Documente Academic
Documente Profesional
Documente Cultură
Farwestern Province
Ministry of Physical Infrastructure Development
Water Resources and Irrigation Development Division Office
Dadeldhura
4 Certified
a The drawings and measurements of the proposed work are based on the field verification.
The design and estimate of the proposed work is based on departmental norms and general engineering
b
principles in practice.
c The proposed estimate is prepared on the basis of approved rate and rate analysis norms.
d All numbers and arithmetical calculations carried out in this estimate are correct.
………… …………
Submitted by Checked & Forwarded by
(Sub-Engineer) (Sub Division Chief)
The submitted cost estimate, drawinggs are correct in accordance with the approved departmental norms
and follow the general engineering principles in practice, hence is recommended for approval.
………………. ………………..
6 Approved
For this work the drawings and amount of NRs…………………………... is approved.
……………………………
(Regional Director)
(FWRID)
Provincial Government
Farwestern Province
Ministry of Physical Infrastructure Development
Water Resources and Irrigation Development Division Office
Dadeldhura
4 Certified
a The drawings and measurements of the proposed work are based on the field verification.
The design and estimate of the proposed work is based on departmental norms and general engineering
b
principles in practice.
c The proposed estimate is prepared on the basis of approved rate and rate analysis norms.
d All numbers and arithmetical calculations carried out in this estimate are correct.
………… …………
Submitted by Checked & Forwarded by
(Sub-Engineer) (Sub Division Chief)
The submitted cost estimate, drawinggs are correct in accordance with the approved departmental norms
and follow the general engineering principles in practice, hence is recommended for approval.
………………. ………………..
6 Approved
For this work the drawings and amount of NRs…………………………... is approved.
……………………………
(Regional Director)
(FWRID)
Project Name:Naar Irrigation Sub-Project
Location:Narfa Bhumi RM-2 Manang
Metalled Hill 0
Earthern 60
Haulage 9.375 Kosh
2 Sand cu.m 9,093.00 1,450.00 0 /km/kg 0.00 0 0.027 /km/kg 0.0 0 0.2500 /km/kg 0.00 0.0000 /kg 0.00 0 5.500 /km/kg 0.00 9,093.00 /cu.m
3 Boulder cu.m 6,846.00 2,400.00 0 /km/kg 0.00 0 0.027 /km/kg 0.0 0 0.2500 /km/kg 0.00 0.0000 /kg 0.00 0 5.500 /km/kg 0.00 6,846.00 /cu.m
4 Gravel cu.m 10,122.00 1,600.00 0 /km/kg 0.00 0 0.027 /km/kg 0.0 0 0.2500 /km/kg 0.00 0.0000 /kg 0.00 0 5.500 /km/kg 0.00 10,122.00 /cu.m
5 Reinforcement Mt. 84,000.00 1,000.00 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.4000 /km/kg 24,000.00 0.1900 /kg 190.00 9.375 9.500 /km/kg 89,062.50 197,252.50 /Mt.
6 Binding Wire kg 120.00 1.00 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.3300 /km/kg 19.80 0.1900 /kg 0.19 9.375 9.500 /km/kg 89.06 229.05 /kg
7 Nails kg 110.00 1.00 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.3300 /km/kg 19.80 0.1900 /kg 0.19 9.375 9.500 /km/kg 89.06 219.05 /kg
10 MS Channel kg 87.00 1.00 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.3300 /km/kg 19.80 0.1900 /kg 0.19 9.375 9.500 /km/kg 89.06 196.05 /kg
11 Barbed wire kg 100.00 1.00 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.4000 /km/kg 24.00 0.1900 /kg 0.19 9.375 9.500 /km/kg 89.06 213.25 /kg
12 160mm 6kg/cm2 Rm 869.44 3.34 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.4500 /km/kg 90.28 0.1900 /kg 0.63 9.375 11.000 /km/kg 344.85 1,305.20 /kg
HDPE pipe
13 140mm 6kg/cm2 Rm 666.90 2.57 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.4500 /km/kg 69.25 0.1900 /kg 0.48 9.375 11.000 /km/kg 264.51 1,001.14 /kg
HDPE pipe
14 125mm 10kg/cm2 Rm 830.96 3.20 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 86.29 0.1900 /kg 0.60 9.375 11.000 /km/kg 329.58 1,247.43 /Rm
HDPE pipe
15 125mm 6kg/cm2 Rm 530.40 2.04 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 55.08 0.1900 /kg 0.38 9.375 11.000 /km/kg 210.37 796.23 /Rm
HDPE pipe
16 110mm 16kg/cm2 Rm 944.06 3.63 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 98.03 0.1900 /kg 0.68 9.375 11.000 /km/kg 374.44 1,417.21 /Rm
HDPE pipe
17 110mm 12.5kg/cm2 Rm 780.00 3.00 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 81.00 0.1900 /kg 0.57 9.375 11.000 /km/kg 309.37 1,170.94 /Rm
HDPE pipe
18 110mm 10kg/cm2 Rm 643.76 2.48 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 66.85 0.1900 /kg 0.47 9.375 11.000 /km/kg 255.33 966.41 /Rm
HDPE pipe
19 110mm 6kg/cm2 Rm 409.50 1.58 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 42.52 0.1900 /kg 0.29 9.375 11.000 /km/kg 162.42 614.73 /Rm
HDPE pipe
20 90mm 10kg/cm2 Rm 435.24 1.67 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 45.19 0.1900 /kg 0.31 9.375 11.000 /km/kg 172.63 653.37 /Rm
HDPE pipe
21 90mm 6kg/cm2 Rm 274.82 1.06 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 28.53 0.1900 /kg 0.20 9.375 11.000 /km/kg 109.00 412.55 /Rm
HDPE pipe
