Sunteți pe pagina 1din 9

Frequently Asked Questions

About Rocket Engine Reliability Programs


Kevin Silke Lockheed Martin Astronautics Denver

Tyrone Jackson The Aerospace Corporation El Segundo


Key Words: Reliability program; Lessons learned; Reliability assessment; FMEA; Fishbone
analysis; Fault tree analysis

SUMMARY & CONCLUSIONS 1. INTRODUCTION

The objective of the Atlas Reliability The need for the Atlas Reliability
Enhancement Program (AREP) was to improve the Enhancement Program (AREP) was identified in 199 1,
Reliability of the Atlas IIA Launch Vehicle without following two consecutive mission failures of the
degrading its performance. This objective was Centaur Upper Stage rocket engine. Although the root
achieved by developing an electronically enhanced causes of the two failures were positively identified and
rocket engine, the Pratt & Whitney (P&W) RLlOE-1, permanently "fixed", the incidents initiated a series of
for the Centaur Upper Stage. Less than three years studies by the USAF, The Aerospace Corporation,
after AREP began, the USAF terminated the program LMA, and P&W into ways of enhancing confidence in
halfway through the test phase of the second the success of Atlas missions.
developmental engine. Even though the program
endedbefore a single RLlOE-1 engine was shipped, a In February 1993, AREP was first started
legacy of lessons learned were indwelled in the when the USAF Space and Missile Systems Center
experiences of the individuals who participated in the (SMC) awarded a contract to LMA to improve the
program. performance and Reliability of Atlas IIA. At that time,
the AREP objective was to enhance thirteen launch
AREP was the first DoD launch vehicle vehicle (LN) subsystems, including five functions of
program to operate under the new Acquisition Reform the RLlOA-4-1 Centaur engine. But budgetw
Initiative, which went into effect in June 1994. Under constraints forced an early suspension of the program.
Acquisition Reform, acquisition processes are LMA, the USAF and Aerospace worked out a prudent
supposed to be based on measurable performance plan for conducting a series of studies to identify an
criteria. However, not every organization that optimal approach for downsizing the program. The
participates in the development of a new system knows studies showed that a significant reduction in the loss
how to define a measurable performance criterion. rate of the Centaur engine would achieve the greatest
That was the challenge facing Lockheed Martin improvement in the Reliability of the L/V.
Astronautics (LMA) when it came time to implement Specifically, the studies identified the ignition,
a process to manage AREP Reliability risk. Knowing control, and chill-down subsystems as the engine
what LMA did for AREP provides insight for others functions that could be enhanced to provide the
wishing to define a performance-based Reliability greatest improvement in L N Reliability. These three
Program. engine functions became known as the three AREP
Initiatives, which would characterize what was
This paper is based on a technical report designated the UlOE-1 engine (Reference 1).
written by The Aerospace Corporation. The
information in this paper is structured in a manner that In October 1994, the AREP contract was
facilitates communicating valuable lessons learned that rewritten to comply with the new Acquisition Reform
are comprehensible to the novice and useful to the Initiative, and the program was started-up a second
expert. The most frequently asked questions regarding time. Under acquisition reform, the L/V supplier,
the AREP Reliability Program are listed in LMA, had the freedom to choose the methodology fix
chronological order. Following each question is an managing program risk. LMA chose to streamline
explanation of the pertinent analytical methods and program risk management with measurable progress
results. criteria. That criteria included timely response to
questions that The Aerospace Corporation frequently
asks programs that are similar to AREP. These

0-7803-5143-6/99/$10.000 1999 IEEE


1999 PROCEEDINGS Annual RELIABILITY and MAINTAINABILITY Symposium 343
fiequently asked questions facilitated the Customer’s which to estimate the Reliability impacts of the launch
understanding of the capabilities and effectiveness of vehicle I engine changes.
the AREP risk management activities. By
streamlining the AREP risk management process, 2. Adjust the Reliability predictions for Atlas
LMA was able to dispense with many of the IIA to reflect the flow-down of its demonstrated
formalities in past LIV Reliability Programs, such as Reliability, by using a factor derived fi-om the
requiring the Customer to approve the Reliability logarithmic ratio of the demonstrated to predicted
Program Plan, Reliability predictions, FMEA, and Reliability for the baseline launch vehicle.
critical items list.
3. Reduce the expected demonstrated loss rate
for the baseline RLlOA-4-1 engine by 71% and use
that value for the allocated loss rate goal of the RLlOE-
2 . FREQUENTLY ASKED QUESTIONS 1 engine.

