Documente Academic
Documente Profesional
Documente Cultură
:
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-352-001
Rev. No. : 0
GENERATOR STEP UP TRANSFORMER
TITLE
SPECIFICATION & DATA SHEET Page. No : Cover
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-352-001
Rev. No. : 0
GENERATOR STEP UP TRANSFORMER
TITLE
SPECIFICATION & DATA SHEET Page. No : 1 / 15
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
For Construction
REV.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
NO.
REV.
HYOSUNG PREPARATION CHECK REVIEW APPROVAL
NO.
SPECIFICATION FOR
POWER TRANSFORMER
Specification
□ : 12-HSM-03621-01
Number
Contents
Section I. General
1. General scope
2. Applicable standard
3. Service ambient conditions
4. Construction
5. Conservators
6. Painting
7. Packing and shipment
8. Tests
Section I. General
1. General scope
2. Applicable standard
4. Construction
5. Painting
7. Tests
1. General Scope
This specification describes three phases, oil immersed, On-load tap changing transformers
suitable for outdoor installation under the service conditions mentioned herein and the
information about the following power transformer which will be supplied by HYOSUNG.
2. Applicable standard
Electrical equipment covered by this specification will be complied with the following standards.
2.1. IEC (International Electro-technical Commission)
2.2. NEMA (National Electrical Manufacturers Association)
3. Service conditions
These transformers are suitable for operation under the following service conditions
4. Construction
4.1 Core
The core consists of three column, parallel, laminated cold-rolled and non-aging silicon-steel
having high permeability and low hysteresis loss.
The steel sheet is thoroughly coated on both sides of each sheet with insulation to reduce eddy
current losses to minimum levels.
Structural rigidity is given to the core by the use of steel plates at the top and the bottom of the
core. So that distortion due to short circuit stresses or transport handling is prevented.
4.2 Windings
Coils are designed and manufactured to withstand impulse voltage and prevent it from distortion
when a short circuit occurs.
Permanent current carrying joints or splices will be welded or clamped, formed, finished and
insulated to avoid concentration of dielectric stresses.
The conductors will be transposed at sufficient intervals to minimize currents and equalize the
current and temperature distribution along the winding.
The conductor material is copper.
4.3 Tank
The transformer is provided with a suitable steel tank of substantial construction which is
oil-tight and gas-tight. All gaskets are made of materials which do not deteriorate under service
conditions.
The tank has sufficient strength to withstand an internal pressure of full vacuum and vacuum
drying without damage or permanent deformation. The transformer tank is provided with
manholes and hand holes of suitable size to afford easy access to the lower ends of bushing
terminals, upper portions of the coils and side position of tap changer.
In the case of core-form transformer the joint between the tank and cover is provided with
suitable flange and gaskets at top of the tank so that the assembly service is oil-tight and
gas-tight. The transformer is provided with lugs for lifting the essential parts also for lifting the
completely assembled transformer filled with oil.
4.4 Radiator
The HYOSUNG radiator is an efficient cooling unit designed for use on large transformers
requiring a self cooling rating. The radiator is detachable and is removed from the transformer
for shipment. The radiator is mounted to the tank directly or separately.
The radiator is all welded sheet metal construction with vertical cooling sections through which
the oil circulates and cools. A formed metal header is welded to each end of the vertical fin
sections. Plugs are fitted at the top and at the bottom of each radiator for filling, draining and air
releasing.
4.6 Conservator
In air seal cell type conservator, the oil surface is completely isolated from the atmosphere by
installing an oil-resistant rubber cell in the interior of the conservator, so that atmospheric
pressure is always maintained without the necessity of employing intervening mediums.
The outside of the rubber cell attached on the inside of the conservator is filled with insulating
oil. The inside is open to the atmosphere through the silica gel breather.
(Refer to the Figure 1.)
Namely, during the operation the insulating oil is always isolated from the air by the oil-resistant
rubber and there is no oxidation or moisture contamination of the oil at all.
And this type conservator allows also the main tank to remain full oil level despite of oil
expansion and contraction with temperature changes.
A pipe connection between the lowest part of the conservator and the cover of main tank permits
the gas from main tank to pass into the conservator through Buchholz relay, so that the
transformer tank will be completely filled with oil.
This type oil preservation system is an ideal device for maintaining the optimum dielectric strength
of insulating oil.
High tension, large capacity transformer in which this system is adopted are highly reliable
and ideal units.
5. Painting
All surfaces are thoroughly cleaned by shot blasting before painting.
Rough surfaces are filed and all surfaces liable to rust are painted with a priming coat immediately
after cleaning followed by two further coats oil resisting and weather resisting paint of good quality.
5.1 Paint
- Main tank, Conservator
All openings for transformer components, (e.g. bushings which have been removed from the
transformer during transport) are covered by means of blanking off plates. All parts are carefully
packed for transport in such a manner that they are protected against mechanical injury and
injurious effects of climatic conditions encountered during transit to their destination, as well as
during long storage before erection.
7. Tests
The following test items will be performed according to the latest IEC standard 60076
after completion of assembling.
--------------------------------------------------------------------------------------------------------
Note : The test marked *, are not tested separately during the transformer factory test.
Instead of HYOSUNG’s factory test, the test report will be submitted by its maker.
But The functional tests will be done at factory.
1) Manufacturer HYOSUNG
2) Design standard IEC
3) Number of windings 2
4) Rated power, ONAN / ONAF, MVA 15 / 20
5) Rated frequency, Hz 50
6) Rated voltages
a) HV, kV 150
b) LV, kV 11
7) Vector group reference YNd1
8) Material of insulation (Thermal class A) Insulation paper
9) Type of cooling ONAN / ONAF
10) Winding temperature rise at average ambient 45
temperature of yearly average (20℃), ℃
a) HV Shielded Continuous
b) LV Double Continuous
c) Tapping Continuous
d) Arrangement (e.g. Core/LV/HV/taps) Core/LV/HV/taps
19) Conductor material
a) HV windings copper
b) LV windings copper
c) Tapping windings copper
20) Conductor insulation
a) HV windings Insulation paper
b) LV windings Insulation paper
c) Tapping windings Insulation paper
d) Connecting leads from winding to tap changer Insulation paper
21) Basic Impulse Insulation Level (BIL) of Windings, kV
a) HV windings 650
b) LV windings 150
c) Neutral winding 95
22) Type of axial coil supports
a) HV windings R-spacer
b) LV windings R-spacer
c) Tapping windings R-spacer
23) Materials used
a) Axial supports and blocks Pressboard
b) Intermediate coil spacers Pressboard
24) Type of major insulation between windings Pressboard
25) Type of impregnate used on insulation Pressboard
26) Core construction
a) Limbs (Flux density), tesla Approx. 1.7T
Generator Step up & Unit DOC. NO. REV. NO. PAGE
Transformers 1009-4261-PE-352-001 0 3/4
BUSHING
34) Basic Impulse Insulation Level (BIL), kV
a) HV Bushing 750
b) LV Bushing 150
c) Neutral Bushing 250
CURRENT TRANSFORMER
35) Rated primary voltage, KV ; HV side 150
LV side 11
36) Rated short time withstand current (1sec), kA
37) Current ratio
a) HV side -
b) LV side -
c) HV Neutral 100/1A
38) Accuracy class
a) For instrument 5%
Generator Step up & Unit DOC. NO. REV. NO. PAGE
Transformers 1009-4261-PE-352-001 0 4/4
b) For protection 5%
39) Burden, VA
a) For instrument 30VA
b) For protection 30VA
EARTHING SWITCH
40) Nominal voltage, kV N/A
41) Rated voltage, kV
42) Rated frequency, Hz
43) Rated current , A
44) Rated short time withstand current (1sec), kA
45) Lightning impulse withstand voltage, kV
46) Power frequency withstand voltage, kV
SURGE ARRESTER
47) Type N/A
48) Rated voltage, kV
49) Rated frequency, Hz
50) Lightning impulse withstand voltage (peak), kV
51) Power frequency withstand voltage, kV
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-452-002
Rev. No. : 0
TITLE SUB VENDOR LIST
Page. No : Cover
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-452-002
Rev. No. : 0
TITLE SUB VENDOR LIST
Page. No : 1 / 2
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
For Construction
REV.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
NO.
REV.
HYOSUNG PREPARATION CHECK REVIEW APPROVAL
NO.
Rev. No. : 0
TITLE SUB VENDOR LIST
Page. No : 2 / 2
WINDING TEMPERATURE
5 INDICATOR MT-ST160F MESSKO(GERMANY)
OIL TEMPERATURE
6 INDICATOR MT-ST160W MESSKO(GERMANY)
REMOTE TAP
19 CONTROL PANEL - HYOSUNG(KOREA)
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-452-005
Rev. No. : 2
SPARE PART LIST & SPECIAL TOOLS
TITLE
LIST WITH DESCRIPTION Page. No : Cover
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-452-005
Rev. No. : 2
SPARE PART LIST & SPECIAL TOOLS
TITLE
LIST WITH DESCRIPTION Page. No : 1 / 2
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
For Construction
REV.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
NO.
REV.
HYOSUNG PREPARATION CHECK REVIEW APPROVAL
NO.
Rev. No. : 2
SPARE PART LIST & SPECIAL TOOLS
TITLE
LIST WITH DESCRIPTION Page. No : 2 / 2
WINDING TEMPERATURE
5 INDICATOR MT-ST160F 1 SET MESSKO(GERMANY)
OIL TEMPERATURE
6 INDICATOR MT-ST160W 1 SET MESSKO(GERMANY)
2 PRESSURE RELIEF DEVICE
7 FOR MAIN TANK & OLTC QT208-60F 1 SET QUALITROL(U.S.A.)
Rev. No. : 0
TITLE ELECTRICAL LOAD LIST
Page. No : Cover
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-482-006
Rev. No. : 0
TITLE ELECTRICAL LOAD LIST
Page. No : 1 / 3
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
For Construction
REV.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
NO.
REV.
HYOSUNG PREPARATION CHECK REVIEW APPROVAL
NO.
A. TR. MK
2. AC Load Calculation
1) 3 Phase AC 400V
• Cooling Fan Motors : 370W x 8EA = 2960 W
• Under Voltage Relay : 5W x 1EA =5W
• Total Continuous Load : 2965W x 1.3(Margin) = 3855 W
2) 1 Phase AC 230V
• Spacer Heater : 100W x 1EA = 100 W
• Incandescent Lamp : 60W x 1EA = 60 W
• Total Continuous Load : 160W x 1.3(Margin) = 208 W
2. AC Load Calculation
3 Phase AC 400V
• Total OLTC Driving Motor
: 1850W x 1.3(Margin) = 2405 W
• Total OLTC Heater
: 60W x 1.3(Margin) = 78 W
Rev. No. : 0
Welding Procedure Specification - Procedure
TITLE
Qualification Record (WPS-PQR) Page. No : Cover
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-001
Rev. No. : 0
Welding Procedure Specification - Procedure
TITLE
Qualification Record (WPS-PQR) Page. No : 1 / 50
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
For Construction
REV.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
NO.
REV.
HYOSUNG PREPARATION CHECK REVIEW APPROVAL
NO.
Page 02/50
1. GENERAL
Hyosung Corporation
DOC.No. 1009-4261-PE-464-001
WPS & PQR REV.No. 0
PAGE 03/50
1. GENERAL
1.1 Scope
This procedure will be applied to the welding for 3×15MW WAMPU HEPP PROJECT
Step-up & Aux transformers to be manufactured in HYOSUNG Chang-won plant.
1.2 References
1.4.2 The Weld surfaces must be free of any airborne dust, paint, moisture, oil, grease ect,
and shall be cleared by grinding, brushing or chipping before welding.
1.4.3 All slags, weld spatters, fluxes of any defect appeared on the welded
surfaces shall be removed to make sound weld by chipping, grinding
or arc air gouging before subsequent welding if applicable.
1.4.4 Min. preheat and Max. interpass temperature specified in WPS shall be
kept continuously during welding.
Hyosung Corporation
DOC.No. 1009-4261-PE-464-001
WPS & PQR REV.No. 0
PAGE 04/50
Parts that are to be joined by welding may be fitted, aligned, and retained
in position during the welding operation by the use of bars, jacks, clamps,
tack welds or temporary attachments.
1.8.1 Tack welds used to secure alignment shall either be removed completely
when they have served their purpose, or their stopping and starting
ends shall be properly prepared by grinding or other suitable means
so that they may be satisfactorily incorporated into the final weld.
1.8.2 When tack welds are to became a part of the finished weld, they shall
be visually examined and defective tack welds removed.
1.8.3 Tack welds shall be made by qualified welders using qualified welding procedures.
1.9.1 The material is identified and is suitable for welding but need not be
certified material
Hyosung Corporation
DOC.No. 1009-4261-PE-464-001
WPS & PQR REV.No. 0
PAGE 05/50
1.9.6 After the temporary attachment has been removed, the surrounding
area is visually inspected.
1.10.1 Back Gouging may be performed by arc air gouging, chipping, grinding
or machining, However, arc air gouging shall be not be permitted on
stainless steel.
1.10.2 The gouging surface shall be ground and free of slag, carbon deposit
and other harmful material and visually inspected before welding.
Hyosung Corporation
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
Page 06/50
Hyosung Corporation
1009-4261-PE-464-001
07/50
2. WELD MAP
2.5 TANK : TOP (COVER)
Hyosung Corporation
1009-4261-PE-464-001
08/50
2. WELD MAP
2.1 TANK : BACK (HV WALL)
Hyosung Corporation
1009-4261-PE-464-001
09/50
2. WELD MAP
2.2 TANK : FRONT (XV WALL)
Hyosung Corporation
1009-4261-PE-464-001
10/50
2. WELD MAP
2.3 TANK : RIGHT (END SIDE)
Hyosung Corporation
1009-4261-PE-464-001
11/50
2. WELD MAP
2.4 TANK : LEFT (END SIDE)
Hyosung Corporation
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
Page 12/50
3. WPS / PQR
Hyosung Corporation
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-013
Rev. No. : 0
TITLE QA PROGRAM MANUAL
Page. No : Cover
QA PROGRAM MANUAL
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-013
Rev. No. : 0
TITLE QA PROGRAM MANUAL
Page. No : 1 / 50
QA PROGRAM MANUAL
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
For Construction
REV.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
NO.
REV.
HYOSUNG PREPARATION CHECK REVIEW APPROVAL
NO.
HYOSUNG CORPORATION
- Following -
1. This manual has precedence over all standards of our company to issue, revise,
interpret and apply.
2. All businesses and job duties carried out in our company have to be practiced
suitably for principles and procedures provided in this manual.
4. Consequently, this manual has to be applied to daily job duties, and the
fundamental and principle provided in this manual have to be well understood.
This manual has precedence over every applicable regulation and manual of our company
to issue and operate and all members shall fulfill effective quality management as specified in
this manual.
The quality management manual (MQM-T001 REV. NO.: J) is prepared by person of charge
of quality management team, and reviewed by the Quality management team general
manager and approved by the Plant manager.
Principle 2 Leadership
Top management shall establish constant management policy and objectives so as that
all members can participate spontaneously to achieve the management policy and
objectives and produce fruits of accomplishment.
1.1 General
This manual specifies on operation of the quality management system when an organization
needs
1.4 In the quality management system specified in this manual, all requirements of ISO 9001:2008 are
included.
CTO
Technology Management
Power Systems Performance Group Industrial Machinery Performance Group Changwon Plant Manager Wind Power Group
Director Director Director Director Customer Support Production Support Strategic Marketing
Management Plannig Quality Inspection Strategic Planning Mfg Control Environmental Safety AE Management
Corporation Support R&D advisor Director Mfg Technology HR
Work Support PTR Sales 1 Director Quality assurance Director
Director PTR Sales 2 PTR Technology Development Director Wind Design 1
TR R&D Welding Machine sales Global Marketing Administration Center Wind Design 2
C/B R&D DTR Sales Director Global Sales 1 Director Emergency Planning Wind Technology
Director E/P Sales PTR Mfg Technology Global Sales 2 HV Motor Design Purchasing
New Business Director Heavy Electrical Sales PTR Inovation Global Sales 3 HV Motor Mfg Quality Management
Director Director
Technology Management Director PTR Mfg Technology Director
R&D Support Global Sales 1 PTR Mfg 1 Gear Solution R&D
Director Director
Global Sales 2 DTR Design
Global Sales 4 DTR Mfg Director
Industrial Machinery
Director Director
Solution Business C/B Mfg contol
Process Business C/B Design 1
C/B Design 2
C/B Design 3
E/P Design
Director E/P Mfg
CS
Director
C/B Mfg Technology
C/B Mfg 1
C/B Mfg 2
SPEX
Director
C/B Developement 1
C/B Developement 2
C/B Development 3
C/B R&D
Definitions of fundamental matters and terms needed to specify or interpret this manual shall
follow ISO 9000:2005. Also, the quality management system specified in this manual shall refer the
following standards.
ISO 9001, KEPIC, International Standard (10 CFR 50 App. B, ANSI/ASME NQA-1 etc.), Contracts,
Applicable code, etc.
3.5 Process
A gathering of interrelated or interactive activities that convert input into output
3.7 Effectiveness
Accomplished rate of intended results after planned activities are realized
3.8 Efficiency
Relationship between accomplished result and used resource
3.10 Product
(1) The product that is required by customer or intended for customer
(2) The intended output as a result of the product realization process
Note. Plan: Establishing objective and process necessary to achieve management result according to
customer requirement and company‟s policy.
Do: Executing every process needed to attain quality objective established accurately and
thoroughly.
Check: Measuring and monitoring process carried out to meet policy, management object and
product requirement and products and evaluate the results.
Action: Developing continual improvement activities to maximize performance according to the
result of measurement and monitoring on process and product.
As written above, our quality management system is to maximize the performance and
effectiveness of processes by putting all processes needed to realize products that satisfy
customer in an efficient and effective system and applying PDCA cycle completely.
Changwon Plant shall establish, document, implement and maintain the quality management
system and continually improve its effectiveness in accordance with the requirements of
International Standard ISO 9001:2008. To do so, Changwon Plant shall
a) have the same process necessary for quality management system with [Appendix 1. Process
linkage diagram], [Appendix 2. Process flow] and apply it to our organization,
b) follow role allotment table [Appendix 3.] for the sequence and interaction of these processes,
c) follow article 8.2.3 (Monitoring and measurement of process) for criteria and methods needed to
ensure that both the operation and control of these processes is effective,
d) be able to use all resources and information necessary to operate and monitor these
processes,
e) carry out monitoring, measurement and analysis of these processes according to article 2.3
(Monitoring and measurement of process) and article 8.4 (Data analysis).
f) implement actions necessary to achieve planned results and continual improvement of these
processes according to article 8.5 (Improvement).
Theses processes necessary for the quality management system shall be managed by the
organization, and shall include management activities, provision of resource, quality realization,
measurement, analysis and improvement. Control of outsourced process that affects on
product conformity shall be identified within our quality management system.
c) the latest version where changes and the current revision status of documents are identified
shall be controlled,
d) the quality management system executive department shall ensure that the latest versions
of applicable documents are used by making out a control ledger,
e) documents shall remain legible and have an identification system for easy identification and
retrieval,
f) documents of external origin which are determined to be needed in order to plan and operate
quality management system shall be identified and their distribution controlled, and
g) obsolete documents shall be withdrawn or abolished by the relevant department in order to
prevent unintended use. Suitable identification shall be applied if it is necessary to be
retained.