22 90 mm 4kg/cm2 Rm 317.46 1.22 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 32.96 0.1900 /kg 0.23 9.375 11.000 /km/kg 125.91 476.56 /Rm
HDPE pipe
23 75 mm 10kg/cm2 Rm 303.16 1.17 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 31.48 0.1900 /kg 0.22 9.375 11.000 /km/kg 120.24 455.10 /Rm
HDPE pipe
24 75 mm 6kg/cm2 Rm 195.26 0.75 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 20.27 0.1900 /kg 0.14 9.375 11.000 /km/kg 77.44 293.11 /Rm
HDPE pipe
25 63 mm 6kg/cm2 Rm 135.98 0.52 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 14.12 0.1900 /kg 0.09 9.375 11.000 /km/kg 53.93 204.12 /Rm
HDPE pipe
26 50mm 6kg/cm2 Rm 85.54 0.33 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 8.88 0.1900 /kg 0.06 9.375 11.000 /km/kg 33.92 128.40 /Rm
HDPE pipe
GI PIPES (Medium
Duty)
1 Rm 1,573.00 12.720 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 343.44 0.1900 /kg 2.41 9.375 11.000 /km/kg 1,311.75 3,230.60 /Rm
100 mm Dia GI Pipe
2 80 mm Dia GI Pipe Rm 1,060.00 8.890 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 240.03 0.1900 /kg 1.68 9.375 11.000 /km/kg 916.78 2,218.49 /Rm
3 65 mm Dia GI Pipe Rm 855.00 6.840 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 184.68 0.1900 /kg 1.29 9.375 11.000 /km/kg 705.37 1,746.34 /Rm
4 Rm 670.00 5.350 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 144.45 0.1900 /kg 1.01 9.375 11.000 /km/kg 551.71 1,367.17 /Rm
50 mm Dia GI Pipe
5 25 mm Dia GI Pipe Rm 328.00 2.560 0 /km/kg 0.00 0 0.082 /km/kg 0.0 60 0.450 /km/kg 69.12 0.1900 /kg 0.48 9.375 11.000 /km/kg 264.00 661.60 /Rm
1 Sand m3 Unskl 3.45 50.00 0.40+((L-10)/10)*0.12 0.88 4.33 2100.00 9093.00 3-1b & 22-1.1(a&b)
2 Boulder m3 Unskl 1.40 50.00 1.10+((L-10)/10)*0.19 1.86 3.26 2100.00 6846.00 3-4 & 22-1.3 (a&b)
3 Gravel m3 Unskl 4.00 50.00 0.30+((L-10)/10)*0.13 0.82 4.82 2100.00 10122.00 3-2b & 22-1.2(a&b)
1 Fell trees, cut up and dispose 5m away from the const. site(12-15cm) (Ref.No. 1.1) Unit/each
Cutting thin vegetation, grubing their roots and disposal 25m far from the const.site(dia.<=30cm &
2 (Ref.No. 1.3) Unit/m2
density>15nr/100m2)
Unskilled labour 0.04 No @ Rs 2100.00 84.00
Contractor's Overhead and Profit @ 15% 12.60
Rate/m2 Rs 96.60
3 Excavation of soft soils including disposal (up to 10 m lead & 1.5 m lift). (Ref.No. 2.9) Unit/m3
Unskilled labour 1.00 No @ Rs 2100.00 2100.00
Tools and plant @ 3% 63.00
Sub total 2163.00
Contractor's Overhead and Profit @ 15% 324.45
Rate/m3 Rs 2487.45
Excavation for foundation, drain, pipeline etc. in boulder mixed soils, disposal(up to 10 m lead & 1.5 m
4 (Ref.No. 2.14) Unit/m3
lift).
Unskilled labour 1.59 No @ Rs 2100.00 3339.00
Tools and plant @ 3% 100.17
Sub total 3439.17
Contractor's Overhead and Profit @ 15% 515.87
Rate/m3 Rs 3955.04
Foundation excavation under water in boulder and gravel ) with disposal up to 10 m lead 1m deep Unit/m3
5 (Ref.No. 2.24.b)
excavation and 4 m lift
Unskilled labour 1.51 No @ Rs 2100.00 3171.00
Tools and plant @3% 95.13
Sub total 3266.13
Contractor's Overhead and Profit @ 15% 489.91
Rate/m3 Rs 3756.04
Earth Work in back filling with ordinary soil in 15 cm layers and hand compcation without sprinkling
6 (Ref.No. 2.25.b) Unit/m3
water (10m lead )
Unskilled labour 0.25 No @ Rs 2100.00 525.00
Tools and plant @ 3% 15.75
Sub total 540.75
Contractor's Overhead and Profit @ 15% 81.11
Rate/m3 Rs 621.86
7 Rubble Masonry works including supply of hard stone blocks. Preparing cement mortar and (Ref.No. 6.1.b) Unit/m3
construction of wall up to 5m high (haulage distance up to 10 m). Cement mortar 1:4
Skilled labour 1.50 No @ Rs 3450.00 5175.00
Unskilled labour 5.00 No @ Rs 2100.00 10500.00
Cement 0.159 M.t @Rs 83702.50 13308.69
Sand 0.45 m3 @Rs 9093.00 4091.85
Stone 1.10 m3 @Rs 6846.00 7530.60
Sub total 40606.14
Contractor's Overhead and Profit @ 15% 6090.92
Rate/m3 Rs 46697.06
Rubble Masonry works including supply of hard stone blocks & constrution of walls up to 5.0 m high
8 (Ref.No. 6.2.a) Unit/m3
(haulage 30.0 m) Dry wall.
Skilled labour 1.00 No @ Rs 3450.00 3450.00
Unskilled labour 2.00 No @ Rs 2100.00 4200.00
Stone 1.10 m3 @Rs 6846.00 7530.60
Sub total 15180.60
Contractor's Overhead and Profit @ 15% 2277.09
Rate/m3 Rs 17457.69
Concreting (cement conc.) of foundations, vert. faces, walls including supply of materials and haulage
9 (Ref.No. 7.2.c) Unit/m3
(dist. up to 30 m). P.C.C. 1:3:6.
10 cutting,bending,placing in position as shown in the drawing & binding by G.I. wire of (Ref.No. 7.5) Unit/mt
reinforcement steel bars for R.C.C works incl. haulage distance of 30 m
Skilled labour 12.00 No @ Rs 3450.00 41400.00
Unskilled labour 12.00 No @ Rs 2100.00 25200.00
Cement 0.00 Mt. @Rs 83702.50 0.00
MS Rods 1.05 mt @Rs 197252.50 207115.12
wires 10.000 kg @Rs 229.05 2290.50
Sub total 276005.62
Contractor's Overhead and Profit @ 15% 41400.84
Rate/mt Rs 317406.46
Concreting (cement conc.) of foundations, vert. faces, walls including supply of materials and haulage
11 (Ref.No. 7.2.d) Unit/m3
(dist. up to 30 m). P.C.C. 1:2:4.
