Sunteți pe pagina 1din 41

Cooling Plant Control Optimization

An Overview
Why Optimize Cooling Plant Control?

• Chillers/Pumps/Cooling Towers Are Largest Energy Consumers1

• Chillers Operate At Part-Load 95% Of The Time

• Chillers Become Progressively Less Efficient At Lower Load Levels

• A Small Increase In Percent Efficiency Results In Big Savings

• Maintenance Is Difficult To Anticipate And Plan

• Many Interrelated Variables Affect Plant Efficiency

1. See the following slides for a breakdown of the percentage of energy of a building’s total energy usage that is devoted to running chillers, chilled
water and condenser water pumps, and cooling tower fans for different regions of the country.

Slide 2 Company Confidential


Building Aggregate Percentage of Energy Devoted Operating a
Chiller Plant – South Region

100%

90% Communication

80% 10% 1%
Process Heat
70%
5%
60% 10%
Comfort Heat
50%

40% Cooling

30%
Power
20%

10% Lighting
0%
Offices Schools Industry Hospitals
(Comfort)

Source: „Energieverbrauch der Privaten Haushalte“; und des Sektors Gewerbe, Handel und Dienstleistaungen, Projektnummer
17/02; Abschlussbericht;
What Benefits should a Chiller Plant
Optimization Program have?
• Ability To Model Part Load Equipment Performance
• Endorsed algorithms for:
– Optimal sequencing of multiple chillers
– Optimal condenser water temperature
– Optimal cooling tower fan sequencing
• Savings Of 10 To 15 % On Annual Plant Power Consumption2
• Centralized Reporting And Monitoring Of Plant Parameters
• Automatic Recording Of Cumulative Energy Savings
• Optional Graphical Presentation Of Energy Savings and Plant Performance Parameters possible
• Avoidance Of Costly Breakdowns

• SBT US has this algorithm, called “CPOP”, for determining optimal chilled water supply and cooling coil
discharge air temperatures patented
• The North American CPOP uses ASHRAE3 endorsed algorithms as above

3 See 2003 ASHRAE HVAC Applications Handbook, pgs, 41.12 – 41.16 and 41.21 – 41.25.
2 For North American systems; the weather and humidity conditions can be different in Europe; so the figures above shall provide a range of potential savings.

Slide 4 Company Confidential


Typical Instrumentation: Primary-Secondary Chilled
Water Plant with Parallel Chillers

S/S S/S S/S

T
LEGEND
S/S S/S S/S.......Start/Stop Control
KW S/S AO from EMS T..........Temperature sensor
T KW.......Kilowatt transducer and sensor
FM........Flow meter

S/S S/S FM
KW S/S T
T
2-way control valves

T S/S S/S c c c c
KW S/S
T FM S/S

V/S pump

Slide 5 Company Confidential


Instrumentation and Data Point List

Analog Inputs Analog Outputs


• Condenser Water Inlet Temperature • (Chiller Inlet Guide Vane Controllers)
• Chilled Water Supply and Return • Cooling Tower Bypass Control
Temps Across Each Chiller • Variable Speed Pump Drive Controller
• Chilled Water Supply and Return
Header Temps
• Chilled Water Flow
• Chiller KW or Amp Transducers
Digital Outputs
• Chilled Water Terminal Unit
Δ Pressure • On/Off:
– Each Chiller
– Each CHW and CW Pump
– Each Tower Fan
Digital Inputs
– Each Variable Speed Pump
• ON/OFF Status Proofs for Chillers, – CHW and CW Isolation Valves
Pumps, Cooling Tower Fans on Each Chiller
• End Switches for Isolation Valves
• Chiller Alarms

Slide 6 Company Confidential


What are main Cooling Plant Optimization
Control Strategies?

