PO Item # Item Pcs ExFactory Pcs (2% mas)

21315 PC 024 S Camisa 35,294 27-Mar 36,000


21318 PC 024 S Camisa 47,059 27-Apr 48,000
21320 PC 024 S Camisa 51,765 29-May 52,800
21321 PC 024 S Camisa 51,765 1-Jul 52,800
21323 PC 024 S Camisa 47,059 1-Aug 48,000
21324 PC 024 S Camisa 35,294 1-Sep 36,000
273,600

Dias de
Mes trabajo Feriados
Marzo 20 Sem santa
Abril 20
Mayo 21 1o Mayo
Junio 21
Julio 22
Agosto 22

Total 126

Produccion /dia= 237,600 1,886 unid/dia


126

Para el plan de camisas necesitare una linea de produccion


ya que una linea de produccion produce 1,900 pcs /dia
cs (2% mas) PO Item # Item Pcs
36,000 21316 RK3735 Pantalon 18000
84,000 21317 RK3735 Pantalon 30000
136,800 21319 RK3735 Pantalon 45000
189,600 21322 RK3735 Pantalon 48000
237,600 21325 RK3735 Pantalon 48000
273,600

Linea de produccion Porcentaje %


1900 50 950
75 1425
100 1900
Linea de produccion Porcentaje %
1250 50 625
75 938
100 1250
ExFactory Pcs (2% mas) AC
3-Apr 18360 18360
10-Apr 30600 48960
4-May 45900 94860
8-Jul 48960 143820
8-Sep 48960 192780
192780

Producción/dia 192780 1530 unidades/dia


126
Para el plan de produccion de pantalones necesitaremos dos lineas de produccion ya
que una linea de produccion produce 1250 PCS/dia
ExFactory Pcs Linea de produccion Porcentaje %
PO Item # Pcs
+ 2% AC cumplimiento Para subsanar retrazos de produccion tendemos las sig opciones 1900 50 950
21315 PC 024 S 35,294 27-Mar 36,000 36,000 26-Mar Horas extras 75 1425
21318 PC 024 S 47,059 27-Apr 48,000 84,000 24-Apr Trabajar sabados 100 1900
21320 PC 024 S 51,765 29-May 52,800 136,800 25-May Agregar otra linea de produccion
21321 PC 024 S 51,765 1-Jul 52,800 189,600 22-Jun Outsourcing --- buscar produccion en otra fabrica

PC 024 S
21323 47,059 1-Aug 48,000 237,600 21-Jul La velocidad de una linea de produccion esta dada por la velocidad de la operacion mas lenta
21324 PC 024 S 35,294 1-Sep 36,000 273,600 17-Aug
1ra. 950/525 min 120 min producira 217
2da. 1425/525 min 120 min producira 326
3ra. 1900/525 min 120 min producira 434
268,235 273,600 Sabado 5 hrs 300 min pruducira 1086
PRODUCCION REAL
PRODUCCION PRODUCCION PRODUCCION PRODUCCION
DIA FECHA L1 L2 EXTRA AC L1 L2 EXTRA AC DIFF