Skilled labour 1.00 No @ Rs 3450.00 3450.00
Unskilled labour 4.00 No @ Rs 2100.00 8400.00
Cement 0.32 Mt. @Rs 83702.50 26784.80
Aggregates 0.85 m3 @Rs 10122.00 8603.70
Coarse sand 0.445 m3 @Rs 9093.00 4046.38
Sub total 51284.88
Contractor's Overhead and Profit @ 15% 7692.73
Rate/m3 Rs 58977.61
Concreting (cement conc.) of super structure including supply of materials and haulage (dist. up to 30
12 m). P.C.C. 1:1.5:3. (Ref.No. 7.4.b) Unit/m3
Skilled labour 0.80 No @ Rs 3450.00 2760.00
Unskilled labour 7.00 No @ Rs 2100.00 14700.00
Cement 0.40 Mt. @Rs 83702.50 33481.00
Aggregates 0.86 m3 @Rs 10122.00 8704.92
Coarse sand 0.425 m3 @Rs 9093.00 3864.52
Sub total 63510.44
Contractor's Overhead and Profit @ 15% 9526.56
Rate/m3 Rs 73037.00
Making wooden forms including supply and selection of mat. fixing, nailing according to drawings,
14 (Ref.No. 8.2.b) Unit/10m2
placing separators, dismantling forms and hauling up to 30 m distance.
12.5mm thick cement sand plastering works including supply and prepartion of materials in 1:4
15 (Ref.No. 12.1.c) Unit/100m2
cement-sand ratio.
Skilled labour 12.00 No @ Rs 3450.00 41400.00
Unskilled labour 16.00 No @ Rs 2100.00 33600.00
Cement 0.538 M.t @Rs 83702.50 45031.94
Estimated By: Checked by: Forwarded by: Approved By:
Sand 1.46 m3 @Rs 9093.00 13275.78
Sub total 133307.72
Contractor's Overhead and Profit @ 15% 19996.15
Total Rs 153303.87
Rate/m2 Rs 1533.03
16 Flush ruled pointing works in boulder stone masonary wall (Cement sand 1:2) (Ref.No. 14.2.b) Unit/100m2
17 Filling by stones in the foundation and levelling including haulage distance upto 30m (Ref.No. 6.5) Unit/each
Unskilled labour 1.50 No @ Rs 2100.00 3150.00
Stone 1.20 m3 @Rs 6846.00 8215.20
Sub total 11365.20
Contractor's Overhead and Profit @ 15% 1704.78
Rate/m3 Rs 13069.98
Filling Soil in Pipeline Trenches in 20cm thick layers and hand compaction amd Water
18 (Ref.No. 2.39.d) Unit/m3
Sprinkler(Haulage distance 10m) GBMS
Making rectangular gabion box (2.0 x 1.0x 1.0m.) with two way knot incl. wire cutting, netting etc.
19 (Ref.No. 16.5.c) Per. No
complete. (Mesh size 100 x 120mm. , mesh wire 10 SWG.,selveged wire=7SWG)
21 125 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.50 No @ Rs 2500.00 3750.00
Helper 1.50 No @ Rs 2100.00 3150.00
Labour 3.00 No @ Rs 3450.00 10350.00
125mm dia. pipe 10Kg/cm2 50.00 Rm @Rs 1247.43 62371.50
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 432.98
Sub total 80106.98
Contractor's Overhead and Profit @ 15% 12016.05
Total 92123.02
Rate/Rm Rs 1842.46
22 160 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 2.00 No @ Rs 2500.00 5000.00
Helper 2.00 No @ Rs 2100.00 4200.00
Labour 4.00 No @ Rs 3450.00 13800.00
125mm dia. pipe 6Kg/cm2 50.00 Rm @Rs 1305.20 65260.00
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 577.30
Sub total 88889.80
Contractor's Overhead and Profit @ 15% 13333.47
22 140 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 2.00 No @ Rs 2500.00 5000.00
Helper 2.00 No @ Rs 2100.00 4200.00
Labour 4.00 No @ Rs 3450.00 13800.00
125mm dia. pipe 6Kg/cm2 50.00 Rm @Rs 1001.14 50057.00
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 577.30
Sub total 73686.80
Contractor's Overhead and Profit @ 15% 11053.02
Total 84739.82
Rate/Rm Rs 1694.79
22 125 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.50 No @ Rs 2500.00 3750.00
Helper 1.50 No @ Rs 2100.00 3150.00
Labour 3.00 No @ Rs 3450.00 10350.00
125mm dia. pipe 6Kg/cm2 50.00 Rm @Rs 796.23 39811.50
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 432.98
Sub total 57546.98
Contractor's Overhead and Profit @ 15% 8632.05
Total 66179.02
Rate/Rm Rs 1323.58
23 110 mm dia. 16 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.50 No @ Rs 2500.00 3750.00
Helper 1.50 No @ Rs 2100.00 3150.00
Labour 3.00 No @ Rs 3450.00 10350.00
125mm dia. pipe 4Kg/cm2 50.00 Rm @Rs 1417.21 70860.50
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 432.98
Sub total 88595.98
Contractor's Overhead and Profit @ 15% 13289.40
Total 101885.37
Rate/Rm Rs 2037.70
24 110 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.50 No @ Rs 3450.00 5175.00
Helper 1.50 No @ Rs 2100.00 3150.00
Labour 3.00 No @ Rs 2100.00 6300.00
110 mm dia. pipe 10Kg/cm2 50.00 Rm @Rs 966.41 48320.50
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 367.09
Sub total 63365.09
Contractor's Overhead and Profit @ 15% 9504.76
Total 72869.85
Rate/Rm Rs 1457.39
25 110 mm dia.6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.50 No @ Rs 710.00 1065.00
Helper 1.50 No @ Rs 2100.00 3150.00
Labour 3.00 No @ Rs 2100.00 6300.00
110 mm dia. pipe 6Kg/cm2 50.00 Rm @Rs 614.73 30736.50
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 263.93
Sub total 41567.93
Contractor's Overhead and Profit @ 15% 6235.19
Total 47803.12
Rate/Rm Rs 956.06
26 110 mm dia. 12.5kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.50 No @ Rs 710.00 1065.00
Helper 1.50 No @ Rs 2100.00 3150.00
Labour 3.00 No @ Rs 2100.00 6300.00
110 mm dia. pipe 12.5Kg/cm2 50.00 Rm @Rs 1170.94 58547.00
Fuel (Petrol) 0.50 Ltr @Rs 105.00 52.50
Miscellenous 2.51 % of Labour Rs 263.93
Sub total 69378.43
Contractor's Overhead and Profit @ 15% 10406.76
Total 79785.19
27 90 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.00 No @ Rs 710.00 710.00
Helper 1.00 No @ Rs 2100.00 2100.00
Labour 2.00 No @ Rs 2100.00 4200.00