[Related Procedure] 1. The procedure for control of HICO standard(CP-34-0004)
2. The procedure for control of documents (CP-14-0014)
3. The procedure for control of purchasing document(CP-24-0060)
4.2.4 Control of records
Our company establishes and maintains records such as the following to provide evidence of
conformity to requirements and the effective operation of the quality management system.
Theses records remain legible, readily identifiable and retrievable, and a documented
procedure is established to define the controls needed for the identification, storage, protection,
retrieval, retention time and disposition of records.
a) Results of management reviews
b) Records of education, training, skills and experience
c) Records of circular inspection on manufacturing process and records of product examination
d) Results of customer requirements checking and results of follow-up activities
e) Design and development input
f) Results of design and development review and necessary actions
g) Results of design and development verification and necessary actions
h) Results of design and development validation and necessary actions
i) Results of design and development changes review and necessary actions
j) Results of supplier evaluation and necessary actions according to the evaluated results
k) Records necessary to validate a special process
l) Records to maintain traceability
m) Customer property lost, damaged or otherwise found to be unsuitable for use
n) Validity evaluation of former results if equipment is found to be unsuitable for requirements
o) Calibration and verification results of measuring devices
p) Results of internal audit
q) Records of release examination
r) Contents of nonconformity and all actions taken including concession
s) Results of corrective action
t) Results of preventive action
u) Other necessary documents
[Related Procedure] The procedure for control of quality records (CP-14-0013)
5.4 Planning
5.4.1 Quality objectives
a) Every general manager shall establish quality objectives according to the quality
management policy determined by the company.
b) Quality objectives shall be measurable in a fixed quantity, be consistent with the quality
management policy, meet requirements for product and include required Q. C and D.
c) Performance of duties for quality objectives shall be in accordance with P, D, C and A cycle.
b) Director in charge (Directors having responsibility for the control of each team in Power &
Industrial Systems Performance Group of Hyosung Corporation are referred as Director in
charge)
Each director in charge has responsibility to control overall quality-related activities of the
team under his control, and to make the team observe this quality management manual.
d) Quality inspection team manager (The Quality Inspection team manager of Power system PU,
and The Quality Assurance team manager Industrial Machinery PU and Wind Turbine)
(1) Performance of receiving inspection for materials and parts purchased from outside
including customer-supplied product, and preparation and maintenance of the record
(2) Overall review of quality-related work of customer requirements
(3) Performance of the verification work for identification and traceability through inspection
and monitoring
(4) Review and approval of inspection and test plans
(5) Review and approval of inspection and test standards
(6) Control of inspection and test schedule
(7) Review, approval and record control of results of inspection and test
(8) Witness request to customer or his representative for inspection of witness points
(9) Identification and traceability control of inspection and testing conditions
(10) Review and approval of disposition plans for nonconformity reports prepared by the
quality inspector
(11) Authority to request work stop in case of occurrence or finding out the important
conditions adverse to quality
(12) Maintenance and control of the testing equipment
(13) Analysis of production defect cause
(2) Maintenance and mending of the building, construction and pipe line
(3) Planning and control of equipment maintenance
- Cost
(1) Planning cost rate and construction of control system for cost rate
(2) Establishment and review middle/long term master plan for innovation of cost rate
(3) Improvement and review of manufacturing cost by analysis of relevance and economical
Efficiency
j) Design team manager (Power transformer, Distribution transformer, Circuit breaker, Electrical
panel, HV electric motor, LV electric motor, Gear solution, Wind design team and Power
transformer R&D, Circuit breaker R&D, Electric motor R&D, Wind Technology team are
referred as Design team and the team managers are referred as Design team manager)
(1) Review of design-related part out of customer requirements
(2) Receiving contract review request from Business team, gathering all opinions of related
team managers in the plant and sending to Business team manager
(3) Overall control of design affairs (including design schedule and support for other team)
(4) Approval of design documents
(5) Interface control of design-related affairs between internal and external organization
(6) Decision of purchasing specifications and establishment and revision of material and
product standard
(7) Approval of QC process chart
(8) Approval of quality plan according to contract requirements
(9) Approval of package specifications according to contract requirements
(10) Verification of technical adequacy for nonconformity disposed as “repair” and “use-as-is”
and record on the nonconformity report
(11) Review of development report when required to develop new items
k) Product team manager (Special motor, Industrial machinery, industrial machinery PU)
Technology development and Foundry, Plant team are referred as Product team, and the
team managers are referred as Product team manager)
The Product team manager has all responsibility and authority of Manufacturing team
manager and Design team manager described in article 5.5.1, m) and n) of this manual.
However, charge to preserve and control the manufacturing facilities shall be on the
technology development team. (Applicable only to Industrial machinery PU)
l) Engineering team manager (Transformer and Circuit breaker engineering team are referred
as Engineering team and the team managers are referred as Engineering team manager)
(1) Review of the application to production of manufacturing drawing
(2) Planning and performance of a long range plan of equipment investment
(3) Establishment and revision of technical standard under review of validity
(4) Processes improvement and fool proof by analysis of loss in manufacturing processes
(5) Performance of automation of equipment/line in manufacturing processes
(6) Improvement of the ways in work
m) Business team manager (The team managers of Power system sales team 1, Power system
sales team 2, Heavy electric systems sales team, Electrical panel sales team, Agent
management team, Plant team, Process sales team, Process engineering team, Overseas
project slaes team, Power system engineering team, Global sales team 1, Global sales team
2, Global sales team 3, Global sales team 4, Rotating machine sales team 1, Rotating
machine sales team 2, Plant ocean sales team, Generator sales team, Gear solution sales,
Industrial machinery sales, Wind turbine sales team, Strategic marketing team are referred
as Business team manager)
The Business team manager has the overall responsibility for contract review affairs.
(1) Receipt and control of customer requirements
(2) Specification and review request of customer requirements
(3) Distribution and control of contract documents
n) Project team manager (The Project 1, 2 team, A/E management team manager are referred
as solution execution team manager)
The Project team manager has responsibility such as follows for power transformer, circuit
Breaker, distribution transformer, mold transformer and electric panel, Wind turbine system
(1) Establishment of schedule for field installation and work control
(2) Performance of test and inspection after installation and maintenance control of the record
(3) Planning, performance and record maintenance of B/S
(4) Receipt and management of customer complaints and maintenance control of the record
(5) Analysis of management results for B/S and A/S, and feedback to related departments
(6) Receipt and management of customer complaints on power transformer, circuit breaker,
distribution transformer, mold transformer, electric panel and control component or
management request to related teams
(7) Feed-back the information of defective products to related departments
(8) Receipt and analysis of the result managed by the related manufacturing department
(9) Storage control of products (applicable only to Changwon Project 2 team)
(10) Control of package, transportation, maintenance and delivery (applicable only to
Changwon Project 2 team)
o) R&D team manager (The team managers of Core technology team, Distributed power system
team, Circuit breaker team , Technology Management team, Power Grid Integration, Power
Grid Solution team, Rotating team, Fuel cell team, Reliability engineering team are referred as
R&D team manager)
(1) Review of development report when required to develop new items
(2) Approval of R&D plans
(3) Approval of R&D documents
(4) Interface control between internal and external organizations related with R&D
(5) Decision of purchasing specifications and establishment and revision of material and
product standard
r) Purchasing team manager(Strategic Purchasing team, Subcontracting & Supply team, Vendor
Support team are referred as Purchaing team manager)
(1) Establishment of material supply and demand program and control of stock
(2) Establishment of basic policy to bring up suppliers and overall control of systematization
(3) Purchasing and supply of imported/domestic materials and installation materials
(4) Control of materials including import (Opening of L/C, marine transportation, insurance,
approval of B/L and acceptance)
(5) Overall purchasing affairs control such as dispatching of purchasing documents,
purchasing contract, etc.
(6) Regular evaluation for registered suppliers
(7) Preparation and distribution of the approved vendor list
(8) Selection and registration control of suppliers
(9) Maintenance and control of purchased materials
(10) Identification and control of purchased materials
(11) Segregation of nonconforming materials from other similar products or materials so as
not to be used together
s) Strategic planning team manger (The team managers of Strategic planning tem in Power
systems PU and Industrial machinery PU of Power & Industrial systems PG are referred as
Strategic planning team manager)
(1) Establishment, adjustment, result analysis and control of management plan
(2) Establishment of a middle/long-term business plan and strategies
(3) Establishment and adjustment of a middle/long-term investment plan
t) Customer support team (C/S team in Power systems PU, Customer support team in Industrial
Machinery PU are referred as Customer support team manager)
(1) Establishment of A/S and B/S plan, performance and maintenance of the record
(2) Receipt and management of customer complaints and maintenance of the record
(3) Analysis of managed results for B/S and A/S and feedback to related departments
(4) Receipt and management of customer complaints on products manufactured by the
Industrial machinery or management request to related teams
(5) Feedback of information on defective products to related departments
(6) Receipt and analysis of the result managed by the related manufacturing department
u) Common duty
Training in a team, corrective action, preventive action, standardization, improvement of
systems and observance of 8 principles of quality management
[Related Procedure]
1. The procedure for management system audit (CP-34-0183)
2. The procedure for nonconforming product management (CP-34-0009)
3. The procedure for issuing & control of correcting management (CP-34-0011)
6.3 Infrastructure
The infrastructure needed to achieve the conformity of product requirements shall be determined,
provided and maintained. The infrastructure shall include, as applicable
a) office, factory and warehouse,
b) facilities and equipments,
c) laboratory and analysis room, and
d) computer network and information system
[Related Procedure]
The procedure for control of manufacturing facilities (CP-79-0001)
Design inputs shall include the following items and be reviewed for adequacy.
(1) Customer requirements
(2) Function and performance requirements
(3) Applicable statutory and regulatory requirements
(4) Information derived from previous similar design
(5) Other requirements essential for design and development
b) Incomplete, ambiguous or conflicting requirements of design-input-requirements shall be
resolved with whom responsible for preparing these requirements, and if necessary, the
results of contract review may be reflected and reviewed in design input step.
c) Changes and revisions to the approved design input data shall be subject to the same
control and approval manner as required for the original.
d) In case of a specific request by customer, or the development of new products, the design
team can hold a design review meeting with the related team and shall maintain the
related records.
7.3.3 Design and development output
a) The designer shall perform the design activity including design calculation and analysis to
convert the requirements, standards and design input contained in the design document of
customer into design output.
b) The design team manager shall control the design activity according to the instruction for
design management so that the designer can obtain accurate design output at a proper time.
Also, he shall obtain and maintain the documented information or other materials gained
from experiences so that the designer can use them.
c) The design document occurred from performing the design activity shall be approved by the
design team manager.
d) The computer program used for design interpretation and input/output control shall be
controlled in accordance with the instruction for design management.
e) Design output data means the design document such as design drawings, design
calculations and specifications confirming that the specified design input requirements are
satisfied, and the design document shall
(1) meet the input requirements for design and developments,
(2) provide appropriate information for purchasing, manufacturing and servicing,
(3) contain or refer to the product acceptance criteria, and
(4) specify the characteristic of product essential for safe and proper use.
f) The design output data shall be legible and in a form suitable for duplication, filing and
revision.
g) The design output data shall be easy and detailed to confirm.
h) The design calculations shall be identified by the title, person who prepared, reviewer,
approver and other data for retrieval.
i) The design output document shall be distributed after checking for errors.
7.3.4 Design and development review
At suitable stage, the design team manager shall call the related teams and carry out the
design review (hereafter, referred as DR). The participants of DR including the team managers
related to the design development shall
7.4 Purchasing
7.4.1 Purchasing process
The procedure shall be established, and according to the procedure, the purchased parts
composing the product supplied to the customer shall be controlled to meet the requirements
of customer. The controlling method for suppliers shall be determined according to the effect of
the purchased parts on the manufacturing process or final product.
The evaluation for supplier shall be carried out as the following based on its ability to supply
parts suitable for the product requirement of our company.
a) Registration of suppliers
(1) Registration of suppliers is composed of two methods. One is the source evaluation that
evaluates the supplier‟s skill and quality assurance ability, and the other is the document
evaluation that evaluates the development and stability of suppliers.
(2) The supplier who wants to register is to be evaluated in accordance with the standard
specifying management, production and quality. If the supplier meets the standard, it
may be registered approved vendor list.
(3) Other matters related to supplier registration shall conform to the procedure for supplier
registration.
b) Evaluation and selection of approved suppliers
(1) A periodic evaluation for defect ratio, delay ratio of delivery date, 5S and cooperation
degree of suppliers through that their management level, skill level, quality control level
and management ability are synthetically revealed shall be performed and the records
shall be maintained and controlled. According to the results of evaluation, the suppliers
shall be controlled in grades.
(2) When purchasing materials and components, the Purchasing team
manager/Subcontracting & purchasing team manager shall select the suppliers
registered in the approved vendor list dependently on the records of suppliers‟
previously demonstrated capability and performance.
c) Acceptance of service
When the inspection is carried out by a third party, to accept or not shall be judged by
verifying the technical data produced.
[Related Procedure]
1. The procedure for subcontract management(CP-24-0005)
2. The procedure for subcontract management(new item)(CP-24-0006)
3. The procedure for evaluation control of suppliers(CP-24-0031)
4. The procedure for supplier registration(CP-24-0029)
d) A sticker shall be attached to the non-accepted product, and a report on nonconformity shall
be issued. The product shall be treated according to the procedure for nonconforming
product managements.
e) When commercial grade items are purchased, it shall be verified that requirements needed
to satisfy the design function are satisfying with the items that are commercially available.
f) For nuclear products, the requirements applied to the first purchase of product shall be
documented, or the related product manual or its duplication shall be maintained to facilitate
reordering.
[Related Procedure] The procedure for receiving inspection management(CE-34-0140)
7.5 Production and service provision
7.5.1 Control of production and service provision
Our company shall carry out production and service provision affecting on the quality under the
controlled conditions as below.
a) Availability of information describing the characteristics of the product
b) Availability of standards, as necessary
c) Use of suitable equipment
d) Availability and use of monitoring and measuring devices
e) Implementation of specified monitoring and measurement
f) Implementation of release to the customer, delivery and post-delivery activities
[Related Procedure]
1. The procedure for control of manufacturing facilities(CP-79-0001)
2. The procedure for measuring instrument management(CP-34-0002)
3. The procedure for independent inspection(each product)
7.5.2 Validation of processes for production and service provision
a) Our company refers a manufacturing defect such as the following that cannot be verified
before use as a special process and it shall be included in the control standard for general
processes and controlled specially.
(1) Welding
(2) Painting
(3) Heat treatment
(4) Compression
(5) Brazing
b) To demonstrate the ability of the processes to achieve planned results, the followings shall
be applied to confirm the validation.
(1) Defined criteria for review and approval of the processes
i) Traceability control
(1) In case that traceability is required on the contract or products requiring traceability are
produced, the objectives and methods to trace shall be specified so that traceability
control can be performed separately through all possible range.
j) Every control record of identification and traceability shall be maintained in the team in
charge.
[Related Procedure]
The procedure for item control and delivery(CP-25-0040)
c) For stock control, appropriate quantity shall be in hand, and the first stocked first delivered
basis shall be maintained.
d) Necessary actions to prevent parts, semi-products and products from damaging and
deterioration shall be taken.
e) To protect the product quality after the final inspection and test, the specified packaging and
handling method shall be maintained until delivered to the place designated by the customer.
f) To maintain the quality during transportation, transporting companies shall be evaluated and
selected.
[Related Procedure] 1. The procedure for material control(CE-24-0219)
2. The procedure for item control and delivery(CP-25-0040)
(2) If necessary, irregular audits can be carried out when significant changes occur to the
functional fields of quality system or when audit deficiency recurs after completion.
b) The yearly audit plan shall be reviewed by the Quality management team manager and
approved by the Plant manager.
[Core processes]
According to the results of data analysis, information on the followings shall be provided.
a) Customer satisfaction
b) Conformity to product requirements
c) Characteristics and trends of processes
d) Contribution of suppliers
8.5 Improvement
8.5.1 Continual improvement
The effectiveness of the quality management system shall be continuously improved through
the following activities.
a) Realization of quality policy
b) Control of quality objectives
c) Internal audit, customer audit and audit by authorized organization
d) Data analysis
e) Corrective and preventive action
f) Management review
[Related Procedure] 1. The procedure for management system audit(CP-34-0183)
2. The procedure for issuing & control of correcting management
(CP-34-0011)
8.5.2 Corrective action
a) When reviewing the report on nonconformity, concession, customer complaints and errors in
audit, and found corrective actions to be taken or serious problems affecting on the quality, a
member of the Quality assurance team shall issue the corrective action request.
b) When any potential cause that can be resulted in nonconformity is found, a member of the
Quality assurance team shall issue the corrective action request to prevent nonconformity in
advance.
c) Conditions affecting on the quality are as the followings.
(1) Process of product (or service), nonconformity at storage or handling, defect
(2) Nonconforming procedures and documents
(3) Nonconforming process control
(4) Wrong schedule
d) The following requirements are defined in documented procedures.
