
Risk Response planning
Output
Risk register (updates)
Identified Risk
Risk owner
Results from qualitative and quantitative risk analysis processes
Agreed response
Specific action to implement the chosen response strategy
Residual and secondary risk (next slides)
Budget and time of responses
Contingency plan and triggers
Secondary Risk
The risks that arise as a direct result of
implementing a risk response.
274
Akram Al-Najjar, PMP,PSP
Source: pmbok guide 2004 Slide 55 anajjar@pmihouse.org +20105394312
275
Strategies for Negative Risks or
Threats
Exercise #4
Mitigation
(Corrective action)
Avoidance Acceptance
(Prevention) (Accept consequences)
Transference
(Shift Responsibility)
276
Risk Monitoring and Control
Is the process of responding to identified and
unforeseen risk. It involves tracking identified risk
, identifying new risks , implementing risk
response plans, and monitoring their
effectiveness.
277
Project Risk Response Audit
An examination of the effectiveness of risk response plans and
the performance of the risk owner.
May be conducted by a third party, the project’s risk officer, or
other qualified personnel.
Discussion
Any question?
278
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
279
PMP Preparation Training
Chapter 12
Project Procurement
Management
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
280
AGENDA
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Procurement Management
281
282
Procurement Management
Planning Executing Controlling Closing
12.3
12.1 Request
12.6
12.2
12.2 12.4 Contract
Contract
Plan Select Closeout
Administration
Contracting Sellers
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Complete
Make Or Issue Receive Formally
Award Substantial
buy RFP Proposal Close
contract amount of
decision Contract
work
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
283
Buyer-seller Relationship
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
284
Plan Purchases and Acquisitions
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
285
Plan Purchases and Acquisitions
Input
Enterprise Environmental Factors– that are considered include
the conditions of the marketplace and what products, services, and
results are available in the marketplace, from whom and under
what terms and conditions.
Organizational Process Assets– provide the existing formal and
informal procurement-related policies, procedures, guidelines, and
management systems that are considered in developing the
procurement management plan and selecting the contract types to
be used.
Project Scope statement–describes the project boundaries,
requirements, constraints, and assumptions related to the project
scope.
W.B.S.
W.B.S. dictionary
Project management Plan
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
or 30 days
286
Plan Purchases and Acquisitions
Tools & Technique
Contract-type selection
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
287
Plan Purchases and Acquisitions
Tools & Technique
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
288
Plan Purchases and Acquisitions
Example
Cost plus incentive fee Calculation
Target cost $210,000
Target Fee $25,000
Target price $235,000
Sharing Ratio 80 / 20
Actual cost $200,000
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
289
Plan Purchases and Acquisitions
Example
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
290
Plan Purchases and Acquisitions
Output
Make-or-Buy Decisions
The documented decisions of what project products,
services, or results will be either be acquired or will be
developed by the project team. This may include decisions
to buy insurance policies or performance bonds contracts to
address some of the identified risks. anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
I.
Statement of Work (SOW) Template
Scope of Work: Describe the work to be done to detail. Specify the hardware and
software involved and the exact nature of the work.
II. Location of Work: Describe where the work must be performed. Specify the
location of hardware and software and where the people must perform the work
III. Period of Performance: Specify when the work is expected to start and end,
working hours, number of hours that can be billed per week, where the work must
be performed, and related schedule information.
IV. Deliverables Schedule: List specific deliverables, describe them in detail, and
specify when they are due.
V. Applicable Standards: Specify any company or industry-specific standards that
are relevant to performing the work.
VI. Acceptance Criteria: Describe how the buyer organization will determine if the
work is acceptable.