Tue 2-Mar 950 217 1,167 4,000 1000 5,000 3,833 2-Mar
Wed 3-Mar 950 217 2,334 4,000 1000 10,000 7,666 3-Mar
Thu 4-Mar 950 217 3,501 10,000 6,499 4-Mar
Fri 5-Mar 950 217 4,668 10,000 5,332 5-Mar
Sat 6-Mar 475 5,143 10,000 4,857 6-Mar
Sun 7-Mar 5,143 10,000 4,857 7-Mar
Mon 8-Mar 950 326 6,419 10,000 3,581 8-Mar
Tue 9-Mar 1,425 326 8,170 10,000 1,830 9-Mar
Wed 10-Mar 1,425 326 9,921 10,000 79 10-Mar
Thu 11-Mar 1,425 326 11,672 10,000 -1,672 11-Mar
Fri 12-Mar 1,425 326 13,423 10,000 -3,423 12-Mar
Sat 13-Mar 713 14,136 10,000 -4,136 13-Mar
Sun 14-Mar 14,136 10,000 -4,136 14-Mar
Mon 15-Mar 1,425 434 15,995 10,000 -5,995 15-Mar
Tue 16-Mar 1,900 434 18,329 10,000 -8,329 16-Mar FINISH PO 1
Wed 17-Mar 1,900 434 20,663 10,000 -10,663 17-Mar 53210
Thu 18-Mar 1,900 434 22,997 10,000 -12,997 18-Mar
Fri 19-Mar 1,900 434 25,331 10,000 -15,331 19-Mar
Sat 20-Mar 1,086 26,417 10,000 -16,417 20-Mar
Sun 21-Mar 26,417 10,000 -16,417 21-Mar
Mon 22-Mar 1,900 434 28,751 10,000 -18,751 22-Mar
Tue 23-Mar 1,900 434 31,085 10,000 -21,085 23-Mar FINISH PO 2
Wed 24-Mar 1,900 434 33,419 10,000 -23,419 24-Mar 53211
Thu 25-Mar 1,900 434 35,753 10,000 -25,753 25-Mar
Fri 26-Mar 1,900 434 38,087 cumplimiento 1ra entrega 10,000 -28,087 26-Mar
Sat 27-Mar 1,086 39,173 10,000 -29,173 27-Mar
Sun 28-Mar 39,173 10,000 -29,173 28-Mar
Mon 29-Mar 1,900 434 41,507 10,000 -31,507 29-Mar
Tue 30-Mar 1,900 434 43,841 10,000 -33,841 30-Mar FINISH PO 3
Wed 31-Mar 1,900 434 46,175 10,000 -36,175 31-Mar 53212
Thu 1-Apr 1,900 434 48,509 10,000 -38,509 1-Apr
Fri 2-Apr 48,509 10,000 -38,509 2-Apr
Sat 3-Apr 48,509 10,000 -38,509 3-Apr
Sun 4-Apr 48,509 10,000 -38,509 4-Apr
Mon 5-Apr 48,509 10,000 -38,509 5-Apr
Tue 6-Apr 1,900 434 50,843 10,000 -40,843 6-Apr
Wed 7-Apr 1,900 434 53,177 10,000 -43,177 7-Apr
Thu 8-Apr 1,900 434 55,511 10,000 -45,511 8-Apr FINISH PO 4
Fri 9-Apr 1,900 434 57,845 10,000 -47,845 9-Apr 53214
Sat 10-Apr 1,086 58,931 10,000 -48,931 10-Apr
Sun 11-Apr 58,931 10,000 -48,931 11-Apr
Mon 12-Apr 1,900 434 61,265 10,000 -51,265 12-Apr
Tue 13-Apr 1,900 434 63,599 10,000 -53,599 13-Apr FINISH PO 5
Wed 14-Apr 1,900 434 65,933 10,000 -55,933 14-Apr 53215
Thu 15-Apr 1,900 434 68,267 10,000 -58,267 15-Apr
Fri 16-Apr 1,900 434 70,601 10,000 -60,601 16-Apr
Sat 17-Apr 1,086 71,687 10,000 -61,687 17-Apr
Sun 18-Apr 71,687 10,000 -61,687 18-Apr
Mon 19-Apr 1,900 434 74,021 10,000 -64,021 19-Apr
Tue 20-Apr 1,900 434 76,355 10,000 -66,355 20-Apr FINISH PO 6
Wed 21-Apr 1,900 434 78,689 10,000 -68,689 21-Apr 53216
Thu 22-Apr 1,900 434 81,023 10,000 -71,023 22-Apr
Fri 23-Apr 1,900 434 83,357 10,000 -73,357 23-Apr

