Nepal Community Reconstruction Program (NCRP)

Baseline Schedule Analysis Report

TO 72036719F00003
Reconstruction of Health and Education Facilities in Sindhuli District

December 16, 2019


Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

Table of Contents
A. General:............................................................................................................................................3
B. Belghari Primary Healthcare Center (BPHC):..................................................................................4
C. Kapilakot Primary Healthcare Center (KPHC):................................................................................7
D. Mahendrajhyadi Primary Healthcare Center (MPHC):...................................................................10
E. Mahadevsthan Health Post (MSHP):..............................................................................................12
F. Bhanu Secondary School (BNSS):.................................................................................................14
G. Dirgha Pradip Secondary School (DPSS).......................................................................................16
H. Shree Secondary School (SSS).......................................................................................................17
1. Note:...............................................................................................................................................19

Page 2 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

Baseline Schedule Analysis Report


Title Reconstruction of Schools and Health Facilities in Sindhuli District
Location Sindhuli, Nepal
Contractor Macro Vantage Levant (MVL)
Software Primavera P6
Analysis Date December 16, 2019
Previous Review November 14, 2019
Approved Baseline N/A - this is DRAFT baseline schedule
Contract Modifications N/A - this is DRAFT baseline schedule
Contract Award Date July 19, 2019
Notice to Proceed (NTP) August 14, 2019
Contract Duration; Calendar Days 540 days
Contract Required Completion Date January 9, 2021
Forecast Completion Date N/A - this is DRAFT baseline schedule

A. General:

1. General requirements:

The following activities are not applicable under WBS “General requirements”. Please adjust to avoid
confusion:

 MILS-1000 <MILSTON> Letter of Award


 MILS-1210 <MILSTON> Payment Terms

For simplicity, please include “Letter of Award” and “Notice to Proceed” under WBS “Contract
milestones”.

2. Mobilization and Demobilization Costs:

CLIN amount for CLIN 4 Mahadevsthan Health Post is incorrect.

Cost allocation for Mobilization and Demobilization aren’t correct for CLINs 1, 2, 3, 4 and 7. As per
“Section H.33 Mobilization and Demobilization Payments” of Contract, following cost should be
allocated for mobilization and demobilization:

Please correct the CLIN amount and mobilization/demobilization costs in the schedule as per below
table.

CLIN Amount 3% 5% 2%
CLIN Facility
Contract Schedule Contract Schedule Contract Schedule Contract Schedule
CLIN $1,405,628.8 $1,405,628.8 $42,168.8 $39,413.6 $70,281.4 $65,689.7 $28,112.5
BPHCC $26,275.88
1 1 1 6 0 4 1 8
CLIN $1,806,387.7 $1,806,387.7 $54,191.6 $54,191.6 $90,319.3 $90,319.4 $36,127.7
KPHCC $36,127.74
2 7 7 3 0 9 5 6
CLIN MPHC $1,404,220.9 $1,404,220.9 $42,126.6 $42,168.6 $70,211.0 $70,281.6 $28,084.4
$28,112.60
3 C 3 3 3 3 5 5 2
CLIN $21,328.6 $21,328.3 $35,547.7 $35,547.4 $14,219.1
MSHP $710,954.96 $710,653.49 $14,219.10
4 5 6 5 5 0
CLIN $1,363,253.3 $1,363,253.3 $40,897.6 $40,897.6 $68,162.6 $68,162.6 $27,265.0
BNSS $27,265.07
5 1 1 0 0 7 7 7
CLIN $1,609,073.1 $1,609,073.1 $48,272.1 $48,272.1 $80,453.6 $80,453.6 $32,181.4
DPSS $32,181.46
6 3 3 9 9 6 6 6
CLIN $1,313,794.1 $1,313,794.1 $39,413.8 $39,413.6 $65,689.7 $65,689.7 $26,275.8
SSS $26,275.88
7 7 7 3 0 1 1 8

Page 3 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

3. Calendars:

Three calendars “6x8Hr W/Nepal Holidays and Weather”, “6X8Hr Without Holidays Nepal” and
“6X8Hr W/Nepal Holidays” are applied for construction activities. The non-working days aren’t in
accordance with public holidays in Nepal.

 Provide a schedule of non-working days (public holidays and weather days) in the schedule
narrative.
 Ensure the non-working days in the schedules are in-line with public holidays in Nepal and
anticipated weather days as shown below.

All external/weather dependent activities should use weather calendar with anticipated non-working
days due to adverse weather. Refer to Attachment J.9 Project Control Systems Guidelines for
anticipated number of non-working days (weather days).

4. Dangling activities:

Several activities have missing links to their start or finish points which can change duration without a
detectable impact to the schedule.

Our goal is to create a dynamic schedule that correctly calculates activity dates when durations change
or work slips or completes out of sequence. When a start-to-start (SS) link connects two activities, a
finish-to-finish (FF) or finish-to-start (FS) link is needed to connect further downstream. Similarly,
when a finish-to-finish (FF) link connects two activities, a start-to-start (SS) or finish-to-start (FS) link
is needed to connect further upstream.

5. Actual dates in baseline schedule:

Because baseline schedule is a depiction of the contractor’s plan when bid, they should not contain
actual dates. The only possible exception to this rule is of Contract Award date. Even the baseline
schedule that is approved months after the start of the project should not have actual dates. Those actual
dates should be submitted as part of the first schedule update submittal.

B. Belghari Primary Healthcare Center (BPHC):

1. Summary:

Title 720367-19-R0-0003-Sindhuli Facilities-CLIN 1- Belghari PHCC-NEPAL-USAID


Plan finish date 08/01/2021 Tasks with no progress 752
Plan remaining duration 500 In progress tasks 2
Normal tasks 748 Completed tasks 5
Summary tasks 0 Total tasks 759
Milestone tasks 10 Resource assignments 1988
Hammock tasks 1 Budget cost $0
Monitor tasks 0 Remaining cost $0
Calendars 11 Actual cost $0
Links 1417 Total cost $0
Resources 10    

Page 4 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

2. Scope of works:

Full scope isn’t covered by schedule. Following activities are in project’s scope but not included in the
schedule:

 Cement sand skirting and pointing works.


 Brick soling and PCC works below lower tie beam.
 Anti-termite before backfilling and apron, floor slab works.

Review the schedule again to ensure that the required activities are covered. Detail all activities within
the scope of works.

3. Dangling Activities:

Following activities have missing links to their start or finish points.