90 mm dia. pipe 10 Kg/cm2 50.00 Rm @Rs 653.37 32668.50
Fuel (Petrol) 0.05 Ltr @Rs 105.00 5.25
Miscellenous 2.51 % of Labour Rs 175.95
Sub total 39859.70
Contractor's Overhead and Profit @ 15% 5978.96
Total 45838.66
Rate/Rm Rs 916.77
28 90 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.00 No @ Rs 3450.00 3450.00
Helper 1.00 No @ Rs 2100.00 2100.00
Labour 2.00 No @ Rs 2100.00 4200.00
90 mm dia. pipe 6 Kg/cm2 50.00 Rm @Rs 412.55 20627.50
Fuel (Petrol) 0.05 Ltr @Rs 105.00 5.25
Miscellenous 2.51 % of Labour Rs 244.73
Sub total 30627.48
Contractor's Overhead and Profit @ 15% 4594.12
Total 35221.60
Rate/Rm Rs 704.43
29 90 mm dia. 4 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.00 No @ Rs 710.00 710.00
Helper 1.00 No @ Rs 2100.00 2100.00
Labour 2.00 No @ Rs 2100.00 4200.00
90 mm dia. pipe 4 Kg/cm2 50.00 Rm @Rs 476.56 23828.00
Fuel (Petrol) 0.05 Ltr @Rs 105.00 5.25
Miscellenous 2.51 % of Labour Rs 175.95
Sub total 31019.20
Contractor's Overhead and Profit @ 15% 4652.88
Total 35672.08
Rate/Rm Rs 713.44
30 75 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.00 No @ Rs 2500.00 2500.00
Helper 1.00 No @ Rs 2100.00 2100.00
Labour 2.00 No @ Rs 2100.00 4200.00
75 mm dia. pipe 10 Kg/cm2 50.00 Rm @Rs 455.10 22755.00
Fuel (Petrol) 0.05 Ltr @Rs 105.00 5.25
Miscellenous 2.51 % of Labour Rs 220.88
Sub total 31781.13
Contractor's Overhead and Profit @ 15% 4767.17
Total 36548.30
Rate/Rm Rs 730.96
31 75 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.00 No @ Rs 710.00 710.00
Helper 1.00 No @ Rs 2100.00 2100.00
Labour 2.00 No @ Rs 2100.00 4200.00
75 mm dia. pipe 6 Kg/cm2 50.00 Rm @Rs 293.11 14655.50
Fuel (Petrol) 0.05 Ltr @Rs 105.00 5.25
Miscellenous 2.51 % of Labour Rs 175.95
Sub total 21846.70
Contractor's Overhead and Profit @ 15% 3277.01
Total 25123.71
Rate/Rm Rs 502.47
32 75 mm dia. 4 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
Plumber 1.00 No @ Rs 710.00 710.00
Helper 1.00 No @ Rs 2100.00 2100.00
Labour 2.00 No @ Rs 2100.00 4200.00
75 mm dia. pipe 4 Kg/cm2 50.00 Rm @Rs 330.20 16510.00
Fuel (Petrol) 0.05 Ltr @Rs 105.00 5.25
Miscellenous 2.51 % of Labour Rs 175.95
Sub total 23701.20
Contractor's Overhead and Profit @ 15% 3555.18
Total 27256.38
Rate/Rm Rs 545.12
34 63 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
35 63 mm dia. 4 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 50 Rm
36 50 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 1000 Rm
37 50 mm dia. 6kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 1000 Rm
38 40 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 1000 Rm
Estimated By: Checked by: Forwarded by: Approved By:
38 40 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 1000 Rm
39 40 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 1000 Rm
Plumber 1.50 No @ Rs 2500.00 3750.00
Helper 1.50 No @ Rs 2100.00 3150.00
Labour 3.00 No @ Rs 2100.00 6300.00
40 mm dia. pipe 6 Kg/cm2 1000.0 Rm @Rs 108.38 108380.00
Fuel (Petrol) 0.37 Ltr @Rs 105.00 38.85
Miscellenous 2.51 % of Labour Rs 331.32
Sub total 121950.17
Contractor's Overhead and Profit @ 15% 18292.53
Total 140242.70
Rate/Rm Rs 140.24
40 32 mm dia. 10 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 1000 Rm
41 32 mm dia. 6 kg/cm2 pipe supplying and laying (butt welded joints including fitting) (Ref.No. 17.2) Per 1000 Rm
49 100 mm dia. GI pipe(Medium duty) supplying and laying (Ref.No. 17.4-1.5) Per 30 Rm
58 15 and 20 mm dia Bend, elbow, union, reducer, flange, connection tap etc. for all types of fittings (Ref.No. 17.4-2.2) Per piece
59 25 and 32 mm dia Bend, elbow, union, reducer, flange, connection tap etc. for all types of fittings (Ref.No. 17.4-2.2) Per piece
Estimated By: Checked by: Forwarded by: Approved By:
59 25 and 32 mm dia Bend, elbow, union, reducer, flange, connection tap etc. for all types of fittings (Ref.No. 17.4-2.2) Per piece
60 40,50 mm dia Bend, elbow, union, reducer, flange, connection tap etc. for all types of fittings (Ref.No. 17.4-2.2) Per piece
61 65,80 mm dia Bend, elbow, union, reducer, flange, connection tap etc. for all types of fittings (Ref.No. 17.4-2.2) Per piece
62 100 mm dia Bend, elbow, union, reducer, flange, connection tap etc. for all types of fittings (Ref.No. 17.4-2.2) Per piece
63 125 mm dia Bend, elbow, union, reducer, flange, connection tap etc. for all types of fittings (Ref.No. 17.4-2.2) Per piece
Gabion const works including Placing in Position Tying by tightening wire closing from top tying Per. No
68 (Ref.No. 16.7.c)
wire=12SWG Box=(2.0 x 1.0x 1.0m.)
Skilled labour 0 No @ Rs 850 0
Unskilled labour 0.2 No @ Rs 580 116
Tying wire 0.7 Kg. @Rs 130.17 91.119
Selvegded Wire 0 Kg. @Rs 130.17 0
207.119
Contractor's Overhead and Profit @ 15% 31.06
Total Rate/no Rs 238.18
Making rectangular gabion box (2.0 x 1.0x 0.3m.) with two way knot incl. wire cutting, netting etc. Per. No
69 (Ref.No. 16.5.e)
complete. (Mesh size 100 x 120mm. , mesh wire 10 SWG.,selveged wire=7SWG)
Skilled labour 0.26 No @ Rs 850.00 221.00
Unskilled labour 0.12 No @ Rs 580.00 69.60
GI wire 13.400 Kg. @Rs 130.17 1744.27
Selvegded Wire 0.250 Kg. @Rs 130.17 32.54
2067.41
Contractor's Overhead and Profit @ 15% 310.11
Total Rate/no Rs 2410.07
Gabion const works including Placing in Position Tying by tightening wire closing from top tying Per. No
70 (Ref.No. 16.7.c)
wire=12SWG Box=(2.0 x 1.0x 0.3m.)