Sat 24-Apr 1,086 84,443 cumplimiento 2da entrega 10,000 -74,443 24-Apr
Sun 25-Apr 84,443 10,000 -74,443 25-Apr
Mon 26-Apr 1,900 434 86,777 10,000 -76,777 26-Apr
Tue 27-Apr 1,900 434 89,111 10,000 -79,111 27-Apr
Wed 28-Apr 1,900 434 91,445 10,000 -81,445 28-Apr FINISH PO 7
Thu 29-Apr 1,900 434 93,779 10,000 -83,779 29-Apr 53217
Fri 30-Apr 1,900 434 96,113 10,000 -86,113 30-Apr
Sat 1-May 96,113 10,000 -86,113 1-May
Sun 2-May 96,113 10,000 -86,113 2-May
Mon 3-May 1,900 434 98,447 10,000 -88,447 3-May
Tue 4-May 1,900 434 100,781 10,000 -90,781 4-May FINISH PO 8
Wed 5-May 1,900 434 103,115 10,000 -93,115 5-May 53218
Thu 6-May 1,900 434 105,449 10,000 -95,449 6-May
Fri 7-May 1,900 434 107,783 10,000 -97,783 7-May
Sat 8-May 1,086 108,869 10,000 -98,869 8-May
Sun 9-May 108,869 10,000 -98,869 9-May
Mon 10-May 1,900 434 111,203 10,000 -101,203 10-May
Tue 11-May 1,900 434 113,537 10,000 -103,537 11-May FINISH PO 8
Wed 12-May 1,900 434 115,871 10,000 -105,871 12-May 53218
Thu 13-May 1,900 434 118,205 10,000 -108,205 13-May
Fri 14-May 1,900 434 120,539 10,000 -110,539 14-May
Sat 15-May 1,086 121,625 10,000 -111,625 15-May
Sun 16-May 121,625 10,000 -111,625 16-May
Mon 17-May 1,900 434 123,959 10,000 -113,959 17-May
Tue 18-May 1,900 434 126,293 10,000 -116,293 18-May FINISH PO 8
Wed 19-May 1,900 434 128,627 10,000 -118,627 19-May 53218
Thu 20-May 1,900 434 130,961 10,000 -120,961 20-May
Fri 21-May 1,900 434 133,295 10,000 -123,295 21-May
Sat 22-May 1,086 134,381 10,000 -124,381 22-May
Sun 23-May 134,381 10,000 -124,381 23-May
Mon 24-May 1,900 434 136,715 10,000 -126,715 24-May
Tue 25-May 1,900 434 139,049 cumplimiento 3ra entrega 10,000 -129,049 25-May FINISH PO 8
Wed 26-May 1,900 434 141,383 10,000 -131,383 26-May 53218
Thu 27-May 1,900 434 143,717 10,000 -133,717 27-May
Fri 28-May 1,900 434 146,051 10,000 -136,051 28-May
Sat 29-May 1,086 147,137 10,000 -137,137 29-May
Sun 30-May 147,137 10,000 -137,137 30-May
Mon 31-May 1,900 434 149,471 10,000 -139,471 31-May
Tue 1-Jun 1,900 434 151,805 10,000 -141,805 1-Jun FINISH PO 8
Wed 2-Jun 1,900 434 154,139 10,000 -144,139 2-Jun 53218
Thu 3-Jun 1,900 434 156,473 10,000 -146,473 3-Jun
Fri 4-Jun 1,900 434 158,807 10,000 -148,807 4-Jun
Sat 5-Jun 1,086 159,893 10,000 -149,893 5-Jun
Sun 6-Jun 159,893 10,000 -149,893 6-Jun
Mon 7-Jun 1,900 434 162,227 10,000 -152,227 7-Jun
Tue 8-Jun 1,900 434 164,561 10,000 -154,561 8-Jun FINISH PO 8
Wed 9-Jun 1,900 434 166,895 10,000 -156,895 9-Jun 53218
Thu 10-Jun 1,900 434 169,229 10,000 -159,229 10-Jun
Fri 11-Jun 1,900 434 171,563 10,000 -161,563 11-Jun