VII. Special Requirements: Specify any special requirements such as hardware or
software certifications, minimum degree or experience level of personnel, travel
requirements, and so on.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
291
The Plan Contracting
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
292
The Plan Contracting
Tools and Technique
Expert judgment
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
293
Outline for a Request for
Proposal (RFP)
I. Statement of Work (SOW) Template
Purpose of RFP
II. Organization’s Background
III. Basic Requirements
IV. Hardware and Software Environment
V. Description of RFP Process
VI. Statement of Work and Schedule Information
VII. Possible Appendices
A. Current System Overview
B. System Requirements
C. Volume and Size Data
D. Required Contents of Vendor’s Response to RFP
E. Sample Contract
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
294
Proposal Evaluation
Criteria
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
295
Request Seller Responses
Inputs Outputs
1. Organizational process assets 1. qualified sellers list
2. Procurement management 2. Procurement document
plan package
3. Procurement documents 3. Proposals
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
296
Request Seller Responses
Tools and Technique
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
297
Select Seller
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Select Seller
Inputs Tools & Techniques
1. Organizational process assets 1. Weighting system
2. Procurement management Plan 2. Independent estimates
3. Evaluation criteria 3. Screening system
4. Procurement document package 4. Contract negotiation
5. Proposals
5. Seller rating system
6. Qualified sellers list
6. Expert judgment
7. Project management plan
• Risk register 7. Proposal evaluation techniques
• Risk related contractual agreements
Outputs
1. Selected sellers 4. Resource availability
2. Contract 5. Requested changes
3. Contract management plan 6. Procurement management plan (updates)
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
298
Select Seller
Input
Organizational Process Assets: Formal or
informal policies that can affect the evaluation of
proposals
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Select Seller
Tools and Technique
Weighting system
Select a single source, who will be asked to
sign a standard contract
Rank and order all proposals to establish a
negotiating sequence
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
299
Point Rating System
• Request for proposal 33 1/3 %
- Technical 50%
- Company 25%
- Previous experience 25%
Presentation 33 1/3 %
- Team 60%
- Format 40%
Price 33 1/3 %
- Day rates 85%
- Expenses 15%
Overall 100%
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
300
Select Seller
Tools and Technique
Independent estimates : For many procurement items , the
procuring organization may prepare its own independent
estimates as a check on proposed pricing .
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Select Seller
Tools and Technique
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
301
Tactics of Negotiation
Attacks, Personal Insults, Good Guy and bad guy,
Deadline, Lying, Limited Authority, Missing man,
Fair and Reasonable, Delay, Extreme Demands,
Withdrawal, and Fait Accompli
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Select Seller
Tools and Technique
Rating Systems : Seller rating systems are
developed by many organizations and use
information such as the seller’s past performance,
quality ratings, delivery performance, and
contractual compliance.
Expert Judgment
Proposal Evaluation Techniques: Many
different techniques can be used to rate and score
proposals, but all will use some expert judgment
and some form of evaluation criteria
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
302
Select Seller
Output
Selected Sellers : are those sellers who have been judged to
be in a competitive range based upon the outcome of the proposal
or bid evaluation, and who have negotiated a draft contract, which
will be the actual contract when an award is made.
Contract – A mutually binding agreement that obligates the seller to
provide the specified product, and obligates the buyer to pay for it
A contract is a legal relationship subject to remedy in the courts
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Select Seller
Output
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
303
Contract Administration
Contract Administration
304
Contract Administration
Outputs
1. Contract documentation 5. Project management plan (updates)
2. Requested changes - Procurement management plan
3. Recommended corrective actions - Contract management plan
4. Org. process assets (updates)
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Contract Administration
Input
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
305
Contract Administration
Tools and Technique
Paperwork
Tracking systems
Dispute-resolution procedures
Approval procedures
Performance reporting
Payment system
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Contract Administration
Tools and Technique
Buyer-Conducted Performance Review: A procurement performance review is a
structured review of the seller’s progress to deliver project scope and quality, within cost and
on schedule, as compared to the contract.
Inspections and Audits: can be conducted during execution of the project to identify
any weaknesses in the seller’s work processes or deliverables.
