Brief Monthly Progress Report

For the Month of July 2019


Project: N-14673.2 Mirfa C – Additional Pumps Group to Supply
DN1200 CS Pipeline to Madinat Zayed
a) Project Start Date: 11 Nov 2018
b) Project Completion Date (PAC): 10 Nov 2020
c) Anticipated Completion Date: 14 February 2021
d) Consultant: ARCADIS
e) Contractor: METITO
f) Award Contract Value (Including VAT): AED 140,758,332.30
g) Vat Amount : AED 6,032,095.38
h) Contract Value (excluding VAT) : AED 134,726,236.92

1. Brief Scope: : Supply, Installation , Testing and commissioning of two new pumps of capacity 34
MIGD per each with all associated mechanical, electrical, civil and ICT works for supplying water
towards Madinat Zayed tanks. Supply and Installation of DN1400 pipelines on the suction side to
connect to the interface point with Mirfa IWPP. Supply and Installation of new piping work including
all associate Valves &fittings at Madinat Zayed to enable reverse flow with the existing CS DN 1200
pipeline
transmit up to 40 MIGD to Mirfa.

2. Project Finance Status


Actual Invoiced up to Cumulative Paid Up
Contract value (AED)
date to date
140,758,332.30 21,219,382.31 21,219,382.31

3a. Progress Summary Cost Driven


Actual Planned Actual Progress Overall
Overall
Overall Progress Progress variance this Variance
Planned
progress this month this month month (%)
Progress(%)
(%) (%) (%) (%)

Cost Driven 1.085 0.93 0.12 0.08 -0.04 -0.155

3b. Progress Summary Effort Driven


Planned Actual
Actual Progress
Planned  Progress Progres Total
  progres variance 
Progress this s this Variance
s this month
month month
Engineering 55.84% 34.75% 10.20% 3.37% -6.83% -21.09%
Procuremen
23.12% 18.55% 8.49% 5.43% -3.06 % -4.57%
t
Construction 1.372% 0.36% 0.68% 0.00% -0.68% -1.012%
Overall 17.42% 13.33% 5.41% 2.50% -2.91% -4.09%

N-14673.2 – Summary Progress – July 2019 1


4. Progress Narrative:
 Identification of Existing underground service and verified by Trial pit in Madina
Zayed.
 Fence Installation for Electrical and Control Building and Switch Gear Building
completed.
 Motor for Main Water Pump reviewed and Approved with comments.
 Structural Design Calculation for Valve Chambers submitted, reviewed and returned
to Contractor.
 Material Submittal for Surge Vessels, Material submittal for Electromagnetic Flow
meter done.
 System Hydraulic Study Transient state submitted, reviewed and returned to the
Contractor.
 Design criteria for structural work re-submitted, reviewed and approved.
 Revised Material Submittal for 33&11 kV Distribution Transformers done.
 P&ID resubmitted, reviewed and returned to Contractor.
 Process Flow Diagram submitted, reviewed and approved with comments
 Excavation, Data Collection and backfilling of 12 Trial pits at Madina Zayed and 31
Trial pits in Mirfa pump station compound completed.

 Drawing submittal of Overall Protection Single Line Diagram submitted , reviewed


and approved.
 Drawing submittal of Proposed CS 1400mm pipeline for plan & profile and Piping
G.A. Drawing for Pumps Room submitted , reviewed and returned to Contractor.
 Structural design of 33kV MV Switchgear building submitted , reviewed and
returned to Contractor.
 Drawing submittal of Overall Plot Plan Drawing, Proposed relocation of 400 mm dia.
Drain pipeline Plan/Profile submitted, reviewed and approved with comments
 Material Submittal for MV VFD and Phase Shift Transformers submitted, reviewed
and approved with comments
 Material Submittal for LV SWGR SMDB LV Capacitor, Vibration Monitoring System,
Pump Room Steel Structure New Extension, UPVC Pipes & Fittings, MV Motor,
Carbon Steel Pipes and Fittings with External Coating and Internal Lining, Butterfly
Valve, Air Release Valve done.

6. Areas of Concern.
 Project Optimization proposal has finalized however need to be formalized
and issue the VO accordingly. Engineering Design of the facilities under
consideration can only be finalized thereafter. Please note that building
construction works cannot start unless the structural size is finalized.
 Submission for civil sub -contractor for approval. Site meeting is arranged
and discussed. Metito informed that they have decided to do the civil works
by themselves rather than assigning to a sub-contractor. Metito advised in

N-14673.2 – Summary Progress – July 2019 2


set up of site organization for Civil works and mobilization of Construction
Manager/site Engineer.
 Schedule Variance. Discussed with Contractor and contractor agreed to
expedite the submission of critical Engineering activities . Technical meeting
has arranged as and where required to expedite structural design submittal
and EIC design. Contractor will submit a recovery schedule to confirm the
action taken and verification of the effectiveness of schedule variance.
Contractor intended to submit the Revised Baseline program after the
approval of EOT due to Project Optimization.

7. Expected Project delay duration: 96 days.

8. Delayed Activity

S.N Delay Mitigation measures

1 Re-Submission of P&ID delayed. Resubmission Technical meeting has been


of Hydraulic study delayed. conducted ,Discussed with Metito and
clarified the comments. Metito
resubmitted accordingly on 28.07.19.
2 Submission of Structural calculation and Separate work shop meeting is arranged
design drawing for Electrical& control building, on 30.07.19 between Arcadis and Metito
pump station extension, New compressor structural Engineer.
building, MV switch gear building.
3 Submission of Cause and Effect Schedule, Metito to expedite the submission.
Operation control philosophy.
4 Preparation and Submission of Piping layout ‐ Metito shall expedite the preparation
For Mirfa pumping station, For interconnecting of design, and drawings of Pipe layout
piping from Mirfa pump station. in the locations mentioned.
5 Submission of Method statement for Metito shall expedite the preparation
Dewatering works, Shoring works is delayed as of method statements of works
per approved program mentioned
6 Submission of Civil Structural Design Drawings Metito to coordinate with concerned
to AbuDhabi Western Municipality is delayed as authorities after get approved item no
per approved program 2.

N-14673.2 – Summary Progress – July 2019 3