Sat 12-Jun 1,086 172,649 10,000 -162,649 12-Jun
Sun 13-Jun 172,649 10,000 -162,649 13-Jun
Mon 14-Jun 1,900 434 174,983 10,000 -164,983 14-Jun
Tue 15-Jun 1,900 434 177,317 10,000 -167,317 15-Jun FINISH PO 8
Wed 16-Jun 1,900 434 179,651 10,000 -169,651 16-Jun 53218
Thu 17-Jun 1,900 434 181,985 10,000 -171,985 17-Jun
Fri 18-Jun 1,900 434 184,319 10,000 -174,319 18-Jun
Sat 19-Jun 1,086 185,405 10,000 -175,405 19-Jun
Sun 20-Jun 185,405 10,000 -175,405 20-Jun
Mon 21-Jun 1,900 434 187,739 10,000 -177,739 21-Jun
Tue 22-Jun 1,900 434 190,073 cumplimiento 4ra entrega 10,000 -180,073 22-Jun FINISH PO 8
Wed 23-Jun 1,900 434 192,407 10,000 -182,407 23-Jun 53218
Thu 24-Jun 1,900 434 194,741 10,000 -184,741 24-Jun
Fri 25-Jun 1,900 434 197,075 10,000 -187,075 25-Jun
Sat 26-Jun 1,086 198,161 10,000 -188,161 26-Jun
Sun 27-Jun 198,161 10,000 -188,161 27-Jun
Mon 28-Jun 1,900 434 200,495 10,000 -190,495 28-Jun
Tue 29-Jun 1,900 434 202,829 10,000 -192,829 29-Jun FINISH PO 8
Wed 30-Jun 1,900 434 205,163 10,000 -195,163 30-Jun 53218
Thu 1-Jul 1,900 434 207,497 10,000 -197,497 1-Jul
Fri 2-Jul 1,900 434 209,831 10,000 -199,831 2-Jul
Sat 3-Jul 1,086 210,917 10,000 -200,917 3-Jul
Sun 4-Jul 210,917 10,000 -200,917 4-Jul
Mon 5-Jul 1,900 434 213,251 10,000 -203,251 5-Jul
Tue 6-Jul 1,900 434 215,585 10,000 -205,585 6-Jul FINISH PO 8
Wed 7-Jul 1,900 434 217,919 10,000 -207,919 7-Jul 53218
Thu 8-Jul 1,900 434 220,253 10,000 -210,253 8-Jul
Fri 9-Jul 1,900 434 222,587 10,000 -212,587 9-Jul
Sat 10-Jul 1,086 223,673 10,000 -213,673 10-Jul
Sun 11-Jul 223,673 10,000 -213,673 11-Jul
Mon 12-Jul 1,900 225,573 10,000 -215,573 12-Jul
Tue 13-Jul 1,900 227,473 10,000 -217,473 13-Jul FINISH PO 8
Wed 14-Jul 1,900 229,373 10,000 -219,373 14-Jul 53218
Thu 15-Jul 1,900 231,273 10,000 -221,273 15-Jul
Fri 16-Jul 1,900 233,173 10,000 -223,173 16-Jul
Sat 17-Jul 233,173 10,000 -223,173 17-Jul
Sun 18-Jul 233,173 10,000 -223,173 18-Jul
Mon 19-Jul 1,900 235,073 10,000 -225,073 19-Jul
Tue 20-Jul 1,900 236,973 10,000 -226,973 20-Jul FINISH PO 8
Wed 21-Jul 1,900 238,873 cumplimiento 5to 10,000 -228,873 21-Jul 53218
Thu 22-Jul 1,900 240,773 10,000 -230,773 22-Jul
Fri 23-Jul 1,900 242,673 10,000 -232,673 23-Jul
Sat 24-Jul 242,673 10,000 -232,673 24-Jul
Sun 25-Jul 242,673 10,000 -232,673 25-Jul
Mon 26-Jul 1,900 244,573 10,000 -234,573 26-Jul
Tue 27-Jul 1,900 246,473 10,000 -236,473 27-Jul FINISH PO 8
Wed 28-Jul 1,900 248,373 10,000 -238,373 28-Jul 53218
Thu 29-Jul 1,900 250,273 10,000 -240,273 29-Jul
Fri 30-Jul 1,900 252,173 10,000 -242,173 30-Jul
Sat 31-Jul 252,173 10,000 -242,173 31-Jul
Sun 1-Aug 252,173 10,000 -242,173 1-Aug