Remaining
ID Description Type Detail
Duration
<CONSTR>. <MOB> Mobilization of Key
MOB-1210 Normal 18 Finish has no successors
Personnels (including get Permits)
OM-1040 <CLSOUT>.<OM>.Owner Training Normal 4 Finish has no successors
<MBB>.<GRD FLR>. Apply IPC Roof
MBB-A-A-1160 Normal 4 Finish has no successors
finish works
MB-E-C-S-
<MB>.<GRD FLR>. Fix Rebars for Columns Normal 10 Finish has no successors
1060
<MBB>.<FND>. Curing fresh Concrete of
MBB-A-F-1220 Normal 7 Finish has no successors
Lower Time Beams
<VB>.<FND>. Curing Fresh Concrete of
VB-B-F-1210 Normal 7 Finish has no successors
Footings
<VB>.<FND>. Curing fresh Concrete of
VB-B-F-1270 Normal 7 Finish has no successors
Upper Tie Beams
<VB>.<FND>. Curing fresh Concrete of
VB-B-F-1280 Normal 7 Finish has no successors
Floor Slab
<VB>.<GRD FLR>. Curing fresh Concrete
VB-B-S-1080 Normal 7 Finish has no successors
of Columns
TWMB-C-F- <TWMB>.<FND>. Curing fresh Concrete of
Normal 7 Finish has no successors
1220 footings
TWMB-C-F- <TWMB>.<FND>. Curing fresh Concrete of
Normal 7 Finish has no successors
1230 Lower Tie Beams
TWMB-C-F- <TWMB>.<FND>. Curing fresh Concrete of
Normal 7 Finish has no successors
1290 Floor Slab
TWMB-C-S- <TWMB>.<GRD FLR>. Curing Fresh
Normal 7 Finish has no successors
1090 Conrete of Columns
MB-E-C-F- <MB>.<FND>. Curing fresh Concrete of
Normal 7 Finish has no successors
1210 Footings
MB-E-C-F- <MB>.<FND>. Curing fresh Concrete of
Normal 7 Finish has no successors
1280 Floor Slab
<CB>.<FND>. Curing fresh Concrete of
CB-G-F-1210 Normal 5 Finish has no successors
Footings
<CB>.<FND>. Curing fresh Concrete of
CB-G-F-1280 Normal 7 Finish has no successors
Floor Slab

4. Incorrect Activity Relationships:

Following activities have incorrect relationships.

Page 5 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

Activity Predecessor
CB-G-A-1030 <CB>.<GRD FLR>. Plaster the Ceiling CB-G-A-1020 <CB>.<GRD FLR>. Plaster the Walls

Re-check entire schedule and correct activity relationship errors similar to above.

5. Incorrect Calendar Assignments:

Several activities have incorrect calendar assignments. Some examples are:

Activity Calendar
SH-1040 <DESIGN> Develop Shop Drawing 6X8Hr W/Nepal Holidays & Weather
SH-1060 <DESIGN> Review & Approve Shop Drawing by A&E and USAID
6X8Hr W/Nepal Holidays & Weather
TOCOR
SH-1050 <DESIGN> Submit Shop Drawing to A&E and USAID TOCOR review & 6X8Hr W/Nepal Holidays & Weather
Approval
FE-1000 <FE>.<GRD FLR>.Install Furniture 6X8Hr W/Nepal Holidays & Weather
FE-1010<FE>.<GRD FLR>.Install Equipment 6X8Hr W/Nepal Holidays & Weather
FINS-1050 <CLSOUT>.<FINS>.Approved Final Inspection, Completion 6X8Hr W/Nepal Holidays & Weather
& Acceptance
ASB-1000 <CLSOUT>.<ASB>.Submit As-Built Drawings 6X8Hr W/Nepal Holidays & Weather
ASB-1010 <CLSOUT>.<ASB>.Approved As-Built Drawings 6X8Hr W/Nepal Holidays & Weather
DEMB-1020 <CLSOUT>.<DEMB>.Final Report 6X8Hr W/Nepal Holidays & Weather
OM-1000 <CLSOUT>.<OM>.Submit O&M Training and Manuals 6X8Hr W/Nepal Holidays & Weather
OM-1060 <CLSOUT>.<OM>.Approved O&M 6X8Hr W/Nepal Holidays & Weather
OM-1010 <CLSOUT>.<OM>.Submit Spare Part List 6X8Hr W/Nepal Holidays & Weather
OM-1020 <CLSOUT>.<OM>.Training Schedule 6X8Hr W/Nepal Holidays & Weather
OM-1030 <CLSOUT>.<OM>.Approved Spare Part List 6X8Hr W/Nepal Holidays & Weather
OM-1040 <CLSOUT>.<OM>.Owner Training 6X8Hr W/Nepal Holidays & Weather
OM-1050 <CLSOUT>.<OM>.Deliver Spare Parts 6X8Hr W/Nepal Holidays & Weather
DEMB-1110<CLSOUT>.<DEMB>.De-mobilization Plan 6X8Hr W/Nepal Holidays & Weather
GH-H-A-1120 <GHH>.<GRD FLR>. Install IPC Flooring 6X8Hr W/Nepal Holidays & Weather
GH-H-E-1040 <GHH>.<GRD FLR>.Install Distribution Boards and Control Panel 6X8Hr W/Nepal Holidays & Weather
GH-H-E-1010 <GHH>.<GRD FLR>. Install Switches and Junction Boxes 6X8Hr W/Nepal Holidays & Weather
GH-H-T-1000 <GHH>.<CLSOUT>. Testing and comissioning for Electrical and 6X8Hr W/Nepal Holidays & Weather
Mechanical Systems

Re-check entire schedule and correct errors in activity calendars similar to above.

6. Mandatory Lags:

Removal of formworks after concreting works for beams and slab should be started only after 21 to 28
days as per paragraph 4.3D under section 3 201 of technical specifications. The removal of formworks
is scheduled to start immediately after curing works not maintaining required gaps between concreting
works and formwork removal. Ensure there is correct relationship and lags between concrete and
formwork removal activities.

Activity Start Finish Remarks


MBB-A-S-1090 <MBB>.<GRD FLR>. Pour Concrete for Suspended
18/05/2020 19/05/2020
Slabs & Beam
MBB-A-S-1120 <MBB>.<GRD FLR>. Curing fresh Concrete of
22/05/2020 29/05/2020
Suspended Slab & Beams
MBB-A-S-1180 <MBB>.<GRD FLR>. Removal of Slab formwork 03/06/2020 05/06/2020
TWMB-C-S-1080 <TWMB>.<GRD FLR>. Pour Concrete for Suspended
03/06/2020 03/06/2020
Slabs and Beams
TWMB-C-S-1100 <TWMB>.<GRD FLR>. Concrete work of Parapet
04/06/2020 09/06/2020
Columns
TWMB-C-S-1110 <TWMB>.<GRD FLR>. Curing fresh Concrete of
10/06/2020 19/06/2020
Suspended Slab and Beams
TWMB-C-S-1020 <TWMB>.<GRD FLR>. Removal of Fromwork from
23/06/2020 25/06/2020
Slab and Beams
SQ-D-G-S-1080 <SQ>.<GRD FLR>. Pour Concrete for Suspended Slabs 10/06/2020 10/06/2020
and Beams