(1) Review of nonconformity (including complaints of customers)
(2) Determination of the cause of nonconformity
(3) Assessment of action‟s necessity in order to prevent reoccurrence
(4) Determination & implementation of necessary action
(5) Recording of the result of Actions taken
(6) Review of effectiveness of taken corrective action
[Related Procedure] 1. The procedure for issuing & control of correcting management
(CP-34-0011)
Section
Manufacture
Production control
Quality assurance
Purchasing
Subcontracting control
Human resources
Service
Design
Related standards
ISO requirements
Section
Production control
Manufactur
Quality assurance
Purchasing
Subcontracting control
Human resources
Service
Design
e
Related standards
ISO requirement
7 Product manufacturing
7.1 Planning of product manufacturing ○ ○ ◎ 24, 25
7.2 Customer-related process 44
Determination of requirements ◎ ◎ ○
7.2.1
related to the product 44
Review of requirements related ◎ ◎ ○
7.2.2
to the product 44
7.5.1 Control of production and service provision ○ 20, 21, 37, 38, 39, 40, 41, 42, 43
Validation of processes for
7.5.2
production and service provision
◎ ◎ 22, 26, 30, 31, 32, 33
8.1 General ○ ○ ○
8.2 Monitoring and measurement
8.2.1 Customer satisfaction ◎ ○ 18,19
8.2.2 Internal audit ◎ 3, 16
8.2.3 Monitoring and measurement of processes ○ ○ ◎ ○ ○ ○ ○ ○ ○ ○ ○ 24, 25, 28,
8.2.4 Monitoring and measurement of product ○ ◎ 23, 37, 38, 39, 40, 41, 42, 43
Section
Production control
Manufactur
Quality assurance
Purchasing
Subcontracting control
Human resources
Service
Design
Related standards
e
ISO requirements
1. The procedure for control of HICO standard (CP-34-0004) 27. The procedure for nonconforming product management
2. The procedure for control of documents (CP-14-0014) (CP-34-0009)
3. The procedure for quality auditor qualification (CP-34-0014) 28. The procedure for qualification and control of inspector
4. The procedure for control of Management manual (CP-34-0181) (CP-34-0155)
5. The procedure for control of quality records (CP-14-0013) 29. The procedure for receiving inspection management
6. The procedure for control of indoctrination of Changwon plant (CE-34-0140)
(CP-21-0024) 30. The procedure for qualification of heat treatment worker
7. The procedure for control of on the job training (CP-21-0029) (CP-34-0190)
8. The procedure for subcontract management (CP-24-0005) 31. The procedure for qualification of painting worker
9. The procedure for subcontract management(new item) (CP-34-0182)
(CP-24-0006) 32. The procedure for qualification of crimping worker
10. The procedure for control of purchasing(CE-24-0105) (CP-34-0147)
11. The procedure for evaluation control of suppliers (CP-24-0031) 33. The procedure for special process control (CP-34-0158)
12. The procedure for control of purchasing document 34. The procedure for issuing & control of correcting
(CP-24-0060) management (CP-34-0011)
13. The procedure for preparation of purchasing specification (CP- 35. The procedure for inspection, handling, storage and control of
86-0020) customer-supplied product (CE-34-0147)
14. The procedure for material control(CE-24-0219) 36. The procedure for qualification of field supervisor
15. The procedure for supplier registration(CP-24-0029) (CP-34-0184)
16. The procedure for management system audit(CP-34-0183) 37. The procedure for independent inspection
17. The procedure for item control and delivery (CP-25-0040) (Power Transformer)(CP-31-0231)
18. The procedure of service management for customer satisfaction 38. The procedure for independent inspection
(Power systems PU) (CP-38-0011) (Circuit breaker Mfg 1 team)(CP-31-0120)
19. The procedure for customer service management(Industrial 39. The procedure for independent inspection
Machinery PU) (CE-25-0401) (Circuit breaker Mfg 2 team)(CP-31-0111)
20. The procedure for control of manufacturing facilities 40. The procedure for independent inspection
(CP-79-0001) (Electrical panel Mfg team)(CP-31-0152)
21. The procedure for measuring instrument management 41. The procedure for independent inspection
(CP-34-0002) ( HV Motor Mfg team)(CP-34-0114)
22. The procedure for welder qualification (CP-34-0177) 42. The procedure for independent inspection
23. The procedure for forwarding inspection (CP-64-0001) (LV Motor Mfg 2 team)(CP-34-0135)
24. The procedure for inspection & test 43. The procedure for independent inspection
(Power systems PU) (CP-34-0056) (Foundry Mfg team)(CP-63-0014)
25. The procedure for inspection & test 44. The design manual (Manual of each product)
(Industrial Machinery PU) (CP-34-0138)
26. The procedure for qualification of brazing worker
(CP-34-0185)
Rev. No. : A
Instructions Manual for Erection,
TITLE
Installation, Operation, Maintenance Page. No : Cover
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-461-009
Rev. No. : A
Instructions Manual for Erection,
TITLE
Installation, Operation, Maintenance Page. No : 1 / 181
DISCIPLINE : PROCUREMENT
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
For Approval
REV.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
NO.
REV.
HYOSUNG PREPARATION CHECK REVIEW APPROVAL
NO.
INSTALLATION,
OPERATION & MAINTENANCE
MANUAL
D
Deessccrriippttiioonn Q’’ttyy
Q
The instructions and procedures included in this manual are intended to provide general guidance to
trained personnel, with experience and expertise in the safe and careful performance of their job.
These instructions and procedures cannot and does not cover all details of every task nor can it cover
all possible situations that may be encountered during the performance of the task.
The User is solely responsible for ensuring that all work is performed safely and without damage to the
transformer and accessories.
● Safety Notations
The following notations are used in this manual to alert the user to potential safety hazards
Table of Contents
Technical Data
Introduction
1.1 Introduction
1.2 Communication
1.3 Personal Protective Equipment (PPE)
1.4 Thought - Joggers for Mitigating Risks
Quality Issues
Equipment Required
Process Flowchart
Ambient Temperature Considerations
Ambient Humidity Considerations
Determining Required Heater Capacity
Pre-Processing Quality Check
5.1 Grounding
5.2 Dew Point Test
5.3 Pre-Processing Dry Out Process
5.4 Oil Acceptance
5.5 Ambient Temperature Check
5.6 Active Part Pre-Heat
5.7 Vacuum Leak Test
5.8 Processing Parameters
5.9 Processing After Short Term Storage
5.10 Vacuum Oil Filling Process
Technical Data
Applicable Standard
Electrical equipment covered by this specification will comply with the following standards.
Service Conditions
This transformer is suitable for operation under the following service conditions.
Ambient temperature
Maximum 38.0℃
Minimum -17.6℃
Altitude Up to 1000 m above sea level
1) Manufacturer HYOSUNG
2) Design standard IEC
3) Number of windings 2
4) Rated power, ONAN / ONAF, MVA 15 / 20
5) Rated frequency, Hz 50
6) Rated voltages
a) HV, kV 150
b) LV, kV 11
7) Vector group reference YNd1
8) Material of insulation (Thermal class A) Insulation paper
9) Type of cooling ONAN / ONAF
10) Winding temperature rise at average ambient 45
temperature of yearly average (20℃), ℃
11) Maximum hot spot temperature rise at average ambient
temperature of yearly average (20℃), ℃ 58
12) No load losses at rated voltage and ratio, kW 21
BUSHING
CURRENT TRANSFORMER
a) For instrument 5%
b) For protection 5%
39) Burden, VA
a) For instrument 12.5VA
b) For protection 30VA
EARTHING SWITCH
Accessory List
WINDING TEMPERATURE
5 INDICATOR MT-ST160F MESSKO(GERMANY)
OIL TEMPERATURE
6 INDICATOR MT-ST160W MESSKO(GERMANY)
REMOTE TAP
19 CONTROL PANEL - HYOSUNG(KOREA)
Painting
1. Liquid paint : Main tank, Conservator
Description Inside Outside
Introduction
Hyosung Industrial Company (HYOSUNG) is a leading and world-class supplier of power transformers
worldwide. Starting with the manufacture of its first 154kV high-voltage transformer in 1969, HYOSUNG
through its advance design, manufacturing and testing capabilities can supply high-quality transformers
through 765kV in both core-form and shell-form designs.
HYOSUNG designs transformers to meet ANSI, IEEE, IEC, JEC and every required national standard.
We also offer:
Oil Filled Reactors Distribution Transformers Compact SF6 Gas
SF6 Power Circuit SF6 Gas Insulated Insulated Switchgear
Breakers Switchgear SF6 Transformers
Changwon Plant
454-2 Nae-Dong, Changwon, Korea 641-712
Fax.+82-55-268-9839
Section 1
Safe Working Practices
These warnings apply to every part of this section and should be considered as applicable to each line
in this section.
1.1 Introduction:
Workers who use this manual should be trained by their company’s Safety organization in the
company’s Safe Working Practices. Workers who have not been trained in Safe Working Practices or
their company’s Safety Program, or companies without a Safety Program should delegate or contract
all work on this equipment to individuals or companies who have been properly trained. This
HYOSUNG manual is not intended to replace the user’s Safety Program or any policies of the user’s
Safety Program.
This section is provided to help remind trained, qualified workers of the risks that may be present when
working on power transformers, and to provide suggestions in some cases to mitigate those risks. This
manual cannot anticipate all conditions that might occur at every jobsite and must be used as a general
reference and not as a procedure for working safely. The contents of this section are presented as
“Thought Joggers” intended to help the user recognize the various risks associated with this type of
work.
Workers must follow all local, state and federal safety requirements and the user’s site-specific Safety
Program requirements. It is the User’s sole responsibility to be aware of all applicable requirements.
Failure to properly mitigate the risks associated with this type of work could result in serious injury or
death.
If your company does not have an OSHA-compliant Safety Program, contact HYOSUNG for no-cost
guidance on sources of Safety training and sources who can help your organization develop a Safety
Program.
1.2 Communication:
Communication is critically important when working with others. Every job should be thoroughly
discussed with the full crew before starting work to ensure that everyone understands the work that will
be performed by each worker and the risks associated with that work. When multiple crews are working
at a site, each crew leader should understand the scope of the other crews’ work as well. When
circumstances change, everyone who might be affected should be informed.
Every worker should have the proper PPE to protect them from all expected risks. The site or worker’s
Safety Co-ordinator should determine the risks that exist at the site and during the tasks performed by
the worker.
In addition to any special equipment that may be required, the following types of common PPE should
be available to the worker at all times, and used when needed.
The following sections are presented as “Thought-Joggers” to help the user determine the possible
risks in the tasks associated with receiving, installing, testing and maintaining the transformer. These
Thought-Joggers are questions and comments that will cover many of the common situations with this
type of work, and should be considered when the job is planned and discussed with the work crew
before the work begins. Thought-Joggers should help the user and the work crew to think through their
approach to performing their tasks safely and to recognize and mitigate any other potential risks that
may exist in performing their tasks.
o Is extreme weather expected? Work should not be performed during high winds, sleet
and hail, lightning, tornados, hurricanes and other extreme weather conditions
o Are ice or snow expected? Ice or snow can create slick roads and walking surfaces.
Workers need to adjust their work to such conditions.
Figure 1.1
(From USBR FIST 5-1)
Clamps A-I have jaws designed to attach to round surfaces like a substation bus or conductor. Clamps
J-M are designed for attaching to flat surfaces.
Transformer deliveries are heavy loads requiring special lifting and moving techniques and
equipment. Transformers should only be moved by people trained and qualified in heavy lifting and
rigging.
All heavy lifts or moves should have a Lifting Plan or a Moving Plan that considers the following
potential risks.
Underground pipes or other unseen hazards should be addressed.
o Are site drawings available to determine the locations of any underground hazards?
o Do steel plates or other devices need to be placed on the ground to better distribute
the weight of the crane, trailer or any loads?
o Are the ground, roadway and any bridges that may be travelled over all rated for the
expected loads?
Safe working clearances from energized lines and equipment must be maintained at all
times.
o Has the crane been properly grounded?
o Will the crane be operated near any energized busses or power lines? Workers
should maintain safe distances from the crane at all times if there is any risk of
contact.
Using cranes, jacks, cribbing, slings or hardware that are not rated for the load can cause
lifting accidents.
o Is the correct weight of the transformer and the crates known?
o Are the equipment, slings and hardware capable of safely lifting the transformer?
o If jacking and sliding will be performed:
Have the hydraulic jacks and hoses been inspected and verified to be in safe
operating condition?
Are the hydraulic jacks gang-operated?
Are gang-operated jacks equally rated with equal performance?
Has the controller been inspected and in safe operating condition?
Are the jacks located squarely below the transformer’s jacking pads?
Are the timbers or rollers in safe condition?
Is the connection point for pulling and sliding the transformer secure and
adequate for the load to be applied?
For the transformer or parts that will be lifted by crane:
Has the crane been inspected and verified that it is in good condition?
Has the angle of the boom been considered in the crane lifting capability?
Will the crane’s outriggers be fully extended and utilized during lifting?
Are the slings and rigging hardware adequately rated for the loads?
Have the angles of the attached slings been considered when
determining the sling and rigging ratings? Sling capabilities must be
de-rated when they are not used to lift loads in a strictly vertical
direction or when they are wrapped around loads rather than attached
to shackles. See Figure 1.2 for some examples. Consult your Safety
Program guidelines or contact HYOSUNG for more information.
Will the loads be properly lifted?
Are tag lines available for controlling the loads when lifted? All loads
should have a tag line attached to help control the location and
movement of the load during the lift.
Have the tops of the crates been set in-place and nailed down before
any crates are lifted? Crates can collapse if lifted without the cover in-
place.
The transformer tank must be connected to the site’s ground grid immediately after it is
placed onto the foundation.
o Is the station ground grid in place?
o Are the ground cables on-hand? If not, use personal protective grounds as a
temporary connection until the permanent cables can be installed.
All work requiring people to perform tasks inside the transformers should be done under the
user’s Confined Space procedures under their Safety Program. The workers should consider
the following possible risks:
o Have the Entrant and Attendant(s) been trained in their Confined Space procedures?
o Does the Attendant know how to contact emergency services, if required? Is a phone
available on-site?
o Is the air monitoring equipment OK to use? Has it been tested and calibrated? Does
it provide audible alarms or other signals if the safe gas levels for working inside the
transformer are not met?
o Was the transformer filled with Nitrogen before this starting this internal work? If the
transformer was filled with Nitrogen, the Nitrogen must be completely removed by
applying vacuum (we recommend down to 1 Torr for at least 30 minutes), then dry-air
can be added before starting ventilation with dry air. Simply ventilating with dry air
may not remove all of the nitrogen inside the transformer and unsafe areas could
exist inside the transformer that may not be detected with the gas monitor.
o Is the air safe to breathe? The transformer should be ventilated by adding dry air at a
sufficient flow rate to purge gasses from the transformer and maintain a sufficient
oxygen level while workers are inside. This can only be verified if a gas monitor is
used. Oxygen needs to be within the required maximum and minimum levels and CO
and CO2 must be below the maximum levels.
o Is the air at risk of fire or explosion? The gas monitor should also monitor explosive
gas levels (Lower Explosive Limit or LEL)
o Are dry-air cylinders being used to ventilate the transformer tank while the worker will
be inside the transformer? If so, it may be necessary to replace the cylinder when the
worker is inside the transformer and a third worker may be necessary for this task.
The Attendant cannot leave their post to replace the dry air cylinder while the worker
is inside the tank. A dry air generator can eliminate this problem.
Do the workers have appropriate clothing for the tasks? Loose clothing and jewelry around
moving parts like fans and motors can cause serious accidents. Fire Retardant (FR) clothing
may be required for some areas or tasks.
Are workers prepared to work in manlifts, on ladders or on top of the transformer?
o Have the workers been trained in manlift operation? Training should be performed in
accordance with the user’s Safety Program.
o Is the manlift properly grounded? Grounding should be performed in accordance with
the user’s Safety Program.
o Is the manlift the right size and rating for the job? The loads and equipment ratings
need to be known.
o Have the ladders been inspected? Ladder inspections should be performed in
accordance with the user’s Safety Program.
o Are the ladders the right type, size and rating for the job?
o Are all ladders properly tied off and secure?
o Is a rope or other system available near the ladder to allow workers to bring tools
and equipment to or from the transformer cover without carrying it as they climb the
ladder? Workers should avoid carrying equipment while climbing ladders.
o Is the transformer equipped with a fall restraint system or other connection points
approved by the user’s Safety Program?
o If a worker falls, will their PPE or other systems limit their fall to a safe distance?
Have workers been trained in the safe operation of all power tools and equipment to be
used on the job?
o Workers should be aware of pinch points and line of fire risks.
o Workers should wear the proper clothing and PPE for the tools and the task
Transformers are filled with hot oil under vacuum. This presents several potential environmental and
safety risks that the workers should consider.
The site should be adequately protected from oil spills during oil storage and handling.
o Are the workers aware of the site’s Spill Prevention Plan and the requirements under
the plan?
o Are berms or other protective devices required under the oil tanks or tankers?
o Are emergency spill kits, absorbents and pads available, if needed?
o Is the area around the tanks, tankers and transformer adequately secured and
protected from vehicles or equipment that could collide with the tanks, tankers or
transformer and cause an oil spill?
o Are all oil and vacuum hoses adequately protected from damage during the vacuum
and oil pumping processes?
Pumped oil can build up a considerable static charge. All equipment used in oil handling
must be properly grounded to bleed off the static charge and protect the site from fires and
explosions.
o Is the transformer tank properly grounded?
o Are all tanks, tankers, and oil processing trailers properly grounded before starting
any oil handling?
o Have all oil hoses been tested to ensure that the internal static wire is intact?
o Are the right types of fire extinguishers available and on-hand?
o Are all transformer bushings adequately grounded during oil filling? The tops of all
bushings should be connected to ground during oil filling. Standard copper mausing
wire is normally sufficient for this purpose.
All major parts of HYOSUNG transformer tanks are designed to withstand full vacuum.
Workers should understand that loads on any part of the transformer can increase the
mechanical stress beyond the designed limits and cause tank damage.
o Are all workers aware that they should stay off of the transformer, and any parts of
the transformer, when vacuum is applied?
o Are all toolboxes, test equipment and other heavy items, or any items that might
need to be retrieved removed from the transformer cover or other parts of the
transformer?
Testing
Transformers require both high-voltage and low-voltage testing. Both types of testing can present
safety risks.
Workers should consider the following:
The equipment users must understand how to safely operate all electrical test equipment before
use.
o Is the test equipment properly grounded according to the manufacturers’ instructions?
o Has the test equipment, including cables and test probes, been inspected before each
use?
o Will all meters and probes be used within their rated voltage or current limits? Meters
must not be used at voltage or current levels beyond their ratings. The voltage and
current rating should be listed on all electrical test equipment, or in the manufacturers’
instructions. This applies to meters, leads and test probes. Voltages greater than 480V
should never be measured directly with a handheld meter, but should be measured with
a proximity meter mounted on a hot stick.
Users must understand the hazards associated with testing power transformers
o Have the test equipment operators and assistants been trained in the safe operation of
their equipment?
o Will test voltages be transformed to unsafe levels by the transformer? AC test voltages
applied to low voltage transformer windings are transformed to higher voltages by the
transformer turns ratio. For example, applying a 10kV Doble test voltage to the XV
terminal of a 230/18kV GSU transformer can produce 128kV on the HV bushing
terminals. Safe working clearances must be maintained.
o Will DC test voltages be applied to the transformer? Transformers can hold a large
capacitive charge when DC test voltages are applied. DC test equipment must always
be discharged according to the manufacturers’ instructions before disconnecting the test
leads.
o Are all workers in the work area where test voltages are being applied aware of the risks
before starting the tests? Does the area around the testing need to be roped off?
o Is the transformer tank under vacuum? Testing should never be performed while the
transformer is under vacuum. A partial vacuum will flash over at a far lower voltage than
a transformer under atmospheric air pressure.
The transformer tank and all cabinets must be grounded at all times.
o Are the ground connections all visible and intact?
While HYOSUNG transformers have not experienced problems with static electrification,
conditions that could cause static electrification conditions should be avoided.
o Do the user’s operational procedures or the transformer’s cooling controls allow pumps
to run for long periods with the transformer de-energized?
To avoid the possibility of causing this problem, the controls for forced-oil cooling
should be designed to only switch pumps on after the transformer is energized.
The cooling control system on transformers with only forced oil cooling should be
designed to automatically switch on the first cooling stage when the transformer
is energized.
Running time should be limited to just a few minutes when testing oil pumps on
de-energized transformers.
Safe working clearances should be maintained at all times when the transformer is energized.
o Is any work required on or near the top of the transformer?
Never work on the transformer cover, or store tools or equipment on the
transformer cover when the transformer is energized at system voltages.
o Have any protective relays caused an alarm or a trip or are any unusual conditions
observed?
Are the responders aware of the various possible causes of alarms or trips? See
the Troubleshooting section 7.8 in this manual for guidance.