• Soft Load Chillers (after having been OFF for a long period of time)

• Demand Limit Chillers

• Optimize Condenser Water Temperature


– Considers dynamics between chillers and towers

• Optimize Multiple Chiller Sequencing


– Dynamic Updating of Part-Load Curves
– Performed via Direct Commands or Operator Advisory Messages

Slide 7 Company Confidential


… more Cooling Plant Optimization Control Strategies

• Optimization Of Chilled Water Temperature2


– Performed via a mathematical model of chillers, CHW pumps, and air handler
fans
– Considers dynamics of chilled water pumps and air handler fans (variable
speed or constant speed) with the chiller
• Optimization of discharge air temperature from cooling coils
• Multiple, Parallel Variable Speed Pump Switchover
• Multiple Chiller Load Allocation

2 The technique of determining and controlling for optimal chilled water and coil discharge air temperature
in a DDC Controller has been patented. (U.S. Patent # 5,963,458: Digital Controller for a Cooling and
Heating Plant Having Near-Optimal Global Set Point Control Strategy, October 5, 1999).

Slide 8 Company Confidential


What influences the Optimized Control of
Chillers ?

• Efficiency (COP) and Power Draw of Chiller(s)


• Efficiency and Power Draw of Peripherie such as Variable Speed
Pump(s), Cooling Towers, and Air Handlers (if applicable)
• Set Points for Chilled Water, Coil Discharge Air, Air Handler Fan
Static Pressure, and Pump Diff Pressure
• Chilled/Condenser Water Temperature And Flow
• Evaporator Tube Fouling
• Outdoor Ambient Wet Bulb Temperature
• Air Flow Through Cooling Tower
• Cleanliness Of Cooling Tower
• Condenser Tube Fouling

Slide 9 Company Confidential


What is the overall Goal of Optimization
Control Strategies?

Minimize total chiller plant operating costs

– Includes analysis and programming logic that considers the


interaction that pumps, cooling towers, and air handler fans have on
the total cost of running the plant

– In all-electric chilled water plants, this reduces to minimizing the


chiller plant power input per ton (kW for Europe) of refrigeration

Slide 10
What Limitations Constrain Chiller Plant
Optimization?

• Chiller Refrigerant Head Above A Minimum Value


• Condenser Water Temperature Above Low Limit Temperature and
Below High Limit Temperature
• Primary Versus Secondary Flow
• Limit on Upward Reset of CHW Temp

Slide 11 Company Confidential


The Five Optimal Control Strategies…

1/ Multiple Chiller Sequencing


2/ Determining Switchover Flow Points for Multiple, Parallel V/S Pumps
3/ Optimizing Condenser Water Temperature
4/ Optimizing Chilled Water Temperature Considering CHW Pump and
AHU Fan Power
5/ Multiple Chiller Load Allocation (Optimal Load Balancing of Parallel
Chillers)

Slide 12 Company Confidential


Optimal Parallel
2/ Optimal Variable-Speed
Parallel Pump
Variable-Speed Sequencing
Pump Sequencing

• Pumps have the same head/flow characteristics

• Options range from simple strategy for sequencing to sequencing


pumps based on maintaining minimum pump KW

• For minimum pump KW strategy, the sequencing decision is based on


predicted KW with one more pump / one less pump operating,
compared to current configuration KW

• Pump ‘wire-to-water’ efficiencies might be considered

Slide 13 Company Confidential


Optimal Parallel Variable-Speed Pump Sequencing
You remember how Pump and System Curves look like?

100

Pump Curve
Total 80 Control Curve
Head System Curve
In 60
m Natural Operating Point
40

20
Maintained Differential
Head Across Sub Circuits

20 40 60 80 100 120 140

m3 per hour

Slide 14 Company Confidential


Optimal Parallel Variable-Speed Pump Sequencing
Ho do the curves look for Parallel Pump
Operating Points ?

m HEAD
60 Point of operation with
with both pumps running
50 Control curve

40
Piping Head Loss
30 Curve
Operation point of each
20 pump when both pumps
Run Operating point for
10 single pump operation

20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 320

m3/hr x 100

Slide 15 Company Confidential


Optimal Parallel Variable-Speed Pump Sequencing
… and how for Variable Speed Operating Points:
A, B, C, D, E ?