Estimated By: Checked by: Forwarded by: Approved By:
Gabion const works including Placing in Position Tying by tightening wire closing from top tying
70 (Ref.No. 16.7.c)
wire=12SWG Box=(2.0 x 1.0x 0.3m.)
Skilled labour 0 No @ Rs 850 0
Unskilled labour 0.12 No @ Rs 580 69.6
Tying wire 0.65 Kg. @Rs 130.17 84.6105
Selvegded Wire 0 Kg. @Rs 130.17 0
154.2105
Contractor's Overhead and Profit @ 15% 23.13
Total Rate/no Rs 177.34
Excavation of Hard rocks without Blasting including disposal (up to 10 m lead & 1.5 m lift) without
71 (Ref.No. 2.6.a) Unit/m3
Chisel
Unskilled labour 5.00 No @ Rs 580.00 2900.00
Tools and plant @ 3% 87.00
Sub total 2987.00
Contractor's Overhead and Profit @ 15% 448.05
Rate/m3 Rs 3435.05
3 PCC work in 1:3:6 cement concrete for floor bed. 0.83 m3 50078.86 41465.30
Making rectangular gabion box (2.0 x 1.0x 0.5m.) 2.00 nos. 9531.45 19062.89
with two way knot incl. wire cutting, netting etc.
complete. (Mesh size 100 x 120mm. , mesh wire
10 SWG.,selveged wire=7SWG)
Gabion const works including Placing in Position 2.00 nos. 238.18 476.36
Tying by tightening wire closing from top tying
wire=12SWG Box=(2.0 x 1.0x 0.5m.)
Total 5.95 m3
2 Stone soling work on the Base bed
Intake Bed 1.00 4.60 1.80 0.15 1.24
Valve Box
0.00 0.00 0.00 0.15 0.00
Total 1.24 m3
3 PCC work in 1:3:6 cement concrete for floor
bed.
Intake Bed 1.00 4.60 1.80 0.10 0.83
Valve Box
0.00 0.00 0.00 0.10 0.00
Total 0.83 m3
4 P.C.C (1:1.5:3) for R.C.C
Bed 1.00 4.60 1.80 0.20 1.66
L-wall 1.00 5.00 0.20 1.50 1.50
S-Wall 2.00 1.80 0.20 1.50 1.08
Valve Box
Cut Off Wall 1.00 8.60 0.20 1.00 1.72
Total 5.96 m3
Deduction
Long Wall 1 2 0.2 0.5 0.20
Total 0.20 m3
6 Form Work
Intake
Wall exterior (Long) 1.00 5.00 1.50 7.50
Wall exterior (Short) 2.00 2.00 1.50 6.00
Wall exterior (Cutoff) 1.00 9.00 1.00 9.00
Wall Interior (Long) 1.00 4.60 1.50 6.90
Wall Interior (Short) 2.00 1.80 1.50 5.40
Wall Interior (Cutoff) 1.00 8.20 1.50 12.30
Total 47.10 m2
Deduction
Long Wall 2.00 2.00 0.50 2.00
Total 2.00 m2
NetTotal 45.10 m2
7
Making rectangular gabion box (2.0 x 1.0x
0.5m.) with two way knot incl. wire cutting,
netting etc. complete. (Mesh size 100 x 2.00 2.00 nos.
120mm. , mesh wire 10 SWG.,selveged
wire=7SWG)
`
8 Stone filling into Gabion Boxes. 2.00 2.00 0.50 1.00 2.00
Total 2.00 m3
m3
2 Stone soling work on the floor bed 12.47 13069.98 163015.33
m3
3
PCC work in 1:3:6 cement concrete for floor bed. 4.32 50078.86 216315.64
m3
4 P.C.C (1:1.5:3) for R.C.C 40.20 73037.00 2935999.75
11 RVT Fittings
11.1 Inlet 4"size
a G.I. Elbow 4" pcs 2.00 3012.20 6024.40
b G.I. Socket 4" pcs 1.00 1896.70 1896.70
c G.I. Union 4" pcs 1.00 5662.95 5662.95
d GI Pipe 4" (0.65+0.4+1.8) m 2.85 4447.23 12674.61
Sub Total Rs 26258.66
11.4 Overflow(4")
a G.I. Elbow-4" pcs 2.00 3012.20 6024.40
b GI pipe-4" (0.25+1.3+0.35) m 1.90 4447.23 8449.74
c GI Nipple 4" 150mm Long pcs 1.00 667.08 667.08
Sub Total Rs 15141.22
Total = Rs 5376007.4
RVT
Levelling ground 1.00 13.10 4.00 0.40 20.96
RVT 1.00 13.10 6.10 1.48 118.27
Valve Box
1 1.80 1.80 1.00 3.24
142.47 m3
2 Stone soling work on the floor bed
RVT
Bed 1.00 13.10 6.10 0.15 11.99
Valve Box
1.00 1.80 1.80 0.15 0.49
12.47 m3
3 PCC work in 1:3:6 cement concrete for floor
bed. RVT
Bed 1.00 13.10 6.10 0.05 4.00
Valve Box
1.00 1.80 1.80 0.10 0.32
4.32 m3
4 P.C.C (1:1.5:3) for R.C.C
Bed 1.00 13.10 6.10 0.28 22.37
L-wall 2.00 12.50 0.25 2.00 12.50
S-Wall 2.00 5.00 0.25 2.00 5.00
Valve Box
Cover 1.00 1.80 1.80 0.10 0.32
40.20 m3
11 RVT Fittings
11.1 Inlet 4"size
a G.I. Elbow 4" 2.00 2.00 pcs
b G.I. Socket 4" 1.00 1.00 pcs
c G.I. Union 4" 1.00 1.00 pcs
d GI Pipe 4" (0.65+0.4+1.8) 2.85 2.85 mtr
Sub Total
11.2 Outlet
a G.I. Pipe 125 mm dia 1 meter long 1 1.00 mtr
b G.I.Tee 125/125/80 1 1.00 pcs
c G.I. Pipe 80 mm dia 0.5 mm long 0.5 0.50 mtr
d Gate Valve 80mm 1 1.00 pcs
e 80/90 GI HDPE Flange Set 1 1.00 pcs
f G.I. Pipe 125 mm dia 1 meter long 1 1.00 mtr
g Gate Valve 125mm 1 1.00 pcs
h 125/140 GI HDPE Flange Set 1 1.00 pcs
Sub Total
11.4 Overflow(4")
a G.I. Elbow-4" 2.00 2.00 pcs
b GI pipe-4" (0.25+1.3+0.35) 1.90 1.90 mtr
c GI Nipple 4" 150mm Long 1.00 1.00 pcs
Quantity and Cost Estimate of : Resorvoir Tank,Valve Box,Fittings and Barbed wire fencing
Size of the Tank
Length 14 Height 2
Width 7
Rate per unit Amount
S.No. Description of Works No. Length Breadth Height Quantity Remarks
(Rs.) (Rs.)
