Sunteți pe pagina 1din 10

TAKING OFF LIST

ITEMS DESCRIPTION UNIT


1 Excavate top soil m2
2 Deposition of top soil m3
3 Excavate to reduce level m3
4 Remove excavated material m3
5 Excavate trench for strip fdn n.e 2.00m m3
6 Filling for excavation m3
7 E.O excavation for rock m3
8 Disposal of water item
9 Concrete blinding m3
10 Remove excavated material m3
11 Ddt. Filling m3
12 Fwk to edges and faces p fdn 250 - 500m high m
13 Concrete in foundation m3
14 Remove excavated materials m3
15 Ddt. filling m3
16 Brickwall in common brick m2
17 Remove excavated materials m3
18 Ddt. Filling m3
19 Filling to make up level m2
20 DPM m2
21 Vertical DPM m
22 Concrete bed m3
BILL NO. 1

ITEM

BILL NO.1

ITEM

D
E

BILL NO 1

ITEM

J
BILL NO 1

ITEM

C
DESCRIPTION

ELEMENT: WORK BELOW LOWER FLOOR FINISH

EXCAVATION
Excavate top soil for deposited average 150mm depth

Remove top soil to be deposited away 2km away off site

Excavate to reduce level maximum depth 0.25m

Remove excavated material from site

Excavate to reduce level on curve on plan maximum depth 0.25m

Remove excavated material from site

Excavate trench to receive foundation starting from reduce level lecel maximum depth not exceeding 2.00m

Filling to excavation with material arising from excavation

Excavate trench to receive foundation starting fro reduce level maximum depth not exceeding 2.00m curve on plan radius 300

DESCRIPTION

ELEMENT: WORK BELOW LOWER FLOOR FINISH (cont'd)

EXCAVATION (cont'd)
Filling to excavation with material arising from excavation, curve on plan radius 3000mm

Filling to excavation with material arising from excavation, curve on plan radius 3000mm

Allow for keeping the surface of the site and excavation free of surface water

CONCRETE
Plain in-situ concrete grade 7 blinding not exceeding 100mm thick laid on earth and include curve on plan radius 3000m
EXCAVATION
Remove excavated material from site

Deduction filling to excavation with material arising from excavation

CONCRETE
Plain in-situ concrete grade 25 in foundation in trench and include curve on plan radius 3000mm

DESCRIPTION

ELEMENT: WORK BELOW LOWER FLOOR FINISH (cont'd)

FORMWORK
Formwork to edges and face of foundation exceeding 250mm high but not exceeding 500mm high

CONCRETE
Plain in-situ concrete in foudation in trenches poured againts faces of formwork

EXCAVATION
Remove excavated material from site

Deduct filling to excavation with material arising from the excavation

BRICKWALL
225mm thick brickwall, broken bricks in cement and sand mortar(1:3) laid in english bond in foundation

EXCAVATION
Remove excavated material from site

Deduction filling to excavate with material arising from excavation

Filling to make up level average 300mm thick with hardcore of clean hard broken stones obtained off site

Sand bliding with 50mm thick laid on hardcore


DESCRIPTION

ELEMENT: WORK BELOW LOWER FLOOR FINISH

WATERPROOFING
Damp proof mrmbrane shall be 4mm thick polythene horizontal or other equal and approved with 100mm top at joint

Ditto; verticall, ditto;

CONCRETE
Concrete grade 25 in bed not exceeding 100mm thick laid on hardcore
UNIT QUANTITY RATE AMOUNT(RM)

m3

m3

m3

m3

m3

m3

m3

m3

m3

UNIT QUANTITY RATE AMOUNT(RM)

m3

m3

m3

m3
m3

m3

m3

UNIT QUANTITY RATE AMOUNT(RM)

m3

m3

m3

m2

m3

m3

m3

m2
UNIT QUANTITY RATE AMOUNT(RM)

m2

m3

S-ar putea să vă placă și