m HEAD
40 100% speed

90%
30
80% A Piping head loss curve
20 70% B
60% C
10 D
E Control curve

20 40 60 80 100 120 140 160 180 200 220 240 260

m3/hr x 100

Slide 16 Company Confidential


Optimal Parallel Variable-Speed Pump Sequencing
Single-Pump Versus Two-Pump Operation Ranges
for Variable Speed Pumps In Parallel

m HEAD
60
Two-pump operating band
50 Control curve
100% s 100% speed
40
Piping head loss
30 Single pump curve
operating band
20 60% s
60% s
10 End-of-curve operation

20 40 60 80 100 120 140 160 180 200 220 240 260 280 300

m3 per hour

Slide 17 Company Confidential


Optimal Parallel Variable-Speed Pump Sequencing
Determining Multiple, Parallel V/S Pump
Switch-Over (Simple Strategy)

60
50
40
30
20
10

20 40 60 80 100 120 140 160 180

Slide 18 Company Confidential


Optimal Parallel Variable-Speed Pump Sequencing
1/ Multiple
Multiple Chiller
Chiller Sequencing
Sequencing

It all starts with: Typical Chiller Manufacturer Published Part Load Performance Curves

Slide 19 Company Confidential


Multiple Chiller Sequencing
Typical Chiller Part-Load Performance Curve

COP

5.0

4.0

3.0

2.0

1.0

10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

% CHILLER LOAD

Slide 20 Company Confidential


Multiple Chiller Sequencing
Modeling Typical Chiller Part-Load Performance
Curve with LSQ2 and LSQDAT Statements
Q& ch ,i [ kW ]
COP =
( Pch ,i + Pchwp + Pcwp )[ kW ]
where : Pch ,i = a 0 ,i + a 1,i (T cwr ,i − T chws ,i ) + a 2 ,i (T cwr ,i − T chws ,i ) 2 + a 3 ,i Q& ch ,i + a 4 ,i Q& 2 ch ,i + a 5 ,i (T cwr ,i − T chws ,i )Q& ch ,i

5.0

4.0

3.0

2.0

1.0

10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

% CHILLER LOAD
Slide 21
Multiple Chiller Sequencing
COP Versus Load Characteristic Curves

500 kW Chiller Part-Load Performance

8
7
6
5
COP

4
COP (Chiller + Pumps)
3
2 COP (Chiller Only)

1
0
0 100 200 300 400 500 600
kW output

Slide 22 Company Confidential


Multiple Chiller Sequencing
Hybrid Chiller Plants - Onpeak
(e.g. electric-driven chillers and steam-driven chillers)

ON-Peak €/kWh(th) Vs. % Load


20

Chiller Only
15
€/kWh

10

Chiller + Pumps
5 + Towers

0
0 50 100 150
Percent Cooling Load
Slide 23 Company Confidential
Multiple Chiller Sequencing
Hybrid Chiller Plants – Off Peak

OFF-Peak €/kWh(th) Vs. % Load


0.05

0.04 Chiller Only

0.03
€/kWh

0.02
Chiller + Pumps
0.01 + Towers

0.00
0 50 100 150
Percent Cooling Load

Slide 24 Company Confidential


Multiple Chiller Sequencing
Consideration of CHW and CW
Pumps in Staging Decisions

COP

5.0

4.0

3.0

2.0
COP a = Includes pump power
COP a
= One chiller operation
1.0
= Two chiller operation

200 400 600 800 1000


Switch over point without considering Switch over point considering
pump power pump power
CHILLER LOAD

Slide 25 Company Confidential


Multiple Chiller Sequencing
Optimum Chiller Combination Selections
(consider previous slide)

• Based on Proportionate Sharing of the Facility Cooling Load Among


Multiple Chillers Using Actual Part-Load Curves

• Chiller Combination with Minimum Predicted Power Draw Selected


ONLY When Another Chiller is Needed

• Chiller Combinations Must Be Valid


– Load ratio range must lie between 30% (adjustable) - 100%
– Chiller(s) cannot be in alarm
– Chiller(s) cannot be locked-out