Do not approach the transformer until it is de-energized if the Buchholz relay,
Gas Accumulation Relay or Pressure Relief Device are in the alarm state.
Never Overload the transformer and exceed the highest Temperature given
specification.
Section 2
General Construction
HYOSUNG manufactures transformers in both core form and shell form construction.
The core is designed and constructed with high permeability, low loss cold-rolled non-aging silicon steel.
Each lamination is coated to insulate the sheets and reduce eddy current losses. The core is designed
with 3 or 5 legs, depending on the transformer design, operational requirements and shipping
dimension limits.
Core legs are held in place with fiberglass bands beneath the windings to withstand shipping impacts.
Upper and lower core yokes are held with stainless steel bands over fiberglass bands and connected
with an insulating buckle to provide maximum mechanical strength and eliminate circulating currents.
The complete core is supported by a structural steel core frame to provide structural rigidity for
withstand of short-circuit and transportation mechanical forces.
Each core steel sheet is precisely cut to size and shape using automated core cutting machines, then
hand stacked into an E-core as shown above, consisting of the legs and bottom yoke in a step-lap
configuration using overlapped mitered joints. The lower core frame and flitch plates are mounted to the
E-core before up-righting. The windings are then added to the E-core and the top yoke and frame are
installed.
The core is divided into sections with insulated ducts between sections for cooling. Sections are
connected in one place with sheet copper jumpers. The core is insulated from the core frame and
grounded through an external connection to provide a convenient test point.
All windings are designed and manufactured to withstand the electrical, mechanical and thermal
stresses of all types of faults and overvoltage conditions like lightning impulses and switching surges as
specified by IEEE Standards and customer specifications.
HYOSUNG’s winding rooms are controlled-access positive-pressure clean rooms designed to minimize
dust and other contaminants during the winding process. The winding rooms are equipped with both
horizontal and vertical winding machines to provide greater manufacturing flexibility.
Windings are designed and constructed with insulated copper conductors in rectangular or continuously
transposed cables. Winding conductors are crimped or welded to leads connecting the windings to
other windings, tap changers or bushings.
After the windings have been constructed, they are clamped and
dried under iso-static pressure to remove moisture from the insulation
and shrink the windings to their clamped, in-service height. The
individual windings are nested into a phase assembly as they are
placed onto each core leg then the leads and support structure are
added.
The windings are then clamped under pressure to the core frame and
the complete active part is dried using a vapor-phase process. After
the final vapor-phase process, all windings are re-compressed to their
designed values and all bolted connections are re-tightened.
Transformers rated 80 MVA and greater are typically equipped with
dash-pots to provide constant clamping pressure to the windings
under all conditions.
HYOSUNG Shell-Form transformers are designed and constructed with a form-fit design. The form-
fit design provides a compact and rigid construction with excellent short-circuit withstand strength,
excellent shipping impact withstand, superior dielectric characteristics, lower oil quantities, and
minimized losses. The form-fit design also provides greater flexibility in meeting special design
requirements such as dimensional tolerances or unusual impedances without sacrificing electrical or
mechanical strength due to the ability to interleave coil groups.
The windings are manufactured in a clean room. Each strand and layer of subdivided conductors is
spirally wrapped with several layers of narrow, high dielectric strength paper. The outermost layer
has a thermoset coating to bond the coils after clamping and drying and enhance mechanical
strength and rigidity during assembly. If the design calls for electrostatic shields, these are also
manufactured in a clean room. The coils are individually dried then connected together into a coil
phase assembly.
Pressboard sheets are formed into channels, washers and spacer block assemblies to direct the oil
flow and maintain electrical clearances. The spacer blocks are located in a precise pattern to align
them transversely throughout each phase. This ensures mechanical strength against short circuit
forces and prevents coil deflection in each coil. The complete phase assemblies including the
windings, oil ducts and shields are dried using a vapor-phase process then lowered into the form-fit
tank bottom and secured into place.
The upper and lower T-beams are installed through the coils and the core laminations are stacked
on fill blocks in and around the coil assemblies, using overlapped joints to increase mechanical
strength and minimize exciting current. The core is constructed of coated laminations of Hipersil, a
cold-rolled, grain-oriented, highly permeable annealed and non-aging silicon steel that can carry
one-third more flux per area than ordinary electrical steel.
The core sections within the coil openings are wedged at the top to compress the core and rigidly
hold the coil assembly in place. The areas between phases are also securely wedged in-place, top
fill blocks are secured in position and vertical wood pieces with pressboard channels are installed
between the top and bottom fill blocks.
When the form-fit top section with the end frames and side channels is installed over the lower
section with the core and coils, the entire transformer is formed into a rigid body that can withstand
shipping and short-circuit stresses. The coil assembly is held in compression by the end frames,
interphase wedges and rigid core
All HYOSUNG transformer tanks and conservator tanks are designed to withstand full vacuum. This
allows the transformer to be oil-filled completely under vacuum, eliminating oxygen and moisture from
the oil and extending the service-life of the transformer.
All gasket joints on the tank utilize rectangular or round o-ring gaskets with grooved flange faces to
provide an oil-tight and gas-tight seal. Gaskets in most areas are nitrile, Buna-n type rubber and
gaskets in higher temperature locations are Viton rubber. HYOSUNG’s gaskets should provide many
years of service before replacement is required.
The tank is generally provided with manholes to permit access into the transformer, if needed. The tank
is also equipped with jacking, lifting and pulling facilities for moving the transformer and is designed to
be lifted or moved without oil.
The tank may be provided with electro-static or flux shields on the tank walls to reduce stray losses.
These shields are grounded to the tank in one location.
HYOSUNG radiators are efficient cooling units designed for use on large transformers requiring a self-
cooling rating. The radiators are detachable and removed for shipment. Radiators are constructed on
stamped steel sheets, welded together to provide a large surface area and internal vertical paths for oil
circulation. Each radiator is equipped with lifting eyes for lifting the radiators during transformer
assembly as well as upper and lower threaded plugs for oil draining or venting. Larger transformers are
equipped with a radiator support structure to reduce mechanical stresses on the radiator piping joints.
Radiators can be equipped with fans to provide forced air cooling. All fans are supplied with OSHA-
compliant stainless steel fan guards. The fan assembly mounting bolts are welded to the outer radiator
in the group, eliminating the need for mounting clamps which can damage radiators and lead to rust
problems.
Heat Exchangers from various suppliers are used on HYOSUNG transformers when forced oil cooling
ratings are required. Heat exchangers require oil pumps to circulate the oil through the cooling tubes.
Fans are also required to force air across the cooling tubes for effective heat removal. Heat
exchangers can be supplied with aluminum, steel or copper tubes and fins depending on customer
requirements.
Heat Exchangers are also equipped with a support structure to reduce mechanical stresses on the
pump and oil piping joints.
Unless the transformer is specified to use a nitrogen blanket or sealed tank oil preservation system,
HYOSUNG will provide a conservator with diaphragm type oil preservation system.
HYOSUNG’s conservator with diaphragm oil preservation system serves as an oil expansion tank and
utilizes a Buna-n or similar rubber bladder to completely isolate the oil from the atmosphere while
holding the oil at a constant pressure as the oil to increases or decreases in volume with increases or
decreases in oil temperature due to load and ambient temperature variations. The outside of the
bladder is in contact with the oil and the inside is in contact with the air. The bladder contracts and
expands with increases or decreases in the oil volume and as it changes, the air moving into or out
from the bladder passes through a dessicant breather to maintain a low moisture level in the air and
bladder.
By preventing exposure of the oil to air, the oxygen and moisture content of the oil can be maintained at
low levels, greatly reducing sludging and acidification of the oil and resulting accelerated aging of the
transformer insulation.
The round conservator tank is equipped with valves that permit the vacuum pressure inside and outside
the bladder to be equalized during vacuum processing, eliminating damage to the bladder. The tank is
also equipped with an oil level gauge that is oriented for easy viewing from ground level.
The conservator tank is also equipped with a drain valve and a vent cock. The vent cock is used to
vent the small amount of nitrogen gas introduced during the last stage of oil filling. The inside of the
conservator tank is equipped with a guard structure that holds the bladder away from the vent cock or
vacuum valve during oil processing and filling.
All HYOSUNG transformers are thoroughly dried out, flushed and impregnated at the factory.
HYOSUNG’s field oil processing and filling procedures do not require costly oil circulations under most
conditions, saving several days of processing time and thousands of dollars in installation costs.
Section 3
Shipment, Receipt and Storage
The transformers are normally shipped without oil. During shipping, the tank is filled with dry air. A
pressure gauge and stop valve are provided to enable the pressure of the inert gas within the tank to
be read upon receipt.
The transformer should arrive with positive pressure, indicating that moisture did not enter the
transformer during shipping. The dry air inside the tank is tested for dewpoint to determine the
insulation moisture level. See the next section, Receiving Transformer and Accessories, for specific
details.
All opening for transformer components, e.g. bushings which have been removed from the
transformer during transport, are covered by means of blanking off plates. All parts are carefully
packed for transport in such a manner that they are protected against mechanical injury and injurious
effect of climatic conditions encountered during transit to their destination, as well as during long
storage before erection.
HYOSUNG designs transformers to withstand a 3G impact in all three directions and mounts an
impact recorder on each transformer during delivery, but any impact of 3G or greater must be
reported immediately to HYOSUNG. Impact recorders are calibrated to ensure accurate data. The
direction of each axis is a function of the mounting of the impact recorder and should be visually
verified one each impact recorder before it is removed from the transformer. The time recorded on
the impact recorder will be Korean time, not local time. Any efforts to match recorded impacts with
the location of the transformer will need to make this time adjustment.
Parts can be damaged or lost during shipping. Following the steps in this section will help to identify
any such parts so they can be repaired or replaced as soon as possible.
Equipment Required:
Packing List
Crowbar, hammer, nails, wrenches and screwdrivers
Digital camera
Dew point tester
1000V megger
Software and connecting cable for impact recorder (if an electronic recorder is used)
1. Check pressure on unit with pressure-vacuum gauge. If zero reading, purge with dry air and
check for leaks. Note that pressure varies with temperature, and this factor should be
considered.
2. Check percent moisture content in transformer. It should never exceed dew point in Figure 3.1.
WORK INSIDE THE TRANSFORMER REQUIRES A CONFINED SPACE PERMIT AND MUST
BE PERFORMED IN ACCORDANCE WITH OSHA REQUIREMENTS.
4. Check de-energized tap changer alignments and contacts with nameplate. Check for shifting of
core and coils, and check for breakage, loose or lost bolts, nuts, etc.
5. Measure the exciting current on each HV winding.
6. Make ratio test on all windings and taps. All windings and taps should check within 0.5%.
7. Check winding continuity and resistance if unit is off ratio.
8. After filling with oil make Megger test on insulation resistance. HV to XV and Ground, XV to HV
and Ground, and HV and XV to Ground. Coils should be under oil for comparison with factory
test measurements.
9. If core yoke shows signs of shifting, disconnect core ground bushing and end frame ground
bushing from tank cover and test end frames to core with 1000 volt Megger. This might happen
when unit has been subjected to severe shocks in transit by carrier.(Minimum acceptable values
are 50 mega-ohms.)
A HYOSUNG Shipment Inspection report form must be filled in and e-mailed to HYOSUNG. All
sections, lines and boxes on the form must be filled in completely. Enter N/A if any areas do not apply.
Contact HYOSUNG if you do not have a copy of the form.
DEWPOINT TEST
1. Measure internal tank temperature and measure the Dew Point temperature of the air inside the
tank.
2. Use Figure 3.1 for pressure between 0 and 5 PSI
3. Use upper and left axes for temperatures recorded in Celsius, use the lower and right axes for
temperatures recorded in Fahrenheit.
1. Verify that all crates, pallets and components listed on the packing list have been
received and check off the appropriate box on the Shipment Inspection Report. Check
all crates and pallets for external damage. Photograph any suspected areas and report
on the Shipment Inspection Report.
2. Open each crate and verify contents against the packing list. Look for water intrusion
or damaged components. Photograph any damaged parts and record missing parts
and damaged parts on the Shipment Inspection Report.
3. Locate the Instruction Manual. It should be in the main control cabinet or in one of the
crates. If not found, call HYOSUNG.
4. Check bushing crates to verify that all internal supports are in place and undamaged.
Verify that crates are roughly level and that all oil filled bushings inside each crate are
inclined with the top oil reservoir elevated. Verify that all bushing stud connectors have
been delivered. Record missing parts and record and photograph any damaged parts.
5. Check lightning arresters to verify that porcelain is not damaged and that all arrester
sections and grading rings have been delivered. Record missing parts and record and
photograph any damaged parts.
6. Check radiators for any signs of damage including dents on plates or edges, paint
damage or missing blanking plates. Record missing parts and record and photograph
any damaged parts.
7. Check all piping sections. Record missing parts and record and photograph any
damaged parts.
8. Check the main control cabinet and any other cabinets provided on the order. Check to
verify that the cabinet is not damaged and all internal components are in-place and
undamaged. Record missing parts and record and photograph any damaged parts.
9. A claim should be filed immediately with the carrier if any missing parts suspected
damage are found.
10. Review the results with the customer. E-mail the Shipment Inspection report, photos,
and other information on any missing or damaged parts to HYOSUNG .
Impact Recorder
Note that impacts recorded by the impact recorder are only an indication of possible damage and not
conclusive evidence that shipping damage or even impacts have occurred. Impact recorders may
record impacts if the impact recorder is accidently kicked by a rigger, if rigging comes in contact with
the recorder, or under similar circumstances. The transformer may also withstand impacts well beyond
3G’s without any damage. The determination of damage can only be made following testing and/or an
internal inspection.
Examination
After the transformer is moved on the pad in the site, its arriving time should be recorded and the
impact recorder data should be examined.
Notification
The recorder is part of the shipment. If it is missing or damaged, the seal broken, or has been disturbed
in any way, a specific carrier's inspection report must be issued by the carrier, to relieve the customer
of responsibility for the recorder.
Examine the recorder in the presence of the carrier's agent. Both the carrier and customer personnel
must check when impacts are recorded in zone B or above.
If impacts are recorded in zone B or above, the customer should notify a HYOSUNG representative (if
one is not present at that time) for advice.
Most types of impact recorders have axis or direction marks on them that correspond to the axis or
direction as recorded on the strip chart or electronic file. The impact recorder should normally be
mounted on the transformer with the orientation of the impact recorder axes as shown below to match
the axes on the transformer.
Vertical or Z-Axis
It must be noted, that in some cases the impact recorder may not be oriented as shown in the photo
above. In these cases, the axes indicated on the strip chart or electronic report will not correspond to
the same axes on the transformer and all impact directions must be adjusted accordingly.
Impacts
Zone-A
Zone-B
The G-range of this zone is between 3G and 6G, including 6G.
Damage may occur in this zone, particularly when impacts greater than 5G have occurred.
The following checks and tests should be performed.
Exciting current
Ratio test
Insulation resistance test
Bushing Current Transformer tests
Functional test for all protective devices
FRA test (If required)
Zone-C
The G-range of this zone is greater than 6G.
Damage may occur in this zone. The same checks and tests listed under Zone-B should be
performed.
Figure
X Y Z
5 10 PM
AM
9 PM
4
8 PM
AM
7 PM
3
6 PM
AM
Zone B Zone B
Zone B
The Shocklog RD298 model impact recorder is battery powered and records impacts in all three
directions. If any significant impacts have occurred during shipment, a blinking red LED will indicate
an alarm condition. The detailed data must be downloaded with a special data cable onto a PC with
Shocklog software loaded. HYOSUNG’s field service engineers are equipped with the necessary
cable and software.
The Lat-Lon DPU model impact recorder is solar powered with a battery backup and transmits GPS
location and travel speed and records of any impacts. The data is continuously updated and available
at the Lat-lon website so no special cables or software are required. The data from these recorders are
monitored daily by the HYOSUNG logistics team.
Note that the X, Y and Z axes are not labeled on the Lat-lon DPU. See the photo below for the
orientation of the axes.
The GPS and communications do not work when the transformer is stored inside an ocean vessel.
Y-Axis
X-Axis
Z-Axis
TRANSFORMERS MUST BE MOVED IN THE UPRIGHT POSITION UNLESS THE UNIT WAS
DESIGNED FOR HORIZONTAL SHIPMENT. THE OUTLINE DRAWING AND THE EXTERNAL
ASSEMBLY DRAWINGS SHOW THE POINTS FOR LIFTING, JACKING OR PULLING THE
TRANSFORMER. NEVER ATTEMPT TO LIFT OR MOVE A TRANSFORMER FROM ANY PART
OTHER THAN THE FACILITIES PROVIDED FOR THAT PURPOSE.
Note the transformer base diagram on the outline drawing and be certain the foundation pad
and piers support the transformer in the designated areas. In some instances a separate base
diagram is supplied and it will be included in the instruction book.
The transformer must be positioned so that adequate air circulation is provided to cool the
transformer.
HYOSUNG’s standard design provides for lifting and pulling the transformer in the shipping
configuration, without oil. If the transformer must be relocated after assembly and oil filling, the
oil must be drained before the transformer is moved. Failure to drain the oil before moving
may result in structural damage.
HYOSUNG does not recommend moving a transformer with any accessories mounted with or
without oil. Such a move is made at the owner’s risk and any damage as a result is not
covered under the warranty.
If the transformer will not be assembled immediately, the following steps should be taken:
Locate the accessories in a secure area where theft is not a concern
Reclose all crates. Replace any plastic covers, place all hardware back into original
containers, nail the crate covers back on. Photograph the reclosed crates.
Ensure that all parts susceptible to rain, ice or wind damage are properly stowed.
Electronic components such as monitoring devices should be stored indoors. Record
the storage location of any parts stored in other areas.
Add dry air to the main tank to 2-3 psi, if pressure is less than 2psi. Photograph the
pressure gauge.
E-mail the information and photos to HYOSUNG . Call the phone number listed in the
Introduction Section for the correct e-mail address for your transformer.
If the transformer will not be oil-filled within 90 days after leaving the factory, the appropriate
HYOSUNG procedure, as listed below, must be followed.
NOTE THAT ALL TRANSFORMERS THAT HAVE BEEN STORED BEYOND 90 DAYS AFTER
THE EX-FACTORY DATE REQUIRE ADDITIONAL OIL PROCESSING. THE OIL
PROCESSING REQUIREMENTS FOR STORED TRANSFORMERS ARE LISTED IN THE OIL
PROCESSING AND FILLING SECTION OF THIS MANUAL.
If the transformer cannot be installed immediately upon arrival and oil filling is impractical, it is possible
to store some transformers under a positive dry air pressure. The maximum length of time under this
storage method is dependent on the transformer kV class as follows.
The transformer pressure and cylinder pressure should be recorded every day for the first two weeks.
These reading should preferably be taken at approximately the same time every day and the time and
temperature also noted on the log.
After two weeks of daily logging, the pressure readings may be reduced to once every seven days.
An accurate log is important as it may be the determining factor in any decisions that may have to be
made on further drying of the windings.
If the transformer must be stored longer than the limit for Short Term Storage, a Medium Term Storage
can be performed with partial oil filling.