Mon 2-Aug 1,900 254,073 10,000 -244,073 2-Aug
Tue 3-Aug 1,900 255,973 10,000 -245,973 3-Aug FINISH PO 8
Wed 4-Aug 1,900 257,873 10,000 -247,873 4-Aug 53218
Thu 5-Aug 1,900 259,773 10,000 -249,773 5-Aug
Fri 6-Aug 1,900 261,673 10,000 -251,673 6-Aug
Sat 7-Aug 261,673 10,000 -251,673 7-Aug
Sun 8-Aug 261,673 10,000 -251,673 8-Aug
Mon 9-Aug 1,900 263,573 10,000 -253,573 9-Aug
Tue 10-Aug 1,900 265,473 10,000 -255,473 10-Aug FINISH PO 8
Wed 11-Aug 1,900 267,373 10,000 -257,373 11-Aug 53218
Thu 12-Aug 1,900 269,273 10,000 -259,273 12-Aug
Fri 13-Aug 1,900 271,173 10,000 -261,173 13-Aug
Sat 14-Aug 271,173 10,000 -261,173 14-Aug
Sun 15-Aug 271,173 10,000 -261,173 15-Aug
Mon 16-Aug 1,900 273,073 10,000 -263,073 16-Aug
Tue 17-Aug 1,900 274,973 6to. Cumplimiento 10,000 -264,973 17-Aug FINISH PO 8
Wed 18-Aug 1,900 276,873 10,000 -266,873 18-Aug 53218
Thu 19-Aug 1,900 278,773 10,000 -268,773 19-Aug
Fri 20-Aug 1,900 280,673 10,000 -270,673 20-Aug
Sat 21-Aug 280,673 10,000 -270,673 21-Aug
Sun 22-Aug 280,673 10,000 -270,673 22-Aug
Mon 23-Aug 1,900 434 283,007 10,000 -273,007 23-Aug
Tue 24-Aug 1,900 434 285,341 10,000 -275,341 24-Aug FINISH PO 8
Wed 25-Aug 1,900 434 287,675 10,000 -277,675 25-Aug 53218
Thu 26-Aug 1,900 434 290,009 10,000 -280,009 26-Aug
Fri 27-Aug 1,900 434 292,343 10,000 -282,343 27-Aug
Sat 28-Aug 1,086 293,429 10,000 -283,429 28-Aug
Sun 29-Aug 293,429 10,000 -283,429 29-Aug
Mon 30-Aug 1,900 434 295,763 10,000 -285,763 30-Aug
Tue 31-Aug 1,900 434 298,097 10,000 -288,097 31-Aug FINISH PO 8
Wed 1-Sep 1,900 434 300,431 10,000 -290,431 1-Sep 53218
Thu 2-Sep 1,900 434 302,765 10,000 -292,765 2-Sep
Fri 3-Sep 1,900 434 305,099 10,000 -295,099 3-Sep
ExFactory Pcs Linea de pro Porcentaje %
PO Item # Pcs
+ 2% AC cumplimiento Para subsanar retrazos de produccion tendemos las sig opciones 1250 50 625
21316 RK3735 18000 3-Apr 18,360 18,360 23-Mar Horas extras 75 938
21317 RK3735 30000 10-Apr 30,600 48,960 9-Apr Trabajar sabados 100 1250
21319 RK3735 45000 4-May 45,900 94,860 30-Apr Agregar otra linea de produccion
21322 RK3735 48000 8-Jul 48,960 143,820 23-Jun Outsourcing --- buscar produccion en otra fabrica
La velocidad de una linea de produccion esta dada por la velocidad de la operacion mas
21325 RK3735 48000 8-Sep 48,960 192,780 17-Aug lenta
192,780 hrs extras
1ra. 625/525 min 120 min producira 143
2da. 938/525 min 120 min producira 214
3ra. 1250/525 min 120 min producira 286
189,000 192,780 Sabado 5 hrs 300 min pruducira 714
PRODUCCION REAL
PRODUCCION PRODUCCION PRODUCCION PRODUCCION
DIA FECHA L1 L2 EXTRA AC L1 L2 EXTRA AC DIFF

