Documente Academic
Documente Profesional
Documente Cultură
Group: five
Name and Surname Student number
Noluthando Khumalo 21915829
Thulasizwe Zikhali 21711108
Ziningi Mnqayi 21854807
Nontobeko Nyawo 21910637
Zamokuhle Nene 2195948
Contents
Introduction...................................................................................................................2
Background to the project.........................................................................................2
Design brief...............................................................................................................2
Project Details...........................................................................................................3
Project requirements.................................................................................................4
Materials inspection and construction.......................................................................4
Tasks Involved In The Project......................................................................................5
Site location conditions.................................................................................................6
Site Establishment, Power Supply And Other Services...............................................7
Small Contractor Development, training and community liaison..................................7
Requirements Of The Occupational Health And Safety Act And Regulations.............8
HSE Policy................................................................................................................8
Health and Safety Plan.............................................................................................8
Project Parameters?...................................................................................................10
What are project teams?............................................................................................10
PROJECT DESIGN PACKAGES...............................................................................12
STANDARD PACKAGE......................................................................................12
DELUX PACKAGE..............................................................................................12
FULL SERVICE PACKAGE................................................................................12
COORDINATION OF DESIGN PACKAGES..........................................................12
Work Breakdown Structure.........................................................................................14
project commencement...........................................................................................14
Project tendering.....................................................................................................14
Site work.................................................................................................................14
Construction activates.............................................................................................14
Substructure........................................................................................................14
Superstructure.....................................................................................................14
Roof construction phase......................................................................................14
Finishing..................................................................................................................14
Project completion...................................................................................................15
References.................................................................................................................16
Introduction
Our clients Mr and Mrs Mark have request we provide an oversight and leadership
role in planning and scheduling of their proposed single storey one-bedroom granny
flat in Kwa Zulu Natal, Durban, and Glenwood. The granny flat will serve as a
retirement home for our clients .We are to supervise progress, on behalf our client
from the planning to the completion of the entire granny flat
.
Design brief
Our clients requested us to provide oversight and leadership role in planning and
scheduling of their proposed single storey granny flat in Durban Glenwood. It
includes one bedroom, a bathroom, kitchen, lounge and a single garage. The house
has to be a simple modern comfortable design suitable for older occupants
The bedroom has built in cupboards and carpet floorings .The bathroom has vinyl
tiles a wash closet, sink, shower and bathtub. The kitchen has a kitchen sink and
built in cupboards. The lounge has simple carpet flooring and the garage has
untinted grano flooring.
All exterior doors and windows are aluminium and are to be fixed according to the
door and window schedule. The interior doors will be timber doors also fixed
according to the door schedule
Interior walls are to be finished with cement plaster and interior quality PVA emulsion
paint. Exterior walls will either be finished with FBA red facebrick or cement plaster
and exterior quality Pva emulsion paint according to the architect’s drawings
The roof will be a hipped roof with fibre cement covering to be completed by
nominated sub-contractor according to Architects drawings.
All electrical and plumbing works will be completed according to the architects
specifications by nominate sub-contractor.
Project Details
A detailed site plan from site clearance to super structures and all the
specification of improvement all in compliance to the SANS 10400 of the
SANS
A prepared bill of quantities or an estimate of the cost and budget, materials
to be purchased or used on site.
Contractors or home builders must be registered with the NHBRC and also
the building must comply with the NHBRC regulations
A work breakdown structure that identifies all major activities
Scheduled start and end dates for each activity
Linkages between activities that clearly identify sequence, floats and critical
path
Intended working hours and resource allocations (plant and labour)
The contractor’s payment weekends
Monthly cash flow projections
Key dates in respect of information required
A risk assessment schedule with plans that could prevent the due completion
date from being met
Site clearance
The site has to be cleared from all debris, vegetation, shrubs and trees not
exceeding 2mm girth according to the standard system of building. Trees and
hedges has to be removed from the site. Site clearance also involves the
removal of top soil, as it may stimulate the growth under the building and
make the building unstable
Excavation
Excavation of surface trenches has to be done in order to create a stable
stand for the walls , excavation must not exceed 2mm depth .excavation can
be done differently, some excavations include having to excavate the whole
area where the structure is going to be built and some excavations include
excavation of walls separately
Soil poising
Soil poisoning has to be done on the sides and bottom of the foundation in
DPC 200 to prevent growth to improve the durability of the structure
Concrete
20mpa unreinforced concrete to be poured on the surface trenches to make
the. Foundation for brickwork and Concrete after brickwork has been laid
Location of the site is in Kwa Zulu Natal, Durban Glenwood (ERF NO. 1057) is on a
sloping site.
