FACULTY OF CIVIL AND ENVIRONMENTAL ENGINEERING

DEPARTMENT OF CIVIL ENGINEERING (JKA)

SEM 1 SESSION 2019/2020

COURSE NAME CIVIL ENGINEERING SOFTWARE - HECRAS

COURSE CODE BFC 43201

SECTION 9

GROUP 6

TOPIC MODIFICATION CHANNEL UNTIL ARI 50 YEARS

LAW JOE WIN (DF170169)


GROUP MEMBERS
WAN SHI YING (DF170175)

LECTURER NAME PUAN ZARINA BINTI MD ALI

SUBMISSION DATE 18 DECEMBER 2019


TABLE OF CONTENT

No. Title Pages


1 Introduction 1
- Problem Statement
- Objectives
- Study Area

2 Literature Review 2

3 Methodology 3
- List and describe methods/apparatus
- Justification on the selection of analysis
- Modification until ARI 50 years

4 Result 9
- Cost estimation

5 Discussion 13

6 Conclusion 14

7 References 15
4.0 RESULT

Before Modification After Modification

River Starion at Ch 0 :

River Starion at Ch 90 :

River Starion at Ch 200 :

1
River Starion at Ch 410 :

River Starion at Ch 580 :

River Starion at Ch 700 :

River Starion at Ch 830 :

2
River Starion at Ch 900 :

River Starion at Ch 990 :

River Starion at Ch 1177.5 :

Based on the modification, it involves cut and fill process. This process requires cost
analyzation to estimate the cost involved in the process.

3
4.1 COST ESTIMATION BASED ON CHANNEL MODIFICATION

Cut – 11589 m3
Fill – 11105 m3

Cut to fill: RM 5.70/m3 (Refer to JPS)[ CITATION Buk14 \l 1033 ]


11105 m3 x RM 5.70/ m3 = RM 63298.50
Cut to dump: RM 15.80/ m3 (Refer to JPS)[ CITATION Buk14 \l 1033 ]
11589 m3 -11105 m3 = 484 m3
484 m3 x RM 15.80/ m3 = RM 7647.20

Total cost estimation:


RM 63298.50 + RM 7647.20 = RM 70945.70