REPORT
1
taken not to inflict the drainage system of the topographic, but road
side drain and cross drainage system shall have to be improved.
For Flexible:-
WBM = 75 mm
PMC SC (Damaged condition
Total = 75 mm
Field Investigation: - The following field investigations have been conducted at site.
I) Topographical survey
II) Soil investigation
III) Road and CD inventory
iv) Traffic survey
Traffic Data: - Traffic census has been conducted in the month of Feb 2019. As per
traffic data CVD and PCU comes to 202 and 1394 respectively. The traffic
data is enclosed here with.
Pavement Design :- Since the work mainly comprises of Widening of existing single lane to
Intermediate lane and Strengthening of the entire carriage way with
flexible pavement, IRC: 37 has been adopted in the design of the stretch.
Provisions
For Road works: - the following provision has been made in this estimate, the details are as
follows:
For Flexible
2
ii) 115 thick G.S.B Gr.-IV overlay on the entire carriage way.
C.D.works:
Camber &
Super elevation:- 2.5 % camber on carriage way and 3 % camber on both side berms in
Flexible pavement has been proposed. The designed super elevation
has been proposed in the estimate.
Drainage: - In the proposed stretch there are 36 numbers of existing CD Works & 5
nos of new culverts are also proposed. The vent age of existing culverts
is adequate for drainage of rain water during rainy season. Provision of
deep drain 1820m (In stretches) in the built-up portions as per the
schedule (enclosed) has been proposed. There is no drainage problem
in the balance portion of the proposed stretch.
3
Protection works: - Provision of Toe wall of Height 1.0m above G.L. has been
proposed for a length of 1000m, of height 1.5m above G.L. has been
proposed for a length of 1173m & Retaining wall of height 2.0m above
G.L. has been proposed for a length 1000m. Further drain with breast
wall has been proposed for a length of 1000m in cutting portions to drain
out the water from uplands. W Metal beam crash barrier has been
proposed for a length of 100m.
Labour and
Materials: - The local Labour will be engaged in the project and the granite stone
product and other materials will be procured from the nearest local quarry
as shown in quarry chart. Stone products will be procured from Gopalpur
quarry, gravel from Bansapal Block quarry, sand for filling from Malda
Nallah Local & sand for mortar from Baitarani River Local (all from
Keonjhar district). Steel from Rourkela and cement from Local, the
nearest approved factory by Ministry will be used in the project. The lead
statement of different materials is enclosed in the estimate.
Plant and
Machineries: - The Plant and machineries will be utilized as per specification of
MORT&H for Road and Bridge works (5th Revision), which will be
procured by the executing agency at his own cost.
Specification: - The work will be carried out as per Specification of Road and Bridge
works (5th Revision), relevant codes of IRC and circular and instructions
of government issued from time to time.
4
DESK / FIELD APPRAISAL -
FORMAT FOR ROAD AND BRIDGE PROJECTS - RIDF - XXV
2. District : Keonjhar
11. If recommended cost is different from the project report cost, give reasons
12. Time required for construction of project: 18 Calendar months
(c) Status of other reaches (Give reasons, : Actual length 13.389 Km.
if any, for not proposing other reaches)
(d) Class of Road (Indicate VR / ODR/ MDR / SH) : ODR
17. Traffic Details {anticipated traffic per day (average) after development} :
Cycle (No.) Cycle Rickshaw Handicraft (No.) Horse drawn Bullock cart Motor cycle
(No.) vehicle (No.) (No.) / scooter
(No.)
0
300 0 0 0 1000
Passenger car / Agricultural Tractor Truck / bus (No.) Truck - Trailor Material transported per
pick up van/ auto / ICV (No.) (No.) annum (output/ input in MT)
rickshaw (No.)
800 60 260 0
Considering traffic 3 MSA and CBR 6% crust provision has been made as per IRC37. The crust
design as per IRC 37,Traffic data, CBR test results, Index maps etc are enclosed in estimate.
The provision has been made as per latest SoR 2014 revised on GST with enhanced Labour rate
of Odisha w.e.f.30.10.2018 and data book.
22. Implementation problems (details of land acquisition, forest clearance, inadequate budget
provisions for ongoing projects, contractor problem etc.) if any.
Not applicable.
Certified that, I have visited site & fully satisfied about the survey, investigation &
also the plan, design for the project.
Executive Engineer
Keonjhar (R&B) Division, Keonjhar
CERTIFICATE OF EXECUTIVE ENGINEER AS PER
WORKS DEPARTMENT
Certified that,
Executive Engineer
Keonjhar (R&B) Division, Keonjhar
CERTIFICATE OF EXECUTIVE ENGINEER FOR
TECHNICAL SANCTION ESTIMATE
Executive Engineer
Keonjhar (R&B) Division, Keonjhar
Check list for preparation of Detailed Project Report
To be submitted for loans under RIDF -XXV
Road / Bridge Project Road Project
7 Infrastructure facilities
i. Organizational structure of the implementing Depts. Works Department
ii. Capacity and preparedness of the implementing Deptt. Works Department
and status of implementation of earlier sanctioned
projects
iii. Quality control infrastructure and mechanism Will be done by the Yes
agency as per terms &
conditions of the
agreement.
iv. Availability of labour Yes
Budget provision
a. For contribution to State Share
b. For subsequent O & M
c. For repayment of loans – Principal and interest
8 Project Risks
i. Land Acquisition No
ii. Forest clearance No
iii. Railway / road crossing No
iv. Construction hazards No
v. Any other risk No
9 Convergence with any other programme No
GENERAL ABSTRACT
SAY Rs 19,47,39,000.00