This is because of the difference in natural ground level, with a boundary wall
(Vibrate wall1, 8m high all around) of 21850mm x 30200mm. EX municipal sewer to
the north next to the stopcock and meter along the boundary wall.
There are three trees on site and two will have to be removed before work
commences. 60mm diameter tree and the 210mm diameter tree. The Brazilian
pepper tree will have to remain on site. 7510mm long x 1500mm high hedge on site,
which will also have to be removed once work starts.
The site has loose sandy material, which is sand whose state is significantly looser
than its critical state. This means the soil has low density or is uncompact and this
causes it to have a tendency to compress when load is applied.
Figu
re 1
Site Establishment, Power Supply and Other Services
The contractor is to make his own arrangements concerning the supply of electrical
power, running water and other essential services. No direct payment will be made
for the provision of these services. The cost thereof is deemed included in the rates
and amounts tendered for the various items of work for which these services are
required.
The contractor shall seek and provide a suitable site for the site camp and
accommodation if necessary.
The Principal Contractor is and remains accountable for the quality and execution of
the health and safety programme for his employees according to the Occupational
Health and Safety Act, Act 85 of 1993. Its regulations together with SANS codes
legally set out minimum standard about Occupational Health and Safety.
While the Principal Contractor may have his own Occupational Health and Safety
measures in place, this specification is included to guide the Principal Contractor in
compiling his health and safety system according to these specifications in order to
legally comply with the Construction Regulations, GNR.84 of 2014. It is the duty of
the Safety Officer and the Principal Contractor to communicate and comply with the
requirements and conditions contained in the various legislation about their
professional capacities in accommodating safety measures in their scope of works.
HSE Policy
Contractors are required to have their own Health and Safety Policy. This policy
should declare their attitude and approach to HSE and the welfare of their
employees and others. The contractor in his capacity as the employer heeds the
responsibility to provide as far as reasonably practicable a safe and healthy working
environment for his employees.
The Principal Contractor should place it upon himself to employ competent workers
where required by the OHS Act and Regulations. This must be done in writing, as all
employees on the project are responsible for their own health as well as the safety of
persons who may be affected by their acts, as per Section 14 of the OHS Act.
Project Parameters?
It is any piece of data that needs to be shared by members of a project or certain
characteristics that can define a project or its aspects.
Cost budget- It is the determination of money that the project will most likely
consume to be completed
Time schedule- It is the duration of a project and life span of its result
Project team is a team whose members usually belong to different groups, have
different functions and are assigned by the project manager to activities for the same
project. They are only used for a defined period.
Main contractor- Is responsible to find and hire right subcontractors and individuals
to complete the job.
client
Mr& Mrs
Mark
project
manager
SNB
Consultants
supliers
Figure 2
PROJECT DESIGN PACKAGES
They are usually based on the scope of work and priced per project...
STANDARD PACKAGE
Initial design consultation
Selection checklist for intended scope
Floorplan and design plan
Cabinet and tile layout elevation
Electrical and lightning plan
List of final selection to be signed off on
DELUX PACKAGE
Initial design consultation
Selection checklist for intended scope
Showroom visits to assist with selection
Floorplan and design plan
Cabinet and tile layout elevation
Electrical and lighting plan
List of final selections to be signed off
Project tendering
Call for project tendering
Adjudicate for project tender
Award project render
Post tender stage
Site work
site establishment
water distribution
landscaping
site layout and plan setting up
Construction activates
Substructure
excavations
concrete framework
reinforcement and curing
completion of foundation
backfilling
Superstructure
build walls to lintel level
install electrical conducts
install pluming conducts
placing precast lintels
inspections
completion of all walls to roof level
Finishing
plastering
windows and lazing
celling’s
floor screed
kitchen and bedroom fittings
bathroom fittings
plumbing fittings and fixture
electrical fittings and fixtures
flooring
security fittings and fixtures
painting of walls
landscaping
Project completion
final inspections
project commission
project handover
References
https://resource.workable.com/construction-manager-job-description
https://www.andersonandrodgers.com/custom-design
https://www.taskmanagementguide.com/glossary/what-are-project-
parameters.php