Performance Reporting : provides management with information about how effectively
the seller is achieving the contractual objectives.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
306
Contract Administration
Output
Contract documentation :Contract documentation includes, but is
not limited to, the contract along with all supporting schedules, requested
unapproved contract changes, and approved change requests. Contract
documentation also includes any seller-developed technical
documentation and other work performance information, such as
deliverables, seller performance reports, warranties, financial documents
including invoices and payment records, and the results of contract-
related inspections.
Requested Changes.
Recommended Corrective Actions
Organizational Process Assets (Updates)
• Correspondence. Contract terms and conditions often require written
documentation of certain aspects of buyer/seller communications, such as
warnings of unsatisfactory performance and requests for contract changes
or clarifications. This can include the reported results of buyer audits and
inspections that indicate weaknesses the seller needs to correct.
• Payment schedules and requests.
• Seller performance evaluation documentation.
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
307
Contract Close Out
Inputs
1. Procurement management plan Tools & Techniques
2. Contract management plan 1. Procurement audits
3. Contract documentation 2. Records management system
4. Contract closure procedure 4.7.3.2.
Outputs
1. Closed Contracts
2. Organizational process assets (updates)
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
308
Contract Close Out
Tools and Technique
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
309
Project Procurement Management
Processes and Key Outputs
Complete
Make Or Issue Receive Formally
Award Substantial
buy RFP Proposal Close
contract amount of
decision Contract
work
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
310
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
311
Chapter 4
312
Understanding Project Integration
Management
Scope Project
Success
Time
PM Knowledge Areas
Cost t
men
Quality g e
a na
HR M
i on
Comm g rat
I nte
Risk j ect
o
Pr
Procure
Concept Development Implementation Close-out
Project Life Cycle
313
314
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
315
Project Integration Management Develop Preliminary Project Scope Statement
Outputs
1. Preliminary Project Scope Statement
Develop
Project
Charter
Develop
Preliminary
Project
Scope
Statement MONITORING & CONTROLLING
PROCESS GROUP
316
Develop Project Management Plan
MONITORING
& CONTROLLING
PROCESS
GROUP
Risk
Identification H R Planning Schedule Development
EXECUTING
PROCESS
Qualitative Quality Planning GROUP
Risk
Analysis
Communication
Planning
Plan
Quantitative
Purchases
Risk
And
Analysis Plan Contracting CLOSING
Acquisitions PROCESS
GROUP
Risk Response Planning
317
Direct & Manage Project Execution
MONITORING
INITIATION Perform & CONTROLLING
PROCESS Quality Assurance PROCESS
GROUP GROUP
Acquire
Project Team
Direct and
Manage
Project
Execution
Develop Information
Project Team Distribution
CLOSING
PLANNING PROCESS
PROCESS Request Select
GROUP
GROUP Sellers Responses Sellers
318
Monitor and Control Project Work
Outputs
• Recommended corrective Actions
• Recommended preventive actions
• Forecasts
• Recommended defect repair
• Requested changes
Akram Al-Najjar, PMP,PSP
anajjar@pmihouse.org
Source: pmbok guide 2004 +20105394312
Outputs
Inputs • Approved change requests
• Project management plan • Rejected change requests
• Requested Changes • Project management plan (updates)
• Work performance information • Project scope statement (updates)
• Recommended preventive actions • Approved corrective Actions
• Recommended corrective actions • Approved preventive actions
• Recommended defect repair • Approved defect repair
• Deliverables • Validated defect repair
• Deliverables
319
Project Integration Management
Scope Verification
INITIATION
PROCESS
GROUP Scope Control
Monitor
Schedule Control
And Control
Project
Work Cost Control
Integrated
Perform Reporting
Change
Control
Manage Stakeholders
EXECUTING
PROCESS
Risk Monitoring and Control
GROUP
Contract Administration
Close Project
320
Project Integration Management
PLANNING
PROCESS
GROUP
Close
Project
EXECUTING
PROCESS
GROUP
Contract
Closure
Organizational Process
Assets 4.2 Develop Preliminary Project Scope Statement
Scope Definitions
Contract
Administration 4.6 Integrated Change Control
Contract Closure
4.7 Close Project
Customer
321
Practice Test Project
Integration Management
322
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
323
Sample Examination Questions
Name ………………………………..