Page 6 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

SQ-D-G-S-1120 <SQ>.<GRD FLR>.Curing fresh Concrete of Slab and


11/06/2020 23/06/2020
Beams
SQ-D-G-S-1140 <SQ>.<GRD FLR>. Removal of formwor from Slab and
24/06/2020 26/06/2020
Beams
VB-B-S-1070 <VB>.<GRD FLR>. Pour Concrete for Slabs and Beams 09/07/2020 09/07/2020
VB-B-S-1090 <VB>.<GRD FLR>. Curing fresh Concrete of Beam &
10/07/2020 19/07/2020
Slab
VB-B-S-1150 <VB>.<GRD FLR>. Removal of Slab formwork 22/07/2020 22/07/2020
CB-G-S-1080 <CB>.<GRD FLR>. Pour Concrete for Suspended Slabs
22/07/2020 22/07/2020
and Beams
CB-G-S-1120 <CB>.<GRD FLR>. Curing fresh Concrete of Slab 24/07/2020 05/08/2020
CB-G-S-1130 <CB>.<GRD FLR>. Formwork Removal from Slab 06/08/2020 09/08/2020
MB-E-C-S-1090<MB>.<GRD FLR>. Pour Concrete for Suspended Slabs
24/07/2020 24/07/2020
and Beams
MB-E-C-S-1150<MB>.<GRD FLR>. Curing fresh Concrete of Suspended
26/07/2020 06/08/2020
Slab
MB-E-C-S-1140<MB>.<GRD FLR>. Formwork Removal from Slab and
07/08/2020 13/08/2020
Beams
SQ-D-F-S-1060<SQ>.<1st FLR>.Pour Concrete for Suspended Slabs and
03/09/2020 03/09/2020
Beams
SQ-D-F-S-1090<SQ>.<1st FLR>.Curing fresh Concrete of Slab and
04/09/2020 16/09/2020
Beams
SQ-D-F-S-1100<SQ>.<1st FLR>.Removal of formwork from Slab &
17/09/2020 20/09/2020
Beams

C. Kapilakot Primary Healthcare Center (KPHC):

1. Summary:

Constraints 0
Open-ended tasks (Does not include ignored links) 30
Out of sequence updates ("broken logic") 1
Lags longer than 0 units 86
Negative lags ("leads") 0
Positive lags on Finish-to-Start links 12
Start-to-Finish links 0
Lags between tasks with different calendars 10
Links to / from summary tasks 0
Duration uncertainty distribution shape 2 0
Total number of items found 139

7. Scope of works:

Full scope isn’t covered by schedule. Following activities are in project’s scope but not included in the
schedule:

 Main Building: First floor is added but activity names are copied from foundation and ground
floor.
 Brick soling and PCC works below lower tie beams (MBB-A-F).
 Cement sand skirting and pointing works (Refer to drawing sheet A000b).
 Anti-termite works before backfilling and apron, floor slab.

Review the schedule again to ensure that required activities are covered. Detail all activities within the
scope of works.

Page 7 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

2. Dangling Activities:

Following activities have missing links to their start or finish points.

Remaining
ID Description Type Detail
Duration
<EXTR>.<DRA>. Install Cement Sand Punning
EXT-DRA-1040 Normal 15 Finish has no successors
Works
SQ-D-F-A-1080 <SQ>.<1st FLR>.Install Doors and Hardware Normal 7 Finish has no successors
<SQ>.<1st FLR>.Install all Plumbing fixtures and
SQ-D-F-P-1050 Normal 10 Finish has no successors
Accessoires
SQ-D-F-E-1040 <SQ>.<1st FLR>.Install Light Fixtures Normal 8 Finish has no successors
<MBB>.<GRD FLR>. Install Floor Tiles with Epoxy
MBB-A-A-1050 Normal 15 Finish has no successors
Grouting
GH-H-F-1100 <GHH>.<FND>. Install Formwork for Slab Flooring Normal 2 Finish has no successors
MBB-A-E-1130 <MBB>.<GRD FLR>.Install Light Fixtures Normal 4 Finish has no successors
VB-B-F-1210 <VB>.<FND>. Curing Footing Concrete Normal 7 Finish has no successors
VB-B-F-1220 <VB>.<FND>. Curing Tie Beam Concrete Normal 7 Finish has no successors
VB-B-F-1270 <VB>.<FND>. Curing Tie Beam Concrete Normal 7 Finish has no successors
VB-B-F-1290 <VB>.<FND>. Curing Floor Slab Concrete Normal 7 Finish has no successors
VB-B-S-1080 <VB>.<GRD FLR>. Curing Columns Concrete Normal 7 Finish has no successors
TWMB-C-F-1240 <TWMB>.<FND>. Curing Neck Columns Concrete Normal 7 Finish has no successors
TWMB-C-F-1280 <TWMB>.<FND>. Curing Tie Beam Concrete Normal 7 Finish has no successors
TWMB-C-F-1300 <TWMB>.<FND>. Curing Floor Slab Concrete Normal 7 Finish has no successors
TWMB-C-S-1090 <TWMB>.<GRD FLR>. Curing Columns Concrete Normal 7 Finish has no successors
SQ-D-F-1210 <SQ>.<FND>. Curing Foundation Concrete Normal 7 Finish has no successors
SQ-D-F-1220 <SQ>.<FND>. Curing Tie Beam Concrete Normal 7 Finish has no successors
<SQ>.<FND>. Curing Neck Columns & Shear walls
SQ-D-F-1230 Normal 7 Finish has no successors
Concrete
SQ-D-F-1280 <SQ>.<FND>. Curing Tie Beam Concrete Normal 7 Finish has no successors
SQ-D-G-S-1110 <SQ>.<GRD FLR>. Curing Columns Concrete Normal 7 Finish has no successors
SQ-D-F-S-1080 <SQ>.<1st FLR>.Curing Columns Concrete Normal 7 Finish has no successors
MB-E-C-F-1210 <MB>.<FND>. Curing Foundation Concrete Normal 7 Finish has no successors
MB-E-C-F-1220 <MB>.<FND>. Curing Tie Beam Concrete Normal 7 Finish has no successors
MB-E-C-F-1280 <MB>.<FND>. Curing Tie Beam Concrete Normal 7 Finish has no successors
MB-E-C-F-1290 <MB>.<FND>. Curing Floor Slab Concrete Normal 7 Finish has no successors
MB-E-C-S-1120 <MB>.<GRD FLR>. Curing Columns Concrete Normal 7 Finish has no successors
CB-G-F-1210 <CB>.<FND>. Curing Foundation Concrete Normal 7 Finish has no successors
CB-G-F-1220 <CB>.<FND>. Curing Tie Beam Concrete Normal 7 Finish has no successors

3. Out of sequence updates ("broken logic"):

 
From Task To Task
ID Description Type ID Description Type Link Details
MILS- <MILSTON> DBA and Car Normal MILS- <MILSTON> Start milestone FS Task MILS-1210
1020 Insurance Submit and 1210 Payment has already started
Approval Terms

4. Incorrect Activity Relationships:

Following activities have incorrect relationships.