1 E/W excavation in Foundation in BMS soil
RVT
13 RVT Fittings
13.1 Inlet 4"size
a G.I. Elbow 4" 2.00 2.00 pcs 1357.17 2714.34
b G.I. Socket 4" 1.00 1.00 pcs 1199.80 1199.80
c G.I. Union 4" 1.00 1.00 pcs 2764.95 2764.95
d GI Pipe 4" (0.65+0.4+1.8) 2.85 2.85 mtr 4447.23 12674.61
13.2 Outlets 3" size For 1 nos outlets
a G.I. Elbow 3" 1.00 1.00 pcs 1357.17 1357.17
b G.I. Elbow -1/2" 2.00 2.00 pcs 86.57 173.14
c G.I. Union 3" 1.00 1.00 pcs 2051.95 2051.95
d G.I. Union -1/2" 1.00 1.00 pcs 178.57 178.57
e G.I. Nipple 3" 75mm long 2.00 2.00 pcs 713.98 1427.96
f GI Nipple -1/2" (75 mm long) 1.00 1.00 pcs 193.58 193.58
g G.I.Equal Tee-1/2" 1.00 1.00 pcs 116.47 116.47
h G.I.Reducing Tee3" *1/2 1.00 1.00 pcs 187.77 187.77
i Brass Union 3" 1.00 1.00 pcs 8701.25 8701.25
j Brass Gate Valve 3" 1.00 1.00 pcs 28222.39 28222.39
k G.I. Pipe3" (0.4 +1.6) 2.00 2.00 mtr 4447.23 8894.46
l G.I. Pipe -1/2" (0.5+0.6+1.2) 2.30 2.30 mtr 477.78 1098.89
13.3 Washout
a G.I. Elbow-2" 1.00 1.00 pcs 320.07 320.07
b GI Nipple 2" 3.00 3.00 pcs 216.27 648.80
c Brass Gate Valve- 2" 1.00 1.00 pcs 4991.31 4991.31
d G.I PIPE 2" (0.25+1.35) 1.60 1.60 mtr 2015.35 3224.56
e Brass union 2" 1.00 1.00 pcs 1548.43 1548.43
f HDPE 63mm/ 4kg-cm2 5.00 5.00 mtr 428.37 2141.85
13.4 Overflow
a G.I. Elbow-2" 2.00 2.00 pcs 320.07 640.14
b GI pipe-2" (0.25+1.3+0.35) 1.90 1.90 mtr 2015.35 3829.17
c GI Nipple 2" 1.00 1.00 pcs 216.27 216.27
70164.20
Total of RVT,Fittings and Barbed wire
6807322.5
fencing =
a Well pi()/4*(2.3+.3*2)^
1 6.61 11.00 72.650 2
72.65 m3 3756.040 272876.306
2 E/W in back filling @ 67 % of
excavation quantity
0.67 48.68 m3 1449.000 70530.800
3 Stone soling work on the floor bed
a Well
1 1.01 12.00 12.150
6 Form work
2 7.23 12.00 173.410
1443.360 250293.058
173.41 m2
7 Supplying and fitting, fixing required
perforated pipes, filters and all other
accessories as per instructions, all
complete.
L.S. 50000.00
3 PCC work in 1:3:6 cement concrete for floor bed. 1.98 m3 50078.86 99381.50
11 RVT Fittings
11.1 Inlet 4"size
a G.I. Elbow 4" 2.00 pcs 3012.20 6024.40
b G.I. Socket 4" 1.00 pcs 1896.70 1896.70
c G.I. Union 4" 1.00 pcs 5662.95 5662.95
d GI Pipe 4" (0.65+0.4+1.8) 2.85 mtr 4447.23 12674.61
Sub Total Rs 26258.66
11.4 Overflow(4")
a G.I. Elbow-4" 2.00 pcs 3012.20 6024.40
b GI pipe-4" (0.25+1.3+0.35) 1.90 mtr 4447.23 8449.74
c GI Nipple 4" 150mm Long 1.00 pcs 667.08 667.08
Sub Total Rs 15141.22
Total = Rs 2390182.0
RVT
Levelling ground 1.00 8.10 2.00 0.40 6.48
RVT 1.00 8.10 4.10 1.48 49.15
Valve Box
1 1.80 1.80 1.00 3.24
58.87 m3
2 Stone soling work on the floor bed
RVT
Bed 1.00 8.10 4.10 0.15 4.98
Valve Box
1.00 1.80 1.80 0.15 0.49
5.47 m3
3 PCC work in 1:3:6 cement concrete for floor
bed. RVT
Bed 1.00 8.10 4.10 0.05 1.66
Valve Box
1.00 1.80 1.80 0.10 0.32
1.98 m3
4 P.C.C (1:1.5:3) for R.C.C
Bed 1.00 8.10 4.10 0.18 5.98
L-wall 2.00 7.50 0.25 2.00 7.50
S-Wall 2.00 3.00 0.25 2.00 3.00
Valve Box
Cover 1.00 1.80 1.80 0.10 0.32
16.80 m3
11 RVT Fittings
11.1 Inlet 4"size
a G.I. Elbow 4" 2.00 2.00 pcs
b G.I. Socket 4" 1.00 1.00 pcs
c G.I. Union 4" 1.00 1.00 pcs
d GI Pipe 4" (0.65+0.4+1.8) 2.85 2.85 mtr
11.4 Overflow(4")
a G.I. Elbow-4" 2.00 2.00 pcs
b GI pipe-4" (0.25+1.3+0.35) 1.90 1.90 mtr
c GI Nipple 4" 150mm Long 1.00 1.00 pcs
Operation Cost
Delivery Discharge 6.11 lps
Working hour 12 hr
Water Delivered per annum 96342.48 m3
Electricity cost 3.125 per unit
Pump Power 25 Hp
Pump power 18.5 Kw
Pumping hour per annum @ 12 hr/day 4380 hour per annum
Electricity charge for a 18.5 KW pump @Rs. 3.125 per unit 253218.75 per annum
Total Electricity For 2 Pumps 506437.5 per annum
Cost of Pump operator 48000 per annum
Total operation cost 554,437.50 Per annum
Maintenance cost
(Assuming one servicing per year)
Pump pull out and reinstallation 10000
Replacing of bush and spare parts 10000
Service charge and unforseen expenditure 10000
Total 30,000.00 Per annum
3 Main pipeline
110 mm.dia. HDPE pipe (6kg/cm2) 1 1365 1365 Rm.