At the end of the storage period, samples of oil must be drawn from the bottom of the transformer and
from the tap changer compartments and tested for electrical strength, power factor and water content.
If the transformer is equipped with pumps, operate one half of the pumps for 30 minutes and then
operate the other half for 30 minutes. Repeat this operation every three months during the storage
period.
If the transformer must be stored for longer than one year after the ex-factory shipping date, all oil filled
components must be mounted and the transformer must be fully oil filled.
Section 4
Installation and Assembly
WORK INSIDE THE TRANSFORMER REQUIRES A CONFINED SPACE PERMIT AND MUST
BE PERFORMED IN ACCORDANCE WITH OSHA REQUIREMENTS.
IF THE TRANSFORMER WAS FILLED WITH NITROGEN GAS, THE NITROGEN MUST BE
REMOVED BY APPLYING VACUUM AT 1 TORR FOR 1 HOUR OR LONGER, BEFORE
BREAKING VACUUM AND REFILLING WITH DRY-AIR AND VENTILLATING THE TANK
4.1 Required Tools and Equipment (See the Safe Working Practices Section for PPE requirements)
The tools and equipment listed below are not supplied by HYOSUNG with the transformer, and must be
supplied by the installation and testing crews.
Carefully move the transformer into the correct position on the substation pad and make certain that
the base is flat and level. Install shims under the base for leveling if necessary.
The transformer tank must be connected to a secure ground before any work is done in or on the
transformer.
An internal inspection should be performed by the HYOSUNG Field Service Engineer or HYOSUNG’s
contractor. If the customer performs the inspection, the inspection should be performed by an
engineer who has been trained in performing transformer inspections. The Engineer will check for any
signs of movement or damage during shipping.
The internal inspection is a Confined Space entry and must be performed in accordance with OSHA
and all other applicable regulations and requirements. See the Safe Working Practices section.
When you open a transformer, take precautions to prevent moisture or dirt entering the transformer or
moisture condensing in the transformer. Always observe these precautions:
Never break vacuum with atmospheric air, always use dry air or dry nitrogen.
4.4.2 Weather
Do not open the transformer or leave it open during rapidly changing weather conditions unless
the opening is completely protected from weather.
Do not open the transformer if the relative humidity is greater than 85%.
Do not work inside the transformer if moisture is condensing on the inside of the tank.
4.4.3 Clothing
Never enter a transformer with dirty or wet clothing. Clean cloth shoe covers or nitrile rubber
overshoes must be worn.
Dry air must be used to ventilate the inside of the tank when it is opened for internal fitting or for
inspection. These restrictions must also be followed:
a. The dry air must have a dew point not higher than -58°F (-50℃).
b. Purge all air hoses with dry air to remove all moisture and dirt prior to
use.
c. Use a pressure regulator to control the pressure of the incoming air.
d. Dry air should be blown into the transformer below the working level to
maintain flow of air out through the cover opening. Air hoses may be
taken into the transformer if they are clean, dry and made from an oil-
proof material.
d. The dry air flow rate should be adjusted to maintain continuous airflow
outward through the tank openings. To conserve dry air and prevent the
entrance of dirt and moisture, place a light cover of plywood, hardboard,
or plastic over the manhole opening. The work should be performed in a
sequence such that when accessories such as bushings are being
installed, only one opening other than the manhole will be open at any
time.
a. Remove all the tools and working material from the transformer.
b. Continue to purge the transformer tank with dry air for 30 minutes after all the
material has been removed.
c. Seal the tank and pressurize it with dry air to 3 PSI.
d. If the next work period and re-opening of the transformer will not occur within
three days, we recommend after sealing the tank, that you pull vacuum on
the transformer to an absolute pressure of 2 torr or less and hold this level
for 4 hours. Break the vacuum with dry air and pressurize the tank to 3 PSI.
Equipment Required:
Calibrated torque wrench
Assorted sockets and crows foot wrenches
Nickel or nickel/graphite anti-seize compound for stainless steel nuts and bolts such as
Chesterton 725 or Loctite Nickel Anti-Seize with application brush
Electrical contact oxide removing grease such as Sanchem NO-OX-ID and clean rags
Procedure:
Nuts and Bolts That Require Torquing with a Calibrated Torque Wrench:
All current carrying connections must be torqued to their required torque values, as listed in the Tables
in Section 4.7, using a calibrated torque wrench. This includes all bottom bushing connection nuts and
bolts, all bushing stud connector hardware, all bushing terminal connector to cable connections, and all
ground cable connection nuts and bolts. This also includes the top terminal of ABB draw lead bushings
and the draw lead jam nut of and top terminal of PCore draw lead bushings (or similar bushing
components if required by other bushing manufacturer).
Conservator support structure bolts must also be torqued to their required torque values using a
calibrated torque wrench.
Special Case – Qualitrol Pressure Relief Device: Qualitrol Series 208 Pressure Relief Devices are
supplied with ½” mounting bolts to attach the cast iron base of the device to the transformer. This may
be changed to M12 bolts by HYOSUNG. These mounting bolts, whether steel or stainless steel, should
be torqued to 30.4 ft-lbs, and a flat washer must be used between the flange and the bolt head or nut.
Applying torque greater than 30.4 ft-lbs, or failure to use a flat washer could cause the cast iron flange
to crack and require the device to be replaced at the installer’s expense.
Special Cases – Bushing and LTC manufacturers specify the torque values for the mounting bolts and
for some current-carrying connections. The manufacturers’ torque values supersede any HYOSUNG
values listed in the Tables in this section.
Note: Any torque values listed in component manufacturers’ bulletins included with this manual
supersede the HYOSUNG standard torque values in this Section for those components.
Cleaning:
All current-carrying surfaces must be cleaned and coated with electrical contact grease to remove all
oxides from the surfaces and protect the surfaces from future oxidation before they are bolted and
connected together.
Thread Lubricants:
All galvanized steel, bronze or brass threaded connections must be made without any thread lubrication.
All external stainless steel threaded connections must be made using a nickel/graphite anti-seize
compound on the threads to prevent galling. All stainless steel threaded connections inside the
transformer and under oil must be made without any anti-seize compound.
Standard Connections:
Spring/Belleville Washer Connections: When connecting flanges or other joints with Spring/Belleville
washers, the connection should be made as shown below. A flat washer must be provided under the
bolt head. The Spring/Belleville washer must have a flat washer between the Spring/Belleville washer
and the flange or other surface to protect the surface from damage. In case of using the Double nuts,
the connection should be made shown below. Lower nut must have a Spring/Belleville washer between
the Lower nut and the flange or other surface. The bolt length must be long enough to provide at least
one full thread beyond the outer end of the nut.
Flat
washer
The minimum length of engagement, X, of the bolt
into the threaded hole should be at least 1 times the
Spring / Belleville diameter of the bolt. The blind hole, Y, should be at
X washer least 0.3 times the diameter of the bolt. Additional
flat washers and Spring/Belleville may be used, if
needed, to meet these requirements.
Table 4.1 applies to galvanized steel, SAE Grade 5 and Stainless Steel Type 304 nuts and bolts through
an un-threaded hole in Steel, Stainless Steel, Copper or Aluminum base material
TABLE 4.1
Galvanized SAE Grade 5 and Stainless Steel Type 304 Hardware
Unthreaded Steel. Stainless Steel, Copper or Aluminum Base Material
Torque in FT-LBS
IN-LB values listed in parenthesis for FT-LB values <20
Table 4.2 applies to Silicon-Bronze and Brass nuts and bolts through an un-threaded hole in Steel,
Stainless Steel, Copper or Aluminum base material.
TABLE 4.2
Brass and Silicon-Bronze Hardware
Unthreaded Steel, Stainless Steel, Copper of Aluminum Base Material
Torque in FT-LBS
IN-LB values listed in parenthesis for FT-LB values <20
Table 4.3 applies to Brass and Silicon-Bronze nuts and bolts through threaded copper or aluminum
base material
TABLE 4.3
Brass and Silicon-Bronze Hardware
Threaded Copper or Aluminum Base Material
Torque in FT-LBS
IN-LB values listed in parenthesis for FT-LB values <20
Copper Aluminum
Base Material (With Threaded (With Threaded
hole) hole)
Bolt Size Torque in FT-LBS (IN-LBS)
M6 1 (12) 0.4 (4.8)
M8 2 (24) 1 (12)
M10 5 (60) 2 (24)
M12 8 (96) 4 (48)
M12 8 (96) 4 (48)
M14 13 (156) 6 (72)
M16 21 9 (108)
M18 29 12 (144)
M20 41 17 (204)
M24 71 30
M30 141 59
M39 318 130
M42 394 163
M48 593 246
Table 4.4 applies to galvanized steel, SAE Grade 5 and Stainless Steel Type 304 nuts and bolts through
an un-threaded hole in Steel, Stainless Steel, Copper or Aluminum base material. Torque values are in
kgf-cm.
TABLE 4.4
Galvanized SAE Grade 5 and Stainless Steel Type 304 Hardware
Unthreaded Steel. Stainless Steel, Copper or Aluminum Base Material
Torque in N-m and kgf-cm
Table 4.5 applies to Silicon-Bronze and Brass nuts and bolts through an un-threaded hole in Steel,
Stainless Steel, Copper or Aluminum base material.
TABLE 4.5
Brass and Silicon-Bronze Hardware
Unthreaded Steel, Stainless Steel, Copper of Aluminum Base Material
Torque in N-m and kgf-cm
Table 4.6 applies to Brass and Silicon-Bronze nuts and bolts through threaded copper or aluminum
base material
TABLE 4.6
Brass and Silicon Bronze Hardware
Threaded Copper or Aluminum Base Material
Torque in N-m and kgf-cm
Copper Aluminum
Base Material (With Threaded hole) (With Threaded hole)
Non-Lubricated Non-Lubricated
Torque Torque
Bolt Size
N-m kgf-cm N-m kgf-cm
M6 1 14 0 5
M8 3 34 1 14
M10 6 65 3 28
M12 11 115 5 49
M12 11 115 5 49
M14 18 185 8 78
M16 28 290 12 120
M18 39 400 16 165
M20 56 570 23 235
M24 96 980 40 410
M30 191 1950 79 810
M39 431 4400 176 1800
M42 534 5450 221 2250
M48 804 8200 333 3400
Table 4.7
Dimension(mm) C
Standard
Bolt &
Nut Hex-Bolt Hex-Nut
A B C A B
B
M6 11.5 10 6 11.5 10
M8 15 13 8 15 13
M10 19.6 17 10 19.6 17
M12 21.9 19 12 21.9 19
M14 25.4 22 14 25.4 22
A
M16 27.7 24 16 27.7 24
M18 31.2 27 18 31.2 27
M20 34.6 30 20 34.6 30 Figure 4.1 Hex-bolt
M22 37 32 22 37 32
M24 41.6 36 24 41.6 36
M27 47.3 41 27 47.3 41
M30 53.1 46 30 53.1 46
M33 57.7 50 33 57.7 50
M36 63.5 55 36 63.5 55 B
M39 69.3 60 39 69.3 60
M42 75 65 42 75 65
M45 80.8 70 45 80.8 70
M48 86.5 75 48 86.5 75 A
M52 92.4 80 52 92.4 80
M56 98.1 85 56 98.1 85
M60 104 90 60 104 90 Figure 4.2 Hex-nut
M64 110 95 64 110 95
M68 115 100 68 115 100
DO NOT ATTEMPT TO OPERATE THE PUMP VALVES WHEN THE PUMPS ARE IN
OPERATION. ALWAYS SHUT OFF THE PUMP MOTOR BEFORE OPENING OR CLOSING ANY
VALVES. FAILURE TO FOLLOW THESE PRECAUTIONS MAY CAUSE EQUIPMENT DAMAGE
AND PERSONAL INJURY.
WORK INSIDE THE TRANSFORMER REQUIRES A CONFINED SPACE PERMIT AND MUST
BE PERFORMED IN ACCORDANCE WITH OSHA REQUIREMENTS.
IF THE TRANSFORMER WAS FILLED WITH NITROGEN GAS, THE NITROGEN MUST BE
REMOVED BY APPLYING VACUUM AT 1 TORR FOR 1 HOUR OR LONGER, BEFORE
BREAKING VACUUM AND REFILLING WITH DRY-AIR AND VENTILLATING THE TANK
This procedure applies to the on-site assembly of all new oil-filled transformers. Many of the tasks
listed below are covered in detail in various HYOSUNG procedures and all work must be done in
conformance with those procedures. This procedure only covers the recommended order for
performing the tasks.
After the transformer tank has been placed on the foundation in the final location, and all parts have
been inventoried, inspected and verified as clean and dry, the transformer assembly should be
performed in the following general order. The exact order of assembly should always be determined
by the installation crew leader, and can be modified as long as safety is not compromised, equipment is
not at risk and test results will not be adversely affected.
Grounding:
The tank ground should be connected to the site’s ground grid, or other secure ground point as soon as
possible after the transformer is placed on the foundation. This is a safety issue and must be done
before any other work is done on the transformer.
Preliminary Tests:
It is recommended that the CT’s be pre-tested before the transformer is assembled and filled with oil. A
full series of ratio, polarity, insulation and excitation tests on each CT will ensure that the correct CT is
installed in the turret properly and that no shipping damage has occurred.
It is also recommended that any bushings showing any signs of shipping damage such as crate
damage or shifted porcelain be tested before the transformer is filled with oil.
Performing these tests before the transformer is filled with oil will minimize the cost and impact of any
problem.
Assembly:
The optimal order of assembly for the major components varies by transformer design and should be
evaluated by the HYOSUNG field service engineer or supervisor on the assembly crew, considering all
of the following issues:
If the transformer was shipped by barge or exposed to salt spray or other corrosive contaminants
during shipping, the transformer tank and all conduits and parts that were exposed must be washed
with a pressure washer before assembly can start. If the site is an energized substation, it may be
necessary to perform this pressure washing before bringing the transformer into the station if the work
cannot be performed safely. Any crates with components found to have moisture intrusion during
shipping must also be pressure washed to remove any corrosive contaminants.
The conservator support structure must be installed and all bolts torqued before the conservator or
conservator piping can be attached. The conservator should be loosely bolted to the conservator
support structure before the conservator piping (including the Buchholz relay, if equipped) is installed
and the conservator position must be adjusted using the slotted holes to align the piping, if the mis-
alignment is greater than 1/8” in any direction, before bolting the piping together and torquing the bolts
that hold the conservator in place.
The turrets must be installed before the bushings or gas collection piping are installed.
If any gas collection piping or conduits, or any LTC operating shafts are designed to be routed over any
manhole or handhole covers, all internal work through these manholes or handholes should be
performed before the piping, conduits or operating shafts are installed, to avoid later partial disassembly.
All cabinets or conduits that were removed for shipping, and are located behind radiators must be
installed before the radiators.
All bushings that are bottom-connected through handholes on the tank wall behind radiators must be
installed and connected internally before the radiators are installed.
Any bushings that require lower corona shields should be measured and evaluated before assembly to
verify whether the bushing can be installed from the top of the turret with the shield attached or whether
the shield must be connected internally after the bushing is mounted in the turret. Bushing shields must
be placed around the conductor or mounted to the bushing bottom before connecting the bushing.
All bushings that require the draw-lead nut or top terminal to be torque to manufacturers’ specified
values must be torque before installing any bushing stud connectors or neutral ground bus connections,
or before testing.
The installation of all radiator or heat exchanger support structures and cooling piping and pumps (if
equipped) must be co-ordinated with the installation of the radiators or heat exchangers to prevent
radiator piping and components from being exposed to excessive mechanical stresses during or after
assembly. If a complicated support system is provided, consult with HYOSUNG before starting the
assembly if a HYOSUNG field service engineer is not on-site.
All arrester support structures must be installed after the radiators or heat exchangers if they are
mounted directly above the radiators or heat exchangers.
Bus or cable connections to neutral bushings should be measured and placed in the proper position,
but final connection to the bushing can be delayed until after commissioning tests are completed.
All accessories such are relays, pressure relief devices, gauges and temperature controllers should be
installed after the risk of damage from installing other components has passed. All wiring to these
components should be tested for insulation strength at 500Vdc before the wiring is terminated at the
devices.
All internal and external cabinet grounds and lightning arrester grounds must be connected before
testing the accessories or wiring.
If the transformer is equipped with pumps, the pumps must not be energized before the transformer
and oil piping is filled with oil.
If the transformer is equipped with a LTC, the LTC must be manually operated over the full range of
taps to verify correct position indication and correct operation of limit switches before operating power
can be connected to the LTC. The LTC cannot be operated electrically before all manual tests are
completed and correct operation is verified, and the LTC cannot be operated electrically or tested
before the transformer and LTC are filled with oil.
If the transformer is equipped with an LTC with an oil filtration system, the filtration system operation
must be thoroughly tested and the filter tank and piping must be filled with oil before any electrical
testing is performed on the filter system or LTC.
The transformer must be filled with oil only after all major components and accessories that cannot be
installed or replaced without removing the oil have been installed.
All bolted connections requiring torques with a calibrated torque wrench, must be torque to the required
value when the connection is first made, and again as a final torque before releasing the transformer for
service.
Bushing stud connectors must be installed after all tests are completed. All connections must be
torque after installation
The transformer must be thoroughly checked for oil leaks after testing is complete.
The transformer and work area must be cleaned and all debris disposed of properly.
X X
Note that the center of the gasket should be approximately in the center of the of the gasket groove.
There must be some practical tolerance for these dimensions, but for flat o-ring gaskets the cross-
sectional area of the gasket (a x b) must be at least as large as the cross-sectional area of the gasket
groove and should be no more than 15% larger. The gasket height should be between 1.25 and 1.75
times the gasket groove depth. Round o-rings should fit in the groove with minimal stretching and the
gasket cross sectional diameter should be between 1.2 and 1.4 times the gasket groove depth.
Gaskets are normally buna-n material, or nitrile with a 70 Durometer value. Viton gaskets may also be
used in higher temperature areas. Gaskets should be coated lightly with Vaseline or a similar product
before installing
Gaskets on vertical flange faces may require a small amount of glue to secure them during assembly.
Other bushing manufactures can have similar torque requirements for current-carrying connections. If
the torque values are not included in the manufacturer’s instruction leaflet or manual, contact
HYOSUNG for guidance.
Failure to properly torque current-carrying parts on bushings can lead to equipment damage, outages
and can void the warranty.
Bushings with glass bowl oil level gauges do not require any special mounting orientation.
Bushings that are mounted horizontally and equipped with an oil level gauge should have the bushing
oriented to facilitate viewing of the gauge from ground level.
Bushings that are mounted on an angle and equipped with a sight glass in the head of the bushing
must have the bushing oriented as shown below so the oil level gauge will provide the correct reading.
Bushings with oil level gauges should be mounted similarly, but the oil level may read slightly high or
low when mounted on an angle.
Bushings mounted on compound angles will require slightly different orientation to properly locate the
oil level gauge. A level placed on the face of the gauge should read level when the bushing is rotated to
the correct mounting position.
Oil Level
Level
Reads
Low
Oil Level
Level
Reads
High
Radiators are easily damaged if they are not lifted properly. Never lift a HYOSUNG radiator from any
part except the factory installed lifting eyes on the upper and lower headers.
