Documente Academic
Documente Profesional
Documente Cultură
2
MIRFA-C - ADDITIONAL PUMPS GROUP TO SUPPLY DN1200 CS PIPELINE TO MADINAT ZAYED
ACTIVITY DESCRIPTIONS
Activities (Actual) Dated: 5-Apr-20 Next Working Day Activities (Planned)
Preparation the MAR,s & MS,s for civil items Preparation the MAR,s & MS,s for civil items
Engineering
Preparation the details shop drawings for civil works Prepartion the details shop drawings for civil works
Preparation the MAR,s & MS,s for Mechanical items Preparation the MAR,s & MS,s for Mechanical items
Preparation the details shop drawings for Mechanical items Preparation the details shop drawings for Mechanical items
Continue Backfilling and compaction further layer around foundation and cable trench in
Completed first layer backfilling for foundation in progress
33kv SWG Bldg.
progress
Completed screed over waterproofing of column footing Preparation for installation of Earthing rod
Reinforcement work of raft slab of transformer and cellar area Continue reinforcement work of raft slab of transformer and cellar area
Inspection of Cleaned rebar with Consultant completed and got approval . Inspection of bottom reinforcement and start top reinforcement.
Page 1 of 1