2.1 How was the Reliability Program Integrated with 4. Construct a bottom-up Reliability model for
the Systems Engineering Process? the RLlOE-1 engine, and determine the optimal
approach for modifying the design of the baseline
The AREP Reliability Program was engine to achieve the allocated loss rate goal for the
functionally an integral part of the AREP Systems RL 1OE- 1 engine.
Engineering Integration Team and each RLlOE-1
Component Product Development Team. LMA 5. Calculate the relative improvement in design
designated a Lead Reliability Engineer as the point of Reliability of the RLlOE-1 engine compared to the
contact (POC) to support all of the AREP teams. baseline RLIOA-4-1 engine.
Typical tasks performed by this POC included flowing
down quantitative Reliability requirements, defining 6. Compare the RLlOE-1 engine predicted loss
design Reliability guidelines, managing the rate to the allocation loss rate goal to determine if the
integration of Reliability engineering tasks within the Reliability Program goal was met. The objective of
AREP Systems Engineering Process, identifying and process steps 1 through 6 was to produce an integrated
assessing Reliability-related risks, and providing input AREP Reliability model.
to component and system design reviews.
7. Apply proven techniques for managing the life
2.2 How were the Reliability Requirements DeJined? cycle Reliability risk of the RLlOE-1 engine.

The AREP contract contained a single 8. Analyze the RLIOE-1 engine test data,
Reliability requirement, which was, “The Reliability bottom-up Reliability model, and failure mode
of the vehicle shall be improved without degrading mitigation methods to verify that life cycle Reliability
performance.” This provided a general goal and risk is adequately managed.
direction for the program, allowing trade studies of the
possible options to define the specific direction using Even though LMA was not required by the
cost-effectiveness measures. Based on pre-AREP Air Force to document an AREP Reliability Program
estimates of achievable improvements to the Plan, LMA and P&W coordinated the creation of an
Reliability of the RLlOA-4-1 engine, a goal was RL10E-1 Rocket Engine Reliability Program Plan.
established by the AREP Reliability Program to This primelsubcontractor program plan was based on
reduce the failure rate of the RL 1OE- 1 engine by 7 1%. the concepts found in MIL-STD-1543A. This resulted
in the following list of tasks and guidelines:
2.3 How was the Reliability Program Planned?
a. Redundant designs and applicable design and
The AREP contract did not require that a safety margins were to be applied to new or modified
formal Reliability Program Plan be written. In lieu of components to the greatest extent feasible.
a formal plan, LMA convened a
Govemment/Contractor Reliability Working Group to b. The component suppliers were to perform part
define the process for allocating and predicting stress derating analysis and part stress failure rate
Reliability for the RLlOE-1 engine. The working predictions.
group defined the Reliability Program as the series of
tasks that were required to accomplish the following c. Component- and subsystem-specific historical
objectives: flight and ground test data was to be used for
calculating failure rates whenever possible. This
1. Calculate the demonstrated Reliability of the provided the most realistic estimates of component and
Atlas IIA based on launch experience up to December subsystem reliabilities.
1993. This provided a “real world” baseline against

344 1999 PROCEEDINGS Annual RELIABILITY and MAINTAINABILITY Symposium


d. Failure mode assessments were to be performed as P&W used an independent methodology to
early as possible, with full cooperation fiom design assess the demonstrated reliability of the RLIOA-4-1
engineers, to ensure the mitigation of potential failure engine. They calculated the RL 1OA-4-1 mission loss
modes and that new and modified components would rate based on 2 failures in 166 Atlas and Titan engine
operate properly with all of the unchanged subsystems. missions, with an engine mission being defined as one
engine operating over two burns. Using the binomial
e. Test data would be used to veri@ the accuracy of distribution, and applying a 90% confidence bound,
the predictions and ensure that the program goal had P&W yielded a demonstrated Reliability of 0.9683.
been achieved. They calculated the corresponding mission loss rate,
using the following formula:
E Relevant Technical Performance Measurements
(TPMs) would be used to monitor the progress of the
Reliability Program. 13. Baseline = - In (0.9683)
= 3.221 losses p e r 100 missions
2.4 What Rationale was Used to Select the Analytical
and Empirical Methods? 2.6 What Methods were Used to Estimate the Relative
Improvement in Design Reliability?
The rationale for selecting an analytical or
empirical method for use in the AREP Reliability P&W estimated the RLlOE-1 engine mission
Program, fiom among the many methods available in loss rate to be 0.924 (down from 3.221). But LMA
the field of Reliability Engineering, was based on the needed a relative Reliability improvement factor for the
relative usefulness of their outputs in achieving one or engine to apply to their Duane Reliability model for
more Reliability Program requirements or goals. Each Atlas IIA. This engine Reliability improvement factor
of the methods that were selected either supported was calculated by taking the ratio of the RLlOE-1 and
quantifying the expected-demonstrated Reliability
RLlOA-4 mission critical loss rates, per the formula:
(e.g., MIL-HDBK-189 Duane Reliability Growth
Model; and MIL-HDBK-217 failure rate models) or
supported qualifying the mitigated design risk (e.g.,
MIL-STD-1629A Failure Mode, Effects and Criticality
Analysis; and Fault Tree Analysis). Together, the
%FR = [ x 100%

selected methods provided high confidence in the where:


assessment of the RL1OE- 1 engine’s design Reliability
and its impact on the Reliability of the Atlas IIA %F R = % reduction in AREP engine mission
launch vehicle. The selected methods are addressed in loss rate
greater detail in the following sections. Ep = Baseline engine demonstrated mission
2.5 What Methods were Used to Estimate the loss rate
Demonstrated Reliability? EA = AREP engine expected demonstrated
mission loss rate
To estimate the demonstrated Reliability af
Atlas IIA at the vehicle, subsystem, and assembly Substituting the appropriate values into the
levels, LMA applied the Duane Reliability Growth above formula yields:
Model (Reference 2) along with standard reliability
predictions. For the vehicle-level estimate, a
conventional Duane model was built. Based on 13
mission failures in 80 Atladcentaur flights, as of the
%FR = ( 3*223.;2y24) x 100% = 71%

selected program cutoff date of December 1994, the


demonstrated Reliability of Atlas IIA was calculated to Therefore, the RL 10E-1 engine met its design
be 92.1%. For the subsystem and assembly level Reliability goal because its mission critical loss rate
estimates, a demonstrated-to-actual ratio of 6.3 13 was was 71% lower than that of the RLlOA-4-1 engine.
calculated fiom the logarithmic ratio between the
Duane model and the vehicle Reliability prediction To determine the relative improvement in the
model. This ratio allowed the “marriage” of AREP vehicle Reliability compared to that of the
demonstrated and predicted Reliability data, and baseline Atlas IIA vehicle, the Reliability prediction
realistic allocation of the vehicle-level demonstrated process in Figure 1 was applied. The objective of this
Reliability to the subsystems and assemblies, process was to produce an integrated AREP Reliability
including the RLl OA-4-1 engine. The flowed-down model to quantify the difference between the design
demonstrated Reliability of the RL lOA-4- 1 engine was reliabilities of the RLlOA-4-1 and RLlOE-1 rocket
0.9884. engines along with the changes in the vehicle
subsystem predictions. Folding P&W’s engine-level

1999 PROCEEDINGS Annual RELIABILITY and MAINTAINABILITY Symposium 345


Reliability assessment into the vehicle-level For the overall Atlas IIA vehicle, LMA
Reliability model, LMA estimated that the RLlOE-1 performed an in-house developed type of failure mode
engine would reduce Atlas IIA mission failure assessment known as a Fishbone Analysis. The
probability by relatively 21%. LMA Reliability Fishbone Analysis approach combines the top-down,
estimates also showed that the goals for all three deductive process of a Fault Tree Analysis (FTA) in
AREP Initiatives had been met. identifying the potential failure modes with the
compensating feature identification of the FMEA
2.1 What Methods were Used to Assess the Potential process. The failure modes are documented using
Failure Modes? compact Cause and Effect diagrams (hence, the name
“Fishbone” Analysis, as the example in Figure 3
Several methods were brought to bear in illustrates) rather than Fault Trees, as nothing more
assessing the design risks. For the RLlOE-1 engine, complex than an “OR” gate is required for these
P&W performed the standard Failure Mode and Effects diagrams. The compensating features are documented
Analysis (FMEA) process illustrated in Figure 2 , on separate Disposition Forms which relate back to the
which is based on MIL-STD-1629A (Reference 3). fishbone diagram through the indentured numbering
The objective of the FMEA was to identify and scheme, providing unique ID numbers for all of the
evaluate each mission critical failure mode of the fishbone diagram elements. LMA has found the
engine, so as to influence its design Reliability and Fishbone Analysis process to be advantageous in
mitigate or eliminate the potential failure modes. All capturing system interaction and integration effects,
of the credible failure modes of each new AREP which is why the RLlOE-1 engine was included in
component design were analyzed to determine the this assessment as well, referring back the P&W
consequences of those failures on the engine system FMEA for engine component compensating features
operation. The analysis identified failure mode and documenting separate dispositions for system
detection methods and compensating features to issues.
prevent, minimize or control failure effects. The
Compensating features included design features, special
inspections, tests, controls, instructions, operational
corrective actions (e.g., replacement, reconfiguration,
repair or preventive maintenance), or other provisions.

Baseline Atlas
Reliability Model

Scaled Baseline Atlas

Reliability Model

Baseline Engine Failure


P&W Assessed Engine Rate and Startup Failure
Improvement Percentage
Probability Reduced by
(71%)
Improvement Percentage
I 1 I

Figure 1. AREP Reliability Modeling Process

346 1999 PROCEEDINGS Annual RELIABILITY and MAINTAINABILITY Symposium


i
System Definition
Performance Inputs To Other Tasks
4
Functional models Change System Safety Analysis
Process and test plans Critical Items List
Drawings Software Hazard Analysis
.-.,.-. -- -- -- -- ,--, -.-,-,--,-.-..- Supportability Analysis
Quality Planning
FMECA Planning Determine Potential
1 Failure Modes Demonstration Testing
Risk Management
Groundrules/Assumptions Failure mode models
t

FMECA Database
Methods

L.,_._.__..__ ______
F a i l u r e M --,.-._..._._.,-.-__
o d e A n d Effects Analysis --.i
Figure 2. FMEA Process Flow

FishboneNo: B I -D S March 1996 Originator: M Malinowskl


&T ...Due to Centaur Propulsion Subsystem Failure of Turbopump Due to ...
B.l.l
Improper thermal Turbine lack of
conditioning prior adequate power of adequate
to MES 1 due to4
.I Incorrect TCV
whedulc
.Z Incorrect CDV .ZPump mal
schedule duetoCDV

1 B.1.6 / B.1.4
. I Leak B torch
igniter suppiy port J
Improper thermal Gedrhox inability Oxidizer pump
conditioning prior to transmit power back of adequate
to MESZ due to... a head rise due to...

Figure 3. Example Fishbone Diagram

1999 PROCEEDINGS Annual RELlABlLllY and MAINTAINABILITY Symposium 347


Identify Fault Detection and Accomodation (FDA) Ensure all FDA modules in
Software Design Document
(SDD) are referenced by

Validate €TA by ensuring all failure modes identified


as redundant in the fault tree have effective detection
and accomodation methods (and inverse, for all single
point failures)

Identify failure signatures (combinationsof software


I . percentages

variables) used to initiate each detection and


accommodation method

I Ensure there are no conflicts among failure signatures


andor outputs for detection and accomodation methods

Figure 4. Fault Detection & Accommodation Assessment Approach

There was one additional analysis used to contribute most to the incidence of engine ignition
assess the design risks. The RLlOE-1 electronic failure: the Ignition System, the non-actuating parts cf
controller utilized a significant degree of redundancy in the valves, particularly the Pre-launch Cool-down
its design, which required software to detect the Check Valve (PLCDV), and the actuating parts of the
failures and reconfigure the system operation to valves with associated plumbing lines. Having
accommodate those failures. Thus a Fault Tree identified the apparent weakness of the RLIOA-4-1,
Analysis resulted, fiom concern about the lack of a P&W defined a design for the FUlOE-1 that
formal method to verify that the Fault Detection & incorporated an improved ignition system, new
Accommodation (FDA) software for the engine Electromechanical Actuators (EMA’s) controlled by an
controller could manage the fvst and second engine mounted Digital Electronic Rocket Engine
occurrences of faults within the RLIOE-1 engine. The Controller (DEREC), and a simpler Propellant Flow
FTA was used to identify all of the failure modes for System. However, an objective examination of the
which accommodation was possible. Several steps possible common cause failure modes shows that the
were then taken, as outlined in Figure 4, to review the U 1OE- 1 engine is
relative likelihood of failure of the E
FDA methods to ensure that all of these failure modes not always lower than that of the RLlOA-4-1 engine.
were adequately addressed and that there would be no Table 1 compares the relative likelihood of RL10E-1
conflicts among the detection and accommodation engine failure, due to common cause failure modes,
methods. with that of the RLlOA-4-1 engine.

2.8 What were the Sources of Reliability Design Should any of these common cause failure
Risk? modes occur prior to or during launch of the Atlas IIA,
a mission critical failure might be the outcome. This
P&W performed an exhaustive study to list was used in evaluating all of the failure mode
identify the sources of reliability design risk for the analyses to ensure that the possibility of common
lU1OA-4-1 engine. Three functions were found to cause failure modes had been addressed and mitigated.

348 1999 PROCEEDINGS Annual RELIABILITY and MAINTAINABILITY Symposium


program compared to the RL10E-1 Reliability
Table 1. Relative Likelihood of RL 1OE- 1 and requirement.
RL 1OA-4- 1 Engine Failure
2.10 How was Reliability Risk Management Progress
Measured and Monitored?
Cause Failure Compared To
The difference between the demonstrated
failure rate of the baseline engine and the predicted
Contamination electrical parts failure rate of the RLlOE-1 was the only Technical
Performance Measurement (TPM) criterion used f a
Higher - DEREC monitoring the progress of the AREP Reliability
Mistimed Command controlled actuator timing
Program. The expected demonstrated Reliability f a
Lower - Fewer the AREP engine was calculated iteratively with the
Fluid Leakage plumbing lines progress of the design definition to measure the degree
Lower - Fewer of success achieved at meeting the Reliability
Fluid Blockage plumbing lines requirements. Figure 5 shows the profile of the
Higher - More calculated percentages of design Reliability
electrical Parts improvement for the RLlOE-1 engine. The rather
Excessive Vibration significant reduction in the delta Reliability
No change - Battery improvement of the engine fiom 4.27% to 1.67%
Over-Powered assembly unchanged between SRR and PDR resulted kom the downsizing
No change - Battery of the AREP objectives.
Under-Powered assembly unchanged
Lower - EMA The AREP Reliability Program TPM was
Over-Pressure controlled actuators defined such that analytical progress could be
Lower - EMA confirmed and potentially deficient areas that could
jeopardize meeting the Reliability requirement could
Under-Pressure controlled actuators
be identified. In retrospect, there were other TPMs
Higher - More heat that could have been used to track AREP Reliability
Over-Temperature sensitive electrical parts Program progress, such as, comparing the number of
Lower - Less cold implemented critical item dispositions versus the total
Under-Temperatwe sensitive plumbing lines number recommended, or comparing the number of
failure modes exercised by test versus the total number
2.9 How were the Reliability Predictions Verified? identified.

Although full development testing of the 2.1 1 What Criteria did The Aerospace Corporation Use
RLlOE-1 engine had not been completed when the to Evaluate the AREP Reliability Program?
program ended, the tests were highly successfbl in
verifying reliable engine operation with the M1 Acquisition Reform was a brand new concept
authority, digital electronic control and fewer valves. when AREP started in 1994. There were no prior
The RL10E-1 engine was scheduled for 134 test firing success stories to refer to for guidance in evaluating the
during four phases of development testing. Only two program. Each member of The Aerospace Corporation
phases of the development test were completed. evaluation team had to apply an evaluation criterion
However, most of the measurable enhancement features that did not direct the activities of LMA. The one
of the engine were verified by test. consensus fact was that AREP was a Demonstration
and Validation Phase Rocket Engine Program. The
For verification of the numerical Reliability
requirement, a Bayesian Analysis Method was used to evaluation criterion that was applied to the AREP
combine the test data with the Reliability model Reliability Program was derived from the then recently
results to ensure that the program goal was still released Rome Laboratory technical report, “A Quality
achieved. Since this was a development test program, Process Approach to Electronics System Reliability”
this required defining criteria on the relevance of any (Reference 4). This report describes evaluation criteria
test failures to a flight configuration. To this end, a that are based on the assessment of process control
Pre-Test Declaration was written defining the indicators and the degree to which they are
conditions that would make a failure non-relevant. implemented as part of the supplier’s way of doing
Although the test program was not completed, this business. For AREP, the identification of process
verification would have effectively required that the test control indicators was combined with an experience-
program be completed without any relevant failures based conjecture that relates process quality levels with
charged to the engine given the relatively small test

1999 PROCEEDINGS Annual RELIABILITY and MAINTAINABILITY Symposium 349


the types and phases of risk mitigation activities to Such a high quality factor translates into a high level
arrive at the evaluation criteria in Table 2. of confidence in the analytical and deterministic results
produced by the program. This can only be achieved
3. CONCLUSION through careful planning and tracking of the Reliability
Program activities. Although AREP was terminated
Based on the evaluation criterion that was prior to verifying the flight Reliability of the RL10E-1
applied by the Aerospace Corporation, the AREP rocket engine, LMA and P&W did show that
Reliability Program had a quality factor rating of 1.0, Acquisition Reform was indeed a value-added concept
which is the highest rating for a Demonstration and that could be implemented with the highest quality
Validation Phase Rocket Engine Reliability Program. results.

Table 2. AREP Reliability Program Evaluation Criteria.

DEMONSTRATION& VALIDATION PHASE


RELIABILITYANALYSIS & RISK REDUCTION
EVALUATION CRITERIA

Reliability predictions are based on Customer's experience with the performance of existing comparable equipment. All
key system reliability parameters (e.g., life, fatigue, false alarm rate, etc.) are defined. Clear engineering rationale is
provided for all expected improvements. Definitionof design/applicationcriteria is complete. Lessons learned data are
available (e.g., derating, environmental sensitivity, manufacturing process, etc.). Expected operating environment
including maintenance is defined and is traceable to Customer's mission description. Reliability models are based on
FMEA, which is conducted along with other fault/failure analysis methods to identify critical itemdparameters and
functionallhardware failure modes. Processing of critical items is tracked and proper disposition of each item's risk is
verified. Analyses are updated with design change data and development test results. Fault detection and
accommodation approaches are defined and related to critical parameters and functions.

Reliability predictions are based on comparisons to current performance of existing comparable equipment. One or two
key system reliability parameters (e.g., life, fatigue, false alarm rate, etc.) are not defined. Clear engineering rationale is
provided for all expected improvements. Definition of design/applicationcriteria is complete. Lessons learned data are
available (e.g., derating, environmental sensitivity, manufacturing process, etc.). Expected operating environment
including maintenance is defined and traceable to Customer's mission description. Reliability models are based on
FMEA, which is conducted along with other faulWailure analysis methods to identify critical items and
functionaVhardwarefailure modes. Processing Of critical items is tracked but proper disposition of each item's risk is
not verified. Analyses are updated with design change data and development test results. Fault detection and
accommodation approaches are defined but not related to critical parameters and functions.

Reliability predictions are based on comparisons to current performance of existing comparable equipment. Several
key reliability parameters are not defined and engineering rationale for expected improvements is weak. Definition of
design/application criteria is complete. Lessons learned data are available (e.g., derating, environmental sensitivity,
manufacturing process, etc.). Expected operating environment including maintenance is defined and traceable to
Customer's mission description. Reliability models are based on FMEA, which is conducted to identify critical items
and functional failure modes. Processing of critical items is not tracked. Analyses are updated with design change data
but not all development test results are included. Fault detection and accommodation approaches are partially defined
and not relatedto critical parameters and functions.

Reliability predictions have limited relevance to current performance of existing comparable equipment. Only a few key
reliability parameters are defined and engineering rational for expected improvements is weak. Definition of
design/application criteria is incomplete. Lessons learned data are partially available (e.g., derating, environmental
sensitivity, etc.) Expected operating environment including maintenance is not traceable to Customer's mission
description. Reliability models ate not based on FMEA, which is conducted to identify critical functional failure modes.
Analyses are updatedwith incompletedesign change data, and developmenttest results are not included. Fault detection
and accommodationapproachesare not defined.

Reliability predictions have no relevance to current performance of existing comparable equipment. No key reliability
parametersand design/application criteria are defined. Lessons learned data are not available. Expected environment
including maintenance is not traceable to Customer's mission description. FMEA or similar analyses not conducted to
i d e n t i critical functional failure modes. Analyses are not updated with design change data or development test results.

350 1999 PROCEEDINGS Annual RELIABILITY and MAINTAINABILITY Symposium


UpdatedAnalysis As
Necessary To Support
I Analysis Analysis Analysis Design Changes Anticipated
Updates
i L b 1

’ = 4.27
%

I
’ *% 1.58

%
’ = 1.55
Demonstrate
-
SRR PDR CDR Qualification AREP Milestones
Time +
Figure 5 . Technical Performance Measurement for AREP Reliability

REFERENCES Kevin Silke (Presenting Author)


Lockheed Martin Astronautics
1. W. M. Van Lerberghe, J. L. Emdee, R. R. Foust, P.O. Box 179
“Enhanced Reliability Features of the RLlOE- 1 Engine”, Mail Stop B2100
Proceedings 1997 International Astronautical Federation Denver, CO 80201
Symposium.
2. Department of Defense, “Reliability Growth Phone: (303) 977-9577
Management,” MIL-HDBK-189, Washington D.C., 1981, pp. 33- Fax: (303) 977-4373
42 & 72. E-mail: Kevin.Silke@LMCO.com
3. Department of Defense, “Procedures for Performing a
Failure Mode, Effects and Criticality Analysis,” MIL-STD- 1629A, Mr. Kevin Silke is the Lead Reliability Engineer for the Atlas
Washington D.C., 1980. Program at Lockheed Martin Astronautics. Previously, he worked
4. RL-TR-93-209, “A Quality Process Approach To for General Dynamics and Safety Factor Associates, Inc. He has
Electronic System Reliability: handbook Procedure,” Rome over ten years experience in Reliability Engineering and Risk
Laboratory, November 1993.
Analysis and has degrees in Electrical Engineering and Business
Management. He has spent his entire professional career in
BIOGRAPHIES Reliability and Risk Assessment of spacecraft, launch vehicles, and
NASA operated high-energy ground research facilities. His
Tyrone Jackson (Correspondence Author) technical skills include creation of software for specialized
The Aerospace Corporation solutions to Reliability and statistical problems. His risk assessment
2350 E. El Segundo Blvd. talents include Reliability modeling and Reliability data analysis,
M41987 fault tree analysis, event sequence analysis, failure/success
El Segundo, CA 90245-4691
database development, common cause failure analysis, Bayesian
Phone: (310) 336-6170 data analysis, Failure Mode and Effects Analysis, uncertainty
Fax: (310) 336-6914 analysis, and Monte Carlo Analysis.
E-mail: Tyrone.Jackson@aero.org
As a member of the technical staff in the Reliability and Quality
Department of The Aerospace Corporation, Mr. Tyrone Jackson is
responsible for evaluating contractors’ Reliability analyses and
advising system program offices on cost-effective management of
Reliability Engineering activities. He has almost twenty years
experience in Reliability Engineering applications and research.
Previously, he has worked for Hughes Aircraft Company, TRW,
and General Dynamics. At each of these companies, he initiated
procedures to integrate Reliability Engineering with the System
Engineering Process. He has developed a number of Reliability
software tools, and has published several papers on Reliability
analysis and management techniques. Mr. Jackson received a
BSEE degree from the Illinois Institute of Technology in 1980. H e
is a member of the IEEE Los Angeles Chapter and has served on
AIAA and SAE G-11 subcommittees.

1999 PROCEEDINGS Annual RELIABILITY and MAINTAINABILITY Symposium 351

S-ar putea să vă placă și