110 mm.dia. HDPE pipe (10kg/cm2) 1 370 370 Rm.
110 mm.dia. HDPE pipe (12.5kg/cm2) 1 1110 1110 Rm.
110 mm.dia. HDPE pipe (16kg/cm2) 1 735 735 Rm.
6 Outlet C1 Fittings(Ch-3+800)
140/125 GI HDPE flange Set 1 1.00 nos.
GI 125mm Pipe 1m Long 2 1.00 2.00 Rm
125/125/65 GI Unequal Tee 1 1.00 nos.
GI 65mm Pipe 0.5m Long 1 0.50 0.50 Rm.
65mm Gate Valve 1 1.00 nos.
65/75 GI HDPE flange Set 1 1.00 nos.
GI Reducer 125/100 1 1.00 nos.
GI 100mm Pipe 1m Long 1 1.00 1.00 Rm.
100mm Gate Valve 1 1.00 nos.
125/100 GI HDPE flange Set 1 1.00 nos.
7 Outlet C2 Fittings(Ch-4+090)
125/100 GI HDPE flange Set 1 1.00 nos.
GI 100mm Pipe 1 m Long 2 1.00 2.00 Rm.
100/100/65 GI Unequal Tee 1 1.00 nos.
GI 65mm Pipe 0.5m Long 1 0.50 0.50 Rm.
65mm Gate Valve 1 1.00 nos.
65/75 GI HDPE flange Set 1 1.00 nos.
100/80 GI Reducer 1 1.00 nos.
GI 80mm Pipe 0.5 m Long 1 1.00 1.00 Rm.
80mm Gate Valve 1 1.00 nos.
80/90 GI HDPE flange Set 1 1.00 nos.
8 Outlet C3 Fittings(Ch-4+380)
80/90 GI HDPE flange Set 1 1.00 nos.
GI 80mm Pipe 0.5 m Long 2 0.50 1.00 Rm.
80/80/65 GI Unequal Tee 1 1.00 nos.
GI 65mm Pipe 0.5m Long 1 0.50 0.50 Rm.
65mm Gate Valve 1 1.00 nos.
65/75 GI HDPE flange Set 1 1.00 nos.
80/65 GI Reducer 1 1.00 nos.
GI 65mm Pipe 0.5 m Long 1 0.50 0.50 Rm.
65mm Gate Valve 1 1.00 nos.
65/75 GI HDPE flange Set 1 1.00 nos.