Activity Predecessor
MB-E-C-S-1060 <MB>.<GRD FLR>. Fix Rebars for MB-E-C-S-1000 <MB>.<GRD FLR>. Install Formwork
Columns for Columns

Re-check entire schedule and correct activity relationship errors similar to above.

8. Incorrect Calendar Assignments:

Several activities have incorrect calendar assignments. Some examples are:

Page 8 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

Activity ID Activity Name Calendar


ASB-1000 <CLSOUT>.<ASB>.Submit As-Built Drawings 6X8Hr W/Nepal Holidays & Weather
ASB-1010 <CLSOUT>.<ASB>.Approved As-Built Drawings 6X8Hr W/Nepal Holidays & Weather
DEMB-1020 <CLSOUT>.<DEMB>.Final Report 6X8Hr W/Nepal Holidays & Weather
DEMB-1110 <CLSOUT>.<DEMB>.De-mobilization Plan 6X8Hr W/Nepal Holidays & Weather
FE-1000 <FE>.<GRD FLR>.Install Furniture 6X8Hr W/Nepal Holidays & Weather
FE-1010 <FE>.<GRD FLR>.Install Equipment 6X8Hr W/Nepal Holidays & Weather
GH-F-A-1020 <GHF>.<GRD FLR>. Plaster the internal Walls 6X8Hr W/Nepal Holidays & Weather
GH-F-A-1080 <GHF>.<GRD FLR>. Fix Collapsable Gate for Generator House 6X8Hr W/Nepal Holidays & Weather
GH-F-A-1120 <GHF>.<GRD FLR>. Install IPC Flooring 6X8Hr W/Nepal Holidays & Weather
GH-H-A-1120 <GHH>.<GRD FLR>. Install IPC Flooring 6X8Hr W/Nepal Holidays & Weather
GH-H-E-1010 <GHH>.<GRD FLR>. Install Switches and Junction Boxes 6X8Hr W/Nepal Holidays & Weather
GH-H-E-1030 <GHH>.<GRD FLR>. Install Light Fixtures 6X8Hr W/Nepal Holidays & Weather
<GHH>.<GRD FLR>.Install Distribution Boards and Control
GH-H-E-1040 6X8Hr W/Nepal Holidays & Weather
Panel
MBB-A-S-1170 <MBB>.<GRD FLR>. Removal of Slab Formwork 6X8Hr W/Nepal Holidays & Weather
OM-1000 <CLSOUT>.<OM>.Submit O&M Training and Manuals 6X8Hr W/Nepal Holidays & Weather
OM-1010 <CLSOUT>.<OM>.Submit Spare Part List 6X8Hr W/Nepal Holidays & Weather
OM-1020 <CLSOUT>.<OM>.Training Schedule 6X8Hr W/Nepal Holidays & Weather
OM-1030 <CLSOUT>.<OM>.Approved Spare Part List 6X8Hr W/Nepal Holidays & Weather
OM-1040 <CLSOUT>.<OM>.Owner Training 6X8Hr W/Nepal Holidays & Weather
OM-1050 <CLSOUT>.<OM>.Deliver Spare Parts 6X8Hr W/Nepal Holidays & Weather
OM-1060 <CLSOUT>.<OM>.Approved O&M 6X8Hr W/Nepal Holidays & Weather
SH-1040 <DESIGN> Develop Shop Drawing 6X8Hr W/Nepal Holidays & Weather
<DESIGN> Submit Shop Drawing to A&E and USAID TOCOR
SH-1050 6X8Hr W/Nepal Holidays & Weather
review & Approval
<DESIGN> Review & Approve Shop Drawing by A&E and
SH-1060 6X8Hr W/Nepal Holidays & Weather
USAID TOCOR
SQ-D-G-S-1140 <SQ>.<GRD FLR>. Formwork Removal from Slab 6X8Hr W/Nepal Holidays & Weather
VB-B-S-1100 <VB>.<GRD FLR>. Removal of Slab formwork 6X8Hr W/Nepal Holidays & Weather

Re-check entire schedule and correct errors in activity calendars similar to above.

5. Mandatory Lags:

Removal of formworks after concreting works for beams and slab should be started only after 21 to 28
days as per paragraph 4.3D under section 3 201 of technical specifications. The removal of formworks
is scheduled to start immediately after curing works not maintaining required gaps between concreting
works and formwork removal. Ensure there is correct relationship and lags between concrete and
formwork removal activities.

Activity Start Finish Remarks


MBB-A-S-1090 <MBB>.<GRD FLR>. Pour Concrete for
22/07/2020 24/07/2020
Suspended Slabs and Beams
MBB-A-S-1110 <MBB>.<GRD FLR>. Curing Slab and Beam
26/07/2020 06/08/2020
Concrete
MBB-A-S-1020 <MBB>.<GRD FLR>. Removal of Slab
07/08/2020 13/08/2020
Formwork
VB-B-S-1070 <VB>.<GRD FLR>. Pour Concrete for Suspended
29/07/2020 29/07/2020
Slabs and Beams
VB-B-S-1090 <VB>.<GRD FLR>. Curing Slab and Beam 30/07/2020 09/08/2020