2. Project sponsors have the GREATEST influence on the scope, quality, time, and cost
of the project during the:
A. Concept phase.
B. Development phase.
C. Execution phase.
D. Close-down phase.
3. Ideally, communication between the project manager and the project team members
Should take place:
A. Via daily status reports.
B. Through approved documented forms.
C. By written and oral communication.
D. Through the formal chain of command.
6. A project management professional can compare earned value performance data to all
of the following project management tools EXCEPT:
A. Critical path analysis.
B. Technical performance metrics.
C. Risk mitigation plans.
D. Forecasted final costs and schedule estimates.
7. During the project planning process, the work breakdown structure should be
Developed to:
A. The sub-project level.
324
B. The level determined by the project office.
C. A level allowing for adequate estimates.
D. The cost center level.
9. A project loses a contractor in the middle of a project. A new project team is formed to
replace the role of the lost contractor and his/her team. As a project manager, what is the
FIRST topic to address to the team in the kick-off meeting?
A. Identify team roles and responsibilities.
B. Review detailed schedule.
C. Discuss cost estimates.
D. Emphasize your authority.
12. Your project is behind schedule due to conflict between team members. Having
resolved the conflict, to get the project back on schedule, you should consider:
A. Crashing the schedule.
B. Performing resource leveling.
C. Conducting reverse resource allocation scheduling.
D. Utilizing the critical chair resources.
14. In which project phase do you have the GREATEST influence on project risk?
A. Conceptual
B. Design
C. Execution
325
D. Implementation
17. When a project manager places a purchase order for a piece of equipment, it
represents which of the following?
A. Commitment
B. Expense
C. Cash out-flow
D. Capital investment
18. The procure audit has all of the following characteristics EXCEPT:
A. It maintains a complete file of contract – related records
B. It is a structured review of the procurement process.
C. It is a review of the various processes from Plan Purchases and Acquisition
through Contract Administration
D. Its objective is to identify successes and failures that warrant recognition
19. You have just taken control of a project in the middle of execution and need to learn
who has approval authority for revisions in scope. Which document provides this
information?
A. Resource assignment matrix
B. Change control plan
C. Project charter
D. Client organization chart
20. Of the following conflict management approaches, which is believed to lead to the
LEAST enduring positive results?
A. Problem solving
B. Avoidance
C. Compromise
D. Forcing
326
A. Multiple lead project managers.
B. A functional organization.
C. A strong matrix organization.
D. A strong traditional manager.
23. A contractor’s deliverable has been delayed 30 days. The process of determining how
this event will affect the project schedule is called risk:
A. Identification.
B. Mitigation.
C. Simulation.
D. Assessment.
25. It is critical for your company to offer its products on the Internet to increase its
market share. The company has no previous experience in this area, but it believes that
knowledge is needed rapidly. As you have shown an interest in the Internet, you are
asked to start planning for this project. What is the FIRST step to take as you begin
planning?
A. Identify the risks.
B. Plan the scope.
C. Establish a resource plan.
D. Complete a cost and schedule estimate.
26. Effective stakeholder management includes all of the following project elements
EXCEPT:
A. Clear requirements definition.
B. Scope change control.
C. Timely status information.
D. Frequent cost reports.
327
28. As part of the quality audit, the scope statement is checked against the work results to
ensure the conformance to the customer requirements. The results should be documented
and used for:
