Documente Academic
Documente Profesional
Documente Cultură
1. Brief Scope: : Supply, Installation , Testing and commissioning of two new pumps of capacity 34
MIGD per each with all associated mechanical, electrical, civil and ICT works for supplying water
towards Madinat Zayed tanks. Supply and Installation of DN1400 pipelines on the suction side to
connect to the interface point with Mirfa IWPP. Supply and Installation of new piping work including
all associate Valves &fittings at Madinat Zayed to enable reverse flow with the existing CS DN 1200
pipeline
transmit up to 40 MIGD to Mirfa.
6. Areas of Concern.
Project Optimization proposal has finalized however need to be formalized
and issue the VO accordingly. Engineering Design of the facilities under
consideration can only be finalized thereafter. Please note that building
construction works cannot start unless the structural size is finalized.
Submission for civil sub -contractor for approval. Site meeting is arranged
and discussed. Metito informed that they have decided to do the civil works
by themselves rather than assigning to a sub-contractor. Metito advised in
8. Delayed Activity