Page 9 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

Concrete
VB-B-S-1100 <VB>.<GRD FLR>. Removal of Slab formwork 13/08/2020 16/08/2020
MBB-A-S-1090 <MBB>.<GRD FLR>. Pour Concrete for
22/07/2020 24/07/2020
Suspended Slabs and Beams
MBB-A-S-1110 <MBB>.<GRD FLR>. Curing Slab and Beam
26/07/2020 06/08/2020
Concrete
MBB-A-S-1020 <MBB>.<GRD FLR>. Removal of Slab
07/08/2020 13/08/2020
Formwork
SQ-D-F-S-1060 <SQ>.<1st FLR>.Pour Concrete for Suspended
22/07/2020 22/07/2020
Slabs and Beams
SQ-D-F-S-1090 <SQ>.<1st FLR>.Curing Slab Concrete 24/07/2020 05/08/2020
SQ-D-F-S-1100 <SQ>.<1st FLR>.Formwork Removal from Slab 06/08/2020 09/08/2020
MBB-A-S-1090 <MBB>.<GRD FLR>. Pour Concrete for
22/07/2020 24/07/2020
Suspended Slabs and Beams
MBB-A-S-1110 <MBB>.<GRD FLR>. Curing Slab and Beam
26/07/2020 06/08/2020
Concrete
MBB-A-S-1020 <MBB>.<GRD FLR>. Removal of Slab
07/08/2020 13/08/2020
Formwork
MB-E-C-S-1090 <MB>.<GRD FLR>. Pour Concrete for
20/08/2020 20/08/2020
Suspended Slabs and Beams
MB-E-C-S-1130 <MB>.<GRD FLR>. Curing Slab Concrete 21/08/2020 01/09/2020
MB-E-C-S-1140 <MB>.<GRD FLR>. Removal of Formwork
02/09/2020 04/09/2020
From Slab
TWMB-C-S-1080 <TWMB>.<GRD FLR>. Pour Concrete for
04/09/2020 04/09/2020
Suspended Slabs and Beams
TWMB-C-S-1100 <TWMB>.<GRD FLR>. Curing Slab
06/09/2020 17/09/2020
Concrete
TWMB-C-S-1140 <TWMB>.<GRD FLR>. Removal of
18/09/2020 23/09/2020
Formwork From Slab
MBB-A-S-1200 <MBB>.<GRD FLR>. Pour Concrete for
10/09/2020 10/09/2020
Suspended Slabs and Beams
MBB-A-S-1160 <MBB>.<GRD FLR>. Curing Slab and Beam
11/09/2020 23/09/2020
Concrete
MBB-A-S-1170 <MBB>.<GRD FLR>. Removal of Slab
24/09/2020 27/09/2020
Formwork

D. Mahendrajhyadi Primary Healthcare Center (MPHC):

1. Summary:

Constraints 0
Open-ended tasks (Does not include ignored links) 20
Out of sequence updates ("broken logic") 1
Lags longer than 0 units 71
Negative lags ("leads") 0
Positive lags on Finish-to-Start links 17
Start-to-Finish links 0
Lags between tasks with different calendars 11
Links to / from summary tasks 0
Duration uncertainty distribution shape 2 0
Total number of items found 120

2. Scope of works:

Full scope isn’t covered by schedule. Following activities are in project’s scope but not included in the
schedule:

 Brick soling and PCC works below lower tie beams (MBB-A-F).
 Cement sand skirting and pointing works (Refer to drawing sheet A000b).
 Anti-termite works before backfilling and apron, floor slab.

Page 10 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

Review the schedule again to ensure that only activities required by project’s scope are covered. Detail
all activities within the scope of works.

3. Dangling Activities:

Following activities have missing links to their start or finish points.

Remainin
ID Description Type g Detail
Duration
<MBB>.<GRD FLR>. Install Water Closet Set &
MBB-A-P-1120 Normal 18 Finish has no successors
Sewer Pipes
<MBB>.<GRD FLR>. Install Complete Plumbing
MBB-A-P-1130 Normal 18 Finish has no successors
fixtures & Accessories
<MBB>.<GRD FLR>.Install Multimedia Projector
MBB-A-C-1020 Normal 10 Finish has no successors
and TV Systems
<MBB>.<GRD FLR>.Install Ceiling Fans and
MBB-A-M-1000 Normal 10 Finish has no successors
Heavy Duty Exhaust Fans
<MBB>.<GRD FLR>. Install Formwork for
MBB-A-S-1130 Normal 10 Finish has no successors
Suspended Slabs and Beams
MBB-A-A-1250 <MBB>.<GRD FLR>. Install Skirting Normal 8 Finish has no successors
<MBB>.<GRD FLR>.Install Multimedia Projector
MBB-A-C-1050 Normal 5 Finish has no successors
and TV Systems
<GHH>.<FND>. Place Formwork for Slab
GH-G-F-1100 Normal 1 Finish has no successors
Flooring
<TWMB>.<FND>. Curing fresh Concrete of
TWMB-C-F-1220 Normal 7 Finish has no successors
Foundations
<TWMB>.<FND>. Curing fresh Concrete of
TWMB-C-F-1230 Normal 7 Finish has no successors
Lower Tie Beams
<TWMB>.<FND>. Curing fresh Concrete of Floor
TWMB-C-F-1280 Normal 7 Finish has no successors
Slab
<TWMB>.<GRD FLR>. Curing fresh Concrete of
TWMB-C-S-1090 Normal 7 Finish has no successors
Columns
<MB>.<FND>. Curing Fresh Concrete of Lower
MB-F-F-1210 Normal 7 Finish has no successors
tie Beams
<MB>.<GRD FLR>. Curing fresh Concete of
MB-F-S-1120 Normal 7 Finish has no successors
Columns
CB-E-F-1210 <CB>.<FND>. Curing fresh Concrete of Footing Normal 7 Finish has no successors
<CB>.<FND>. Curing fresh Concrete of Tie
CB-E-F-1220 Normal 7 Finish has no successors
Beams
<CB>.<FND>. Curing fresh Concrete of Tile
CB-E-F-1270 Normal 7 Finish has no successors
Beam
<CB>.<FND>. Curing fresh Concrete of Floor
CB-E-F-1290 Normal 7 Finish has no successors
Slab
<CB>.<GRD FLR>. Curing fresh Concrete of
CB-E-S-1110 Normal 7 Finish has no successors
Columns

4. Out of sequence updates ("broken logic")

 
From Task To Task
ID Description Type ID Description Type Link Details
MILS- <MILSTON> DBA and Car Normal MILS- <MILSTON> Start FS Task MILS-1210 has
1020 Insurance Submit and 1210 Payment milestone already started
Approval Terms

5. Incorrect Activity Relationships:

Several activities have incorrect relationships. Some examples are:

Activity Predecessor
CB-E-S-1010 <CB>.<GRD FLR>. Install Formwork for CB-E-S-1070 <CB>.<GRD FLR>. Fix Rebars for Suspended Slabs and
Suspended Slabs and Beams Beams

Page 11 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

Re-check entire schedule and correct activity relationship errors similar to above.

9. Incorrect Calendar Assignments:

Several activities have incorrect calendar assignments. Refer to Sections B.5 and C.6 above.

6. Mandatory Lags:

Removal of formworks after concreting works for beams and slab should be started only after 21 to 28
days as per paragraph 4.3D under section 3 201 of technical specifications. The removal of formworks
is scheduled to start immediately after curing works not maintaining required gaps between concreting
works and formwork removal. Ensure there is correct relationship and lags between concrete and
formwork removal activities.