HYOSUNG radiators are equipped with lifting eyes on the upper and lower header pipes. These lifting
eyes are the only points where rigging can be attached for lifting the radiators.
To remove the radiators from their crates, there are two possible methods:
1. If two cranes are available, connect slings for one crane to the lower header lifting eyes and the
other crane’s slings to the upper header lifting eyes. Slowly lift both sides simultaneously,
keeping the radiators approximately horizontal.
2. If only one crane is available, connect slings to the upper header lifting eyes and slowly lift the
radiator, uprighting it before lifting it from the crate. The bottom of radiator should be supported
by a board to protect the drain plug from damage during lifting.
Radiators should be set on boards on the ground if they will not be installed immediately after lifting
from the crates.
Radiators are gasketed and sealed at the factory. Open the flange cover plates and inspect the internal
part of the radiators to ensure that they are clean and dry before mounting them.
When installing radiators, great care must be taken to ensure that none of the gaskets fall from the
gasket groove and become pinched when the flanges are bolted together. If the gasket is not lubricated
and a light amount of Vaseline used in the gasket groove is not sufficient to hold the gasket in-place, it
may be necessary to use a very small amount of glue in the gasket grooves on vertically oriented
flange faces.
Do not run pumps without oil or with the valves closed to avoid damage to the pumps.
Fan motors must be checked to ensure that drain plugs are properly installed. Fans may be equipped
with directional plugs that must all be oriented to prevent moisture intrusion in the mounted position.
Contact HYOSUNG if you have any questions.
Conservators, pipes, radiators and heat exchangers should all be checked before installation to ensure
that any bags of silica gel or other items that may have been placed inside for shipping are removed
before installation.
The transformer may be furnished with more than one pressure relief device. In general, one device
should be provided for every 10,000 gallons of total oil volume. If removed for shipping, the pressure
relief devices need to be re-installed using new gaskets. The pressure relief devices are rated for
vacuum and do not need to be removed during vacuum processing.
Note that the cast base of the Qualitrol Pressure Relief Device can be easily broken if the mounting
bolts are over torqued. The ½” or M12 mounting bolts must be torqued to 30.4 FT-LBS and no higher.
Refer to the following drawing and steps listed below for installation of the semaphore.
NOTE: Do not remove more than one cover mounting screw. The cover is under spring Pressure and
could be released.
2. Locate the mounting hole of the semaphore assembly (Item 15 in the drawing) over the location
of the removed screw and reconnect the mounting screw – do not fully tighten the screw yet.
3. Align the tip of the semaphore directly above the indicating pin (Item 8 in the drawing) in the
center of the pressure relief device cover.
4. Tighten the mounting screw
5. Check the semaphore for free movement from horizontal to vertical position.
6. Set the semaphore in a horizontal position (as shown in the drawing) with the top of the
semaphore directly the indicating pin.
Section 5
Vacuum Oil Processing Procedures
Quality Issues:
Processing, dry-out and oil impregnation are all affected by temperature. Follow the appropriate
procedures for the specific ambient temperature conditions during installation.
The transformer cover and walls will flex inward when the transformer is under full vacuum. All
cable and bus connections to the top of bushings must be disconnected to ensure that they are
not damaged from the movement they will experience.
No workers may stand on the transformer cover when the transformer is under vacuum.
No electrical tests may be performed while the transformer is under vacuum.
Failure to observe the stand time requirement may cause incomplete insulation impregnation,
leading to transformer failure upon energization.
Equipment Required:
Processing trailer with hoses, fittings, filters, vacuum chamber and sufficiently rated heaters.
o Vacuum pumps should have a minimum 150 CFM capacity (4300 liter/minute) and must
be capable of attaining a 0.1 Torr blank-off vacuum pressure.
o Connections from the pump to the transformer tank must be as short as possible and a
diameter of three inches. There should be no low spots in the vacuum line in which oil or
water can collect. The vacuum system (pumps and hoses) must be capable of attaining
a blank off pressure of 0.1 Torr or less.
Vacuum/pressure gauge
o The pressure in the tank during vacuum operations must be measured through a
connection to the top section to the section of the tank above the oil level. Do not take
pressure measurements at locations other than the tank itself. We recommend
measuring the pressure in the tank with a properly calibrated aneroid gauge or
manometer. Mercury gauges are not to be used under any circumstance.
Hi-Pot Oil Test Set (IEC156)
Dew Point Test Set
Process Flowchart:
The Process Flowchart shows all of the standard and optional steps included in this procedure. The
process steps are color coded as follows and the Procedure section or subsection is listed in each
process step on the flowchart.
These steps are required for vacuum processing all oil-filled transformers.
These steps are only required when specified by HYOSUNG or the customer, or if field tests
on the oil after filling do not meet all requirements.
These steps are only required if the transformer fails the dew point test and requires dry out
before the start of vacuum processing.
These steps are only required if the vacuum processing is performed in cold weather and the
temperature of the transformer’s active part is less than 10°C (50°F).
These steps are only required if the transformer processing is started more than 90 days and
less than 181 days after the transformer is shipped from the factory.
Figure 5.1
N
Oil Tests OK?
Section 5.4 Table 5.1
Oil Acceptance
Y
Ambient N Short term vacuum
Temp ≥ 50ºF? Section 5.6
Y
Reject Oil 20% Oil fill
Section 5.6
Processing
N
≤ 90 Days after
ex-factory
date? Hot oil circulation
Section 5.6
Processing Y Section 5.6
N
≤ 150 Days after Optional
ex-factory Vacuum Leak Test Active Part
Section 3.5 date? Sect. 5.7 Pre-Heating
Temporary N
Outlet oil
Y
Storage temp ≥ 50ºC?
Y Stand Time
Table 5.3
Extended Stand
Time
Table 5.4
Finish
When the 24-hour average ambient temperature at the site over the two days prior to the start of
vacuum processing is not less than 10°C (50°F), HYOSUNG’s standard processing requirements shall
be observed.
When the 24-hour average ambient temperature at the site over the two days prior to the start of
vacuum processing is less than 10°C (50°F), HYOSUNG’s cold weather processing requirements in
Section 5.6, Active Part Pre-Heat, shall be observed.
When the relative humidity at the site is greater than 85% at any time while the transformer is open, the
transformer must be continuously ventilated with dry air while open, must not be open for more than
8 hours during any day and must be placed under vacuum at the end of each day for not less than
12 hours when the transformer is open for any assembly work. This is in addition to any vacuum
requirements under HYOSUNG’s standard processing requirements.
Example: Calculate the amount of heating required to raise the oil temperature to 60°C (140°F) when
the ambient temperature is 20°C (68°F) and the flow rate is 40GPM.
H = 40 × (60-20) × 0.108 = 172.8 kW or H = 40 × (140-68) × 0.06 = 172.8 kW
5.1 Grounding
Verify that tank ground is connected to the site ground grid. If not, make the connection to the
site ground grid or another reliable ground source.
Ground the oil processing trailer to the transformer tank, or site ground grid.
Ground any generator that may be used.
Install static ground wires to the top of each bushing and connect these to the tank.
All oil hoses must contain internal static wires. The hoses must be tested to verify electrical
continuity between the fittings on both ends before each use.
All temporary grounds must be removed after the work is completed.
Transformer oil can generate a large static charge when pumped through hoses or pipes, Also,
electrical fields in energized substations and power plants can induce high voltages on unground
ed transformer windings. All oil hoses must be equipped with internal static discharge wires and
all tanks, tankers, transformers and processing trailers must be securely grounded.
If the Dew Point test is not satisfactory, apply vacuum to 1 Torr for 12 hours or longer. Refill the
transformer with dry air (minimum -50°C dew point) and wait for 12 hours or longer then repeat the Dew
Point test on the transformer. If the test is satisfactory, go to Section 5. If the test is not satisfactory,
apply vacuum again for 12 hours or longer, refill with dry air again and wait for 12 hours again before
retesting. If the retest is not satisfactory, the active part pre-heating process described in Section 5.6
must be performed.
Oil Testing
The oil supplier must provide a certified test report on the bulk oil from which the delivered oil was
obtained and the oil must meet the following requirements for acceptance. The dielectric strength of
the delivered oil must also be tested on-site using IEC60156 before acceptance and before being
placed into any other tank or tanker.
<Measurement>
a. Take oil samples from the following positions of transformer. Make sure that the
sample container is clean and dry.(The bottom of main tank)
b. Pour oil into the test cup and fix it.
c. Wait for five minutes. When there is no air bubble, apply voltage.
d. At this time, one sample of oil has to be tested five times every one minute.
Refer to the valve positions as shown in Section 5.10 – Vacuum Oil Filling Process
Configure the processing trailer vacuum and oil hoses, and transformer valves, including any
equalizing valves, for initial vacuum
Pull vacuum on the transformer (and LTC, if equipped) to 1 Torr or below. Hold vacuum at this
level for 30 minutes.
Close the lower radiator or heat exchanger shut-off valves, but leave the upper valves open.
Configure the remaining valves for Initial Oil Filling, as shown in Section 5.10 – Vacuum Oil Filling
Process. If the transformer is equipped with a LTC, keep LTC equalization valves open.
If the average daily ambient temperature is below 0°C (32°F), the transformer should be covered
with insulating blankets to facilitate the heating of the active part.
Maintain vacuum at 10 Torr or less during oil filling and fill the main tank with about 20% of the total
oil volume using the oil processing trailer’s pumps, filters, heaters and vacuum chamber. The
temperature of the oil leaving the oil processing trailer should be maintained as close to the
maximum 75°C (167°F) as possible, and not less than 50°C (122°F).
When the tank is about 20% filled, stop the pumps and configure the processing trailer vacuum and
oil hoses, and transformer valves for Oil Filtering as shown in Section 5.10 – Vacuum Oil Filling
Process. If the transformer is equipped with a LTC, keep LTC equalization valves open.
Maintain the temperature of the oil leaving the oil processing trailer as close to the maximum 75°C
(167°F) as possible, and not less than 50°C (122°F) and maintain the vacuum level at 10 Torr or
below.
Continue vacuum/hot oil circulation until all three conditions below have been met:
o Transformer outlet oil temperature has reached 50°C or greater, as measured at the input to
the processing trailer.
o The transformer oil temperature gauge reads 10°C (50°F) or greater (the gauge should be
reading the internal tank temperature)
o The temperature of the oil leaving the transformer has reached or exceeded 50°C and has
stabilized
NOTE: If the oil processing trailer is equipped with sufficient heaters, the transformer is properly
blanketed and after 12 hours or more of hot oil circulation it is still not possible to reach and
maintain the 50°C transformer outlet oil temperature, contact HYOSUNG . An alternate 30°C
outlet oil /10°C tank/ 12 hour process may be authorized.
A spray inlet nozzle attached to a temporary manhole cover may also be used, if available.
The spray must be directed away from any bushings inside the tank to eliminate the risk of
thermal shock damage to the bushings.
Drain all the oil from the tank with vacuum and back-fill with dry air.
Immediately start the Vacuum Oil Filling Process as listed in Section 5.10 below.
After the required Vacuum Level Prior to Oil Filling as listed in Table 5.3 is reached, close the
vacuum valve at the oil processing trailer and wait for 10 minutes then monitor the vacuum level. If
the pressure rises more than the maximum allowable level listed in Table 5.2 below, it should be
checked for leaks and any leaks repaired before starting again.
If there are no leaks and the pressure still rises more than the maximum allowable level, the
transformer insulation may be wet. Fill the transformer with dry air, wait 6 hours then retest the Dew
Point.
Table 5.2
Maximum Allowable Vacuum Leak Rate
Tank Oil Volume (Gallons) Torr Rise in 10
Minutes
Less than 5000 0.80
5001-7500 0.53
7501-10,000 0.40
10,001-12,500 0.32
12,501-15,000 0.27
15,001-17,500 0.23
17,501-20,000 0.20
20,001-22,250 0.17
Table 5.3
≥69kV to ≥230kV to
Vacuum Treatment and Oil Filling ≤69kV ≥345kV
<230kV <345kV
Class Class
Class Class
2mm Gap 45 kV 52 kV 55 kV 60 kV
After Oil Max. Water Content of Oil 20 ppm 10 ppm 10 ppm 10 ppm
Filling
Max. Oil Power Factor
0.05 % 0.05 % 0.05 % 0.05 %
at 25°C
Stand Time
After oil filling, the transformer must not be energized before the time listed under “Stand Time After Oil
Filling Before Energization” in Table 5.3. When the transformer must be energized as quickly as
possible, the stand time can start as soon as the core and coils have been covered with oil. If hot oil
circulation is performed, the circulations can be made during the stand time.
After stand time is complete and the transformer is energized, there is no additional hold time required
before the transformer can carry load up to the full nameplate rating.
Hot oil circulation is not required for HYOSUNG’s standard oil processing process. Hot oil circulation is
only required when:
o The transformer has not been assembled within 150 days after leaving the factory and the HV
voltage class is ≤230kV (See Short Term Storage in Section 3)
o After the transformer is filled with oil, the tested oil fails to meet any of the following Processing
Parameters listed in Table 5.3 for After Oil Filling ( Min. Dielectric Strength per IEC60156 test at
1mm or 2mm gaps, Max. Water Content of Oil, or Max Oil Power Factor)
o Required or specified by the customer
o When specified by HYOSUNG (when special requirements such as extra low moisture or
dissolved gas requirements exist)
After the transformer has been fully filled with oil, configure the oil hoses and valves as shown in the
Oil Filtering in Figure 5.10. If the transformer is equipped with a LTC, keep LTC equalization valves
closed.
Circulate oil through the transformer and the oil processing trailer’s heaters, vacuum chamber and
filters maintaining a 1 Torr or stronger vacuum in the vacuum chamber.
Control the flow rate to provide an oil temperature into the transformer of 75°C (167°F) and an oil
temperature out of the transformer of 50°C (122°F) or greater. The temperatures shall be measured
in the oil processing trailer so oil temperature into the transformer will be the temperature of the oil
leaving the trailer.
If the minimum oil temperature out of the transformer cannot be maintained, verify that the heaters
are sufficiently rated (See Determining Required Heater Capacity). It may be necessary to add
insulating blankets to the transformer or construct a heated enclosure around the transformer.
After the oil temperature out of the transformer reaches and is stabilized at 50°C (122°F) or greater,
the count of circulated gallons can start. For one required pass, circulate the total quantity of oil as
listed on the nameplate. For two required passes, circulate two times the total quantity of oil as
listed on the nameplate, etc.
If an oil sample is required for moisture, the sample must be drawn within 10 minutes after the end
of the circulation, while the oil is still hot. Record the oil temperature and include this information
with the paperwork for the sample that is sent to the test lab.
After the hot oil circulation is complete, remove the oil hoses and configure all valves to their normal
(in-service) positions as shown in the Valve Nameplate drawing in Section 10.
5.9 Processing After Short Term Storage (Refer to Section 3.5. Not approved for transformers
greater than 230kV or for storage beyond 150 days after leaving the factory)
Follow the requirements herein and the parameters listed in Table 5.3, except for the requirements
listed below in Table 5.4.
Table 5.4
Processing After Short Term Storage
Vacuum Treatment and Oil Filling ≤ 230kV
Class
Vacuum Min. Vacuum Hold Time After 24 Hours
Reaching Specified Vacuum
Level, Before Oil Filling
After Oil Hot Oil Circulation Passes 2
Filling Required
Stand Time After Oil Filling 48 Hours
Before Energization
Figure 5.5
Initial Vacuum
Notes: Valves Va, Vb, Vc, Vd and connecting hoses or pipes are not supplied with the transformer.
All valve locations are approximate and shown for function only.
1. Review the LTC instruction manual and remove all LTC accessories that could be damaged
during vacuum oil filling (dehydrating breather, rapid pressure rise relay, etc.).
2. Inspect all vacuum and oil hoses for cleanliness before using.
3. Check electrical continuity with an Ohm-meter on all oil hoses before using. Do not use any
hoses that do not pass this test since the static discharge wire is not functional.
4. Remove the conservator’s desiccant breather from its mounting flange and store in a safe place.
Also close the valves for RPRR, B-H relay, etc.
5. Connect all vacuum hoses and vacuum valves as shown in Figure 5.5. Note that the
transformer main tank and LTC tank must both have vacuum applied simultaneously.
6. Connect oil hoses as shown in Figure 5.5.
7. Configure all valves as shown in Figure 5.5. Open all cooling system valves.
8. Be sure the removal the equalizing pipe between main tank and LTC for transportation purpose.
9. Pull vacuum on the main tank and LTC at the level specified in Table 5.3.
10. Check the leakage rate per Section 5.7 and Table 5.2.
11. After leakage rate has been determined to be within limits, hold the vacuum at the level and
time specified in Table 5.3.
12. After the specified vacuum has been applied for the specified length of time, proceed to the next
step – Initial Oil Filling.
Figure 5.6
Initial Oil Filling
1. With the valves still in the same configurations as shown in Figure 5.5, open the Upper Filter
Valve and start oil filling through the heaters, vacuum chamber and filters of the oil processing
trailer within the flow rate limits listed in Table 5.3 while maintaining the vacuum level specified
in Table 5.3.
2. When the oil has been filled to a level approximately 4”-6” below the tank cover, configure all
valve positions as shown in Figure 5.6 (close vacuum valve so vacuum will be pulled through
the main tank conservator and the LTC conservator) (Note that the LTC conservator is not
equipped with a diaphragm)
3. Continue oil filling the main tank until the conservator Oil Level gauge indicates 25°C or
indicates 4. Stop oil filling.
4. Proceed to the next step – LTC Oil Filling
Figure 5.7
LTC Oil Filling
Figure 5.8
Break Vacuum and Final Filling
Figure 5.9
Final Valve Positions
1. Configure all valves as shown in Figure 5.9. Keep all cooling system valves open.
2. Verify that the supply valves for the gas accumulation relay and Online-Gas monitor(if equipped)
is open and vent any trapped air in the gas accumulation relay or Buchholz relay through the
sample valve.
3. Draw an oil sample and have the sample analyzed for dissolved gasses and physical properties
by a qualified laboratory. The oil sample should be taken while the oil is 30°C or greater to
provide meaningful percent moisture saturation values, and the oil sample temperature must
accurately be measured and provided to the lab with the sample.
4. Do not energize the transformer until the required stand time has been met, as specified in
Table 5.3 and the oil sample results have been received and approved by HYOSUNG.
5. If oil test results are not acceptable, additional oil processing is required depend on our manual.
Oil Filtering
Figure 5.10
Oil Filtering
1. If additional oil filtering or hot oil circulations are required for the main tank and/or the
LTC, configure all valves as shown in Figure 5.10.
2. For filtering, use new ½ micron filters and circulate the oil through the oil processing trailer
3. The main tank and LTC compartments should be circulated separately, and not at the same time.
4. For hot oil circulations, follow the steps in Section 5.8
Section 6
Commissioning Tests
General Test Procedures:
Lethal voltages can be generated during transformer testing. Test equipment should only be used by,
and tests should only be performed by, trained and qualified technicians.
If additional details or documentation are required for any components, contact HYOSUNG
1. Assembly and outline inspection
Description Acceptance Criteria
1.1 Assembly and outline inspection will be done ⊙ The inspection results shall be satisfied with
in accordance with the approved specification approved drawings.
and drawings.
1.2 Construction, painting and welding condition will
be inspected visually.
6. BCT test
Description Acceptance Criteria
1) The BCT shall be measured ratio with both ⊙ Measuring Current is within ±10% of standard
voltage & current method ⊙ The polarity : subtractive.
2) The BCT polarity shall be check by DC current
Inductive kick method or other available method.
9. SFRA
Description Acceptance Criteria
1) The tests will be performed with the transformer ⊙ For reference only
Fully assembly condition and with oil by DOBLE
M5400.
2) The frequency will cover the frequency range
from 20Hz to 2MHz.
3) All bushings will be tested as Doble Standard
test connections.
Section 7
Power Transformer Maintenance and Repair
7.1 General Requirements for Inspection and Maintenance
The inspection items are classified into three categories in this manual.
The routine inspection should be made preferably daily on every transformer in service. Oil
temperature and/or winding temperature, load current, ambient temperature and oil level in
transformer should be daily checked and recorded.
The periodical inspection should be made occasionally, once every six months or once every
three years in order to ascertain the good performance of a transformer and its parts. Most of
the periodical inspections should be made in detail when the transformer is de-energized.
Repainting of radiators and transformer tanks, and exchange of parts, gaskets and bearings of motors
should be planned and executed regularly as a part of an effective preventive maintenance program to
ensure reliable performance.
If any protective relays alarms occur, investigate the trouble in accordance with the Troubleshooting
section below.
It is essential to determine all relay actions and their sequence when investigating any power system
alarm or trip.
Any abnormal symptoms such as unusual noises, high or low oil levels, high temperatures, oil escaping
from the pressure relief device, etc., should be investigated and corrected as quickly as possible.
HYOSUNG recommends that owners keep critical spare parts on-hand for each transformer. Lead-
times on some parts like high voltage bushings can be as long as one year. A proactive approach of
stocking spare parts can ensure that a failed component can be quickly replaced, avoiding lengthy
outages.
Transformers cannot or should not be operated without the following components in good functional
condition:
Bushings
Lightning arresters
Protective relays (Buchholz, rapid pressure rise, gas accumulation, pressure relief, etc.)
Cooling components and controls (fans, pumps, circuit breakers, contactors, relays, etc.)
Trip and alarm circuit relays
Many transformers share common components. A well-planned universal spare parts plan can cover
several transformers with a relatively small number of spare parts. HYOSUNG can assist in
developing a spare parts plan if support is needed.
The establishment of the report and recording of the condition and repair of the transformers is required
for a good maintenance program.
A preventive maintenance system will operate satisfactorily with the following records.
An equipment record
This may range from a simple index card and card file to an equipment database which
contains the basic information of a transformer itself such as the serial number, the location,
size, etc.
A repair record
This should keep a running record of all maintenance and repairs performed on a transformer.
It is the essential diagnostic record for avoiding future difficulties.
This should include a list of the points to be checked or measured on a transformer and the
establishment of the time that these checks should be made. The results of all regular
inspections should be retained in a file or database.
Table 7.1
No. Items Method Action
Table 7.2
No. Items Method Action
1. Breather Check the discoloration of silicagel in If the color of silicagel has
(6 months) breather due to absorbed moisture. turned pink by more than two
thirds, dry out or exchange it.
2. Fan motors Measure insulation resistance of fan If insulation resistance is less
(3 years) motors with a 500V megger. than 2MΩ, replace motor.
3. Control panel Check the water-tightness of control Replace the rubber gasket if
and terminal box panel and a terminal box. it is worn or damaged.
(3 years)
4. Switches, circuit Check the tightness of all control Tighten any loose
breakers, wiring connections. connections.
contactors and Test all switches, relays and alarms. Repair or replace, as needed
control relays Megger test wiring.
(3 years)
Thermovision checks on Circuit Tighten, repair or replace, as
Breaker and Contactor terminals needed
5. Oil Leaks Check all gasketed connections and Regasket, or repair if needed
(Annual) complete tank for signs of leakage.
4. Exciting current Doble or similar individual phase test Contact HYOSUNG if any
at low voltage method. significant changes are
(3 years) found from factory or
previous field tests
5. Bushing Ratio, and excitation and megger tests Contact HYOSUNG if any
current significant changes are
transformers found from factory or
(3 years) previous field tests
6. Protective relays Functional test of all controls and relays Replace any faulty
and controls components
(3 years)
Table 7.4
No. Material and Parts Maintenance frequency Remarks
1. Bushings and Clean as required for local Coastal environments and
insulators conditions. locations near industrial
sites will require more
frequent cleaning. Visible
corona is a sign that
cleaning is needed.
2. Radiators and heat Clean as required for local Use care when cleaning.
exchangers conditions. Use compressed air or low
pressure water. Do not use
pressure washers.
3. Paint As required Touch-up painting should
be performed after
commissioning and
whenever maintenance is
performed. Complete
repainting should be
required less often if touch-
up painting is done
regularly.
4. Fans and pumps Expected life is ten years. Replace when needed
5. LTC Per the manufacturer’s manual.
7.8 Troubleshooting
When the transformer does not perform as expected, it is important that the cause of the action be
determined and corrected. Troubleshooting is an art that requires logic, experience and knowledge of
how the system and equipment are designed to operate and how they are constructed.
This instruction leaflet is intended to give general instructions concerning recommended practices for
repairing weld leaks in power transformers or their auxiliaries. Variations of these instructions may be
desirable for special repair tasks, but normally weld leaks can be successfully sealed if these
instructions are followed.
Repair Steps
De-energize the transformer.
If the liquid has not been removed, pull a vacuum of several pounds per square inch above the
liquid to stop the liquid leak. This may be done with a vacuum pump or by sealing all fittings on
the tank and draining sufficient oil to obtain the necessary vacuum to obtain a neutral or
negative head pressure at the weld area. Be careful not to apply negative pressures to any
sensitive components like Hydran or similar monitoring devices or to RPRR relays. Oil head
pressure is approximately 1/2psi per foot.
Peen the weld leak area, if possible, with the ball end of a ball-peen hammer or with a blunt or
round-nosed chisel.
Grind or brush the paint from the area to be welded and the ground lead for the arc welding
machine.
DC current, straight polarity is preferred with the transformer connected to positive, grounded
polarity and the electrode connected to negative polarity. The welding machine must adjusted to
supply the desired welding current to ensure that the weld will have adequate fusion and is not
at risk of burning through the base material.
Clean and remove any residual oil with denatured alcohol or another petroleum distillate.
Apply a string bead sealing weld over the weld defect in a single, quick pass. This weld should
be deposited horizontal or vertically depending upon circumstances. If the weld is deposited
vertically, it is recommended that it be made downward to drive any liquid seepage ahead of the
weld.
Successive beads should be deposited adjacent to and over the first sealing bead or a single
pass may be weave across it to complete the weld.
Remove all slag between each successive weld bead or pass.
Clean the repaired area and check with a dye penetrant or other suitable test to be sure the
defect has been repaired.
After testing for leaks, re-clean the area and apply touch-up paint.
where the elements join the header or each other, the following procedure is recommended.
Close the radiator valves between the radiator and the transformer case. Drain the liquid from
the radiator and remove the radiator from transformer case.
Grind or brush the paint from the area to be repaired. Also remove any liquid, dirt or foreign
matter.
If the weld to be repaired is around the header flange use 3mm diameter electrodes with current
settings between 115 to 125 amperes. Weld horizontally around the flange.
An oxygen-acetylene welding technique is recommended for repairing a weld along the edge of
an element, a weld joining the elements to each other, or a weld joining the elements to the
header. The recommended procedure for repairing a leak along the edge of an element is
outlined below:
Figure 7.7 Radiator Section prepared for welding Figure 7.8 Radiator Section after welding
o Heat the full length of the seam with the oxy-acetylene torch to drive out all trapped oil.
o Find the exact location of the leak by means of a suitable leak detector.
o When the exact location of the leak has been determined, notch the edge of the element
as shown in Figure 7.7 at points 50 to 75mm on either side of the leak. These notches
may be cut with a hack saw, a file, or a small grinder.
o Start by filling one of the notches. Next, fill in the second notch. Finally fuse the edges of
the element between the notches moving forward with a slightly weaving motion. Be
sure to tie this weld into both filled notches.
Figure 7.8 shows the repaired element before touching up the repaired area.
Clean the repaired area and check with a suitable leak detector to be sure the leak has been
stopped.
After testing for leak is, re-clean the area and apply touch-up paint.
Section 8
Recommended Minimum Transformer Protection
Application: This applies to all HYOSUNG oil-filled transformers and reactors.
General: IEEE Standard C37.91, the Guide for Protecting Power Transformers details the types of
protection available for power transformers and their application. The design of relay protection
systems and the determination of relay settings should only be performed by trained and qualified
personnel with expertise in the subject.
This document covers different sizes and types of transformers with specific minimum protection
requirements.
All transformers must be protected from conditions that could cause damage to the transformer such as
excessive mechanical and thermal forces from fault currents, excessive insulation stress from
overvoltages or thermal damage from high operating temperatures.
Types of Transformers: For this document, transformers will be divided into the following general
groups.
Small Power Transformers in Substations or Powerplants: In general, these transformers are not
greater than 34.5kV or 10MVA and can be three-phase or single-phase in banks of three or alone.
This does not include powerplant UAT or SST transformers in this range or wind turbine step up
transformers.
Powerplant Generator Step-Up Transformers: In general, these transformers can be three-phase or in a
bank or three single-phase transformers. The voltage class can be as high as 750kV and ratings can
be as great as 1000MVA or more.
Powerplant Auxiliary (UAT) Transformers: In general, these transformers are less than 100MVA, and
the HV voltage classes of UAT’s are at the generator voltage level (<25kV) and the HV voltage classes
of SST’s are at transmission system voltage levels (to 750kV).
Distribution Substation Step-Down and Powerplant Start-Up (SST) Transformers: In general, these
transformers are less than 100MVA and at voltages of 345kV and less.
Transmission Autotransformers: In general, these transformers are at voltages of 230kV and above, at
ratings to 1000MVA or greater and can be three-phase or in banks of 3 single phase units.
Wind Substation Step-Up Transformers: In general, these transformers have voltage classes to 345kV
and are rated up to 250MVA or greater.
Wind Turbine Step-Up Transformers: In general, these transformers have voltage classes no greater
than 34.5kV and are rated less than 5MVA.
Relay Device Numbers: IEEE Standard device numbers are listed in Table 8.1, and used for circuit
diagrams for each type of transformer detailed below.
Table 8.1
Device Description
24 volts per hertz relay
26 apparatus thermal device
46 reverse-phase or phase-balance current relay (negative sequence current relay)
49 machine or transformer thermal relay
50N instantaneous neutral overcurrent relay
51 ac time overcurrent relay
51G ac time ground overcurrent relay
51N ac time neutral overcurrent relay
51NB ac time neutral overcurrent backup relay
51NT ac time neutral overcurrent torque controlled relay
52 ac circuit breaker
59 overvoltage relay
60 voltage or current balance relay
63 pressure switch (rapid pressure rise relay or Buchholz surge)
63LTC pressure switch (LTC rapid pressure rise – Buchholz or other)
63PRD pressure switch (pressure relief device)
64 ground detector relay
67 ac directional overcurrent relay
67G ac directional ground overcurrent relay
71 oil level relay
71C critical oil level relay
86 lockout relay
87 differential protective relay
87G ground differential protective relay
96 gas accumulation relay (separate device or Buchholz gas accumulation)
96LTC gas accumulation relay (Buchholz gas accumulation)
Symbols:
The following symbols are used in this document.
Symbol Represents
Transformer windings
Wye-connection
Delta-connection
Lightning Arrester
52 Circuit breaker
XX
Device that trips lockouts or local circuit breakers and isolates the transformer
from all sources of energization. Device number indicates relay type.
XX
Device that performs an alarm to a manned location. Device number
indicates relay type.
Ground connection
The following recommended minimum protection schemes are based on typical winding configurations,
but should be modified accordingly if the winding configuration differs from that shown. Also, other
protection should be provided for special transformers. Water cooled transformers, for example, should
be equipped with water flow and leak detection protection. Gas cooled transformers should also be
equipped with gas densiometer and pressure relays.
51 51N
52
52 52 52
52
Transmission Autotransformers:
52
52
51
Fuse/Disconnect Switch
52 52 52
Wind turbine step-up transformers on collection circuits should be fused and equipped with a
disconnect switch. The collection circuit should be protected with an overcurrent relay, typically located
in the feeder breaker. The collection circuit must also be protected from overvoltages with lightning
arresters. This minimal protection scheme is only recommended because no alarm or trip circuits are
provided for these transformers at many windfarm sites. The user must be aware that this type of
protection scheme will not, in some cases, adequately protect the transformer from tank rupture or
catastrophic events, and is designed to protect the rest of the collection system.
When trip and alarm circuits are provided, a better protection scheme should include alarms for
pressure relief (63PRD) and high temperatures (49) and trips for rapid pressure rise (63) and volts/Hz
(24)
Section 9
Mechanical Drawings
H1 H2 H3
X1 X2 X3
X1 X2 X3
H1 H2 H3
X1 X2 X3
VIEW A-A'
# NOTE #
1. ALL DIMENSION ARE IN MILLIMETERS.
2. DIMENSION AND WEIGHT WILL BE CHANGED
SLIGHTLY AFTER DETAIL DESIGN.
VIEW "A", FLANGE
VIEW "A", FLANGE
Electrical
Operation & Maintenance
Drawings
Manual
R0
Section 11
Electrical Drawings
Rev. No. : 1
TITLE SHIPPING PROCEDURE
Page. No : Cover
SHIPPING PROCEDURE
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-010
Rev. No. : 1
TITLE SHIPPING PROCEDURE
Page. No : 1 / 16
SHIPPING PROCEDURE
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
For Construction
REV.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
NO.
REV.
HYOSUNG PREPARATION CHECK REVIEW APPROVAL
NO.
- Table of Contents -
No. Description
1.0 Scope
2.0 Purpose
3.0 Packing
4.0 Marking
5.0 Handling
A4(210mm x 297mm)
PACKING PROCEDURE
1.0 Scope
1.1 This procedure is intended to specify the requirement of packing, marking and handling and
transportation of Equipment and it’s accessories as per HYOSUNG STANDARD
1.3 Others
The transformer body will be packed and shipped with filled oil
The radiators of transformer will be separately packed in Water Proof Wooden Crates for Shipping.
1.5 The impact recorder for all equipment and above transformer will be attached during transportation.
2.0 Purpose
The purpose of this procedure is to provide the method of packing, marking and handling for protection
of the materials against corrosion, physical damage, of any effect which would lower the quality
or cause the items deteriorate during the time they are shipped, handled and stored.
3.0 Packing
All Equipment Packing Method should be considered for Ocean Transit, for lnland transit
in rough road condition, for storage in the Site.
3.1 Preparation before packing.
All materials should be dry, clean, and free from all defects prior to packing.
Protection against environment corrosion caused by extremes of humidity, condensation, rain,
sand, salted air, and sea spray be provide.
The following requirements may be considered as minimum essential protective measures for materials :
(a) All threaded areas shall be coated with a metallic base waterproof lubricant or grease.
(b) If required by technical specifications, Vapor space inhibiting oil or vapor phase inhibiting powder,
silica gel or N2 purge be used to protect all internal metallic surfaces of equipment.
3.2 Unless otherwise specified the equipment interior shall be thoroughly cleaned and dried.
3.3 Spare parts included in the scope of supply shall be separately packed and shipped together
with the equipment.
3.4 In case of Export packing, Vapor phase inhibiting powder fogged inside the equipment or
N2 purged inside the equipment, the flanged openings will be covered with 6mm steel plates,
min. 4 bolts & gasket.
A4(210mm x 297mm)
PACKING PROCEDURE
3.5 All opening for transfomer components, e.g. bushings which have been removed from the transformer
during transport, are covered by means of blanking off paltes.
3.6 The Transformer should arrive with positive pressure, indicating that moisture did not enter
the transformer during shipping.
3.7 For preventing corrosion during Ocean Transit, The Tarpaulin will be provided.
A4(210mm x 297mm)
PACKING PROCEDURE
4.0 MARKING
4.1 Shipping Mark production
(1) Indication an recognizable project mark.
(2) When shipping mark is made of A4 paper, the shipping mark shall be printed with coated paper
(3) For the Indonesia Custom Clearance, The Sample of Shipping mark will be provided from the Purchaser.
(2) The further information should be recorded clearly such as type and size of material & equipment
according to P.O. requirement.
It will be recognized where the package is used.
The packing list cover is adheres to the outside of package box to identify easily.
The packing list is wrapped up in transparent vinyl and kept with packing list cover.
For the Indonesia Custom Clearance, The Sample of Packing List will be provided from Purchaser.
(1) The packing list shall be prepared all contents for each packing box, so anyone has it know
the contents such as part name, the number of partand construction material
of the packing box without opening the packing box cover.
※ For review of customs clearance firm, The packing list 1st Version shall be provided
at least 3 weeks before to the Purcharger.
4.8 The each stage(including Loading & Unloading Picture from the Truck and inner picture of packed box)
of packing shall be taken photographs, and then the photographs shall be submitted to customer.
4.9 The Packing Inspection Foam will be provided at least 1weeks before inspection.
A4(210mm x 297mm)
PACKING PROCEDURE
5.0 Handling
5.1 GENERAL
(1) Before using handling tool and equipment, they will be inspected about their capability.
(2) Experienced or trained personnel will be assigned to the operation of special handling
and lifting equipment.
5.2 The handling methods including devices & equipment will be determined by ;
(1) Characteristics of the items to be handled such as size, weight, center of gravity.
5.3 Handling operation will be done with care to prevent damage to the machined surface,
and distortion of shape of dimension.
5.4 The sling length will be chosen according to piece dimension. The angle formed by both sling strands
must not exceed 60° in general.
A4(210mm x 297mm)
PACKING PROCEDURE
A4(210mm x 297mm)
PACKING PROCEDURE
7.1 Shipping marks on all crates shall attached on the 2sides in box
INK
MARK LOCATION SIZE Remarks
COLOR MATERIAL
High
Optimum
Main quality
sige for Written in large letters
Shipping Black waterproof Both sides
each as possible
mark ink or
package
oil paint
C
Sling
a
mark and Both sides
r High
Center of Optimum
e quality
gravity sige for
Red waterproof
mark each
M ink or
Top mark : Both package
a oil paint
ends
r
Other Others : both
k
marks ends
If required,
High
Only for packages
quality
Approximate Both sides, exceeding 5tons :
Black waterproof 15cm and over
weight ends, and top hand writing is
ink or
permissible : unit
oil paint
shall be tons
Yellow
letters Do not overlap
Packing L : 14cm
on black Enamel Upper part of Front with care mark :
list cover W : 18cm
back- use tin plated
ground
A4(210mm x 297mm)
PACKING PROCEDURE
A4(210mm x 297mm)
PACKING PROCEDURE
Waterproof Box
Category item
HV Bushing X
Bushing LV Bushing X
LVN Bushing X
Paint X
Painting Materials
Thinner X
HV Chamber X
Chamber
LV Chamber X
A4(210mm x 297mm)
PACKING PROCEDURE
8.2 Crate
The construction of wooden framed boxes or crates shall be based on below picture
Materials shall be securely bolted to the box or crate floor and restrained in such a manner
as not to permit any movement or vibrating during transportation.