3 Main pipeline
110 mm.dia. HDPE pipe (6kg/cm2) 1365 Rm. 956.06 1305021.90
110 mm.dia. HDPE pipe (10kg/cm2) 370 Rm. 1457.39 539234.30
110 mm.dia. HDPE pipe (12.5kg/cm2) 1110 Rm. 1595.70 1771227.00
110 mm.dia. HDPE pipe (16kg/cm2) 735 Rm. 2037.70 1497709.50
Sub Total Rs 5113192.70
6 Outlet C1 Fittings(Ch-3+800)
140/125 GI HDPE flange Set 1.00 nos. 5683.14 5683.14
GI 125mm Pipe 1m Long 2.00 Rm. 2635.64 5271.28
125/125/65 GI Unequal Tee 1.00 nos. 6453.64 6453.64
GI 65mm Pipe 0.5m Long 0.50 Rm. 1068.54 534.27
65mm Gate Valve 1.00 nos. 11930.29 11930.29
65/75 GI HDPE flange Set 1.00 nos. 2580.79 2580.79
GI Reducer 125/100 1.00 nos. 6714.69 6714.69
GI 100mm Pipe 1m Long 1.00 Rm. 1912.71 1912.71
100mm Gate Valve 1.00 nos. 28531.76 28531.76
125/100 GI HDPE flange Set 1.00 nos. 5658.26 5658.26
Sub Total Rs 57862.77
7 Outlet C2 Fittings(Ch-4+090)
125/100 GI HDPE flange Set 1.00 nos. 5658.26 5658.26
GI 100mm Pipe 1 m Long 2.00 Rm. 1912.71 3825.42
100/100/65 GI Unequal Tee 1.00 nos. 3622.76 3622.76
GI 65mm Pipe 0.5m Long 0.50 Rm. 1068.54 534.27
65mm Gate Valve 1.00 nos. 11930.29 11930.29
65/75 GI HDPE flange Set 1.00 nos. 2580.79 2580.79
100/80 GI Reducer 1.00 nos. 2028.79 2028.79
GI 80mm Pipe 0.5 m Long 1.00 Rm. 1304.29 1304.29
80mm Gate Valve 1.00 nos. 14322.29 14322.29
80/90 GI HDPE flange Set 1.00 nos. 2914.29 2914.29
Sub Total Rs 48721.45
8 Outlet C3 Fittings(Ch-4+380)
80/90 GI HDPE flange Set 1.00 nos. 2914.29 2914.29
GI 80mm Pipe 0.5 m Long 1.00 Rm. 1304.29 1304.29
80/80/65 GI Unequal Tee 1.00 nos. 2028.79 2028.79
GI 65mm Pipe 0.5m Long 0.50 Rm. 1068.54 534.27
65mm Gate Valve 1.00 nos. 11930.29 11930.29
65/75 GI HDPE flange Set 1.00 nos. 2580.79 2580.79
9 Outlet C4 Fittings(Ch-6+331)
65/75 GI HDPE flange Set 3.00 nos. 1068.54 1071.54
GI 65mm Pipe 0.5 m Long 1.50 Rm. 2580.79 2582.29
65/65/65 GI Equal Tee 1.00 nos. 1528.54 1529.54
65mm Gate Valve 2.00 nos. 11930.29 11932.29
Sub Total Rs 17115.66
5 PCC 1:2:4 for RCC lined canal 0.60 Cu.m 58977.61 35310.70
S.N. Description of work No. Length Breadth Height Quantity Unit Remarks
6 Wooden Formwork
For bed of Inlet and Outlet 2.00 3.74 0.10 0.75
For Cover of Inlet and Outlet 2.00 0.91 0.76 1.38
2.00 3.34 0.100 0.67
For bed of Main Chamber 1.00 10.20 0.10 1.02
1.00 1.62 1.62 2.61
1.00 6.46 0.15 0.97
Total 7.40 Sqm
7 Fittings for Structure
110/100 GI HDPE flange set 1.00 1.00 Nos
100 mm GI 1 m long pipe 6.00 6.00 Rm
100 mm Gate Valve 2.00 2.00 Nos
100 mm GI Elbow 2.00 2.00 Nos
50 mm GI 1 m long pipe for Overflow 1.00 1.00 Nos
50 mm GI 1 m long pipe for Washout 1.00 1.00 Nos
50 mm Washout Valve 1.00 1.00 Nos
3 Supply of Materials
3.1 GI Pipe 50mm dia 8 10 80.00 Rm.
3.2 GI Pipe 25mm dia 4 6.75 27.00 Rm.
3.3 GI Wire For Binding 4 5.00 kg
1
Making rectangular gabion box (2.0 x 1x
0.3m.) with two way knot incl. wire
cutting, netting etc. complete. (Mesh size
100 x 120mm. , mesh wire 10
SWG.,selveged wire=7SWG)
15 15.00 nos.
2
Gabion const works including Placing in
Position Tying by tightening wire closing
from top tying wire=12SWG Box=(2.0 x
1.0x 0.3m.) 15 15.00 nos.
3
Stone filling into Gabion Boxes.
15 2.00 1 0.30 9.00 m3
3 Supply of Materials
3.1 GI Pipe 50mm dia 80.00 Rm. 2015.35 161228.00 Incl Weld
3.2 GI Pipe 25mm dia 27.00 Rm. 1086.43 29333.61 Incl Weld
3.3 GI Wire For Binding 5.00 kg 241.79 1208.94
Total= Rs. 193532.02
1
Making rectangular gabion box (2.0 x
1x 0.3m.) with two way knot incl. wire
cutting, netting etc. complete. (Mesh
size 100 x 120mm. , mesh wire 10
SWG.,selveged wire=7SWG)
15.00 nos. 2410.07 36150.98
2
Gabion const works including Placing
in Position Tying by tightening wire
closing from top tying wire=12SWG
Box=(2.0 x 1.0x 0.3m.) 15.00 nos. 177.34 2660.11
3
Stone filling into Gabion Boxes.
9.00 m3 8131.65 73184.85
13 Making rectangular gabion box (2.0 x 1.0x 0.5m.) with two way
knot incl. wire cutting, netting etc. complete. (Mesh size 100 x
120mm. , mesh wire 10 SWG.,selveged wire=7SWG) No 2.00 2.00 9531.45 19062.89
Making rectangular gabion box (2.0 x 1x 0.3m.) with two way knot
16 incl. wire cutting, netting etc. complete. (Mesh size 100 x 120mm. ,
mesh wire 10 SWG.,selveged wire=7SWG)
No 15.00 15.00 2410.07 36150.98
28 Suspender Rm 434.14
50.00 50.00 21707.00
22 Fittings and Miscellenous
LS 166577.61 14447.23 40000.00 180554.49 40000.00 441579.33 1.00 441579.33
A Civil Works
1 RVT,Valve Box, and Barbed Wire Fencing-120 Cu.m No. 1.00 5376007.37
3 Field Outlets No. 4.00 911197.13
4 RCC Intake No. 1.00 741734.32
5 Pipelines No. 1.00 9522685.34
6 Pipe Protection No. 1.00 131318.09
7 Cable Crossing 50 metre No. 1.00 1169254.27
Sub Total (A) 17852196.52
Slicing of Work
Name of Project :- Humda Irrigation Sub-Project
Name of Work :- Irrigation Feasibility Study
SN Name of structure Unit Slice 1 (NCB Part) Slice 2 Slice 3 (WUA Contribution) Slice 4
Total Quantity (WUA Payable) (Departmental)
Quantity Cost Quantity Cost Quantity Cost Quantity Cost
A Civil Works
1 RVT,Valve Box, and Barbed Wire Fencing-120 Cu.m 1.00 No. 1.00 5,376,007.37
3 Field Outlets 5.00 No. 5.00 911,197.13
4 RCC Intake 1.00 No. 1.00 741,734.32
5 Pipelines 1.00 No. 1.00 6,835,139.44 1.00 2687545.90
6 Pipe Protection Work 1.00 No. 1.00 131,318.09
7 Cable Crossing 50 metre 1.00 No. 1.00 1,169,254.27
Sub-Total(D) 4463049.12
Amount
S.No. Description of Works Remarks
(Rs.)
A. GOVERNMENT PART
1 Sump Well Structure Rs.2,012,453.61
2 Reservoir Tank and Barbed Wire Fencing Rs.6,807,322.48
Slicing of Work
Name of Project :- Koltadi Irrigation Project
Name of Work :-Lift Irrigation Feasibility Study
SN Name of structure Unit Slice 1 (NCB Part) Slice 2 (WUA Slice 3 Slice 4 (Departmental)
Total Quantity Payable) (WUA Contribution)
Quantity Cost Quantity Cost Quantity Cost Quantity Cost
A Civil Works
1 (Sump Well) 1.00 No. 1.00 2,012,453.61
2 RVT,Valve Box, and Barbed Wire Fencing 1.00 No. 1.00 6,807,322.48
4 Orifice Intake with Covered Canal 1.00 No. 1.00 505,226.78 .
5 Field Outlet 3.00 No. 3.00 #REF!
6 Pump House 1.00 No. 1.00 #REF!
7 Pipelines 1.00 No. 1.00 Err:509 Err:509 Err:509
8 Pumps and accessories with Transportation and Installation 2.00 No. 2.00 491,340.00
9 Electric Lines 1.00 No. 1.00 1,284,128.75
A Civil Works
1 (Sump Well) No. 1.00 2,012,453.61
2 RVT,Valve Box, and Barbed Wire Fencing No. 1.00 6,807,322.48
3 Orifice Intake with Covered Canal No. 1.00 505,226.78
4 Field Outlet No. 3.00 #REF!
5 Pump House No. 1.00 #REF!
6 Pipelines No. 1.00 Err:509
7 Pumps and accessories with Transportation and Installation No. 1.00 491,340.00
8 Electric Lines No. 1.00 1,284,128.75
Sub Total (A) #REF!