Activity Start Finish Remarks


MB-F-S-1090 <MB>.<GRD FLR>. Pour Concrete for Suspended
03/04/2020 03/04/2020
Slabs and Beams
MB-F-S-1130 <MB>.<GRD FLR>. Curing fresh Concrete of Slab 05/04/2020 14/04/2020
MB-F-S-1140 <MB>.<GRD FLR>. Fromwork Removal from Slab 19/04/2020 21/04/2020
TWMB-C-S-1080 <TWMB>.<GRD FLR>. Pour Concrete for
12/05/2020 12/05/2020
Suspended Slabs and Beams
TWMB-C-S-1100 <TWMB>.<GRD FLR>. Curing fresh Concrete of
15/05/2020 25/05/2020
Slab
TWMB-C-S-1130 <TWMB>.<GRD FLR>. Removal of Formwork
26/05/2020 28/05/2020
from Slab
CB-E-S-1080 <CB>.<GRD FLR>. Pour Concrete for Suspended
17/05/2020 17/05/2020
Slabs and Beams
CB-E-S-1120 <CB>.<GRD FLR>. Curing fresh Concrete of Slab 18/05/2020 27/05/2020
CB-E-S-1130 <CB>.<GRD FLR>. Formwork Removal from Slab 01/06/2020 02/06/2020
MBB-A-S-1090 <MBB>.<GRD FLR>. Pour Concrete for Suspended
03/07/2020 03/07/2020
Slabs and Beams
MBB-A-S-1230 <MBB>.<GRD FLR>. Curing fresh Concrete of
05/07/2020 15/07/2020
Suspended Slab
MBB-A-S-1240 <MBB>.<GRD FLR>. Remove formwork from
16/07/2020 19/07/2020
Suspended Slab
MBB-A-S-1150 <MBB>.<GRD FLR>. Pour Concrete for Suspended
28/08/2020 28/08/2020
Slabs and Beams
MBB-A-S-1280 <MBB>.<GRD FLR>. Curing fresh Concrete of Slab
30/08/2020 09/09/2020
& Beams

E. Mahadevsthan Health Post (MSHP):

1. Summary:

Constraints 0
Open-ended tasks (Does not include ignored links) 14
Out of sequence updates ("broken logic") 1
Lags longer than 0 units 67
Negative lags ("leads") 0
Positive lags on Finish-to-Start links 13
Start-to-Finish links 0
Lags between tasks with different calendars 10
Links to / from summary tasks 0
Duration uncertainty distribution shape 2 0
Total number of items found 105

2. Scope of works:

Page 12 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

Full scope isn’t covered by schedule. Following activities are in project’s scope but not included in the
schedule:

 Brick soling and PCC works below lower tie beams (MBB-A-F).
 Cement sand skirting and pointing works (Refer to drawing sheet A000b).
 Anti-termite works before backfilling and apron, floor slab.

Following activities aren’t required for Mahadevsthan HP.

 PCS-1090 <PRECON> Prep. & Submit Demolition Plan.


 PCA-1090 <PRECON> Review & Approve Demolition Plan.

Review the schedule again to ensure that only activities required by project’s scope are covered. Detail
all activities within the scope of works.

3. Budgeted Total Cost:

Budgeted total cost is incorrect. Please comply with the total cost for facility as per Contract clause B.3
Task Order Price.

Budgeted Total Cost as per Contract Budgeted Total Cost as per Schedule
$710,954.96 $710,653.49

4. Dangling Activities:

Following activities have missing links to their start or start or finish points.

Remaining
ID Description Type Detail
Duration
<CONSTR>. <MOB> Mobilization of Key
MOB-1210 Normal 20 Finish has no successors
Personnels (including get Permits)
<CONSTR>. <MOB> Establish and construct
MOB-1010 Normal 22 Finish has no successors
MVL. Central Office,LSA & Warehouse
<CLSOUT>.<OM>.Submit O&M Training and
OM-1000 Normal 12 Start has no predecessors
Manuals
EXT-LAND-1080 <EXTR>.<LAND>. Install Signboards Normal 4 Finish has no successors
SQ-B-F-1210 <SQ>.<FND>. Curing Foundation Concrete Normal 7 Finish has no successors
SQ-B-F-1220 <SQ>.<FND>. Curing Tie Beam Concrete Normal 7 Finish has no successors
SQ-B-F-1230 <SQ>.<FND>. Curing Neck Columns Concrete Normal 7 Finish has no successors
SQ-B-F-1280 <SQ>.<FND>. Curing Floor Slab Concrete Normal 7 Finish has no successors
SQ-B-G-S-1090 <SQ>.<GRD FLR>. Curing Columns Concrete Normal 7 Finish has no successors
VB-C-F-1210 <VB>.<FND>. Curing Foundation Concrete Normal 7 Finish has no successors
VB-C-F-1220 <VB>.<FND>. Curing Tie Beam Concrete Normal 7 Finish has no successors
WM-D-F-1220 <WM>.<FND>. Curing footing Concrete Normal 7 Finish has no successors
TL-E-S-1100 <TL>.<GRD FLR>. Curing Columns Conrete Normal 7 Finish has no successors

5. Out of sequence updates ("broken logic"):

 
From Task To Task
ID Description Type ID Description Type Link Details
MILS- <MILSTON> DBA and Car Normal MILS- <MILSTON> Start FS Task MILS-1210
1020 Insurance Submit and 1210 Payment Terms milestone has already started
Approval

6. Incorrect Activity Relationships:

Several activities have incorrect relationships. Some examples are:

Page 13 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

Activity Predecessor
MBB-A-S-1010 <MBB>.<GRD FLR>. Install Formwork for MBB-A-S-1080 <MBB>.<GRD FLR>. Fix Rebars for Suspended
Suspended Slabs and Beams Slabs and Beams
SQ-B-G-S-1010 <SQ>.<GRD FLR>. Install Formwork for SQ-B-G-S-1070 <SQ>.<GRD FLR>. Fix Rebars for Suspended
Suspended Slabs and Beams Slabs and Beams
VB-C-S-1010 <VB>.<GRD FLR>. Install Formwork for Suspended VB-C-S-1060 <VB>.<GRD FLR>. Fix Rebars for Suspended Slabs
Slabs and Beams and Beams

Re-check entire schedule and correct activity relationship errors similar to above.

10. Incorrect Calendar Assignments:

Several activities have incorrect calendar assignments. Refer to Sections B.5 and C.6 above.

7. Mandatory Lags:

Removal of formworks after concreting works for beams and slab should be started only after 21 to 28
days as per paragraph 4.3D under section 3 201 of technical specifications. The removal of formworks
is scheduled to start immediately after curing works not maintaining required gaps between concreting
works and formwork removal. Ensure there is correct relationship and lags between concrete and
formwork removal activities.