Tue 2-Mar 625 625 4,000 1000 5,000 4,375 2-Mar


Wed 3-Mar 625 1,250 4,000 1000 10,000 8,750 3-Mar
Thu 4-Mar 625 1,875 10,000 8,125 4-Mar
Fri 5-Mar 625 2,500 10,000 7,500 5-Mar
Sat 6-Mar 2,500 10,000 7,500 6-Mar
Sun 7-Mar 2,500 10,000 7,500 7-Mar
Mon 8-Mar 625 3,125 10,000 6,875 8-Mar
Tue 9-Mar 938 4,063 10,000 5,937 9-Mar
Wed 10-Mar 938 5,001 10,000 4,999 10-Mar
Thu 11-Mar 938 5,939 10,000 4,061 11-Mar
Fri 12-Mar 938 6,877 10,000 3,123 12-Mar
Sat 13-Mar 6,877 10,000 3,123 13-Mar
Sun 14-Mar 6,877 10,000 3,123 14-Mar
Mon 15-Mar 938 7,815 10,000 2,185 15-Mar
Tue 16-Mar 1,250 9,065 10,000 935 16-Mar FINISH PO 1
Wed 17-Mar 1,250 10,315 10,000 -315 17-Mar 53210
Thu 18-Mar 1,250 11,565 10,000 -1,565 18-Mar
Fri 19-Mar 1,250 12,815 10,000 -2,815 19-Mar
Sat 20-Mar 12,815 10,000 -2,815 20-Mar
Sun 21-Mar 12,815 10,000 -2,815 21-Mar
Mon 22-Mar 1,250 1,250 286 15,601 10,000 -5,601 22-Mar
Tue 23-Mar 1,250 1,250 286 18,387 1er. Cumplimiento 10,000 -8,387 23-Mar FINISH PO 2
Wed 24-Mar 1,250 1,250 286 21,173 10,000 -11,173 24-Mar 53211
Thu 25-Mar 1,250 1,250 286 23,959 10,000 -13,959 25-Mar
Fri 26-Mar 1,250 1,250 286 26,745 10,000 -16,745 26-Mar
Sat 27-Mar 714 714 28,173 10,000 -18,173 27-Mar
Sun 28-Mar 28,173 10,000 -18,173 28-Mar
Mon 29-Mar 1,250 1,250 286 30,959 10,000 -20,959 29-Mar
Tue 30-Mar 1,250 1,250 286 33,745 10,000 -23,745 30-Mar FINISH PO 3
Wed 31-Mar 1,250 1,250 286 36,531 10,000 -26,531 31-Mar 53212
Thu 1-Apr 1,250 1,250 286 39,317 10,000 -29,317 1-Apr
Fri 2-Apr 39,317 10,000 -29,317 2-Apr
Sat 3-Apr 39,317 10,000 -29,317 3-Apr
Sun 4-Apr 39,317 10,000 -29,317 4-Apr
Mon 5-Apr 39,317 10,000 -29,317 5-Apr
Tue 6-Apr 1,250 1,250 286 42,103 10,000 -32,103 6-Apr
Wed 7-Apr 1,250 1,250 286 44,889 10,000 -34,889 7-Apr
Thu 8-Apr 1,250 1,250 286 47,675 10,000 -37,675 8-Apr FINISH PO 4
Fri 9-Apr 1,250 1,250 286 50,461 2do. Cumplimiento 10,000 -40,461 9-Apr 53214
Sat 10-Apr 714 714 51,889 10,000 -41,889 10-Apr
Sun 11-Apr 51,889 10,000 -41,889 11-Apr
Mon 12-Apr 1,250 1,250 286 54,675 10,000 -44,675 12-Apr
Tue 13-Apr 1,250 1,250 286 57,461 10,000 -47,461 13-Apr FINISH PO 5
Wed 14-Apr 1,250 1,250 286 60,247 10,000 -50,247 14-Apr 53215
Thu 15-Apr 1,250 1,250 286 63,033 10,000 -53,033 15-Apr
Fri 16-Apr 1,250 1,250 286 65,819 10,000 -55,819 16-Apr
Sat 17-Apr 714 714 67,247 10,000 -57,247 17-Apr
Sun 18-Apr 67,247 10,000 -57,247 18-Apr
Mon 19-Apr 1,250 1,250 286 70,033 10,000 -60,033 19-Apr
Tue 20-Apr 1,250 1,250 286 72,819 10,000 -62,819 20-Apr FINISH PO 6
Wed 21-Apr 1,250 1,250 286 75,605 10,000 -65,605 21-Apr 53216
Thu 22-Apr 1,250 1,250 286 78,391 10,000 -68,391 22-Apr
Fri 23-Apr 1,250 1,250 286 81,177 10,000 -71,177 23-Apr