A. Estimating future projects.
B. Changing the project scope.
C. Defining future project tasks.
D. Validating the quality process.
30. Which of the following techniques is used to control the project schedule?
A. Pareto diagram
B. Performance measurement
C. Parametric modeling
D. Statistical sampling
31. Pareto analysis, cause and effect, and flow charts are all tools used in quality:
A. Control.
B. Benchmarking.
C. Planning.
D. Verification.
32. Elements of changing a project schedule include all of the following EXCEPT:
A. Obtain the appropriate levels of approval.
B. Submit the appropriate change requests.
C. Evaluate the impact of a change to the schedule.
D. Adjust the project end date to the schedule variance.
34. All of the following assist in determining the impact of a scope change EXCEPT:
A. Project charter.
B. Baseline.
C. Performance measurement.
328
D. Milestones.
35. A project was estimated to cost $1.5 million and scheduled to last six months. After
three months, the earned value analysis shows the following:
BCWP = $650,000
BCWS = $750,000
ACWP = $800,000
What are the schedule and cost variances?
A. SV= +$100,000 / CV= +$150,000
B. SV= +$150,000 / CV= -$100,000
C. SV= -$50,000 / CV= +$150,000
D. SV= -$100,000 / CV= -$150,000
37. Scope change control MUST be integrated with all of the following control processes
EXCEPT:
A. Schedule.
B. Cost.
C. Procurement.
D. Quality.
38. Reviewing work products and results to ensure that all were completed satisfactorily
and formally accepted is part of:
A. Risk management.
B. Quality control.
C. Change control management.
D. Scope verification.
40. Due to cuts in funding, your project has been terminated. The scope verification
process:
A. Should be delayed until the project is completed.
B. Should determine the correctness of the work results.
C. Should establish and document the level and extent of completion.
329
D. Will form the basis of the project audit.
41. During the contract close-out, the project manager needs to document the:
A. Formal acceptance.
B. Statement of work.
C. Payment schedule.
D. Change control procedure.
42. You've been engaged to manage a project. The estimated cost of the project is
$1,000,000. The project sponsor has approved this amount. Your earned value
calculations indicate that the project will be completed on time and under budget by
$200,000. Based on this calculation, your personal profit will decrease by $2,000.
At the completion of this project, the project manager will document and archive all
project information. This information may be used for future projects in all areas
EXCEPT:
A. Estimating durations.
B. Administering contracts.
C. Resolving conflicts.
D. Allocating resources.
44. You've been engaged to manage a project. The estimated cost of the project is
$1,000,000. The project sponsor has approved this amount. Your earned value
calculations indicate that the project will be completed on time and under budget by
$200,000. Based on this calculation, your personal profit will decrease by $2,000.
Given the estimated decrease in personal profit, what action should you take?
A. Invoice for the full $1,000,000 based on the contract.
B. Add tasks to improve the outcome and increase the actual project cost.
C. Inform the end-user that you can add features to the project in order to use the entire
budget.
D. Communicate the projected financial outcome to the project sponsor.
45. You are building a water treatment facility. Routine tests reveal that there are
contaminants in the water but that they have an extremely low risk for causing any
sickness. As the project manager, you should:
A. Inform the public that a detailed examination has been ordered to determine the
extent to which the problem exists.
B. Do nothing because there is extremely low risk for sickness except for some effects
330
on small children and the elderly.
C. Tell the public there is no problem, except for small children and the elderly who
need to boil the water before drinking.
D. Educate the public about the advances on water treatment technology and the industry
efficiency and safety record.
46. A KEY activity for achieving customer satisfaction is to define:
A. The business use.
B. Requirements.
C. Product specificity.
D. Change control.
47. When it appears that a design error will interfere with meeting technical performance
objectives, the PREFERRED response is to:
A. Decrease the performance value to equal the assessed value.
B. Develop alternative solutions to the problem.
C. Increase the specified value to set a new performance goal.
D. Reduce the overall technical complexity of the project.
48. The disorientation experienced by people who suddenly find themselves living and
working in a different environment is known as:
A. Culture shock.
B. Sociocentrism.
C. Temporal shock.
D. Ethnocentrism.
49. What is the MOST effective process to ensure that cultural and ethical differences do
not impede success of your multi-national project?
A. Co-locating
B. Training
C. Forming
D. Teaming
331