Slide 26 Company Confidential


Multiple Chiller Sequencing
Predicted Chiller KW Draw for Different Chiller Combinations

Plant kW Cooling

Slide 27 Company Confidential


Multiple Chiller Sequencing
Method of Determining COP Sequence Order of Chillers
(used for chiller shut-down logic)

COP

5.0
slope = 0 when x=-B/2A

4.0 Max COP

3.0

COP = Ax*x+Bx+C
2.0
x = % chiller load

Load at which
1.0
max COP occurs

10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

% CHILLER LOAD

Slide 28 Company Confidential


Multiple Chiller Sequencing
Condenser Water Temperature Optimization
Considers Interaction of Chiller and Cooling Tower

• First Priority: - Maintain condenser water temp and CW flow per


cell between high and low limits

• Second Priority: - Cycle tower fans to maintain minimum chiller


plus tower power

Condenser Water Temperature Optimization


Slide 29 Company Confidential
Considers Interaction of Chiller and Cooling Tower
The Pressure Enthalpy Diagramm - Basics and Control Strategies

(log P)

subcooling
condension

expansion compression
evaporation

superheat

Enthalpy
Condenser Water Temperature Optimization
Considers Interaction of Chiller and Cooling Tower
Control Constraints On Condenser Water Temperature:

• Maintain Above A Low Limit Temp/ Below A High Limit Temp


• Maintain Between A Low and High Limit CW flow per cell
– Maintain above low limit to avoid poor heat transfer and tower fouling
– Maintain below a high limit to avoid tower nozzle and header damage

• Increase Tower Fan Speed


– At High Limit Value of Condenser Water Temperature
– When Maximum Chiller Power Is Reached

Condenser Water Temperature Optimization


Slide 31 Company Confidential
Considers Interaction of Chiller and Cooling Tower
DDC Algorithm for Optimizing Tower Air Flow

• Open Loop Tower Fan Control Concept


– Advantages

• Based on ASHRAE paper by Braun and Diderrich (1990)


– Optimize tower fan sequencing
– Optimize tower fan air flow

RAFtwr = 1 − γ twr ( PLRtwr, cap − PLR) PLRfreecooling < PLR < 1. 0


[
RAFtwr = 4PLR1 − γ twr (PLRtwr,cap − PLRfreecooling ) PLR < 0.25 ]
Condenser Water Temperature Optimization
Slide 32 Company Confidential
Considers Interaction of Chiller and Cooling Tower
Optimum Tower Air Flow: Parameter Calculations

Parameter Single-Speed Fans Two-Speed Fans Variable-Speed Fans


PLRtwr, cap PLR0 2 ⋅ PLR0 3 ⋅ PLR0
γ twr 1 2 1
PLRtwr, cap 3⋅ PLRtwr, cap 2⋅ PLRtwr, cap
1
PLR0 =
⎛ Pch,des ⎞
⎜ ⎟ ⋅ S ⋅ (atwr,des + rtwr,des )
⎜P ⎟
⎝ twr,des ⎠
where:
⎛ Pch,des ⎞
⎜ ⎟ = the ratio of the chiller power to cooling tower fan power at design conditions
⎜P ⎟
⎝ twr,des ⎠
(changein chiller power)
S = Sensitivity=
(changein condenserwater temperature) × (chiller power)
(atwr,des + rtwr,des ) = the sum of the tower approach and range at design conditions

Condenser Water Temperature Optimization


Slide 33 Company Confidential
Considers Interaction of Chiller and Cooling Tower
Tower Fan Sequencing Rules for Optimal Operation

• Variable Speed Fans


– Open tower cells sequentially with fans at minimum speed.
Then, operate all cells with fans at equal speeds.

• Multi-Speed Fans
– Increment the lowest speed fans first when adding tower fan
capacity. Reverse for removing capacity.

