CONTRACT No. N-14673.

2
MIRFA-C - ADDITIONAL PUMPS GROUP TO SUPPLY DN1200 CS PIPELINE TO MADINAT ZAYED

DAILY PROGRESS REPORT # 317


CONTRACT DETAILS WEATHER REPORT REPORTING DETAILS
SITE / LOCATION MIRFA PUMPING STATION & MADINAT ZAYED PS TEMPERATURE (C) 33-27 REPORTING DAY 5-Apr-20
PROJECT TITLE ADDITIONAL PUMPS GROUP TO SUPPLY DN 1200 CS HUMIDITY (%) 64% REPORT NO #317
CLIENT TRANSCO WIND SPEED (KpH) 18 Km/H Contract Period(Days) 825

CONSULTANT ARCADIS WEATHER / SKY Sunny Remaining Period(Days) 315

CONTRACTOR METITO LLC Time Elapsed (Days) 61.82%


CONTRACT No. N-14673.2 MANPOWER DETAILS EQUIPMENT DETAILS
CONTRACT EFFECTIVE DATE 11-Nov-18 DIRECT STAFF 31 DIRECT EQUIPMENT 16

CONTRACT COMPLETION DATE 14-Feb-21 INDIRECT STAFF 17 INDIRECT EQUIPMENT 12

ACTIVITY DESCRIPTIONS
Activities (Actual) Dated: 5-Apr-20 Next Working Day Activities (Planned)
Preparation the MAR,s & MS,s for civil items Preparation the MAR,s & MS,s for civil items
Engineering

Preparation the details shop drawings for civil works Prepartion the details shop drawings for civil works

Preparation the MAR,s & MS,s for Mechanical items Preparation the MAR,s & MS,s for Mechanical items

Preparation the details shop drawings for Mechanical items Preparation the details shop drawings for Mechanical items

Continue Backfilling and compaction further layer around foundation and cable trench in
Completed first layer backfilling for foundation in progress
33kv SWG Bldg.

progress

Completed screed over waterproofing of column footing Preparation for installation of Earthing rod

Housekeeping of construction area in progress Continue housekeeping in construction area

Continue dewatering & discharging Continue dewatering & discharging


Electrical Bldg

Housekeeping and barrication Housekeeping and barrication

Reinforcement work of raft slab of transformer and cellar area Continue reinforcement work of raft slab of transformer and cellar area

Inspection of Cleaned rebar with Consultant completed and got approval . Inspection of bottom reinforcement and start top reinforcement.

Trial pits work in progress Trial pits work continue


Zayed PS
Madinat
Materials Delivered

Signature Reviewed by;


Musthafa Valappil
El Sayed Nasr (Project Manager)
Date : 5-Apr-20 Resident Engineer