Sat 24-Apr 714 714 82,605 10,000 -72,605 24-Apr


Sun 25-Apr 82,605 10,000 -72,605 25-Apr
Mon 26-Apr 1,250 1,250 286 85,391 10,000 -75,391 26-Apr
Tue 27-Apr 1,250 1,250 286 88,177 10,000 -78,177 27-Apr
Wed 28-Apr 1,250 1,250 286 90,963 10,000 -80,963 28-Apr FINISH PO 7
Thu 29-Apr 1,250 1,250 286 93,749 10,000 -83,749 29-Apr 53217
Fri 30-Apr 1,250 1,250 286 96,535 3er. Cumplimiento 10,000 -86,535 30-Apr
Sat 1-May 96,535 10,000 -86,535 1-May
Sun 2-May 96,535 10,000 -86,535 2-May
Mon 3-May 1,250 97,785 10,000 -87,785 3-May
Tue 4-May 1,250 99,035 10,000 -89,035 4-May FINISH PO 8
Wed 5-May 1,250 100,285 10,000 -90,285 5-May 53218
Thu 6-May 1,250 101,535 10,000 -91,535 6-May
Fri 7-May 1,250 102,785 10,000 -92,785 7-May
Sat 8-May 102,785 10,000 -92,785 8-May
Sun 9-May 102,785 10,000 -92,785 9-May
Mon 10-May 1,250 104,035 10,000 -94,035 10-May
Tue 11-May 1,250 105,285 10,000 -95,285 11-May FINISH PO 8
Wed 12-May 1,250 106,535 10,000 -96,535 12-May 53218
Thu 13-May 1,250 107,785 10,000 -97,785 13-May
Fri 14-May 1,250 109,035 10,000 -99,035 14-May
Sat 15-May 109,035 10,000 -99,035 15-May
Sun 16-May 109,035 10,000 -99,035 16-May
Mon 17-May 1,250 110,285 10,000 -100,285 17-May
Tue 18-May 1,250 111,535 10,000 -101,535 18-May FINISH PO 8
Wed 19-May 1,250 112,785 10,000 -102,785 19-May 53218
Thu 20-May 1,250 114,035 10,000 -104,035 20-May
Fri 21-May 1,250 115,285 10,000 -105,285 21-May
Sat 22-May 115,285 10,000 -105,285 22-May
Sun 23-May 115,285 10,000 -105,285 23-May
Mon 24-May 1,250 116,535 10,000 -106,535 24-May
Tue 25-May 1,250 117,785 10,000 -107,785 25-May FINISH PO 8
Wed 26-May 1,250 119,035 10,000 -109,035 26-May 53218
Thu 27-May 1,250 120,285 10,000 -110,285 27-May
Fri 28-May 1,250 121,535 10,000 -111,535 28-May
Sat 29-May 121,535 10,000 -111,535 29-May
Sun 30-May 121,535 10,000 -111,535 30-May
Mon 31-May 1,250 122,785 10,000 -112,785 31-May
Tue 1-Jun 1,250 124,035 10,000 -114,035 1-Jun FINISH PO 8
Wed 2-Jun 1,250 125,285 10,000 -115,285 2-Jun 53218
Thu 3-Jun 1,250 126,535 10,000 -116,535 3-Jun
Fri 4-Jun 1,250 127,785 10,000 -117,785 4-Jun
Sat 5-Jun 127,785 10,000 -117,785 5-Jun
Sun 6-Jun 127,785 10,000 -117,785 6-Jun
Mon 7-Jun 1,250 129,035 10,000 -119,035 7-Jun
Tue 8-Jun 1,250 130,285 10,000 -120,285 8-Jun FINISH PO 8
Wed 9-Jun 1,250 131,535 10,000 -121,535 9-Jun 53218
Thu 10-Jun 1,250 132,785 10,000 -122,785 10-Jun
Fri 11-Jun 1,250 134,035 10,000 -124,035 11-Jun
Sat 12-Jun 134,035 10,000 -124,035 12-Jun
Sun 13-Jun 134,035 10,000 -124,035 13-Jun
Mon 14-Jun 1,250 135,285 10,000 -125,285 14-Jun
Tue 15-Jun 1,250 136,535 10,000 -126,535 15-Jun FINISH PO 8
Wed 16-Jun 1,250 137,785 10,000 -127,785 16-Jun 53218
Thu 17-Jun 1,250 139,035 10,000 -129,035 17-Jun
Fri 18-Jun 1,250 140,285 10,000 -130,285 18-Jun
Sat 19-Jun 140,285 10,000 -130,285 19-Jun
Sun 20-Jun 140,285 10,000 -130,285 20-Jun
Mon 21-Jun 1,250 141,535 10,000 -131,535 21-Jun
Tue 22-Jun 1,250 142,785 10,000 -132,785 22-Jun FINISH PO 8
Wed 23-Jun 1,250 144,035 4to. Cumplimiento 10,000 -134,035 23-Jun 53218
Thu 24-Jun 1,250 145,285 10,000 -135,285 24-Jun
Fri 25-Jun 1,250 146,535 10,000 -136,535 25-Jun
Sat 26-Jun 146,535 10,000 -136,535 26-Jun
Sun 27-Jun 146,535 10,000 -136,535 27-Jun