• Variable/Multi-Speed Fans
– Operate all cells with variable speed fans first
– Control all variable speed fans at equal speeds
– Increment lowest speed fans first when adding tower capacity
– Command a multi-speed fan to SLOW when all variable speed
fans match the SLOW speed when either incrementing or
decrementing tower capacity
– Decrement variable speed fans first when removing tower fan
capacity

Condenser Water Temperature Optimization


Slide 34 Company Confidential
Considers Interaction of Chiller and Cooling Tower
Optimal Chilled Water and Cooling Coil Discharge Air
Temp Control

Control Strategy:

• Reset Chilled Water Temperature Upward Until:

Ptot = Pcomp + Ppump + PAHU

(log P)
is minimized

subcooling condension

expansion
compression
evaporation

superheat

Optimal Chilled Water and Cooling Coil Discharge Air


Temp Control
Slide 35 Company Confidential
Enthalpy
Mathematical Models of Cooling Plant Components

• Chiller Pchlr = K comp ⋅ ΔTchw


3
⎛ 1 ⎞
• Chilled water pump Ppump = K pump ⎜⎜ ⎟⎟
⎝ ΔTchw ⎠
• Air handler fan
3 3
⎛ 1 ⎞ ⎛ 1 ⎞
Pfan = K fan ⎜⎜ ⎟⎟ = K ' fan ⎜⎜ ⎟⎟
⎝ ΔTair ⎠ ⎝ ΔTchw ⎠

Optimal Chilled Water and Cooling Coil Discharge Air


Temp Control
Slide 36 Company Confidential
Chilled Water Temperature Optimization –
Problem Formulation

Ptot = ∑P comp
+ ∑P pump
+ ∑P fan

The optimum Δ T chw is found by :


d ( Ptot )
=0
d ( Δ T chw )
3( ∑ K + ∑K )
⇒ Δ T chw , opt = 4 pump fan

∑K comp

The optimum chilled water su pply temp is :


T chws , opt = T chwr − Δ T chw , opt

Optimal Chilled Water and Cooling Coil Discharge Air


Temp Control
Slide 37 Company Confidential
Relationship Between Chiller, CHW Pump, and AHU Power
Consumption, with CHW Temperature and Load

Power Consumption Vs. CHW Delta T

8000
7000 Chiller Pow er
6000
Power (KW)

5000 CHW Pump Pow er


4000
3000 AHU Fan Pow er
2000
1000 Total Pow er
0
0 5
2.5°C 10
5°C 15
7.5°C

CHW Delta T (°C)

Slide 38 Company Confidential


Calculating Optimum Coil Discharge Air Temperature

RH
• First, calculate optimum CHW
supply temp
• Assume air-water energy balance
at coil at each steady-state load
• Solve for return CHW temp from
Tma Tda
each coil
C
• Calculate optimum discharge air
temp from:
C
– Measured values of CFM, Tma and
Tchws Tda, CHW supply temp
– Calculated values of coil CHW
flow, ω, Topt,chws

Slide 39 Company Confidential


Multiple Chiller Load Allocation
(Optimal Load Balancing of Parallel Chillers)

€/hr dC A dC B dCC
Necessary Condition : = =
50 dx A dxB dxC
40 Constraint : L = xA + xB + xC
CC = aC xC + bC xC + cC
B 2

30 A C
C A = a A x A + bA x A + c A
2
C B = a B xB + bB xB + cB
2

20

10

100 200 300 400 500 600 700 800 900 1000

CHILLER LOAD

Slide 40 Company Confidential


Summary

• Chiller Performance Is A Function Of Many Interrelated Variables

• Continuously Optimizing Control Performance Over Time Requires


Adaptive Algorithms

• DDC Controllers Can Use Methods Such As:


– Storing Part-Load Equipment Performance as Data Points
– Altering Stored Part-Load curves from Actual Data Points
– Least Squares Curve Fitting of Equipment Performance Data Points
– Calculating Minimum Value of Parabolic Performance Curves

• Adaptive Chiller Control Algorithms Are Superior Because Energy


Savings Are Continuously Optimized

Slide 41 Company Confidential

S-ar putea să vă placă și