A4(210mm x 297mm)
PACKING PROCEDURE
A4(210mm x 297mm)
PACKING PROCEDURE
TABLE-1
NO Description Under 1.5 ton 1.5~2.0 TON 2.0~4.0 TON 4.0~7.0 TON
2 Header 90 x 45 90 x 60 90 x 60 90 x 90
5 Side frame 90 x 24 90 x 30 90 x 30 90 x 30
11 End frame 90 x 24 90 x 30 90 x 30 90 x 30
6,12 Strut 90 x 24 90 x 30 90 x 30 90 x 30
7,13 Diagonal 90 x 24 90 x 30 90 x 30 90 x 30
15 Joist 90 x 60 90 x 60 90 x 60 90 x 90
8 Side plate L=15, P=9 L=15, P=9 L=15, P=12 L=15, P=12
14 End plate L=15, P=9 L=15, P=9 L=15, P=12 L=15, P=12
16 Top plate L=15, P=9 L=15, P=9 L=15, P=12 L=15, P=12
4 Heater borad L=15, P=9 L=15, P=9 L=15, P=12 L=15, P=12
# If length of box is over than 3000mm, skid is selected from next level lumber
A4(210mm x 297mm)
PACKING PROCEDURE
- Insulation Oil Standard, Brand, Maker, Net & Gross Weight is marked at
everyone on the top and sides of the drum(at least 3 spot) with stencil
when the pack to 1SET(4-Drum).
- The 'Drum Marking' as the picture will be applied only when the drum unit package.
- Steel Drum Color : Orange
A4(210mm x 297mm)
PACKING PROCEDURE
A4(210mm x 297mm)
PACKING PROCEDURE
THICKNESS
LOWER UPPER
(m/m)
GROSS W/T (TON)
Under 2 TON ~ ~
A4(210mm x 297mm)
PACKING PROCEDURE
9.0 Sample Photos
BUSHING RADIATOR
CONSERVATOR CHAMBER
TRANSFORMER TRANSFORMER
(Above 10MVA)
COMPLETED PACKING
A4(210mm x 297mm)
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-011
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : Cover
PAINTING PROCEDURE
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-011
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 1 / 14
PAINTING PROCEDURE
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
For Construction
REV.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
NO.
REV.
HYOSUNG PREPARATION CHECK REVIEW APPROVAL
NO.
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 2 / 14
Contents
1. Scope
2. Liquid Paint
3. Powder Coating
4. Description of Paint
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-011
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 3 / 14
1. Scope
This procedure shall apply to HYOSUNG's products.
The SSPC standard will be applied for this procedure
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-011
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 4 / 14
2. Liquid Paint
1. Storing Paint
2. Mixing Paint
3. Straining Paint
4. Thinning Paint
5. Preparation of the Surface
6. Applying the Paint
7. Painting Environment
8. Dry Film Thickness
9. Use and Care of Spray Equipment
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-011
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 5 / 14
1. Storing Paint
1.1 Store all paints and thinners preferably in a well ventilated room kept at 5C(41F) or over. Do not store
paints adjacent to radiators, steam lines or other heat source. Paints in storage shall not exceed
38C(100F). When necessary to store paints outdoors, protect them from excessive heat or direct rays of
the sun. Emulsion type paints are susceptible to damage from freezing and shall not be stored outdoors.
During cold weather allow paints, it is not only uneconomical but may also result in separation of resin
and pigment.
1.2 The containers of paint shall remain unopened until required for use. Containers which have been
opened to remove part of the contents shall be used before the others and shall be kept tightly covered
to prevent oxidation and evaporation. Store new shipment of paints until previous shipments have
been used. Test paint that has been in storage for a long time to see that it has not deteriorated during
storage.
1.3 Store paints which are subject to abnormal pigment settling in a manner as will permit the
container to be turned over once each month to aid in keeping the pigment in suspension.
2. Mixing Paint
2.1 Adequate mixing of paints is necessary to put settled pigments back into suspension. When paints is
improperly mixed, the paint in the top part of the container will be too rich in oil and thinner and paint in
the lower part too high pigment content. This condition results in defective paint films which may be soft,
does not dry properly, is chalky or adheres poorly.
2.2 The paint room shall be equipped with mechanical mixing equipment such as drum rollers and tumblers
or shakers for smaller sized container. Some drum are equipped with built-in agitators which can be
turned by hand or by motors, but these are not efficient and may require hours of stirring to obtain
smooth homogeneous paint. Stir paint frequently when standing unused and always stir before any is
removed from the container. Pigments do not remain in suspension indefinitely.
2.3 Hand mixing is rotary for small containers 5 gallons or less but requires to much time and labor for
larger quantities which are better mixed with power driven mixing equipment. Before mixing a can of
paint remove paint skins by straining a portion of the top liquid through a fine screen or cheesecloth, when
necessary. When the pigment has settled to form a cake, pour off pigment and work them into a smooth
paste using a side strong paddle. Gradually add the top liquid and thoroughly mix it in with the pigment.
When paint appears to be well mixed, complete mixing by pouring the paint from one can to another
several times.
When pigment setting is light, mixing may be done by stirring the paint in the container with a strong side
paddle using a rotary lifting motion to lift the pigment off the bottom and mix it into the liquid on the
top
2.4 Mixing by bubbling air through the paint is not permitted because paints are deteriorated by rapid
oxidation and close viscosity control cannot be maintained.
3. Straining Paint
3.1 Strain paints containing dirt specks and paint skins through wire or cloth screen (approx. 40 mesh) or
through a double layer of cheesecloth. Straining of paint may be done either before or after thinning.
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-011
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 6 / 14
4. Thinning Paint
4.1 Paints are adjusted in consistency by the addition of thinners to obtain the viscosity best suited for the
method of application. The type of thinner to be used is specified in the process or finish
specification and no other thinner shall be used without engineering approval. Thinners shall not be
added unless necessary for proper application of the paint.
4.3 Thinned paints are susceptible to pigment setting and require frequent stirring. Stir thinned paint in open
contains frequently with wide paddles or by motor driven mixers. Pressure spray tanks shall be
equipped with agitators, preferably motor driven, and operated continuously while in use.
4.4 When large quantities of paint are used, paint circulating system are sometimes used. The paint is mixed
and stored in the paint room and continuous re-circulated through pipes between paint room and
spray booths. Maintain continuous re-circulation to prevent pigment setting. To prevent skinning and
gelling of oxidizing types of paints, maintain an inlet atmosphere of carbon dioxide or nitrogen in the
paint container at all times.
4.5 Strain paint in circulating systems continuously by passing through suitable strainers installed in the
pipe lines. Strainers shall be installed in the outlet tube of pressure spray tanks and are recommended on
the outlet tube of hand spray gun containers. Clean strainers at frequent intervals.
4.6 Stir paints in dip and flow tanks or circulate frequently to assure uniformity at all times. Add thinner
frequently to maintain correct viscosity. When not in use, keep tanks closed with air tight covers to retard
evaporation and skinning.
4.7 Measure viscosity of the paint according to KS M5451 using Krebsstomer Viscosity meters.
Paints shall be thinned to obtain viscosities specified in the process or finish specification.
4.8 Measure viscosity of the paint at frequent intervals to insure uniform viscosity during the period of
application. Measure viscosity at the start of each shift and each time paint in put into pressure tanks or
paints containers. For circulating systems check viscosity daily at the start of the first shift.
5.1 Failure to recognize the importance of proper preparation of the surface is responsible for
many cases of poor adhesion and poor rust protection. High quality paints may fail to give
satisfactory service when applied on wet, rusty, oily or dirty surfaces. Make certain that
surfaces are clean, dry and free from rust and scale before applying paints. The surface
temperature of the steel shall be at least 5℉ above the dew-point and it will be performed
under less than 80% humidity of relativity
5.2 Air blasting with shot or other abrasive materials is the best method for removing rust, scale,
weld slag and spatter. When this can not be done, use wire brushes, scrapers and abrasive
cloths to clean the surface.
5.3 Before applying paint on hard surfaced or glossy painted surfaces. It is advisable to dull the surface by
sanding lightly with 240 abrasive paper to promote adhesion of the next coat. Take care not to cut through
paint film while sanding. After sanding, clean surface by wiping with a clean cloth dampened with
solvent.
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-011
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 7 / 14
5.4 If, as the result of sanding, bare metal is exposed restore the finish system pretreatment and primer
using approved touch-up procedures.
6.1 Faulty application of paint is responsible for many cases of paint defects and failures. Each
coat of paint shall be smooth and thick enough to hide the uniform wet appearance when
being applied. Paint too heavily applied will not dry normally and may have a poor appear-
ance from runs, sags and wrinkling. When multiple coats are applied, it is advisable to have
a different color for each coat to assist the painter in applying the paint uniformly.
6.2 When brushing, apply the paint with overlapped strokes and avoid brush marks and run as mush as
possible. Use good brushes and take care of them between operations, keeps the bristles do not bend out
of shape. Clean brushes for storage by washing them first with paint thinner and finally with soap and
water.
6.3 When drying, apply uniform films which have a glossy wet appearance. Use cone shape spray for small
narrow areas and a fan shaped spray for large areas. Hole spray gun perpendicular to the surface and
about 20cm for the surface. Adjust air pressure and fluid feed to produce a smooth wet film. Use a
uniform straight sweeping motion. Do not vary the stroke. Keep nozzles and fluid tips clean by washing
with paint thinner
6.4 Each stroke of the gun shall overlap previous strokes from one third to one-half the width of the coat.
Avoid spraying dry dusty looking films by having the paint thinned to the correct
viscosity and by not holding gun too far away from the surface. Adjust atomizing pressure
to correspond with the fluid pressure on pressure spray tanks. Keep atomizing pressure as
low as possible to avoid dusty paint films but high enough to atomize the paint properly. An
increase in fluid pressure will increase the flow of paint and will require higher atomizing
pressure. Take care to coat sharp edges and bottom surface of flanges with the proper thickness of
paint.
7. Painting Conditions
7.1 Low temperature, high humidity and sometimes the lack of daylight slow up the rate of drying, In
cold weather moisture may condense on metal surfaces indoors when the dew point of the air is reached.
Atmospheric fumes may cloud or fog the surface of paint film.
Proper ventilation, temperature control and good lightning are essential to obtaining good results.
Working areas should be located where the air can be filtered. Avoid strong air current blowing over
painted surfaces. Temperatures of the air should not fall below 4C and, preferably, should be from 15
∼32C. And there shall be no moisture on the steel. The surface temperature of the steel shall be at least
5F above the dew point.
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-011
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 8 / 14
8.1 Measure film thickness of the dried films on significant areas to determine if they comply with process
of finish specification requirements. Measure film thickness on steel or magnetic surface or non-magnetic
surfaces, using a coating thickness gage supplied by DUO-CHECK, Germany.
9.1 Clean spray guns after each day of use by flushing gun with solvent. Remove air cap and
wash it with solvent. Wash fluid tip with solvent. Keep gun well lubricated. Keep fluid needle
packing nut tight but not so tight that it grips the needle. Do not immerse the whole gun in
solvent as this will damage the packing around the fluid needle.
9.2 Keep holes in the air cap free of dried paint or other foreign matter by cleaning with solvent and blowing
with an air blast. Keep fluid tip seat and other similar surface clean to prevent air leaks and fluttery
spray.
9.3 Use air hole of sufficient size to provide an adequate supply of air. Holes 0.5cm dia, shall not be used
over 3.6M in length. Hose 0.8cm dia, shell not be used in lengths over 15M.
Clean fluid hose after use by flushing with solvent and blowing with an air blast.
Do not allow kinks in air hose during use. Keep all connection nuts well tightened in use.
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-011
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 9 / 14
3. Powder Coating
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 10 / 14
1.1 Powder coating keeps away from a long term storage. If there is a disbanding of film or caking defect,
please, Don't use that powder.
1.2 Good storage is no direct ray of light or no heat source and well ventilated less than 30C on room
temperature. But, on storage, powder keeps away from storage with oil, solvent and water.
1.3 According to high atmosphere temperature, if there is a caking defect, you have to use vibrating Seive
which has a mesh of 150m.
2. Equipment control
2.1 Air container or pipe line is often dried. so, It has to be no condensation. Compressor has to install Air
Dryer and oil separator which prevent a pinholes, nozzle no spraying and caking defect in powder feeding
pump.
2.2 In order to get high electrostatic efficiency, It has to remove powder on Earthing Bar in spray
Booth, and measure earth condition with Galvanometer and resistance has to be less than
500 ohms.
2.3 Sticked powder on Gun Nozzle has to clean with Air and brush paint brush in booth.
3. Surface treatment
3.1 Surface treatment is improved quality of coating after removing scale on object.
3.2 Surface treatment method operates with Shot Blast the same method as liquid coating process.
4. Application
4.1 Powder coating which is fluidities with air current in Hopper, is carried to spray Gun through insulated
cable. Spray Gun is operated 30∼100kV in electrostatic power supply.
4.2 Edge of electrostatic spray Gun is operated 40∼80kV. It is coated with corona charge by an air of
dielectric break down strength is more than 3kV/mm.
4.3 Edge of electrostatic spray Gun has Diffuser which can control powder spray pattern.
4.4 Generally, each of Gun has 300∼400g/min feeding quantity. Spray efficiency has more or less 60%
and recovery powder has more or less 30%.
4.5 In order to spark prevention, Gun has to be 25∼30cm away from object. Air current in spray
Booth has to flow from outside to inside to flow out powder dust. Powder density in Booth
has to manage less than explosion limit (10 g/m3 Air). Difference kind of powder coating
has to check about difference physical properties and has not to use difference kind of powder in same
Booth.
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-011
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 11 / 14
4.6 Baking oven uses light oil or LPG. and indirect heating method which rise temperature with closed heat
exchange. Also, Oven has to maintain 230C for 10 min (Metal temperature 160℃) so, powder has to be
wetted on object surface.
4.7 When it uses recovery powder, It has to Seive with 200∼300m before Spray. When it sprays on big
size, the ratio of recovery and new powder is in the 3:1 ratio. When it sprays on small size or complex
object, the ratio of recovery and new powder is in the 1:1 ratio.
5. Inspection
5.1 Coated product has to be checked about Coating badness and measured coated thickness.
Measure instrument used the same liquid measure instrument.
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-011
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 12 / 14
4. Description of Paint
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 13 / 14
Description Outside
◎ Note : To protect the transformer insulation oil be polluted by impurities of radiator, the Inside
of radiator shall be coated with varnish.
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-011
Rev. No. : 1
TITLE PAINTING PROCEDURE
Page. No : 14 / 14
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : Cover
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-012
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : 1 / 12
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
For Construction
REV.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
NO.
REV.
HYOSUNG PREPARATION CHECK REVIEW APPROVAL
NO.
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : 2 / 12
Shop inspection
Test plan& Procedure
POSCO ENG/WAMPU PJT
10001303_0001, 4, 5
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : 3 / 12
Applied
Description of POSCO Factory/
Classification Specificatio HICO WEP
Inspection /Test ENG Place
n
1. Dimension & H W R
Construction Check (Ro)
2. Winding Resistance H W W
Measurement (Ro)
3. Winding Insulation H W W
Resistance Measurement
(Ro)
5. Phase Relationship H W W
Check (Ro)
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : 4 / 12
IEC 60076-3
21. Shipping preparation H W W
Inspection(S)
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : 5 / 12
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : 6 / 12
EXCITING CURRENT(A)
%Io = ───────────────── × 100
RATED CURRENT(A)
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : 7 / 12
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : 8 / 12
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : 9 / 12
A=5 min
B=5 min
C=120×(50Hz/240Hz)=25 sec or
C=120×(50Hz/180Hz)=33 sec
D=5 min
E=5 min
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-464-012
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : 10 / 12
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : 11 / 12
Rev. No. : 1
TITLE SHOP TEST PLAN & PROCEDURE
Page. No : 12 / 12
H1 H2 H3
X1 X2 X3
X1 X2 X3
H1 H2 H3
X1 X2 X3
VIEW A-A'
# NOTE #
1. ALL DIMENSION ARE IN MILLIMETERS.
2. DIMENSION AND WEIGHT WILL BE CHANGED
SLIGHTLY AFTER DETAIL DESIGN.
VIEW "A", FLANGE
VIEW "A", FLANGE
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-128-020
Rev. No. : 1
TRANFORMER LOCAL PANEL
TITLE
SPECIFICATION & DRAWINGS Page. No : Cover
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-128-020
Rev. No. : 1
TRANFORMER LOCAL PANEL
TITLE
SPECIFICATION & DRAWINGS Page. No : 1 / 26
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
For Construction
REV.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
NO.
REV.
HYOSUNG PREPARATION CHECK REVIEW APPROVAL
NO.
FOR CONSTRUCTION
SPECIFICATION
of
LOCAL CONTROL PANEL
for
POWER TRANSFORMER
Date: 27/11/13
1 Printed in Korea
Technical Information for Construction
A. General Specification
1. Scope
This specification covers the design and manufacturing of local control panel of
power transformer for POSCO ENG / INDONESIA WAMPU project.
2. Condition of Service
1) Installation: Outdoor
2) Altitude: Up to 1000 feet above sea level
3) Ambient temperature: -5 ~ 45℃
5. Dimension
Item Width (mm) Depth (mm) Height (mm)
6. Material
This panel is fabricated of steel plate of 2.3mm thickness or above.
B. Technical Specification
1. Power
1) AC power: 3 phase 50Hz AC 400V
2) AC control power: 1 phase 50Hz AC 230V
3) DC control power DC 110V
4) Supply: Supplied by customer
2. Wiring
1) Cable type: XHHW
2) Cable color and size: Refer to attached drawing.
3) Indication of phase and polarity are available.
2 Printed in Korea
Technical Information for Construction
4. Other equipments
1) Illumination lamp
■ AC 230V 20W
■ Fluorescent lamp
□ Out of scope
2) Space heater
■ Rating AC 230V 100W, Connected to 230V power source
□ Out of Scope
3) Name plate
Material: SUS
Letter color: Black
Background: Silver
5. Tests
1) Tested by HICO QC team
2) Test items
■ Construction and appearance inspection
■ Apparatus operation inspection
■ Insulating resistance test
3 Printed in Korea
1
1
1
1
1
1
1
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-128-022
Rev. No. : 1
OLTC MOTOR DRIVE UNIT
TITLE
CIRCUIT DIAGRAM Page. No : Cover
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
DOCU. NO. :
3x15MW WAMPU HEPP PROJECT 1009-4261-PE-128-022
Rev. No. : 1
OLTC MOTOR DRIVE UNIT
TITLE
CIRCUIT DIAGRAM Page. No : 1 / 8
DISCIPLINE : Electrical
PROJECT NAME : 3×15MW WAMPU HEPP PROJECT
For Construction
REV.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
NO.
REV.
HYOSUNG PREPARATION CHECK REVIEW APPROVAL
NO.