ID Task Task Name Duration Start Finish Predecessors Resource Names Cost Jul 12, '20 Jul 19,

esource Names Cost Jul 12, '20 Jul 19, '20 Jul 26, '20 Aug 2, '20 Aug 9, '20 Aug 16, '20
Mode S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
1 Initiation 0 days Sun 7/12/20 Sun 7/12/20 $0.00 7/12
2 Requirement 3 days Mon Wed 1 Planing Team $50.00 Planing Team
Gathering 7/13/20 7/15/20
3 System Designing 4 days Thu 7/16/20 Tue 7/21/20 2 Designing Team,Paid Softwares,High
$90.00
End Hardware Designing Team,Paid Softwares,High End Hardware
4 Estimation, Effort, 2 days Wed Thu 7/23/20 3 Document $210.00 Document Softwaree,Acceptance team
Cost 7/22/20 Softwaree,Acceptance
5 coding 6 days Fri 7/24/20 Fri 7/31/20 4 coding Team $73.00 coding Team
6 Tesing 2 days Mon 8/3/20 Tue 8/4/20 5 Testing Team,Changes Need $78.00 Testing Team,Changes Need
7 Implimentation 5 days Wed 8/5/20 Tue 8/11/20 6 customer Interaction,real time work
$80.00 customer Interaction,real time work
8 Project Close Out 1 day Wed 8/12/20Wed 8/12/207 $50.00

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 8/16/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone