Sunteți pe pagina 1din 30

Chapter 1 contains the following:

1. INTRODUCTION

1.1. Overview of System X

1.2. Purpose of this Document

1.3. Formal Reviewing

1.4. Objectives of System Test

 2. SCOPE AND OBJECTIVES


o 2.1. Scope of Test Approach - System Functions
 2.1.1. Inclusions
 2.1.2. Exclusions
o 2.2. Testing Process
o 2.3. Testing Scope
 2.3.1. Functional Testing
 2.3.2. Integration Testing
 2.3.3. Business (User) Acceptance Test
 2.3.4. Performance Testing
 2.3.5. Regression Testing
 2.3.6. Bash & Multi-User Testing
 2.3.7. Technical Testing
 2.3.8. Operations Acceptance Testing (OAT)
o 2.4. System Test Entrance/Exit Criteria
 Entrance Criteria
 Exit Criteria

3. TEST PHASES AND CYCLES

o 3.1. System Testing Cycles


o 3.1.1. Test Cases by Release version.
o 3.1.2. Automated Testing.
o 3.2. Software Delivery
o 3.2.1. Release Schedule.
o 3.3. Formal Review Points
o 3.3.1. Review Points.
o 3.3.2. Progress/Results Monitoring
 4. System Test Schedule
 5. RESOURCES
o 5.1. Human
o 5.2. Hardware
o Hardware components required
o 5.3. Software
o Test Host environments
o Test Branch Software
o Error Measurement System
 6. ROLES AND RESPONSIBILITIES
o 6.1. Management Team
o 6.2. Testing Team
o 6.3. Business Team
o 6.4. Testing Support Team
o 6.5. External Support Team

7. Error Management/Configuration Management

 8. STATUS REPORTING
o 8.1. Status Reporting

 9. ISSUES/RISKS & ASSUMPTIONS

 9.1. Issues/Risks

 9.2. Assumptions
 10. Signoff
 11. APPENDICES
o 11.1. Purpose of Error Review Team.
o 11.2. Error Review Team Meeting Agenda.
o 11.3. Classification of Bugs
o 11.4. Procedure for maintenance of Error logging system.
o 11.5. Overnight Processing - Checking Bookkeeping & CIS
 11.7. SOFTWARE QUALITY ASSURANCE MEASURES
o (i) DATES.
o (ii) EFFORT.
o (iii) VOLUME.
o (iv) QUALITY.
o (v) TURNAROUND.
1. INTRODUCTION

1.1. Overview of System X

To aim of this phase of the project is to implement a new X System platform that will
enable:

 Removal of legacy office systems


 Introduction of ABC
 Processing of Special Transactions
 No constraint on location of capture
 Enable capture of transactions for other processing systems
 New Reconciliation Process
 Positioning for European ECU Currency and future initiatives

This programme will result in significant changes to the current departmental and inter-
office processes. The functionality will be delivered on a phased basis.

Phase 1 will incorporate the following facilities :

 Replacement of the legacy System A


 New Reconciliation System
 Outsourcing system for departments in different european countries.
 New/Revised Audit Trail & Query Facilities
[Detailed inclusions are listed later in this document]

1.2. Purpose of this Document

This document is to serve as the Draft Test Approach for the Business Systems
Development Project.

Preparation for this test consists of three major stages:-

 The Test Approach sets the scope of system testing, the overall strategy to be
adopted, the activities to be completed, the general resources required and the
methods and processes to be used to test the release. It also details the activities,
dependencies and effort required to conduct the System Test.

 Test Planning details the activities, dependencies and effort required to conduct the
System Test.

 Test Conditions/Cases documents the tests to be applied, the data to be


processed, the automated testing coverage and the expected results.

1.3. Formal Reviewing

There will be several formal review points before and during system test. This is a vital
element in achieving a quality product.

1.3.1. Formal Review Points

1. Design Documentation
2. Testing Approach
3. Unit Test Plans
4. Unit Test Conditions & Results
5. System Test Conditions
6. System Test Progress
7. Post System Test Review

1.4. Objectives of System Test

At a high level, this System Test intends to prove that :-

 The functionality, delivered by the development team, is as specified by the business


in the Business Design Specification Document and the Requirements
Documentation.
 The software is of high quality; the software will replace/support the intended
business functions and achieves the standards required by the company for the
development of new systems.

 The software delivered interfaces correctly with existing systems, including Windows
98.

[Detailed objectives are listed later in this document.]

1.4.1. Software Quality Assurance involvement

The above V Model shows the optimum testing process, where test preparation commences
as soon as the Requirements Catalogue is produced. System Test planning commenced at
an early stage, and for this reason, the System test will benefit from Quality initiatives
throughout the project lifecycle.

The responsibility for testing between the Project & Software Qualtiy Assurance (S.Q.A.) is
as follows:

 Unit Test is the responsibility of the Development Team


 System Testing is the responsibility of SQA
 User Acceptance Testing is the Responsibility of the User Representatives Team
 Technology Compliance Testing is the responsibility of the Systems Installation &
Support Group.

2. SCOPE AND OBJECTIVES


2.1. Scope of Test Approach - System Functions
2.1.1. INCLUSIONS
The contents of this release are as follows :-

Phase 1 Deliverables

o New & revised Transaction Processing with automated support


o New Customer Query Processes and systems
o Revised Inter-Office Audit process
o Relocate Exceptions to Head Office
o New centralised Agency Management system
o Revised Query Management process
o Revised Retrievals process
o New International Reconciliation process
o New Account Reconciliation process

2.1.2. EXCLUSIONS
When the scope of each Phase has been agreed and signed off, no further inclusions will be
considered for inclusion in this release, except:

(1) Where there is the express permission and agreement of the Business Analyst and the
System Test Controller;

(2) Where the changes/inclusions will not require significant effort on behalf of the test
team (i.e. requiring extra preparation - new test conditions etc.) and will not adversely
affect the test schedule.

[See Section 9.1.]

2.1.3. SPECIFIC EXCLUSIONS

 Cash management is not included in this phase


 Sign On/Sign Off functions are excluded - this will be addressed by existing
processes
 The existing Special Order facility will not be replaced
 Foreign Currency Transactions
 International Data Exchanges
 Accounting or reporting of Euro transactions

Reference & Source Documentation:

1. Business Processes Design Document - Document Ref: BPD-1011


2. Transaction Requirements for Phase 1 - Document Ref: TR_PHASE1-4032
3. Project Issues & Risks Database - T:\Data\Project\PROJECT.MDB
4. The System Development Standards - Document Ref: DEVSTD-1098-2
5. System Development Lifecycle - Document Ref: SDLC-301
 

2.2. Testing Process

The diagram above outlines the Test Process approach that will be followed.
 

a. Organise Project involves creating a System Test Plan, Schedule & Test Approach, and
requesting/assigning resources.

b. Design/Build System Test involves identifying Test Cycles, Test Cases, Entrance & Exit Criteria,
Expected Results, etc. In general, test conditions/expected results will be identified by the Test
Team in conjunction with the Project Business Analyst or Business Expert. The Test Team will then
identify Test Cases and the Data required. The Test conditions are derived from the Business
Design and the Transaction Requirements Documents

c. Design/Build Test Procedures includes setting up procedures such as Error Management


systems and Status reporting, and setting up the data tables for the Automated Testing Tool.

d. Build Test Environment includes requesting/building hardware, software and data set-ups.

e. Execute Project Integration Test - See Section 3 - Test Phases & Cycles

f. Execute Operations Acceptance Test - See Section 3 - Test Phases & Cycles

g. Signoff - Signoff happens when all pre-defined exit criteria have been achieved. See Section 2.4.

2.2.1. Exclusions

SQA will not deal directly with the business design regarding any design / functional issues /
queries.
The development team is the supplier to SQA - if design / functional issues arise they should
be resolved by the development team and its suppliers.

2.3. Testing Scope


Outlined below are the main test types that will be performed for this release. All system
test plans and conditions will be developed from the functional specification and the
requirements catalogue.
 

2.3.1. Functional Testing


The objective of this test is to ensure that each element of the application meets the
functional requirements of the business as outlined in the :

 Requirements Catalogue
 Business Design Specification
 Year 2000 Development Standards
 Other functional documents produced during the course of the project i.e. resolution
to issues/change requests/feedback.

This stage will also include Validation Testing - which is intensive testing of the new Front
end fields and screens. Windows GUI Standards; valid, invalid and limit data input; screen &
field look and appearance, and overall consistency with the rest of the application.

The third stage includes Specific Functional testing - these are low-level tests which aim
to test the individual processes and data flows.

2.3.2. Integration Testing


This test proves that all areas of the system interface with each other correctly and that
there are no gaps in the data flow. Final Integration Test proves that system works as
integrated unit when all the fixes are complete.

2.3.3. Business (User) Acceptance Test


This test, which is planned and executed by the Business Representative(s), ensures that
the system operates in the manner expected, and any supporting material such as
procedures, forms etc. are accurate and suitable for the purpose intended. It is high level
testing, ensuring that there are no gaps in functionality.

2.3.4. Performance Testing


These tests ensure that the system provides acceptable response times (which should not
exceed 4 seconds).
2.3.5. Regression Testing
A Regression test will be performed after the release of each Phase to ensure that -

 There is no impact on previously released software, and


 to ensure that there is an increase in the functionality and stability of the software.

The regression testing will be automated using the automated testing tool.

2.3.6. Bash & Multi-User Testing


Multi-user testing will attempt to prove that it is possible for an acceptable number of users
to work with the system at the same time. The object of Bash testing is an ad-hoc attempt
to break the system.

2.3.7. Technical Testing


Technical Testing will be the responsibility of the Development Team.

2.3.8. Operations Acceptance Testing (OAT)


This phase of testing is to be performed by the Systems Installation and Support group,
prior to implementing the system in a live site. The SIS team will define their own testing
criteria, and carry out the tests.

2.4. System Test Entrance/Exit Criteria

2.4.1. Entrance Criteria
The Entrance Criteria specified by the system test controller, should be fulfilled before
System Test can commence. In the event, that any criterion has not been achieved, the
System Test may commence if Business Team and Test Controller are in full agreement that
the risk is manageable.

  All developed code must be unit tested. Unit and Link Testing must be completed
and signed off by development team.
  System Test plans must be signed off by Business Analyst and Test Controller.
  All human resources must be assigned and in place.
  All test hardware and environments must be in place, and free for System test use.
  The Acceptance Tests must be completed, with a pass rate of not less than 80%.

Acceptance Tests:
25 test cases will be performed for the acceptance tests. To achieve the acceptance criteria
20 of the 25 cases should be completed successfully - i.e. a pass rate of 80% must be
achieved before the software will be accepted for System Test proper to start. This means
that any errors found during acceptance testing should not prevent the completion of 80%
of the acceptance test applications.

Note: These tests are not intended to perform in depth testing of the software.
[For details of the acceptance tests to be performed see
X:\Testing\Phase_1\Testcond\Criteria.doc]

Resumption Criteria
In the event that system testing is suspended resumption criteria will be specified and
testing will not re-commence until the software reaches these criteria.

2.4.2. Exit Criteria
The Exit Criteria detailed below must be achieved before the Phase 1 software can be
recommended for promotion to Operations Acceptance status. Furthermore, I recommend
that there be a minimum 2 days effort Final Integration testing AFTER the final fix/change
has been retested. [See section 9.3]

  All High Priority errors from System Test must be fixed and tested
  If any medium or low-priority errors are outstanding - the implementation risk must
be signed off as acceptable by Business Analyst and Business Expert
  Project Integration Test must be signed off by Test Controller and Business Analyst.
  Business Acceptance Test must be signed off by Business Expert.

3. TEST PHASES AND CYCLES


There will be two main stages of testing for the new application during System Test :-

 System Testing
 Operations Acceptance Testing

3.1. System Testing Cycles

The main thrust of the approach is to intensively test the front end in the first two releases,
thus raising approximately 80% of errors in this period. With the majority of these errors
fixed, standard and/or frequently used actions will be tested to prove individual elements
and total system processing in Release v0.3. Regression testing of outstanding errors will be
performed on an ongoing basis.

When all errors (which potentially impact overall processing) are fixed, an additional set of
test cases are processed in Release v0.4 to ensure the system works in an integrated
manner. It is intended that Release v0.4 be the final proving of the system as a single
application. There should be no A or B class errors outstanding prior to the start of Release
v0.4 testing.

Test Cases by Release version:

Testing by Phase  
  Acceptance 1
Release v0.1 Functional 1
  User Acceptance 
  Acceptance 2
Release v0.2 Functional 2
  Regression 1
  Acceptance 3
  Functional 3
Release v0.3 Performance 1
  Bash & Multi-User Testing
  Regression 1
  Regression 2
  Integration 1
  Technical 1
Release v0.4 Regression 1
  Regression 2
  Regression 3
  Installation Test
Contingency Per Bug Fix Test Only

3.1.2. Automated Testing


Automated testing tools will be used in the test environment for functional and regression
testing. The main focus of the automated testing will be the regression testing of the
previously delivered functionality - i.e. when development version 0.2 of the software is
delivered the majority of the regression testing of the functionality delivered in development
version 0.1 will be automated. It is estimated that the full benefit of the automated testing
will only occur when the tests have been executed three or more times.

3.2. Software Delivery


During System Test the release of new versions of the software will be co-ordinated
between the Development Team leader and the System Test Controller. However, unless it
concerns a fix to a very serious error, new versions should only be released when a agreed
targets have been reached (i.e. the next version contains fixes to X or more numbers of
bugs).

Release Schedule:

Functionality to  v0.1 v0.2 v0.3 v0.4 v1.0


be Delivered * 1st May 17th May 31st May 18th June 29th June
1. Function A          
2. Process B       No New Bug Fix
3. Euro Reqs'       Functionality contingency
4. Y2K Reqs.       to be release
5. Inter Office Trans       delivered only.
6. International Trans.       in this  
7. Other.       release.  

* (per functional spec, by priority)

Notes:
It is intended that 80% of the functionality will have been tested in full prior to the Phase 3
Release.
All the functionality must be present in the Phase 3 Release.
No previously undelivered functionality will be accepted for testing after Phase 3.

3.3. Formal Reviewing


There will be several formal review points before and during system test, including the
review of this document. This is a vital element in achieving a quality product.
3.3.1. Formal Review Points

1. Design Documentation - Requirements Specification & Functional Specification


2. System Test Plan
3. Unit Test Plans & Test Conditions
4. Unit Test Results
5. System Test Conditions
6. System Test Progress/Results
7. Post System Test Review
8. Integration Test Results
9. Pilot Implementation Review
10. Project Review

The diagram above outlines the Test Approach. Boxes 1 - 6 show the major review stages
prior to Test execution. Boxes 7 - 10 show the phases planned for & after test execution.

While the above diagram concentrates on the testing aspect of SQA's role, there is an
ongoing role also, in ensuring the quality of the major deliverables throughout the lifecycle
of the project. SQA's role will be to ensure that all Quality Inspections occur for all the
agreed deliverables and that follow up actions and initiatives are pursued.
 

3.3.2.  Progress/Results Monitoring

 Acceptance Test 1 Results


 Test Results - Release v0.1
 Test Results - Release v0.2
 Test Results - Release v0.3
 Performance Test 1 Results
 Regression 1 & 2 Results
 Test Results - Release v0.4
 Technical Test Results

4. System Test Schedule


These are screenshots of several high level views of the project schedule.
These schedules are intended as examples only and probably will not correspond exactly with the
rest of the test plan.
. RESOURCES
5.1. Human
 

Resource Type  Resource Title  No.  Date Req'd  Who  Status 


           

Project Mgmt/Functional  Business Analyst   1  -  A.N. Other  Assigned 

           

Testing  Test Controller   1   - A. Smith  Assigned 

  Testers   4   1st May   To Be Assigned 

           

Test Support Team  Support Programmers   4  15th May   To be Assigned 

  Technical Support   1  1st May   To be Assigned 

  WAN Support   1  25th May   To be Assigned 

           

Technical - External  CIS Support  1  25th May   To be Assigned 

  Bookkeeping Support   1  15th May   To be Assigned 

  External Liaison Support   1  25th May C. Jones  Assigned

           

Business  Business Expert/   1  1st May   To be Assigned 


Business Representative 

           

5.2. Hardware
One seperate, controlled system will be required for the initial phase
of testing, setup as per one standard, complete office environment.
In order to maintain the integrity of the test environment his network
will not be accessible to anybody outside this project. The printers are
also exclusively for use by the test network.

Hardware components required

 1 Network Controller
 6 Networked PC's (See below)
 1 DAP Workstation
 1 Motorola 6520
 1 Alpha AXP Server
 1 Batch Waste Printer
 1 HP LaserJet 4v Printer

PC Specifications
            The 6 PC's required for the test environment will include the following:
            1 x P100, 1Gb HD, 16Mb RAM [Current Minimum Specification]
            3 x P166, 1.5Gb HD, 32Mb RAM [Current Standard Specification]
            1 x P333, 2.5Gb HD, 64Mb RAM [Current Maximum Specification]
These specifications are the various specifications currently in use in different branches.

1 x Pentium running Windows NT is also required as the Test center for controlling and
executing the automated testing.

5.3. Software
Test IMS environments
Test IMS region X will be required for System Testing. Additional or amended
data will be populated where required.

Test Environment Software


System Test will be run on the following Software Versions :-
            Custom Destop Vers.97.0.1
            Windows 95 Operating System
            Visual Basic 5 Runtime Files
            MS Office 97
            Novell Netware

Error Measurement System


This system test will use a bespoke MS Access database Error Management system.
A new database will be implemented for the sole use of this project.

[See Chapter x ]

6. ROLES AND RESPONSIBILITIES


6.1. Management Team
Project Leader - B. Ruthlenn
Ensure Phase 1 is delivered to schedule, budget & quality
Ensure Exit Criteria are achieved prior to System Test Signoff
Regularly review Testing progress with Test Controller.
Liaise with external Groups e.g. New Systems
Raise and manage issues/risks relating to project or outside Test Teams control.
Review & sign off Test approach, plans and schedule.

SQA Project Leader - C. Nicely


Ensure Phase 1 is delivered to schedule, budget & quality
Regularly review Testing progress
Manage issues/risks relating to System Test Team
Provide resources necessary for completing system test.

6.2. Testing Team


Test Planner / Controller - D. Everyman
Ensure Phase 1 is delivered to schedule, budget & quality
Produce High Level and Detailed Test Conditions
Produce Expected Results
Report progress at regular status reporting meetings
Co-ordinate review & signoff of Test Conditions
Manage individual test cycles & resolve tester queries/problems.
Ensure test systems outages/problems are reported immediately and followed up.
Ensure Entrance criteria are achieved prior to System Test start.
Ensure Exit criteria are achieved prior to System Test signoff.

Testers
Identify Test Data
Execute Test Conditions and Markoff results
Raise Software Error Reports
Administer Error Measurement System

6.3. Business Team


Business Analyst - E. Showman
Review high level / detailed test plans for System Test
Define Procedures
Resolve design issues
Resolve Business issues
Take part in daily test Error Review Team meetings

Business Representative - ?? (To be Assigned)


Execute User Acceptance Testing
Define Test Conditions/Expected Results for Business Acceptance Test
Resolve user issues
Resolve Design issues

6.4. Testing Support Team


Support Programmers
Take part in daily Error Review Team meetings
Co-ordinate/provide support for system test.
Resolve errors
Re-release test software after amendments
Support Systems Testers

6.5. External Support Team


CIS Support
Provide CIS support, if required.
Resolve CIS queries, if required.

IMS Support
Provide System Test Support
Support IMS Regions
Resolve Spooling Issues (if necessary)
Bookkeeping Integration & Compliance (if necessary)
Resolve queries arising from remote backup

Bookkeeping Support
Provide Bookkeeping Technical support, if required.
Resolve queries, if required.

Technical Support
Provide support for hardware environment
Provide support for Test software
Promote Software to system test environment

Access Support
Provide and support Test Databases

. Error Management & Configuration Management


During System Test, errors will be recorded as they are detected on Error Report forms. These
forms will be input on the Error Management System each evening with status "Error Raised"
or "Query Raised". The Error Review Team will meet each morning (10am, Conference Room)
to review and prioritise DN's raised the previous day, and assign them or drop them as
appropriate. This team will consist of the following representatives:-

  A. Boring - Development Team Leader


  B. Curie - Business Analyst
  C. Durine - Test Controller
  D. Ewards - Business Representative

Errors, which are agreed as valid, will be categorised as follows by the Error Review Team :-

 Category A - Serious errors that prevent System test of a particular function continuing
or serious data type error
 Category B - Serious or missing data related errors that will not prevent implementation.
 Category C - Minor errors that do not prevent or hinder functionality.

Category A errors should be turned around by Bug Fix Team in 48 hours (this is turn around
from time raised at Error Review Team meeting to time fix is released to System Test
environment). In the event of an A error that prevents System Test continuing, the turnaround
should be within 4 hours.
Category B errors should be turned around in 1 day; while
Category C errors should be turned around in 3 days.

However, the release of newer versions of the software will be co-ordinated with the Test
Controller - new versions should only be released when agreed, and where there is a definite
benefit (i.e. contains fixes to X or more numbers of bugs).
 

8. STATUS REPORTING
8.1. Status Reporting
Test preparation and Testing progress will be formally reported during a weekly Status Meeting.
The attendees at this meeting are :-
 

 Byron Ruthlenn - Project Manager


 Dion Ryan- Business Design Team
 Pat Smith - Development Team Leader

A status report will be prepared by the Test Controller to facilitate this meeting. This report will
contain the following information :-

1. Current Status v. Plan (Ahead/Behind/On Schedule)


2. Progress of tasks planned for previous week
3. Tasks planned for next week including tasks carried from previous week
4. Error Statistics from Error Measurement system
5. Issues/Risks
6. AOB.

. Issues, Risks and Assumptions


9.1. Issues/Risks
1. No further changes or inclusions will be considered for inclusion in this release except (1)
where there is the express permission and agreement of the Business Analyst and the System
Test Controller; (2) Where the changes/inclusions will not require significant effort on behalf of
the test team and will not adversely affect the test schedule. This is a potentially serious issue, as
any major changes to design will entail additional time to re-plan testing and to create or amend
test conditions
.
Resp : Byron Ruthlenn
Final list of inclusions to be Signed off.

2. The design of the software must be final, and design documentation must be complete,
informative and signed off by all parties prior to System Test proper commences.

Resp : D.A. Stone

3. A weakness in the 'phased delivery' approach is that the the high degree of interdependency in
the code means that the smallest changes can have serious effects to areas of the application
which apparently have not been changed. The assumption of the test team is that previously
delivered and tested functionality will only require regression testing to verify that it 'still' works.
I.e. testing will not be intended to discover new errors. Because of this I recommend that there be
a minimum 2 days regression testing AFTER the final fix/change has been retested. This
however, imposes a fixed time constraint on the completion of system testing which requires the
agreement of the Project Leader.

Resp : Byron Ruthlenn

4. Automated Testing
The majority of the Regression testing will be performed using the automated test tool. However,
due to the workload required to implement (and debug) the test tool fully it is likely that the
return will only be maximised after the 3rd time running the regression test suite for each release.
The other major uses of the test tool are for (1) Load Testing, (2) Multi-User Testing, and (3)
Repetitive data entry.

Resp : Test Controller

9.2. Assumptions

 Software will be delivered on time.


 Software is of the required quality.
 The software will not be impacted by impending Y2K compliance changes to the external
software infrastructure - i.e. any external software changes will have to be compatible
with this application.
 All "Show-Stopper" bugs receive immediate attention from the development team.
 All bugs found in a version of the software will be fixed and unit tested by the
development team before the next version is released.
 Functionality is delivered to schedule.
 Required resources available.
 All service agreements will be met.
 The automated test tool will function & interface correctly with the software.
 All documentation will be up to date and delivered to the system test team.
 Functional and technical specifications will be signed off by the business.
 All service agreements will be met.
 The Intranet will be fully functional prior to project commencement. 

. Formal Signoff
This document must be formally approved before System Test can commence. The following
people will be required to sign off :-

Group Signatures:
Project Manager Byron Ruthlenn
SQA Colm Jones
Testing Team Dion Hais
Development Team      Erwin Smith

11. APPENDICES
11.1. Purpose of Error Review Team.

Ensure maximum efficiency of the development and system testing teams for the release of the
new office software through close co-operation of all involved parties.

This will be achieved through daily meetings whose function will be to

 Agree status of each raised Error


 Prioritisation of valid Error's
 Ensure that enough documentation is available with Error's.
 Agree content and timescale for software releases into System test.
 Ensure one agreed source of Error reporting information.
 Identify any issues which may affect the performance of system testing.

11.2. Error Review Team Meeting Agenda.

 Review any actions from last meeting.

 Classify and prioritise each Error.

 Review Error's raised for Duplicates etc.


 Agree priority of each Error
 Determine adequacy of documentation associated with raised Error's.
 Agree release content and timescale.

 Review of assigned actions from meeting.

 AOB

11.3. Classification of Bugs

1.  An "A" bug is a either a showstopper or of such importance as to radically affect the
functionality of the system i.e. :

    - Examples of showstoppers


            - If, because of a consistent crash during processing of a particular type of application, a
user could not complete that type of
               application.
            - Incorrect data is passed to legacy system resulting in corruption or system crashes

    - Example of severally affected functionality


            - Calculation of repayment term/amount are incorrect
            - Incorrect credit agreements produced
2.  Bugs would be classified as "B" where :
     - a less important element of functionality is affected
            - Example : a value is not defaulting correctly and it is necessary to input the correct
value

     - data is affected which does not have a major impact


            - Example : where, for instance, some element of client capture was not propagated to the
database

     - there is an alternative method of completing a particular process


            - Example : a problem might occur reading all the details of a credit - this change can be
manually input.

3. "C" type bugs are mainly cosmetic bugs i.e. :


            - incorrect / no helptext on screens
            - drop down lists repeat an option
 

11.4. Procedure for maintenance of Error Management system.

1.  The Test Controller will refer any major error/anomaly to either Devopment Team Leader or
designated representative on the development team before raising a formal error record. This
has several advantages :- 
- it prevents the testers trying to proceed beyond 'showstoppers' 
- it puts the developer on immediate notice of the problem 
- it allows the developer to put on any traces that might be necessary to track down the error. 
2.  All bugs raised will be on the correct Error form, and contain all relevant data. 
3.  These errors will be logged on the day they occur with a status of 'RAISED' 
4.  There will be a daily 'System Test Support Group' meeting to discuss, prioritise and agree all
logged errors. 
During this meeting some errors may be dropped, identified as duplicates, passed to
programmer, etc. 
5.  The Error Log will be updated with the status of all errors after this meeting. e.g. with pgmr,
dropped, duplicate. 
6.  Once errors have been fixed and 'rebundelled' for a release the paper forms must be passed to
the Test Controller and he will change their status to 'Fixed to be retested' 
7.  Once the error has been retested and proven to be corrected the status will be changed to
'Closed' 
8.  Regular status reports will be produced from the Error system, for use in the Error Review
Team meetings. 

11.5. Overnight Processing - Checking Accounting & Audit & CIS

Test Requirement  Check Items  Level of


Testing 
Accounting
When spooling complete the Summary report should be 1. Legacy Txs on 1. Checking
checked against :  Report  at 
1. Similar Legacy Transactions  V  field level 
2. Test Input forms  Office Transactions
on  2. Checking
Report  at 
field level 
2. Summary report 

Applic input forms 
Accounting : after open/amend the amendment report should 1. Amendment 1. Satisfy as
be checked:  report  to 
1. For rejected open/amend instructions  reasons for 
2. Detail should correspond to input Applic Forms  2. Amendment rejection 
report 
V  2. Checking
Test input forms  at 
field level 
Print off Account and Customer records and check field detail Bookkeeping - Input Checking at 
against applic input forms/branch summary report  tx's  field level 

Test Input
forms/Amend rpt

11.7. SOFTWARE QUALITY ASSURANCE MEASURES


(i) DATES.

- Start date of SQA involvement.

(ii) EFFORT.

- No. of SQA Man Days Test Planning


- No. of SQA Man Days Reviewing Test Plans
- No. of SQA Man Days Executing Tests

(iii) VOLUME.

- No. of Tests Identified

(iv) QUALITY.
- No. of Tests Passed First Time
- Percentage of Tests Passed First Time
- No. of Error's Raised During Regression Testing
- No. of Error's Generated as a Result of Incorrect Fixes

- No. of Error's Raised by Category (A/B/C)


- No. of Error's Raised by Reason Code
- No. of Error's Raised by High Level Business Function

(v) TURNAROUND.

- Average Error Turnaround Time

S-ar putea să vă placă și