Mon 28-Jun 1,250 147,785 10,000 -137,785 28-Jun
Tue 29-Jun 1,250 149,035 10,000 -139,035 29-Jun FINISH PO 8
Wed 30-Jun 1,250 150,285 10,000 -140,285 30-Jun 53218
Thu 1-Jul 1,250 151,535 10,000 -141,535 1-Jul
Fri 2-Jul 1,250 152,785 10,000 -142,785 2-Jul
Sat 3-Jul 152,785 10,000 -142,785 3-Jul
Sun 4-Jul 152,785 10,000 -142,785 4-Jul
Mon 5-Jul 1,250 154,035 10,000 -144,035 5-Jul
Tue 6-Jul 1,250 155,285 10,000 -145,285 6-Jul FINISH PO 8
Wed 7-Jul 1,250 156,535 10,000 -146,535 7-Jul 53218
Thu 8-Jul 1,250 157,785 10,000 -147,785 8-Jul
Fri 9-Jul 1,250 159,035 10,000 -149,035 9-Jul
Sat 10-Jul 159,035 10,000 -149,035 10-Jul
Sun 11-Jul 159,035 10,000 -149,035 11-Jul
Mon 12-Jul 1,250 160,285 10,000 -150,285 12-Jul
Tue 13-Jul 1,250 161,535 10,000 -151,535 13-Jul FINISH PO 8
Wed 14-Jul 1,250 162,785 10,000 -152,785 14-Jul 53218
Thu 15-Jul 1,250 164,035 10,000 -154,035 15-Jul
Fri 16-Jul 1,250 165,285 10,000 -155,285 16-Jul
Sat 17-Jul 165,285 10,000 -155,285 17-Jul
Sun 18-Jul 165,285 10,000 -155,285 18-Jul
Mon 19-Jul 1,250 166,535 10,000 -156,535 19-Jul
Tue 20-Jul 1,250 167,785 10,000 -157,785 20-Jul FINISH PO 8
Wed 21-Jul 1,250 169,035 10,000 -159,035 21-Jul 53218
Thu 22-Jul 1,250 170,285 10,000 -160,285 22-Jul
Fri 23-Jul 1,250 171,535 10,000 -161,535 23-Jul
Sat 24-Jul 171,535 10,000 -161,535 24-Jul
Sun 25-Jul 171,535 10,000 -161,535 25-Jul
Mon 26-Jul 1,250 172,785 10,000 -162,785 26-Jul
Tue 27-Jul 1,250 174,035 10,000 -164,035 27-Jul FINISH PO 8
Wed 28-Jul 1,250 175,285 10,000 -165,285 28-Jul 53218
Thu 29-Jul 1,250 176,535 10,000 -166,535 29-Jul
Fri 30-Jul 1,250 177,785 10,000 -167,785 30-Jul
Sat 31-Jul 177,785 10,000 -167,785 31-Jul
Sun 1-Aug 177,785 10,000 -167,785 1-Aug
Mon 2-Aug 1,250 179,035 10,000 -169,035 2-Aug
Tue 3-Aug 1,250 180,285 10,000 -170,285 3-Aug FINISH PO 8
Wed 4-Aug 1,250 181,535 10,000 -171,535 4-Aug 53218
Thu 5-Aug 1,250 182,785 10,000 -172,785 5-Aug
Fri 6-Aug 1,250 184,035 10,000 -174,035 6-Aug
Sat 7-Aug 184,035 10,000 -174,035 7-Aug
Sun 8-Aug 184,035 10,000 -174,035 8-Aug
Mon 9-Aug 1,250 185,285 10,000 -175,285 9-Aug
Tue 10-Aug 1,250 186,535 10,000 -176,535 10-Aug FINISH PO 8
Wed 11-Aug 1,250 187,785 10,000 -177,785 11-Aug 53218
Thu 12-Aug 1,250 189,035 10,000 -179,035 12-Aug
Fri 13-Aug 1,250 190,285 10,000 -180,285 13-Aug
Sat 14-Aug 190,285 10,000 -180,285 14-Aug
Sun 15-Aug 190,285 10,000 -180,285 15-Aug
Mon 16-Aug 1,250 191,535 10,000 -181,535 16-Aug
Tue 17-Aug 1,250 192,785 5to. Cumplimiento 10,000 -182,785 17-Aug FINISH PO 8
Wed 18-Aug 192,785 10,000 -182,785 18-Aug 53218
Thu 19-Aug 192,785 10,000 -182,785 19-Aug
Fri 20-Aug 192,785 10,000 -182,785 20-Aug
Sat 21-Aug 192,785 10,000 -182,785 21-Aug
Sun 22-Aug 192,785 10,000 -182,785 22-Aug
Mon 23-Aug 192,785 10,000 -182,785 23-Aug
Tue 24-Aug 192,785 10,000 -182,785 24-Aug FINISH PO 8
Wed 25-Aug 192,785 10,000 -182,785 25-Aug 53218
Thu 26-Aug 192,785 10,000 -182,785 26-Aug
Fri 27-Aug 192,785 10,000 -182,785 27-Aug
Sat 28-Aug 192,785 10,000 -182,785 28-Aug
Sun 29-Aug 192,785 10,000 -182,785 29-Aug
Mon 30-Aug 192,785 10,000 -182,785 30-Aug
Tue 31-Aug 192,785 10,000 -182,785 31-Aug FINISH PO 8
Wed 1-Sep 192,785 10,000 -182,785 1-Sep 53218
Thu 2-Sep 192,785 10,000 -182,785 2-Sep
Fri 3-Sep 192,785 10,000 -182,785 3-Sep