0 ROAD CONSTRUCTION TECHNOLOGY ER. SABIN POKHREL 3.6 Construction of Cement Concrete Pavement • Construction of pavement slab
• Design and placement of joints
3.6 Construction of Cement Concrete Pavement • CEMENT GROUTED CONCRETE: • Open graded aggregate mix of minimum size 18~25mm is laid on prepared subgrade • Dry rolled to provide 80% of rolled thickness. • Grout: mix of cement, coarse sand and water • Applied on the surface.s 3.6 Construction of Cement Concrete Pavement • ROLLED CONCRETE LAYER: • Lean mix of aggregate, sand, cement and water is laid on prepared subgrade or sub base course. • Rolling similar to WBM • Tandem rollers are preffered and rolled before final setting time. • Both cement grouted and rolled concrete are suitable for base course only. 3.6.1 Construction of Concrete Slab • Basically 2 methods:
• ALTERNATE BAY METHOD
• CONTINUOUS BAY METHOD
3.6.1 Construction of Concrete Slab • ALTERNATE BAY METHOD: • Construction of one slab in alternate succession • Next or intermediate bays are followed after a week or so • Provides additional working convenience for laying slab • Construction joints are easier to provide • Numerous transverse joints are to be provided resulting in high cost for construction and smoothness in riding is reduced. 3.6.1 Construction of Concrete Slab
• Traffic has to be completely halted or diverted
3.6.1 Construction of Concrete Slab • CONTINUOUS BAY METHOD: • All slabs laid in sequence • Construction joints provided at the end of day’s work • Construction of half of the pavement width can be done at a time and traffic can be diverted on the other half • Generally in practice 3.6.1 Construction of Concrete Slab • MATERIALS: • Cement: OPC in general but RHPC may also be used • Coarse Aggregate: Max size < ¼ of slab thickness • Gradation of coarse aggregate range from 50 to 4.75 or 40 to 4.75 mm • Free from harmful materials 3.6.1 Construction of Concrete Slab • LIMITS: • Crushing value< = 30% • Impact Value <= 30% • LAA <= 30% • Soundness <= 12 % Na2SO4, <= 18% MgSO4 3.6.1 Construction of Concrete Slab
• Fine Aggregates: Natural sand or crushed stone
3.6.1 Construction of Concrete Slab PROPORTIONING OF CONCRETE: • Develop minimum compressive strength 280 kg/cm3 at 28 days or higher values 3.6.1 Construction of Concrete Slab • PLANTS AND EQUIPMENTS: • Concrete mixer, batching equipment, wheel barrows, internal vibrators, float, straight edge, brush, and other small tools 3.6.1 Construction of Concrete Slab • CONSTRUCTION STEPS: • Preparation of Subgrade and Sub base: • Properly drained, plate bearing test result 5.54 kg/cm2 (Modulus of subgrade reaction) • Checked 2 days in advance and should be kept moist at the time of placing concrete 3.6.1 Construction of Concrete Slab • PLACING OF FORMS: • Steel or wooden forms • Depth = thickness of pavement • Maximum deviation during entire work < 3mm from straight edge 3m in length 3.6.1 Construction of Concrete Slab • BATCHING OF MATERIAL AND MIXING: • Proportion of coarse and fine aggregates are proportioned WRT no. of bags of cement and put in the mixture • Batch mixer mixes the materials in uniform manner with uniformity in color and is homogeneous • Water introduced within first 15 seconds of mixing • Mixing completes approximately in 1 and half minutes 3.6.1 Construction of Concrete Slab • TRANSPORTING AND PLACING OF CONCRETE: • Mixed concrete should be used immediately, within the prepared form to a required thickness • No segregation should take place • Redistribution can be done by shovels 3.6.1 Construction of Concrete Slab • COMPACTING AND FINISHING: • Compaction by power driven finishing machine or vibrating hand screed • For smaller width of slab and corner of junction, hand consolidation is considered • Further compacted by longitudinal float • Tested for grade and level 3.6.1 Construction of Concrete Slab • CURING: • For initial curing Covered with jute mats and water is poured • Final curing is done by saturating by water for 14 days • OPENING TO TRAFFIC: • After concrete acquires adequate strength or after 28 days of curing 3.6.2 Construction of Joints • Joints provided for expansion, contraction and warping of the slabs • Expansion joints provided to allow for expansion • Provided at interval of 50~60 m for smooth interface laid in winter and 90~120m for summer • 140m spacing for rough interface • Gap width of expansion joint: 20~25mm 3.6.2 Construction of Joints • Contraction joints provided to permit the contraction • Spaced closer than expansion joints • Maximum spacing in unreinforced cement concrete 4.5 m and for RCC of thickness 20cm is 14m 3.6.2 Construction of Joints • LONGITUDINAL JOINTS: • Provided for width more than 4.5 m • Prevents longitudinal cracks • Acts as hinge and helps maintaining the level of slabs 3.6.2 Construction of Joints • TRANSVERSE JOINTS: • Staggered arrangement, uniform arrangement and skew arrangement • Allows interaction of water and ingress of stone grits • If subgrade is clayey soil, mud pumping occurs • Joint spaces should be filled with compressible joint filler first and sealed with sealer. 3.6.2 Construction of Joints • REINFORCEMENTS: • In the form of welded wire fabric or bar mats • Holds the cracked slab portions together 3.6.2 Construction of Joints • The prestressing technique is used in continuous lengths upto 120m without joints • Advantage is the elimination of the joints w/o inducing cracks • Low maintainance cost