Activity Start Finish Remarks


MBB-A-S-1090 <MBB>.<GRD FLR>. Pour Concrete for
23/06/2020 24/06/2020
Suspended Slabs and Beams
MBB-A-S-1110 <MBB>.<GRD FLR>. Curing Slab and Beam
25/06/2020 03/07/2020
Concrete
MBB-A-S-1140 <MBB>.<GRD FLR>. Removal of Formwork
10/07/2020 13/07/2020
From Slab 3
TL-E-S-1090 <TL>.<GRD FLR>. Pour Concrete for Suspended
18/06/2020 18/06/2020
Slabs and Beams
TL-E-S-1110 <TL>.<GRD FLR>. Curing Slab and Beam
19/06/2020 30/06/2020
Concrete
TL-E-S-1120 <TL>.<GRD FLR>. Removal of Slab Formwork 03/07/2020 05/07/2020
SQ-B-G-S-1080 <SQ>.<GRD FLR>. Pour Concrete for
05/07/2020 05/07/2020
Suspended Slabs and Beams
SQ-B-G-S-1100 <SQ>.<GRD FLR>. Curing Slab and Beam
08/07/2020 16/07/2020
Concrete
SQ-B-G-S-1110 <SQ>.<GRD FLR>. Removal of Fromwork from
19/07/2020 22/07/2020
Slab
WM-D-S-1080 <WM>.<GRD FLR>. Pour Concrete for
19/07/2020 19/07/2020
Suspended Slabs and Beams
WM-D-S-1100 <WM>..<GRD FLR>. Curing Slab and Beam
22/07/2020 02/08/2020
Concrete
WM-D-S-1140 <WM>..<GRD FLR>. Removal of Slab formwork 05/08/2020 06/08/2020
VB-C-S-1070 <VB>.<GRD FLR>. Pour Concrete for Suspended
22/07/2020 22/07/2020
Slabs and Beams
VB-C-S-1090 <VB>.<GRD FLR>. Curing Slab Concrete 24/07/2020 05/08/2020
VB-C-S-1130 <VB>.<GRD FLR>. Formwork Removal from
06/08/2020 07/08/2020
Slab

F. Bhanu Secondary School (BNSS):

1. Summary:

Constraints 0
Open-ended tasks (Does not include ignored links) 5
Out of sequence updates ("broken logic") 1
Lags longer than 0 units 60

Page 14 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

Negative lags ("leads") 0


Positive lags on Finish-to-Start links 11
Start-to-Finish links 0
Lags between tasks with different calendars 12
Links to / from summary tasks 0
Duration uncertainty distribution shape 2 0
Total number of items found 89

2. Scope of works:

Full scope isn’t covered by schedule. Following activities are in project’s scope but not included in the
schedule:

 Brick soling and PCC works below lower tie beams.


 Cement sand skirting and pointing works (Refer to drawing sheet A000b).
 Anti-termite works before backfilling and apron, floor slab.
 Carpet flooring.

Review the schedule again to ensure that only activities required by project’s scope are covered. Detail
all activities within the scope of works.

3. Dangling Activities:

Following activities have missing links to their start or start or finish points:

Remaining
ID Description Type Detail
Duration
<CONSTR>. <MOB> Mobilization of Key
MOB-1210 Normal 20 Finish has no successors
Personnels (including get Permits)
<CONSTR>. <MOB> Establish and construct
MOB-1010 Normal 20 Finish has no successors
MVL. Central Office,LSA & Warehouse
CB-B-F-1280 <CB>.<FND>. Curing floor Concrete of Floor Normal 7 Finish has no successors
CB-B-S-1110 <CB>.<GRD FLR>. Curing Floor Concrete Normal 7 Finish has no successors

4. Out of sequence updates ("broken logic")

 
From Task To Task
ID Description Type ID Description Type Link Details
MILS- <MILSTON> DBA and Car Normal MILS- <MILSTON> Start milestone FS Task MILS-1210
1020 Insurance Submit and 1210 Payment has already started
Approval Terms

5. Incorrect Activity Relationships:

Several activities have incorrect relationships. Some examples are:

Activity Predecessor
EXT-BOND-1070 <EXTR>.<BOND>.Apply Paint on Walls CB-B-F-1210 <CB>.<FND>. Curing footings Conrete

Re-check entire schedule and correct activity relationship errors similar to above.

11. Incorrect Calendar Assignments:

Several activities have incorrect calendar assignments. Refer to Sections B.5 and C.6 above.

Page 15 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

8. Mandatory Lags:

Removal of formworks after concreting works for beams and slab should be started only after 21 to 28
days as per paragraph 4.3D under section 3 201 of technical specifications. The removal of formworks
is scheduled to start immediately after curing works not maintaining required gaps between concreting
works and formwork removal. Ensure there is correct relationship and lags between concrete and
formwork removal activities.

Activity Start Finish Remarks


MBB-A-S-1090 <MBB>.<GRD FLR>. Pour Concrete for
05/07/2020 05/07/2020
Suspended Slabs and Beams
MBB-A-S-1230 <MBB>.<GRD FLR>. Curing Slab Concrete 08/07/2020 16/07/2020
MBB-A-S-1240 <MBB>.<GRD FLR>. Removal of Forkwork from
19/07/2020 29/07/2020
Slab
CB-B-S-1080 <CB>.<GRD FLR>. Pour Concrete for Suspended
26/07/2020 26/07/2020
Slabs and Beams
CB-B-S-1120 <CB>.<GRD FLR>. Curing Slab & Beam Concrete 29/07/2020 07/08/2020
CB-B-S-1130 <CB>.<GRD FLR>. Fromwork Removal from
15/08/2020 19/08/2020
Slab/Beams
MBB-A-S-1150 <MBB>.<FRS FLR>. Pour Concrete for
09/09/2020 09/09/2020
Suspended Slabs & Beams
MBB-A-S-1270 <MBB>.<FRS FLR>. Curing Slab and Beam
10/09/2020 17/09/2020
Concrete
MBB-A-S-1300 <MBB>.<FRS FLR>. Removal of Formwork from
18/09/2020 21/09/2020
Slab and Beams

G. Dirgha Pradip Secondary School (DPSS)

1. Summary:

Constraints 0
Open-ended tasks (Does not include ignored links) 8
Out of sequence updates ("broken logic") 1
Lags longer than 0 units 56
Negative lags ("leads") 0
Positive lags on Finish-to-Start links 15
Start-to-Finish links 0
Lags between tasks with different calendars 9
Links to / from summary tasks 0
Duration uncertainty distribution shape 2 0
Total number of items found 89

2. Scope of works:

Full scope isn’t covered by schedule. Following activities are in project’s scope but not included in the
schedule:

 Brick soling and PCC works below lower tie beams.


 Cement sand skirting and pointing works (Refer to drawing sheet A000b).
 Anti-termite works before backfilling and apron, floor slab.

Review the schedule again to ensure that only activities required by project’s scope are covered. Detail
all activities within the scope of works.

3. Dangling Activities:

Following activities have missing links to their start or start or finish points:

Page 16 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

Remaining
ID Description Type Detail
Duration
DEMB-1010 <CLSOUT>.<DEMB>.Final Clean-UP Normal 3 Finish has no successors
OM-1000 <CLSOUT>.<OM>.Submit O&M Normal 23 Start has no predecessors
Training and Manuals
MOB-1210 <CONSTR>. <MOB> Mobilization of Normal 20 Finish has no successors
Key Personnels (including get Permits)
EXT-LAND-1080 <EXTR>.<LAND>. Construct Side walks Normal 15 Finish has no successors
CB-B-F-1220 <CB>.<FND>. Curing fresh Concrete of Normal 7 Finish has no successors
Lower Tie beams
CB-B-F-1270 <CB>.<FND>. Curing fresh Concrete of Normal 7 Finish has no successors
Upper Tie Beams
CB-B-F-1290 <CB>.<FND>. Curing fresh Concrete of Normal 7 Finish has no successors
Floor Slab

4. Out of sequence updates ("broken logic")

 
From Task To Task
ID Description Type ID Description Type Link Details
MILS- <MILSTON> DBA and Car Normal MILS- <MILSTON> Start milestone FS Task MILS-1210
1020 Insurance Submit and 1210 Payment has already started
Approval Terms

12. Incorrect Calendar Assignments:

Several activities have incorrect calendar assignments. Refer to Sections B.5 and C.6 above.

9. Mandatory Lags:

Removal of formworks after concreting works for beams and slab should be started only after 21 to 28
days as per paragraph 4.3D under section 3 201 of technical specifications. The removal of formworks
is scheduled to start immediately after curing works not maintaining required gaps between concreting
works and formwork removal. Ensure there is correct relationship and lags between concrete and
formwork removal activities.

Activity Start Finish Remarks


MBB-A-S-1090 <MBB>.<GRD FLR>. Pour Concrete for
17/05/2020 18/05/2020
Suspended Slabs and Beams
MBB-A-S-1230 <MBB>.<GRD FLR>. Curing fresh Concrete of
19/05/2020 28/05/2020
Suspended Slab
MBB-A-S-1280 <MBB>.<GRD FLR>. Formwork Removal from
02/06/2020 05/06/2020
Slab and Beams
MBB-A-S-1150 <MBB>.<FST FLR>. Pour Concrete for
30/07/2020 30/07/2020
Suspended Slabs and Beams
MBB-A-S-1270 <MBB>.<FST FLR>. Curing fresh Concrete of
31/07/2020 13/08/2020
Slab and Beams
MBB-A-S-1290 <MBB>.<FST FLR>. Removal of fromwork
14/08/2020 20/08/2020
from Slab and Beams
CB-B-S-1080 <CB>.<GRD FLR>. Pour Concrete for Suspended
09/08/2020 09/08/2020
Slabs and Beams
CB-B-S-1120 <CB>.<GRD FLR>. Curing Slab and Beam
13/08/2020 23/08/2020
Concrete
CB-B-S-1130 <CB>.<GRD FLR>. Remvoval of formwork from
26/08/2020 28/08/2020
Slab and Beam

H. Shree Secondary School (SSS)

1. Summary:

Page 17 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

Constraints 0
Open-ended tasks (Does not include ignored links) 7
Out of sequence updates ("broken logic") 1
Lags longer than 0 units 50
Negative lags ("leads") 0
Positive lags on Finish-to-Start links 9
Start-to-Finish links 0
Lags between tasks with different calendars 12
Links to / from summary tasks 0
Duration uncertainty distribution shape 2 0
Total number of items found 79

2. Scope of works:

Following activities are not required by project scope.

EXT-RETN-1050 <EXTR>.<RETN>.Construct Brick walls on Retaining wall


EXT-BOND-1030 <EXTR>.<BOND>.Construct RCC Foundation (repeated)

Review the schedule again to ensure that only activities required by project’s scope are covered. Detail
all activities within the scope of works.

3. Dangling Activities:

Following activities have missing links to their start or start or finish points:

ID Description Type Remaining Detail


Duration
MOB-1020 <CONSTR>. <MOB> Establish and construct Normal 25 Finish has no successors
CMC's and USAID Field Office
MBB-A-F-1015 <MBB>.<FND>. Install Bricks soling under Normal 4 Finish has no successors
Footing
MBB-A-E-1080 <MBB>.<FST FLR>.Install Conduits, trays and Normal 15 Finish has no successors
fittings
MBB-A-F-1230 <MBB>.<FND>. Curing Neck Columns and Shear Normal 7 Finish has no successors
walls Concrete
MBB-A-F-1280 <MBB>.<FND>. Curing Tie Beam Concrete Normal 7 Finish has no successors
MBB-A-S-1220 <MBB>.<GRD FLR>. Curing Columns and Shear Normal 7 Finish has no successors
wall Concrete

4. Out of sequence updates ("broken logic")

 
From Task To Task
ID Description Type ID Description Type Link Details
MILS- <MILSTON> DBA and Car Normal MILS- <MILSTON> Start milestone FS Task MILS-1210
1020 Insurance Submit and 1210 Payment has already started
Approval Terms

13. Incorrect Calendar Assignments:

Several activities have incorrect calendar assignments. Refer to Sections B.5 and C.6 above.

10. Mandatory Lags:

Removal of formworks after concreting works for beams and slab should be started only after 21 to 28
days as per paragraph 4.3D under section 3 201 of technical specifications. The removal of formworks
is scheduled to start immediately after curing works not maintaining required gaps between concreting

Page 18 of 19
Reconstruction of Schools and
Baseline Schedule Analysis Report Health Facilities in Sindhuli District
Task Order No. 72036719F00003

works and formwork removal. Ensure there is correct relationship and lags between concrete and
formwork removal activities.

Activity Start Finish Remarks


MBB-A-S-1090 <MBB>.<GRD FLR>. Pour Concrete for
23/06/2020 24/06/2020
Suspended Slabs and Beams
MBB-A-S-1230 <MBB>.<GRD FLR>. Curing Slab Concrete 25/06/2020 03/07/2020
MBB-A-S-1240 <MBB>.<GRD FLR>. Formwork removal From
09/07/2020 12/07/2020
Slab
MBB-A-S-1150 <MBB>.<FST FLR>. Pour Concrete for
30/08/2020 01/09/2020
Suspended Slabs and Beams
MBB-A-S-1260 <MBB>.<FST FLR>. Curing Slab Concrete 02/09/2020 11/09/2020
MBB-A-S-1270 <MBB>.<FST FLR>. Formwork Removal from
13/09/2020 17/09/2020
Slab
1. Note:

This Schedule Analysis Report is not the conclusive list of comments. The Contractor is required to
address all non-compliances in the schedules including those identified above.

Yamanta R. Niroula
Deputy Construction QA Manager
Nepal Reconstruction Engineering Services (NRES)

Page 19 of 19